Loading...
HomeMy WebLinkAbout2009-04-15; Planning Commission; ; PCD/GPC 09-01 - CAPITAL IMPROVEMENT PROGRAM BUDGETTfclty of Carlsbad Planning Department • A REPORT TO THE PLANNING COMMISSION P.C. AGENDA OF: April 15, 2009 Item No. G) Application complete date: NIA Project Planner: Pam Drew Project Engineer: Steve Jantz SUBJECT: PCD/GPC 09-01 -CAPITAL IMPROVEMENT PROGRAM BUDGET 2009-2010 -Request for a Planning Commission Determination of General Plan Consistency for the proposed Fiscal Year 2009-2010 Capital Improvement Program Budget. I. RECOMMENDATION That the Planning Commission ADOPT Planning Commission Resolution No. 6554 APPROVING PCD/GPC 09-01 based upon the findings and subject to the conditions contained therein. II. INTRODUCTION This project, the proposed Fiscal Year (FY) 2009-2010 Capital Improvement Program (CIP) Budget, is being presented to the Planning Commission for a determination of General Plan consistency. The project consists of 9 new City CIP projects and 4 new CIP projects submitted by Carlsbad Municipal Water District (CMWD) for a total of 13 new CIP projects (projects which have not been included in previous years' CIP). Sections 65401 and 65402 of the State of California Government Code require that new public works projects recommended for planning, initiation, construction, or for property acquisition in the upcoming fiscal year be reviewed for conformity with the adopted General Plan. Staff has reviewed all of the proposed new projects included in this year's CIP and concludes that all are consistent with the General Plan. Therefore, the General Plan consistency determination can be made. III. PROJECT DESCRIPTION AND BACKGROUND The requested determination of General Plan consistency covers 13 new projects added to the CIP for consideration as part of the proposed budget for fiscal year 2009-2010. Determinations of General Plan consistency for the CIP are necessary when new projects are added to the build- out CIP. This year's projects fall into the following project type categories: Drainage; Water and Streets. A list of the projects by type is attached as Exhibit "A." Descriptions of the projects are attached as Exhibit "B." This CIP project list is subject to change during the fiscal year. Some projects not currently on the list may need to be added as a result of City Manager recommendations and/or City Council decisions. Any new projects which might be added to the CIP in this manner would first be brought to the Planning Commission for consideration of a General Plan Consistency finding. PCD/GPC 09-01 -2009-201 tAPITAL IMPROVEMENT PROGRA' April 15, 2009 Pa e2 IV. ANALYSIS Staff has reviewed the proposed FY 2009-2010 CIP for consistency with the City's General Plan. Table 1, below ("General Plan Consistency"), identifies the elements, goals, objectives, and policies of the General Plan which are relevant to the new projects being proposed this year. The new projects' consistency with these goals, objectives, and policies are discussed on the following page. (For discussion purposes, like projects have been grouped together.) TABLE 1: GENERAL PLAN CONSISTENCY GENERAL PLAN REFERENCE TEXT Land Use Element A City which ensures the timely provision of adequate public Growth Mgmt. & Public facilities and services to preserve the quality of life of residents. Facilities Goal A.I Land Use Element A City which maintains a system of public facilities adequate Growth Mgmt. & Public for the projected population. Facilities Goal A.2 Land Use Element A City which protects and conserves natural resources, fragile Environmental ecological areas, unique natural assets and historically Goal A.I significant features of the community. Circulation Element A City with an adequate circulation infrastructure to serve the Streets & Traffic Control projected population. Goal A.2 Circulation Element A City with properly maintained, smooth functioning and safe Streets & Traffic Control traffic control systems. GoalA.4 Circulation Element To provide an adequate circulation infrastructure concurrent Streets & Traffic Control with or prior to the actual demand for such facilities. Objective B.1 Circulation Element To design streets for the safe and efficient movement of people, Streets & Traffic Control goods and services within and through the City in the most Objective B.2 environmentally sound and aesthetically pleasing manner possible. Public Safety Element A City which minimizes injury, loss of life, and damage to Flood Hazards property resulting from the occurrence of floods. Goal A City Projects: Drainage Projects There are four new drainage projects being proposed this year. These projects are: I) the preparation of a Preliminary Design Study for slope repairs to mitigate for drainage and erosion issues between Park Drive and Bayshore Drive; 2) a geotechnical and engineering analysis to determine remediation measures for subsurface drainage issues on Marca Place; 3) the PCD/GPC 09-01 -2009-201 tAPITAL IMPROVEMENT PROGRA' April 15, 2009 Pae 3 installation of a runoff collection and treatment system at Fire Stations 1 through 5; 4) and the installation of a sub-drain system on the pedestrian bridge near Rancho Carrillo Park. These projects are consistent with the Land Use Element, Growth Management & Public Facilities Goal A. I, A City which ensures the timely pr9vision of adequate public facilities and services to preserve the quality of life of residents; Goal A.2, A City which maintains a system of public facilities adequate for the projected population; Land Use Element, Environmental Goal A.I, A City which protects and conserves natural resources, fragile ecological areas, unique natural assets and historically significant features of the community. In addition, Public Safety Element, Flood Hazards, Goal A, to minimize injury, loss of life, and damage to property resulting from the occurrence of floods. Streets Projects There are five new street projects being proposed this year. These projects are: 1) slope stabilization on a landslide-prone site on Camino Hills Drive near the intersection of Jackspar Drive; 2) an investigative study for future roadway realignment alternatives for Carlsbad Boulevard between Manzano Drive and La Costa Avenue; 3) constructing an eastbound right tum lane on eastbound Palomar Airport Road at the intersection to southbound Paseo del Norte; 4) constructing an eastbound left tum lane on Palomar Airport Road at the intersection to northbound Paseo del Norte; and 5) constructing dedicated right tum lanes on the westbound, southbound and northbound legs of the intersection of Palomar Airport Road and College Boulevard. These projects are consistent with Circulation Element, Streets and Traffic Control, Goal A.2, A City with an adequate circulation infrastructure to serve the projected population; Goal A.4, A City with properly maintained, smooth functioning and safe traffic control systems; Objective B.1, To provide an adequate circulation infrastructure concurrent with or prior to the actual demand for such facilities; and Objective B.2, which requires streets to be designed for safe and efficient movement of people, goods and services within the city. CMWD Projects: Water Projects There are four new water projects being proposed this year by the CMWD. These projects are: 1) a study to establish priorities for a comprehensive reservoir repair and maintenance program; 2) constructing a high pressure reducing station within the City right-of-way and closing certain valves within Kelly Ranch Village "E" development, or installing a pipeline on Cannon Road and El Camino Real in order to connect to the 25 5 water pressure zone to reduce the water pressure below the 125 psi standard; 3) converting an existing 12-inch potable water pipeli_ne, which crosses under I-5 between Avenida Encinas and Camino de las Ondas, to a recycled water pipeline; and 4) constructing a recycled water transmission line from the Carlsbad Water Recycling Facility (CWRF), located on A venida Encinas, to Chinquapin A venue to provide recycled water to the Village area, parks, medians, and the Coastal Rail Trail. These projects are consistent with Land Use Element, Growth Management, and Public Facilities Goal A.I, which requires timely provision of adequate public facilities and services; and Goal A.2, which requires maintenance of a system of public facilities adequate for the projected population. • • PCD/GPC 09-01-2009-2010 CAPITAL IMPROVEMENT PROGRAM April 15, 2009 Pa e4 Summary Staff has concluded that all of this year's CIP projects are consistent with the City's General Plan. V. ENVIRONMENTAL REVIEW For purposes of compliance with the California Environmental Quality Act (CEQA), the FY 2009-2010 CIP Budget's new projects have been analyzed for potential adverse impacts on the environment. Environmental analysis of the CIP is complex in that adoption of the budget occurs with a single action, but that action approves a lengthy list of activities which may vary widely in terms of timing, magnitude, and potential impacts. The activities range from purely administrative actions, such as studies, to major public works projects, such as constructing new tum lanes and recycled water transmission lines. The new funding requests listed in the 2009- 2010 CIP Budget fall into general categories (discussed below) for purposes of CEQA analysis, depending upon the nature of the activity being funded. (Exhibit "A," attached, lists each of the CIP project activities and indicates the environmental status of the project under CEQA.). If funding requests in the CIP do not meet the definition of a "project" for purposes of CEQA, these projects are noted as "not a project" in the Exhibit "A" table. Other projects are exempt categorically or statutorily, or are exempt because it can be seen with certainty that there is no possibility that the activity will have a significant effect on the environment. These types of projects or activities are not subject to any further CEQA review. These projects are listed in Exhibit "A" as "exempt" with a notation as to the section of the CEQA Guidelines which applies. The applicable sections of CEQA Guidelines are summarized below: a. Section 15301 categorically exempts projects or activities that consist of the operation, repair, maintenance, or minor alteration of existing structures, facilities, mechanical equipment, or topographic features, involving negligible or no expansion of use beyond that existing at the time of the lead agency's decision. b. Section 15302 categorically exempts certain projects or activities which involve the replacement or reconstruction of existing facilities and will have substantially the same purpose and capacity of the facility or structure replaced or reconstructed. c. Section 15303 categorically exempts certain projects which involve the construction and location of a limited number of new, small, facilities or structures where only minor modification is made to the exterior of the structure. There is another, special class of statutorily exempt projects. Those in this category are being proposed for preliminary design work and related studies or the preliminary work has already begun. For the projects in this category, there is insufficient information at this time to determine whether the project will result in any significant environmental impacts until some preliminary design work has been completed. An essential part of the design process for these projects will be collecting and analyzing the information needed to assess environmental impacts. It is PCD/GPC 09-01 -2009-201 IAPITAL IMPROVEMENT PROGRA' April 15, 2009 Pae 5 important to note that the projects in this group are not being approved for construction at this time, and no discretionary permits are being approved, even though funds for future construction may be shown in the budget. Adoption of the CIP will not have a legally binding effect on later activities with respect to the projects in Category II because approval to construct a project in this category cannot occur until environmental review has been completed and a document certified. Certification of the environmental document for each project in this category will occur concurrent with or prior to approval to construct the project. For purposes of adoption of the CIP, the action to fund design work is, therefore, statutorily exempt from CEQA because preliminary design for these projects constitutes a "feasibility or planning study" as provided in Section 15262 of the CEQA Guidelines. However, that section also requires that feasibility and planning studies must still include consideration of environmental factors. Given that these activities currently involve feasibility or planning study only, the potential environmental impacts have been considered to the extent possible. These project activities are not being approved beyond the study phase at this time. Prior to final City Council action on these projects, CEQA review must be completed. These projects are listed in Exhibit "A" as "exempt per 15262." Finally, some CIP projects may require additional CEQA review. In any case, as discretionary permits are requested, each of these projects will be required to comply with all appropriate CEQA requirements. The table in Exhibit "A" identifies the status of these projects as realistically as possible. In conclusion, the proposed FY 2009-2010 CIP Budget as described in this report is fully in compliance with CEQA for all three types of projects. VI. SUMMARY In summary, pursuant to California Government Code Sections 65401 and 65402, staff recommends that the Planning Commission find that the proposed FY 2009-2010 Capital Improvements Program Budget is consistent with the City's General Plan. ATTACHMENTS: 1. Planning Commission Resolution No. 6554 (PCD/GPC) 2. Exhibit "A" (CIP Projects by Project Type with Environmental Status) 3. Exhibit "B" (CIP Project Descriptions) • • Exhibit "A" April 15, 2009 FY 2009-2010 CAPITAL IMPROVEMENT PROGRAM PROJECTS (BY PROJECT TYPE) WITH ENVIRONMENTAL STATUS The following table contains all of the new capital projects included in the 2009-2010 Capital Improvement Program Update. The projects are grouped by project type (left-hand column). The second column identifies the project by name. The third column indicates the environmental status of the project (as discussed in the "Environmental Review" section of the staff report). Details of the project description (under the project name) are contained in Exhibit B "Technical Appendix." Projects which do not meet the definition of a "project" under CEQA are identified in the right- hand column as "not a project." No future CEQA review will be required for those projects. Other projects are categorically or statutorily exempt for a variety of reasons. They may fall under the General Rule exemption or they may be categorically or statutorily exempt. There are several exemption categories that _may apply to the various projects ( e.g., maintenance and/or repair of existing facilities, minor expansion of existing facilities, etc.). These projects are indicated as "exempt per" the specific CEQA section that applies to that project. Some CIP new funding requests may fall within a special exempt category: those projects which are at this time statutorily exempt pursuant to Section 15262 of CEQA as preliminary design, planning, or feasibility studies. These projects are still in the conceptual design or planning phase and will ultimately: 1) return to either the Planning Commission or City Council for further discretionary action where additional environmental documentation will be certified; or 2) undergo additional environmental review and documentation if the results of the preliminary design/study indicates it would be necessary. These projects are indicated as "exempt per 15262." Other CIP projects may require CEQA review. Some of these projects are currently undergoing review individually or as part of a larger project. Others have not yet undergone the necessary review and will have to do so when the project has been better defined. Still others may have already been reviewed pursuant to CEQA and have been included in previously certified/adopted CEQA documents (prior compliance). In any case, as discretionary permits are requested, each of these projects will be required to comply with all appropriate CEQA requirements. 1 NEW CAPITAL IMP,VEMENT PROGRAM PROJECT!Y TYPE WITH ENVIRONMENTAL STATUS PROJECT TYPE PROJECT NAME ENVIRONMENTAL STATUS City Pro.iects: Drainage Park Drive Drainage and Street Improvements Potential ND/MND Marca Place Drainage Improvements Exempt per 15262 Fire Station 1-5 Drainage Systems Exempt per 15301 Rancho Carrillo Water Seepage Potential ND/MND Streets Camino Hills Drive and Jackspar Drive Slope Exempt per 15262 Stabilization Carlsbad Boulevard Realignment Study, Phase 2 Exempt per 15262 Palomar Airport Road and Paseo Del Norte Right Exempt per 15301 Tum Lane Palomar Airport Road and Paseo Del Norte Left Tum Exempt per 15301 Lane Palomar Airport Road and College Boulevard Right Potential ND/MND Tum Lanes CMWD Pro_jects: Water Reservoir Repair/Maintenance Program Study Exempt per 15262 Kelly Ranch Domestic Water Pressure Reduction Exempt per 15302 I-5 Crossing: Avenida Encinas to Camino del las Exempt per 15301 Ondas Carlsbad Water Recycling Facility (CWRF) to Exempt per 15262 Chinquapin A venue Recycled Water Transmission Main 2 • • FY 2009-2010 CAPITAL IMPROVEMENT PROGRAM PROJECT DESCRIPTIONS Exhibit "B" April 15, 2009 CAPITAL PROJECT DESCRIPTION DRAINAGE_pRQJECTS -PARK DRIVE DRAINAGE AND STREET IMPROVEMENTS PROJECT NAME PROJECT NO. PROJECT LOCATION_MAP: Park Drive Drainage And Street Improvements.Doc PROJECT LOCATION: Park Drive between Bayshore Drive and the residential driveway at 4650 Park Drive. PROJECT DESCRIPTION: This phase of the project includes the preparation of a Preliminary Desig Study. The Preliminary Design Study will include geotechnical investigation and analysis, biological report, preliminary hydrology and hydraulic analysis, and slope and existing utility analysis. Three alternatives will be developed to mitigate the drainage and erosion issue. The results of the Preliminary Design Analysis will determine the appropriate improvements to construct. f_ROJ_EC_T_NEED: The slope easterly of Park Drive has a history of erosion and drainage issues. Several attempts to prevent the erosion and control the drainage have proven successful for a limited time. The groundwater is seeping through the cracks in the retaining wall causing extensive corrosion to the retaining wall. Complaints have been received regarding the erosion, sedimentation, algae and safety issues. FINANCING: Puraose Study Environmental Design Property Acquisition Administration Total Cost= Estimated. Cost $55,500 $45,500 $35,500 $2,000 $17,000 $155,500 Funding Sol.If.Ce GCC GCC GCC GCC GCC PROJE_CT LOCATION MAP: CAPITAL PROJECT DESCRIPTION DRAINAGE PROJECT_S -MARCA PLACE DRAINAGE IMPROVEMENTS PROJECT NAME PROJECT LOCATION: Marca Place PROJECT DESCRIPTION: PROJECT NO. Subsurface conditions require an investigation of geotechnical conditions under Marca Place and an engineering analysis to determine the appropriat, remediation measures for the road surface. After the analysis and design o' the recommended remediation measures, funds for construction will be requested. PROJECT NEED: Residents have repeatedly contacted the Construction Management Division and Streets Maintenance Division requesting maintenance of the street. Marca Place has been repaired multiple times. Fl_N_ANCING: Pur.12.ose Study Design Property Acquisition Administration Total Cost= Estimated Cost $15,500 $35,500 $2,000 $12,000 $65,000 Eundin.9. S0_urce GCC GCC GCC GCC Marca Place Drainage Improvements.Doc CAPITAL PROJECT DESCRIPTION DRAINAGE PROJECTS-FIRE STATIONS 1-5 DRAINAGE IMPROVEMENTS PROJECT NAME PROJECT NO. PROJECT LOCATION MAP: PROJECT LOCATION: At Fire Stations 1, 2, 3, 4 and 5. PROJECT DESCRIPTION: Under the City's NPDES Permit, fire apparatus washing runoff is prohibited from entering the City's storm drain system. In an effort to comply with this requirement, Fire Stations 1 through 5 will be retrofit with the construction of permanent Best Management Practices (BMP's) to treat the wash water and control the runoff before entering the storm drain system. PROJECT NEED: Fire Station 6 is the only facility to have a permanent runoff collection and treatment system. Fire Stations 1 through 5 currently use a vacuum system which collects the wash water. The vacuum system is viewed as a temporary solution to comply with the permit until a permanent BMP solution is installed. FINANCING: PurQOSe Design Construction Administration Total Cost= Estimated Cost $25,000 $145,000 $55,000 $225,000 Funding Source GCC GCC GCC PROJECT LOCATION MAP: Rancho Carrillo Seepage.Doc CAPITAL PROJECT DESCRIPTION DRAINAGE PROJECTS -RANCHO CARRILLO WATER SEEPAGE PROJECT NAME PROJECT LOCATIO_N: PROJECT NO. Adjacent to the south abutment of the pedestrian bridge near Rancho Carrillo. PROJECT DES_CRIPTION: Water is seeping through the south abutment of the pedestrian bridge and through the earth slope around the bridge abutment. A sub-drain syste needs to be installed to convey water away from the bridge abutment an adjacent sewer manhole at the south end of the bridge. PROJECT NEED: The project is needed to prevent erosion around the bridge abutment which would undermine the structural support of the bridge. The sub-drain is also needed to convey water away from the sewer manhole at the end of the bridge to prevent water intrusion into the manhole. FINANCING: Pureose Design Construction Ad min/Inspection Total Cost= Estirnated Cost $8,000 $40,000 $5,000 $53,000 Funding Source GCC GCC GCC CAPITAL PROJECT DESCRIPTION CIRCULATION SYSTEM STREET PROJECTS -CAMINO HILLS DRIVE AND JACKSPAR DRIVE SLOPE STABALIZATION PROJECT NO. PROJECT LOCATION MAP: Camino Hills and Jackspar Slope Stabilization.doc PROJECT NAME PROJECT LOCATION: The project is located on Camino Hills Drive on the sloped area north of the Camino Hills Mobile Home subdivision near the intersection of Jackspar Drive. PROJECT DESCRIPTION: The project is located on a landslide prone site. A buttress system was· constructed during the earthwork for the mobile home subdivision to help stabilize the slope. However, there is gradual movement of the slope that is damaging the adjacent street. The project will consist of geotechnical investigations, development of alternative approaches to a solution, and the preparation of design plans. The construction costs for the recommended solution will be presented and considered in a future Capital Improvement Program cycle. It is anticipated the slope stability improvement will consist of installing vertical shear pins (steel I-beams) to prevent failure of the shear plane. The shear pins will be spaced approximately 6 feet apart and will be located below grade. PROJECT NEED: The project is needed to prevent a landslide that could potentially damage the city's infrastructure. FINANCING: PurQose Study Design Total Cost= Estimated Cost $25,000 $62,000 $87,000 Funding Source GCC GCC CAPITAL PROJECT DESCRIPTION CIRCULATION SYSTEM STREET PROJECTS -CARLSBAD BLVD REALIGNMENT STUDY PHASE 2 PROJECT NO. PROJECT LOCATION MAP: Carlsbad Blvd Realignment Phase 2.doc PROJECT NAME PROJECT LOCATION: Carlsbad Boulevard between Manzano Drive and La Costa Avenue. PROJECT DESCRIPTION: Conduct an investigative study of future roadway realignment alternatives. infrastructure needs, land uses, commercial land development options, publi park and coastal access opportunities, and related long term coastal planning issues, constraints, and processes will be analyzed. The second phase study of a multi-year project such as this would not require permits or environmental review at this time. PROJECT NEED: An initial feasibility/realignment study was completed in 2000. The next phase of this project will prepare a study to analyze more detailed alternatives and create options and cost estimates for the realignment of Carlsba"d Blvd from Manzano Drive to La Costa Avenue. FINANCING: Pureose Study Administration Total Cost= Estimated Cost $200,000 $50,000 $250,000 Funding Source GCC GCC CAPITAL PROJECT DESCRIPTION CIRCULATION SYSTEM STREET PROJECTS -PALOMAR AIRPORT ROAD AND PASEO DEL NORTE RIGHT TURN LANE PROJECT NO. PROJECT LOCATIO_NMAP: PAR and PON Right Tum Lane.doc PROJECT NAME , ~t ·.:. ·:~. ~ • ' ~~~?."' W • •J i ,,.,•.d,!l{ 1 t.;~ ~ 1~1" :~~ .. ,. l • • ' . l·~;'.S 1:\ ;4:rf':'~ i, ~~I\\~ ,,r-.Jl&...,41~ •11-1.";_, .. • • ' ;~: --,1f·; PROJECT LOCATION: Eastbound Palomar Airport Road to southbound Paseo Del Norte. PROJECT DESCRIPTIQN: Construct an eastbound right turn lane on eastbound Palomar Airport Road a the intersection to southbound Paseo del Norte. The project would includ construction of a 250 foot long lane in addition to a 90 foot long transition. Traffic signal modifications will also be required. PROJECT NEED: The widening will . provide for the construction of a right turn lane which will enable this leg of the intersection to operate at an acceptable level of service in the buildout condition. This project was identified as part of the environmental review of the proposed Legoland Hotel project. FINANCING: Pur,eose Design Construction Administration Total Cost= Estimated Cost $43,312 $433,122 $60,637 $537,071 Funding Source Developer/GCC Developer/GCC Developer/GCC CAPITAL PROJECT DESCRIPTION CIRCULATION SYSTEM STREET PROJECTS -PALOMAR AIRPORT ROAD AND PASEO DEL NORTE LEFT TURN LANE PROJECT NO. PROJECT LOCATION MAP: PAR and PON Left Tum Lane.doc PROJECT NAME PROJECT LOCATION: Eastbound Palomar Airport Road to northbound Paseo Del Norte. PROJECT DESCRIPTION: Construct an eastbound left turn lane on Palomar Airport Road at th intersection of Paseo del Norte. The project would include construction of a 60' foot long lane in addition to a 97 foot long transition. PROJECT_NEE_ll: The widening will accommodate a longer left turn lane which will enable this leg of the intersection to operate at an acceptable level of service in the buildout condition. Project MS 07-02 is conditioned to pay a 13% fair share for the construction of this project. FJNANCING: Pure,ose Design Construction Administration Total Cost= Estimated Cost $15,753 $157,530 $22,054 $195,337 Fundiaa.§s,urce Developer/GCC Developer/GCC Developer/GCC CAPITAL PROJECT DESCRIPTION NONE CIRCULATION SYSTEM STREET PROJECTS -PALOMAR AIRPORT ROAD AND COLLEGE BOULEVARD PROJECT NAME PROJECT NO. PROJECT LOCATION MAP: PAR and College Intersection.doc PROJECT LOCATION: At the intersection of the Palomar Airport Road and College Boulevard. PROJECT DESCRIPTION: Construct dedicated right turn lanes on the WB, SB and NB legs of the intersection. Project includes construction of storm drain improvements within the southbound lane and an inlet on the northeast corner to collect runoff fro hole #7 of the Crossings Golf Course. Project work may also require .reconstruction of median improvements, striping and signal modifications, and acquisition of necessary right-of-way. PROJECT NEED: Required to meet Growth Management Standards. FINANCING: Purpose Estimated Cost Funding Source Design/Studies $165,000 TIF/GCC Environmental $27,500 TIF/GCC Construction $645,000 TIF/GCC Total Cost= $837,500 CAPITAL PROJECT DESCRIPTION NONE WATER DISTRIBUTION SYSTEM -RESERVOIR REPAIR/MAINTENANCE PROGRAM STUDY PROJECT NAME PROJECT NO. PROJECT LOCATION MAP: Reservoir Repair-Maintenance Program Study.Doc PROJECT_LOCATION: Steel Reservoirs: Buena Vista, C, D-1, D-2, E, Elm, Ellery, La Cost~ and Skyline. PSC Reservoirs: Santa Fe 11, La Costa High and B (TAP) PROJECT DESCRIPTION: Conduct a study to establish priorities for a comprehensive reservoir repair an maintenance program. Evaluate existing available data from construction drawings, diving and cleaning activities, and inspection reports. Recommend to most cost effective program that meets all standards, requirements and regulations. PROJECT NEED: Most of the steel reservoirs in the CMWD are approaching their estimated operational lifespan. It is anticipated the recommended maintenance program activities will promote tank longevity, enhance water quality, and satisfy California Department of Public Health (CDPH) reservoir requirements. FINANCIN_G: Pur2ose Study Administration Total Cost= Estimated Cost $100,000 $25,000 $125,000 Funding Source Water Replacement Water Replacement CAPITAL PROJECT DESCRIPTION NONE WATER DISTRIBUTION SYSTEM -KELLY RANCH DOMESTIC WATER PRESSURE REDUCTION PROJECT NAME PROJECT NO. PROJECT LOCATI_ON MAP: Kelly Ranch High PR Station.Doc PROJECT LOCATION:: Within Kelly Ranch Village "E" development. PROJECT.DE.SCRIPTION: Property owners in the Kelly Range Village "E" development are experiencing water pressure beyond the 125 psi City of Carlsbad Engineering Standard. The. project includes constructing a pressure reducing station within the city right-a~ way and closing certain valves to decrease the pressure below the 125 psi standard. An alternative pressure reducing option would be to install a pipeline on Cannon Road and El Camino Real in order to connect to the 255 water pressure zone. PROJECT NEED: The City's Operation Department has received numerous complaints of high water pressure in the area and has indicated the high pressure has caused failures of the fittings and subsequent flooding of the homes experiencing high water pressure. FIN_ANCING: Purg_ose Design Construction Administration Total Cost= Estimat~d Cost $40,000 $280,000 $35,000 $355,000 Funding Source Water Replacement Water Replacement Water Replacement CAPITAL PROJECT DESCRIPTION NONE RECYCLED WATER PROJECTS -1-5 CROSSING AVENIDA ENCINAS TO CAMINO DE LAS ONDAS PROJECT NAME PROJECT NO. PROJECT LOCATION_M_AP: 1-5 Crossing Ave Encinas To Camino Del Las Ondas.Doc PROJECT LOCATION: Under 1-5 between Avenida Encinas and Camino de las Ondas. PROJECT DES_CRIPTION: Convert an existing 12-inch potable water pipeline crossing under 1-5 to, recycled water. Two connection points would be required, west of 1-5 m Avenida Encinas and east of 1-5 on Camino de las Ondas. PROJECT NEE_D: Converting the pipeline to recycled water would provide an increase in capacity from the water reclamation plant to the service area east of 1-5. Currently the only recycled water pipeline crossing 1-5 from the reclamation plant is along Poinsettia Lane. This additional 1-5 crossing would increase reliability with a second crossing. FINANCING: Puraose Design Construction Administration Total Cost= Estimated Cost $13,200 $110,000 $11,000 $134,200 Funding Source Water Replacement Water Replacement Water Replacement CAPITAL PROJECT DESCRIPTION NONE RECYCLED WATER PROJECTS -CARLSBAD WATER RECYCLING FACILITY (CWRF) TO CHINQUAPIN AVENUE RECYCLED WATER TRANSMISSION MAIN PROJECT NO. PROJECT LOCATION MAP: CWRF To Chinquapin Recycle Water Transmission Main.Doc PROJECT NAME PROJECT LOCATION: Located in Avenida Encinas from the Carlsbad Water Recycling Facility to Cannon Road and continuing northerly to Chinquapin Avenue along a corridor east and parallel to the NCTD right-of-way. PROJECT DESCRIPTION: Prepare design plans for a recycled water transmission line in the existing railroad right-of-way connecting the Carlsbad Water Recycling Facility to the Recycle Water Phase Ill area. The purpose is to improve system hydraulics by connecting to an existing transmission line in Cannon Road to the Village area. The line will be installed with the Vista/Carlsbad Sewer Project to minimize construction costs. PROJECT NEED: The project will improve the recycled water system hydraulics and water quality with the interconnection to the current system. The project will provide recycled water to the Village area, parks, medians and the Coastal Rail Trail. FINANCING: Pure.ose Design Administration Total Cost= Estimated Cost $220,000 $30,000 $250,000 Funding Source Water Replacement Water Replacement