HomeMy WebLinkAbout2024-10-29; City Council; ; Updated Amount of Construction Contract for the El Camino Real Widening from Sunny Creek Road to Jackspar Drive ProjectCA Review GH Meeting Date: Oct. 29, 2024 To: Mayor and City Council From: Scott Chadwick, City Manager Staff Contact: Brandon Miles, Associate Engineer brandon.miles@carlsbadca.gov, 442-339-2745 Hossein Ajideh, Engineering Manager hossein.ajideh@carlsbadca.gov, 442-339-2756 Subject: Updated Amount of Construction Contract for the El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project District: 2 Recommended Actions Adopt a resolution awarding a construction contract to Dick Miller, Inc. for the El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project in an updated amount not to exceed $3,993,598 and authorizing an additional appropriation of $116,050 from gas tax funds to Capital Improvement Program Project No. 6094. Executive Summary/Explanation & Analysis This project will widen northbound El Camino Real from Sunny Creek Road to Jackspar Drive to add a third northbound vehicle lane, as shown in Exhibit 2, to meet the city’s design standards and the standards in the city’s General Plan and Growth Management Plan. The project will also provide new sidewalks, new streetlights and enhanced buffered bike lanes. On Sept. 10, 2024, the City Council authorized award of the construction contract to Dick Miller, Inc. in an amount not to exceed $3,882,738 and authorized an additional appropriation in an amount of $600,000 from TransNet1 and $250,000 in gas tax funds, for a total additional appropriation of $850,000. Upon closer review, staff discovered a clerical error in which the contractor’s submitted bid form showed an amount of $3,882,738 but the online bidding portal PlanetBids showed a bid amount of $3,993,598. Under the terms of the bid documents, if there is a discrepancy between the written price on the bid form and the price submitted through the online bidding portal, the online bidding portal price prevails. Staff request that the City Council award the construction contract for the project to Dick Miller, Inc., in an updated amount of $3,993,598 and authorize an additional appropriation of $116,050 from gas tax funds to Capital Improvement Program Project No. 6094. 1 TransNet is the county sales tax that funds transportation projects. Oct. 29, 2024 Item #4 Page 1 of 7 Carlsbad Municipal Code Sections 3.28.080(C) and 3.28.080(I)(6), which cover purchasing in construction contracts, require the City Council’s approval for all formally bid contracts when the value exceeds $200,000, as this project does. Fiscal Analysis The project is currently funded using TransNet and gas tax funds. An additional appropriation of $116,050 of gas tax funds is required to award the contract with the updated contract amount. Available funding and the estimated construction costs for the project are shown in the table below: Carlsbad Municipal Code Sections 3.28.040(C)(5) and 3.28.090(B) authorize the City Manager or designee to approve change orders in an amount equal to the contingency set at the time of project award, which for this project is $650,000. Next Steps Once the City Council authorizes award of the construction contract to Dick Miller, Inc. with an updated contract amount of $3,993,598, staff will issue a purchase order, schedule a pre-construction meeting with Dick Miller, Inc. and issue a notice to proceed for construction of the project. Construction is expected to commence in December 2024, with a duration of about 12 months and an estimated completion date of December 2025. Environmental Evaluation The City Planner, through the process outlined in Carlsbad Municipal Code Section 19.04.060, has determined that the project belongs to a class of projects that the state Secretary for Natural Resources has found do not have a significant impact on the environment. It is therefore categorically exempt from the requirement for the preparation of environmental documents in accordance with Guideline Section 15303(d) Class 3 of the California Environmental Quality Act. In making this determination, the City Planner has found that the exceptions listed in Section 15300.2 of the guidelines do not apply to this project. The project is consistent with 15303(d) Class 3 because it consists of construction limited to new facilities, such as street improvements El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project Capital Improvement Program Project No. 6094 Total appropriation to date $5,860,000 Total expenditures and encumbrances to date -$847,412 Total available funding $5,012,588 Construction contract – Dick Miller, Inc. -$3,993,598 Construction contingency -$650,000 Construction management, inspection, material testing, support services and staff support (estimated) -$485,000 Total estimated project costs -$5,128,598 Remaining balance -$116,010 Additional appropriation requested (rounded) $116,050 Oct. 29, 2024 Item #4 Page 2 of 7 of reasonable length. The project fills in an existing gap in pedestrian and street facilities. A notice of this determination was circulated to the public for a 10-day period, which began on Oct. 19, 2022, and ended on Oct. 31, 2022, and no appeal was filed. Exhibits 1. City Council resolution 2. Location map Oct. 29, 2024 Item #4 Page 3 of 7 Exhibit 1 Oct. 29, 2024 Item #4 Page 4 of 7 RESOLUTION NO. 2024-240 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, AWARDING A CONTRACT TO DICK MILLER, INC. FOR THE EL CAMINO REAL WIDENING FROM SUNNY CREEK ROAD TO JACKSPAR DRIVE PROJECT IN AN UPDATED AMOUNT NOT TO EXCEED $3,993,598 AND AUTHORIZING AN ADDITIONAL APPROPRIATION IN AN AMOUNT OF $116,050 FROM GAS TAX FUNDS TO CAPITAL IMPROVEMENT PROGRAM PROJECT NO. 6094 WHEREAS, the City Council of the City of Carlsbad, California, has determined it is necessary, desirable and in the public interest to construct the El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project, Capital Improvement Program, or CIP, Project No. 6094; and WHEREAS, Carlsbad Municipal Code, or CMC, Sections 3.28.080(() and 3.28.080(1)(6), which govern purchasing in construction contracts, require the City Council to award all formally bid contracts when the value exceeds $200,000; therefore, the project is subject to this requirement; and WHEREAS, on Sept. 10, 2024, the City Council authorized award of the project to Dick Miller, Inc. in an amount not to exceed $3,882,738, which was the amount the contractor submitted on its bid form; and WHEREAS, the contractor's online bidding portal's amount was $3,993,598; and WHEREAS, the bid documents indicate that if there is a discrepancy between the written price on the bid form and the price submitted via the online bidding portal, the online bidding portal price prevails; and WHEREAS, staff request award of the contract to Dick Miller, Inc. for the project in an updated amount of $3,993,598; and WHEREAS, CMC Sections 3.28.040{C)(S) and 3.28.090(8) authorize the City Manager or designee to approve change orders in an amount equal to the contingency set at the time of project award, which is $650,000 for the project; and WHEREAS, staff request an additional appropriation in an amount of $116,050 from gas tax funds to CIP Project No. 6094; and WHEREAS, the City Planner, through the process outlined in CMC Section 19.04.060, has determined that the project belongs to a class of projects that the state Secretary for Natural Resources has found do not have a significant impact on the environment. It is therefore categorically exe mpt from Oct. 29, 2024 Item #4 Page 5 of 7 the requirement for the preparation of environmental documents pursuant to Guideline Section 15303(d) Cla ss 3 of the California Environmental Quality Act; and WHEREAS, in making this determination, the City Planner has found that the exceptions listed in Section 15300.2 of the Guidelines do not apply to this project. The project is consistent with 15303(d) Class 3 because it consists of construction limited to new facilities, such as street improvements of rea sonable length. The project fills in an existing gap in pedestrian and street facilities. A notice of this determination was circulated to the public for a 10-day period, which began on Oct. 19, 2022, and ended on Oct. 31, 2022, and no appeal was filed. follows: NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as 1. That the above recitations are true and correct. 2. That the bid of $3,993,598 submitted by Dick Miller, Inc. for construction of the El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project, CIP Project No. 6094, is accepted, and the Mayor is authorized to execute the contract for the project with the updated contract amount. 3. That the City Manager or designee is authorized to approve construction change orders up to $650,000 for the El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project, CIP Project No. 6094. 4. That the City Manager or designee is authorized to appropriate $116,050 from gas tax funds to CIP Project No. 6094. 5. That the City Manager or designee is authorized to sign all other documents necessary for regulatory compliance, to extend funding opportunities, or to otherwise implement and finalize the project, all of which are subject to review and approval as to form by the City Attorney's office. 6. That the award of this contract is contingent upon Dick Miller, Inc. executing the required contract and submitting the required bonds and insurance policies, as described in the contract, within 20 calendar days after adoption of this Resolution. The City Manager may grant reasonable extensions of time to execute the contract and assemble the required bonds and insurance policies. Oct. 29, 2024 Item #4 Page 6 of 7 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 29th day of October, 2024, by the following vote, to wit: AYES : NAYS: ABSTAIN: ABSENT: BLACKBURN, BHAT-PATEL, ACOSTA, BURKHOLDER. NONE. LUNA. NONE. KEITH BLACKBURN, Mayor SHERRY FREISINGER, City Cl erk (SEAL) EL C A M I N O R E A L JAC K S P A R D R RE E F C R SU N N Y C R E E K R D LONGFELLO W R D FO R E C A S T L E C T DON M I G U E L D R FROST AV CAM I N O H I L L S D R KEA T S P L DON Q U I X O T E D R DON T O M A S O D R RAN C H O C A R L S B A D D R BYRON P L PLOT DATE: 6/16/2021 PATH: S:\EngGIS\Madison_Power\Location maps\El Camino Real Widening- Sunny Creek road to Jackspar.mxd PROJECT NAME EXHIBITPROJECTNUMBER60942EL CAMINO REAL WIDENING FROM SUNNY CREEK ROAD TO JACKSPAR DRIVE PROJECT LOCATION MAP CARLSBAD VISTA OCEANSIDE ENCINITAS SAN MARCOS Vicinity Map ³ PLOTTED BY: MPower SITE SITE ³NOT TO SCALE Exhibit 2 Oct. 29, 2024 Item #4 Page 7 of 7