BACKGROUND:
DATA:
The City Council has directed staff to conduct a series of presentations, open houses
and public meetings to gather input on Streetscape Phase V. These meetings have
been held in January 1993 and also are scheduled for February 1993. Staff will
report the results of the meetings to the City Council in late February.
Streetscape Phase V is the last phase of a comprehensive street enhancement
program in the Redevelopment area that started in 1988. The project on Carlsbad
Village Drive has been designed to make the street an inviting gateway to downtown
Carlsbad.
Key features of Streetscape Phase V will include raised medians, new traffic signals
at the intersection of Jefferson Street and Roosevelt Street, signal upgrades at
Harding Street and State Street, a traffic signal interconnect system, gas-lamp style
lighting, new curb and gutter, sidewalk improvements, attractive landscaping, some
decorative cross-walks and a storm drainage system. It is estimated that these
improvements will cost $2.5 million with funding coming from a $12 million bond
allocation issued by the Redevelopment Agency in 1988. By law, this money must be
used in or to benefit the Redevelopment Area.
A construction start of September 1993 or May 1994 is anticipated. Input from
property owners, merchants, residents and citizens is being solicited to help determine
the preferred construction start date. Construction of the project is expected to take
eight months.
Due to the complicated nature of the construction and the need to stage various
phases of construction, staff is proposing a detour to Grand Avenue for westbound
Carlsbad Village Drive traffic at Harding Street. One lane eastbound only would be
permitted from State Street to Harding Street. This detour would be in effect for the
first 12 weeks of the project. Associated with the detour would be re-striping of State
Street between Carlsbad Village Drive and Grand Avenue to allow southbound traffic
TRAFFIC SAFE1Y COMMISSION
Staff Report
COMMISSION MEETING OF: February 1, 1993
(Continued)
ITEM NO. 6B
only. In Stage 1 this segment would be a temporary one-way street during the first
12 weeks of the project. In Stages 2 and 3 one lane of traffic in each direction on
Carlsbad Village Drive will be permitted.
RECOMMENDATION:
Information report only. No action is required by the Traffic Safety Commission.
NECESSARY CI1Y COUNCIL ACTION:
The City Council will provide direction to staff for implementing Streetscape Phase
V after public input has been received.