HomeMy WebLinkAboutGPA 15-02; OCEAN VIEW POINT; UPDATED GEOTECHNICAL INVESTIGATION REPORT; 2018-08-07w
Cl IR.ISTIAN WI IEELER.
[NC.IN[[~INC
UPDATED GEOTECHNICAL INVESTIGATION REPORT
CARLSBAD TRACT CT-15-07
TWAIN A VENUE
CARLSBAD. CALIFORNIA
SUBMITTED TO
GAYLHYNEK
PO BOX401
GILROY. CALIFORNIA 95021-0451
SUBMITTED BY
CHRISTIAN WHEELER ENGINEERING
3980 HOME A VENUE
SAN DIEGO, CALIFORNIA 92105
AUG 1 6 2018
CITY OF CARLSBAD
PLANNING DIVl~!OM
3980 !!omc .\venue• ~an D,~go, C-\ ')2[05 • 619-350-1"'00 t f-i.-\X 619-.1.'i0-1 7 01
TABLE OF CONTENTS
PAGE
Introduction and Project Description ......... . ·•·•••••••••••••• .. •••••• ..................... 1
Project Scope ....... . •••••••••••••••••••••••••••••••••••••••••••••••••••••• .. 2
Findings ............... . . .................................................................... 2
Site Description .. ..2
General Geology and Subsurface Conditions ....................................... . . ..... 3
Geologic Setting and Soil Description ...... .
Topsoil ....
Subsoil
Slopewash ..... .
Old Paralic Deposits
Santiago Formation.
Goundwater ....
Conclusions ........................................... .
Recommendations .......................... .
Grading and Earthwork
General ........ .
Pre-Grade Meeting ..................... .
Observation of Grading ................ .
Clearing and Grubbing ................. .
Site Preparation
Transition Building Pads .............. .
Select Grading.
Cut And Fill Slope Construction .....
Excavation Characteristics .......... .
Processing of Fill Areas ................. .
..3
.3
.. 3
. ...... 3
.. 3
. .. .4
. ................ 4
. ............................................................................. 5
. ...... 6
•••••••••••••••••••••••••••••••••••••••••••••••••••••••••••••• .. 6
. .............................................................. 6
. .... 6
. .... 6
. .... 6
....... .7
. . .7
•••••••••••••••••••••••••••••••••••••• ................. 7
. .................. 7
. .. 8
Compaction and Method of Filling ........................................ .
. .... 8
. ................ 8
Surface Drainage ..................... .
Grading Plan Review ................................ .
Slope Stability
General .......................................... .
Erosion Control ................... .
Foundations
General
Footing Dimensions ......................... .
Bearing Capacity
Foundation Reinforcement .... .
Post-Tensioned Foundations .. .
Lateral Load Resistance ........ .
Settlement Characteristics ...... .
. ............ 8
. ...... 9
........... 9
··············· .................................................................. 9
. ................ 9
................... 10
.................. 10
. ..... 10
............ 10
. ................. 11
. .................... 11
. ........................... 11
. ......................... 12
Expansive Characteristics......................................... . ................. 12
Foundation Excavation Observation .......... 12
Foundation Plan Revtew .................................................................................................................................... 12
Soluble Sulfates ......... . ............................................................................................. 12
Seismic Design Factors .................................... .
On-Grade Slab .
General ............................... .
Interior Floor Slab
Under-Slab Vapor Retarders ............................... .
Exterior Concrete Flatwork ..
Swimming Pools .....
. ..................... 13
. .............. 13
••••••••••••••••••••••••••••••••••• 13
.............. 13
..14
. ... 14
, .... 15
CWE 2180124.02
Carlsbad Tract CT-15-07
Twain Avenue, Carlsbad, California
Masonry Earth Retaining Walls
Foundations
..................... 15
........................................................... 15
Passive Pressure ................................................................................................................................................... 15
Active Pressures ................................................................................................................................................... 15
Waterproofing and Wall Drainage Systems........................... . ................. 16
Backfill.............. . ................................................................... 16
Limitations .......................................................................................... . ...................................................................... 16
Review, Observation and Testing .. . . .... 16
Uniformity of Conditions ................................ . . ....... 16
Change m Scope .
Time Limitations
Professional Standard
Client's Responsibility
FIGURES
Figure 1
PLATES
Plate 1
Plate 2
Plate 3
TABLES
Table I
Table II
APPENDICES
Appendix A
Appendix B
Appendix C
ATTACHMENTS
Site Vicinity Map
Site Plan & Geotechnical Map
Fill Over Natural Slope Detail
Retaining Wall Subdrain Detail
Post-Tensioned Foundations
Seismic Design Factors
. .... 17
.. 17
••·••··············· 17
••••••••••••••• 18
Data From CWE 201.116 Geotechnical Report
References
Recommended Grading Specifications -General Provisions
CWE 2180124.02
Carlsbad Tract CT-15-07
Twain Avenue, Carlsbad, California
w
CHRISTIAN WHEELER
[NGIN[[RING
UPDATED GEOTECHNICAL INVESTIGATION REPORT
CARLSBAD TRACT CT-15-07
TWAIN A VENUE
CARLSBAD, CALIFORNIA
INTRODUCTION AND PROJECT DESCRIPTION
This report presents an updated geotechnical report for the subject residential subdivision and
associated improvements to be developed at the southern end of Twain Avenue, in the city of
Carlsbad, California. Figure Number 1, presented on the following page, provides a vicinity map
showing the location of the project.
It is our understanding that the subject project will consist of a 13-lot residential subdivision with
associated improvements, including an access street. It is anticipated that the structures will be one
and/or two stories high, and of wood-frame construction. Shallow foundations and conventional
concrete slab-on-grade floor systems are anticipated. However, post-tensioned foundations may be
utilized. Based on the available plans, grading will consist of cuts and fills of up to about 10 feet
and 16 feet in depth, respectively. Proposed cut and fill slopes will be graded at a 2:1 (horizontal to
vertical) or flatter inclination, and extend to a maximum height of about 10 feet and 31 feet,
respectively. Bio-filtration basins are proposed for each lot.
To aid in the preparation of this report, we were provided with a set of grading plans prepared by
Landmark Consulting, plot date September 6, 2017. A copy of the grading plan has been used as the
base for our Site Plan and Geotechnical Map, and 1s included herein as Plate No. 1. In addition, we
have reviewed our "Updated Geotechnical Investigation Report, Kirgis Subdivision, Carlsbad Tract
02-06", dated October 10, 2013 (CWE 2110148.0lR). Appropriate data from this geotechnical report
is presented in Appendix A. This data was used in the preparation of this updated report.
3980 !Tome .-\,·enue • ~an Diego, C.\ 92105 • 619-550-1700 • F.\X 619-SS0-1701
CWE 2180124.02 August 7, 2018 Page No. 2
This report has been prepared for the exclusive use of Gay! Hynek and their design consultants for
specific application to the project described herein. Should the project be changed in any way, the
modified plans should be submitted to Christian Wheeler Engineering for review to determine their
conformance with our recommendations and to determine whether any additional subsurface
investigation, laboratory testing and/ or recommendations are necessary. Our professional services
have been performed, our findings obtained and our recommendations prepared in accordance with
generally accepted engineering principles and practices. This warranty is in lieu of all other
warranties, express or implied.
PROJECT SCOPE
The scope of our services included a site reconnaissance, a review of our previous geotechnical
reports, and a limited review of the current project plans. The update report includes providing
any additional geotechnical recommendations that, in our opinion, are necessary, including
updated seismic design parameters for the proposed project in accordance with the 2016 edition of
the California Building Code (CBC).
FINDINGS
SITE DESCRIPTION
The subject site is a nearly rectangular-shaped parcel of land approximately 21.9 acres in area,
located at the southern end of Twain Avenue, in the City of Carlsbad, California. The site is
further identified as Assessor's Parcel Number 212-010-03. Undeveloped canyon lands bound the
site to the west, south, and east, while a residemiaJ subdivision bounds the site to the north.
In general, a gently sloping mesa top that generally descends to the south characterizes the
uppermost, northern portion of the site. Moderately steep canyon lands descend to south, east, and
west from the uppermost, mesa top area of the site. The existing on-site elevations within those
portions of the site to receive improvements range from about 330 feet in the northern portion of
the site to about 270 feet in the southwestern portion of the site. The site appears to remain
essentially unchanged from the time that we performed our previous observations.
CWE 2180124.02 August 7, 2018 Page No. 3
GENERAL GEOLOGY AND SUBSURFACE CONDITIONS
GEOLOGIC SETTING AND SOIL DESCRIPTION: The subject site is located in the Coastal
Plains Physiographic Province of San Diego County and is underlain by a relatively minor amount of
native residuum, Quaternary-age old paralic deposits, and Cretaceous-age deposits of the Santiago
Formation. The following provides a discussion, based on our subsurface explorations and our past
experience with nearby projects, of the soil types expeL"ted to be encountered beneath the property.
TOPSOIL: A topsoil layer was encountered at the surface in most of our exploratory test
trenches. The topsoil layer has an approximate thickness of 1 foot. The topsoil material
generally consists of dark brown, moist, loose, silty sand (SM). It should be noted that topsoil
was not encountered in our test trench T-9, excavated in the northwest portion of the site.
These deposits were judged to have a low potential for expansion (EI between 21 and 50).
SUBSOIL: A subsoil layer was encountered within our exploratory test trenches excavated in
the northern, eastern, and southeastern portions of the proposed improvement area. The
subsoil was generally noted below the topsoil layer, but was also noted at the surface within
the northeast portion of the site. The thickness of the subsoil layer ranged from
approximately 1 foot to 1 ½ feet. The subsoil was noted to primarily consist of brown, moist,
loose to medium dense, clayey sand (SC). These deposits were judged to have a moderate
potential for expansion (EI between 51 and 90).
SLOPEWASH (Qsw): A layer of slopewash material was noted below the topsoil layer
within our exploratory test trenches excavated in the southwest portion of the proposed
improvement area. The layer had an approximate thickness ranging from 1 ½ to 2 feet. The
materials within the slopewash layer generally consisted of dark brown, wet, soft, sandy clay
with a slight amount of gravel and cobble (CL). These deposits were judged to have a
moderate potential for expansion (EI between 51and 90).
OLD PARALIC DEPOSITS (Qop): Underlying the topsoil and subsoil layers, a layer of
old paralic deposits mantles the northern, eastern, and southeastern portions of the proposed
improvement area. These deposits were identified in the referenced geotechnical report as
•
CWE 2180124.02 August 7, 2018 Page No. 4
terrace deposits. The approximate location of the contact between the old paralic deposits and
underlying Santiago Formation is shown on Plate No. 1. This contact typically occurs at an
elevation of 310 feet. Generally, the old paralic deposits are thickest within the upper areas in
the eastern portion of the improvement area, and thin towards the lower portions. The old
paralic deposits generally consisted of orangish-brown, moist, dense to very dense, clayey sand
with some gravel and cobble (SC). The old paralic deposits were found to possess a very low
expansion potential (EI=6).
SANTIAGO FORMATION (Tsa): The site is ultimately underlain by Tertiary-age deposits
of the Santiago Formation. The formational materials were noted below the terrace deposits
in the northern, eastern, and southeastern portions of the proposed improvement area and
below the topsoil, subsoil, and slopewash layers in the south-southwestern portions. The
materials of the Santiago Formation mainly consisted of light brown to light orangish-brown,
moist, dense to very dense, clayey sand (SC) and light brown to white, silty sand (SM). The
formational materials also consisted of lesser amounts of light olive brown, moist, very stiff to
hard, sandy day (CL). The sandy portions of the Santiago Formation were judged to have a
low expansion potential (EI between 21 and 50). The clayey portions of the Santiago
Formation, which appear to comprise a relatively small amount of the formational material,
were found to possess a medium expansion potential (El=85).
GROUNDWATER: No groundwater or seepage was encountered in any of the areas of the site
investigated. However, it should be recognized that minor groundwater seepage problems may
occur after development of a site even where none were present before development. These are
usually minor phenomena and are often the result of an alteration in drainage patterns and/ or an
increase in irrigation water. Based on the permeability characteristics of the soil and the anticipated
usage and development, it is our opinion that any seepage problems which may occur will be
minor in extent. It is further our opinion that these problems can be most effectively corrected on
an individual basis if and when they occur
CWE 2180124.02 August 7, 2018 Page No. 5
CONCLUSIONS
In general, our findings indicate that the subject property is suitable for the construction of the
proposed subdivision and associated improvements, provided the recommendations provided herein
are followed. The main geotechnical conditions encountered that affect the proposed development
are potentially compressible surficial soils, expansive soils, and cut/fill transitions. These conditions
are discussed hereinafter. It should be recognized that some of the recommendations provided
hereinafter to mitigate a certain potentially adverse condition may also be applicable to another
condition.
• A relatively thin mantle of potentially compressible topsoil, subsoil, and slopewash ranging
between about 2 to 3 feet in combined thickness caps the site. Deeper compressible soils may
exist in areas of the site not investigated. These materials are considered unsuitable, in their
present condition, for the support of settlement sensitive improvements, and should be
removed and replaced as compacted fill.
• A relatively small percentage of the Santiago formation deposits encountered in our trenches
was found to be moderately expansive (EI=85). It is recommended that select grading be
performed to mitigate this condition. le should be realized that Santiago Formation deposits
are inherently highly heterogeneous, and the relative amounts of different soils exposed in
our trenches may not be representative of areas of the site not investigated. If select grading
cannot be performed due to the lack of sufficient low expansive soils, the foundation
recommendations contained in this report may have to be changed.
• Proposed grading and site preparation will result in a cut/fill transition for some of the lots.
Structures and improvements spanning cut/fill transitions may experience detrimental
differential settlements due to the different compression characteristics of native and fill soils.
In order to mitigate this condition, it is recommended that the cut portion of the lot be
undercut as described hereinafter. Undercutting the cut portions of the lots will also facilitate
future drainage, trenching and landscaping.
The general geology and geologic hazards as described in the original report remains unchanged. The
site is located in an area that is relatively free of geologic hazards that will have a significant effect on
•
CWE 2180124.02 August 7, 2018 Page No. 6
the proposed construction. The most likely geologic hazard that could affect the site is ground
shaking due to seismic activity along one of the regional active faults. However, construction in
accordance with the requirements of the 2016 edition of the California Building Code and the local
governmental agencies should provide a level of life-safety suitable for the type of development
proposed.
RECOMMENDATIONS
GRADING AND EARTHWORK
GENERAL: All grading should conform to the guidelines presented in Appendix J of the
California Building Code, the minimum requirements of the City of Carlsbad, and the
Recommended Grading Specifications and Special Provisions attached hereto, except where
specifically superseded in the text of this report.
PRE-GRADE MEEl'ING: It is recommended that a pre-grade meeting, including the owner's
representative, grading contractor and a representative from Christian Wheeler Engineering, take
place to discuss the recommendations of this report and address any issues that may affect grading
and construction operations.
OBSERVATION OF GRADING: Observation by the Geotechnical Consultant is essential during
the mass grading operation to confirm conditions anticipated by our investigation, to allow
adjustments in design criteria to reflect actual field conditions exposed, and to determine that the
grading proceeds in general accordance with the recommendations contained herein. Continuous or
periodic observation should be provided at the discretion of the Geotechnical Consultant.
CLEARING AND GRUBBING: Site preparation should begin with the removal of all existing
improvements and trash, as well as any existing vegetation from the areas of the site to be graded.
The debris resulting from this operation should be disposed of off-site. This should include all root
balls from trees, all natural brush and all significant root material.
CWE 2180124.02 August 7, 2018 Page No. 7
SITE PREPARATION: It is recommended that existing topsoil, subsoil, and slopewash
underlying proposed settlement-sensitive improvements, including all proposed fills, should be
removed in their entirety. Based on the geotechnical information available, the anticipated removal
depths range from about 2 feet to 3 feet. However, deeper removals may be needed in areas not
investigated or due to unforeseen conditions. Actual removal depths will be determined by our
representative. All excavated areas should be approved by the geotechnical engineer or his
representative prior to replacing any of the excavated soils. Where necessary to achieve planned site
grades, the removed materials may be replaced as compacted fill provided they are thoroughly mixed
as described hereinafter, and moisture conditioned prior to placement.
TRANSITION BUILDING PADS: It is recommended that old paralic deposits and formational
soils underlying the cut portion of the proposed transition lots be undercut to a minimum depth
of 4 feet below finish pad grade, or 2 feet below the bottom of footings {1 foot below retaining
wall footing keys) whichever is deepest. The undercuts should be performed in such a way that
low areas with impaired drainage are not created. Undercut areas should be backfilled with
properly compacted, low expansive fill (EI between 21 and 50}.
SELECT GRADING: Portions of the Santiago Formation were determined to possess a medium
expansive potential {El=85). Expansive soils should not be placed within 5 feet from finish pad
grade, and 20 feet from the face of fill slopes. In addition, expansive soils within 5 feet from finish
pad grade in proposed cut areas should be removed and replaced with low expansive fill {EI between
21 and 50} compacted to at least 90 percent.
CUT AND FILL SLOPE CONSTRUCTION: Cut and fill slopes may be constructed at an
inclination of 2: 1 or flatter (horizontal to vertical}. Compaction of fill slopes should be performed by
back-rolling with a sheepsfoot compactor at vertical intervals of 4 feet or less as the fill is being
placed, and track-walking the face of the slope when the slope is completed. As an alternative, the fill
slopes may be overfilled by at least 3 feet and then cut back to the compacted core at the design line
and grade. Keys should be made at the toe of fill slopes in accordance with the recommendations
presented under "Compaction and Method of Filling." A subdrain is recommended for transition fill
over cut slopes. A subdrain detail is provided in the attached Plate No. 2.
•
CWE 2180124.02 August 7, 2018 Page No. 8
EXCAVATION CHARACTERISTICS: It is anticipated that the cuts proposed in the
aforementioned grading plans may be achieved with conventional, large heavy-duty grading
equipment in good working order. However, concretions requiring special grading and handling
consideration may be encountered within the Santiago Formation. In addition, zones of very dense
deposits that are difficult to excavate with light trenching equipment may be encountered within the
Santiago Formation.
PROCESSING FILL AREAS: Prior to placing any new fill soils or constructing any new
improvements in areas that have been cleaned out to receive fill, the exposed soils should be
scarified to a depth of about 12 inches, moisture-conditioned, and compacted to at least 90 percent
relative compaction. In areas to support fill slopes, keys should be cut into the competent
supporting materials. The keys should be at least ten feet wide, and be sloped back into the hillside
at least two percent. The keys should extend at least one foot into the competent supporting
materials. A subdrain is recommended at the heel of the keyway. Where the existing ground has a
slope of 5:1 (horizontal to vertical) or steeper, it should be benched into as the fill extends upward
from the keyway.
COMPACTION AND MElHOD OF FILLING: All fill and backfill placed at the site should be
compacted to a relative compaction of at least 90 percent of its maximum dry density as determined
by ASTM Laboratory Test D1557. Fills should be placed at or slightly above optimum moisture
content, in lifts six to eight inches thick, with each lift compacted by mechanical means. Fills should
consist of approved earth material, free of trash or debris, roots, vegetation, or other materials
determined to be unsuitable by the Geotechnical Consultant. Fill material should be free of rocks or
lumps of soil in excess of twelve inches in maximum dimension, and free of rocks over six inches in
diameter within the upper three feet of pad grade.
Utility trench backfill within five feet of the proposed structures and beneath driveways, concrete
flat work, and pavements should be compacted to a minimum of 90 percent of its maximum dry
density.
SURFACE DRAINAGE: The drainage around the proposed improvements should be designed
to collect and direct surface water away from proposed improvements and the top of slopes
CWE 2180124.02 August 7, 2018 Page No. 9
toward appropriate drainage facilities. Rain gutters with downspouts that discharge runoff away
from the structure and the top of slopes into controlled drainage devices are recommended.
The ground around the proposed improvements should be graded so that surface water flows
rapidly away from the improvements without ponding. In general, we recommend that the ground
adjacent to structure slope away at a gradient of at least 5 percent for a minimum distance of 10 feet.
If the minimum distance of 10 feet cannot be achieved, an alternative method of drainage runoff
away from the building at the tennination of the 5 percent slope will need to be used. Swales and
impervious surfaces that are located within 10 feet of the building should have a minimum slope of 2
percent.
Drainage patterns provided at the time of construction should be maintained throughout the life
of the proposed improvements. Site irrigation should be limited to the minimum necessary to
sustain landscape growth. Over watering should be avoided. Should excessive irrigation, impaired
drainage, or unusually high rainfall occur, zones of wet or saturated soil may develop.
GRADING PLAN REVIEW: The final grading plans should be submitted to this office for review
in order to ascertain that the recommendations of this report have been implemented, and that no
additional recommendations are needed due to changes in the anticipated development plans.
SLOPE STABILITY
GENERAL: All slopes at the subject development should be constructed at a slope ratio of 2: 1
(horizontal to vertical) or flatter. Maximum anticipated cut and fill slope heights will be less than
about 20 feet and 27 feet, respectively. Based on the strength parameters of the on-site soils in their
natural and mechanically compacted states, it is our opinion that the proposed slopes will be stable in
regards to deep-seated slope failure and surficial slope failure. All fill slopes should be constructed in
accordance with the grading recommendations presented above.
EROSION CONTROL: The placement of cohesionless soils at the face of slopes should be
avoided. Slopes should be planted as soon as feasible after grading. Sloughing, deep rilling and
slumping of surficial soils may be anticipated if slopes are left unplanted for a long period of time,
•
CWE 2180124.02 August 7, 2018 Page No. 10
especially during the rainy season. Care should be taken to ensure the proper drainage of all surface
runoff away from the slope face. Saturation of the slope caused by excessive or improperly
channeled runoff could detrimentally affect the surficial stability of the slope. Irrigation on and
adjacent to slopes should be carefully monitored to insure that only the minimum amount
necessary to sustain plant life is used. Over-irrigating could not only be erosive but may
significantly increase the chance for slope surficial stability problems and should be avoided.
FOUNDATIONS
GENERAL: Based on our findings and engineering judgment, the proposed structures may be
supported by conventional continuous and isolated spread footings, provided the site is prepared as
recommended in this report. As an alternative post-tensioned foundations may be utilized. The
following recommendations are considered the minimum based on soil conditions and are not
intended to be lieu of structural considerations. All foundations should be designed by a qualified
structural engineer.
FOOTING DIMENSIONS: Spread footings supporting proposed single-and two-story structures
should have a minimum embedment depth of 12 inches and 18 inches below lowest finish pad
grade, respectively. Continuous footings for single-and two-story structures should have a
minimum width of 12 inches and 15 inches, respectively. Isolated footings should have a minimum
width of 24 inches. Minimum dimensions for footings supporting light exterior improvements
should be 12 inches in depth and width. Minimum dimensions for footings supporting exterior
retaining walls should be 18 inches in depth and 24 inches in width. Footings located adjacent to
slopes should be extended to a depth such that a minimum horizontal distance of 10 feet exists
between the bottom of the footing and the face of the slope. The footing setback distance from the
top of slopes may be modified by using deepened footings. Plans for any footings that will not
comply with the specified setbacks should be submitted to the Geotechnical Engineer for specific
review and approval prior to construction.
BEARING CAPACITY: Conventional continuous spread footings with a minimum embedment of
12 inches and width of 12 inches may be designed for an allowable soil bearing pressure of 2,500
pounds per square foot. This value may be increased by 700 pounds per square foot for each
CWE 2180124.02 August 7, 2018 Page No. 11
additional foot of embedment and 400 pounds per square foot for each additional foot of width up to
a maximum of 4,000 pounds per square foot. The bearing value may also be increased by one-third
for combinations of temporary loads such as those due to wind or seismic loads.
FOUNDATION RflNFORCEMENT: The project structural engineer should provide
foundation reinforcement recommendations. However, based on the anticipated soil conditions, we
recommend that the minimum reinforcing for continuous footings should consist of at least 2 No. 5
bars positioned near the bottom of the footing and 2 No. 5 bars positioned near the top of the
footing.
POST-TENSIONED FOUNDATIONS: Post-Tensioned foundations may be utilized for the
support of the subject structures. We are providing in tabular form below the post tension related
design parameters from the Post Tensioning Institute, 3'd edition.
TABLE I, POST-TENSIONED FOUNDATIONS
Post-Tensioning Institute (PTI)-3rd Edition
Edve Moisture Variation, em
Center Lift 1ft) 9.0
Edve Lift fh! 5.4
Differential Soil Movement, -um
Center Lift fin) .19
Ed,ze Lift (in! .41
A minimum depth of 12 inches below adjacent finished grade is recommended for perimeter beams.
Soil bearing values provided in the bearing capacity paragraph are also applicable for post tensioned
foundations. Footings located adjacent to slopes should be extended to a depth such that a minimum
horiwntal distance of 8 feet exists between the bottom of the footing and the face of the slope.
LA 'fERAL LOAD RESISTANCE: Lateral loads against foundations may be resisted by friction
between the bottom of the footing and the supporting soil, and by the passive pressure against the
footing. The coefficient of friction between concrete and soil may be considered to be 0.35. The
passive resistance may be considered to be equal to an equivalent fluid weight of 350 pounds per
cubic foot. This assumes the footings are poured tight against undisturbed soil. If a combination of
the passive pressure and friction is used, the friction value should be reduced by one-third. The upper
CWE 2180124.02 August 7, 2018 Page No. 12
12 inches of footing embedment should not be considered when calculating passive pressures, unless
the footing abuts a concrete slab-on-grade or a paved surface.
SETTLEMENT CHARACTERISTICS: The anticipated total and differential settlement is
expected to be less than about 1 inch and 1 inch over 40 feet, respectively, provided the
recommendations presented in this report are followed. It should be recognized that minor cracks
normally occur in concrete slabs and foundations due to concrete shrinkage during curing or
redistribution of stresses, therefore some cracks should be anticipated. Such cracks are not
necessarily an indication of excessive vertical movements ..
EXP ANS IVE CHARACTERISTICS: Provided the site preparation recommendations described
in this report are implemented, the prevailing foundation soils are assumed to have a low expansive
potential (EI between 21 and 50). The recommendations within this report reflect these conditions.
FOUNDATION EXCAVATION OBSERVATION: All foundation excavations should be
observed by a representative of this office prior to the placement of forms or reinforcement in order
to verify that the footings have the proper dimensions and that the soil conditions are as anticipated.
FOUNDATION PLAN REVIEW: The final foundation plan and accompanying details and notes
should be submitted to this office for review. The intent of our review will be to verify that the plans
used for construction reflect the minimum dimensioning and reinforcing criteria presented in this
section and that no additional criteria are required due to changes in the foundation type or layout. It
is not our intent to review structural plans, notes, details, or calculations to verify that the design
engineer has correctly applied the geotechnical design values. It is the responsibility of the design
engineer to properly design/ specify the foundations and other structural elements based on the
requirements of the structure and considering the information presented in this report.
SOLUBLE SULFA TES: The water soluble sulfate content of foundation soils should be
determined after grading in accordance with California Test Method 417. Nevenheless, Type II
modified Portland cement is recommended for concrete in contact with soil.
CWE 2180124.02 August 7, 2018 Page No. 13
SEISMIC DESIGN FACTORS
The seismic design factors applicable to the subject site are provided below. The seismic design
factors were determined in accordance with the 2016 California Building Code. The site
coefficients and adjusted maximum considered earthquake spectral response acceleration
parameters are presented in the following Table II.
TABLE II: SEISMIC DESIGN FACTORS
Site Coordinates: Latitude 33.138°
LonP-itude -117.299°
Site Class D
Site Coefficient Fa 1.065
Site Coefficient Fv 1.582
Soectral Resoonse Acceleration at Short Periods S, 1.087 e
Soectral Response Acceleration at 1 Second Period S1 0.418 •
SMs-F,S, 1.158 •
s~n -FvS1 0.662 •
5Ds=2/3*5Ms 0.772 •
$01 =2/3*$Mt 0.491 •
Probable ground shaking levels at the site could range from slight to moderate, depending on such
factors as the magnitude of the seismic event and the distance to the epicenter. It is likely that the
site will experience the effects of at least one moderate to large earthquake during the life of the
proposed improvements.
ON-GRADE SLABS
GENERAL: It is our understanding that if conventional foundations are utilized for the support of
the proposed structures, the floor system for the proposed structures will consist of an on-grade
concrete slab. The following recommendations are considered the minimum slab requirements based
on the anticipated soil conditions, are not intended in lieu of structural considerations.
INTERIOR FLOOR SLABS: The minimum floor slab thickness should be 4 inches (actual), and
the floor slab should be reinforced with at least No. 3 reinforcing bars placed at 18 inches on center
each way. Slab reinforcement should be supported on chairs such that the reinforcing bars are
CWE 2180124.02 August 7, 2018 Page No. 14
positioned at mid-height in the floor slab. The slab reinforcement should extend into the perimeter
foundations at least 6 inches.
UNDER-SLAB VAPOR RETARDERS: The following recommendations apply to conventional
slabs-on-grade. Steps should be taken to minimize the transmission of moisture vapor from the
subsoil through the interior slabs where it can potentially damage the interior floor coverings.
Local industry standards typically include the placement of a vapor retarder, such as plastic, in a
layer of coarse sand placed directly beneath the concrete slab. Two inches of sand are typically
used above the plastic. In this case it is further recommended that the plastic be underlain by a 6-
inch-thick gravel layer placed over filter fabric such as Mirafi 140N or equivalent. The vapor
retarder should be at least 15-mil Stegowrap® or similar material with sealed seams and should
extend at least 12 inches down the sides of the interior and perimeter footings. The sand should
have a sand equivalent of at least 30, and contain less than 10% passing the Number 100 sieve and
less than 5% passing the Number 200 sieve. The membrane should be placed in accordance with
the recommendation and consideration of ACI 302, "Guide for Concrete Floor and Slab
Construction" and ASThl E1643, "Standards Practice for Installation of Water Vapor Retarder
Used in Contact with Earth or Granular Fill Under Concrete Slabs." It is the flooring contractor's
responsibility to place floor coverings in accordance with the flooring manufacturer specifications.
EXTERIOR CONCRETE FLA TWORK: Exterior concrete slabs on grade should have a
minimum thickness of 4 inches and be reinforced with at least No. 3 bars placed at 18 inches on
center each way (ocew). Driveway slabs should have a minimum thickness of 5 inches and be
reinforced with at least No. 4 bars placed at 12 inches ocew. Driveway slabs should be provided
with a thickened edge a least 12 inches deep and 6 mches wide. All slabs should be provided with
weakened plane joints in accordance with the American Concrete Institute (ACD guidelines.
Special attention should be paid to the method of concrete curing to reduce the potential for
excessive shrinkage cracking. It should be recognized that minor cracks occur normally in concrete
slabs due to shrinkage. Some shrinkage cracks should be expected and are not necessarily an
indication of excessive movement or structural distress.
CWE 2180124.02 August 7, 2018 Page No. 15
SWIMMING POOLS
Swimming pools may be constructed as part of the proposed development or by future individual
homeowners. If the proposed pool is a settlement sensitive vanishing edge pool or a zero edge
pool, it is recommended that it be founded in the formational soils underlying the compacted fill.
Depending on the pool location, this recommendation may necessitate a foundation system
consisting of concrete cast-in-place piers. Appropriate foundation recommendations will be
provided by this office after the proposed swimming pool layout is available.
EAR1HRETAINING WALLS
FOUNDATIONS: Foundations for proposed retaining walls should be constructed in accordance
with the recommendations for shallow foundations presented previously in this report.
PASSIVE PRESSURE: The passive pressure forthe anticipated foundation soils may be
considered to be 300 pounds per square foot per foot of depth. The upper foot of embedment
should be neglected when calculating passive pressures, unless the foundation abuts a hard surface
such as a concrete slab. The passive pressure may be increased by one-third for seismic loading.
The coefficient of friction for concrete to soil may be assumed to be 0.30 for the resistance to
lateral movement. When combining frictional and passive resistance, the friction should be
reduced by one-third.
ACTIVE PRESSURE: The lateral soil pressure for the design of unrestrained earth retaining
structures with level backfill may be assumed to be equivalent to the pressure of a fluid weighing
35 pounds per cubic foot (pd). An additional 13 pcf should be added to the above value for a 2:1
{horizontal to vertical) sloping backfill condition. These pressures do not consider any other
surcharge. If any are anticipated, this office should be contacted for the necessary increase in soil
pressure. These values are based on a drained backfill condition.
Seismic lateral earth pressures may be assumed to equal an inverted triangle starting at the bottom
of the wall with the maximum pressure equal to 8.SH pounds per square foot (where H = wall
height in feet) occurring at the top of the wall.
•
CWE 2180124.02 August 7, 2018 Page No. 16
WATERPROOFING AND WALL DRAINAGE SYSTEMS: The need for waterproofing
should be evaluated by others. If required, the project architect should provide (or coordinate)
waterproofing details for the retaining walls. The design values presented above are based on a
drained backfill condition and do not consider hydrostatic pressures. Unless hydrostatic pressures
are incorporated into the design, the retaining wall designer should provide a detail for a wall
drainage system. Typical retaining wall drain system details are presented as Plate No. 3 of this
report for informational purposes. Additionally, outlets points for the retaining wall drain system
should be coordinated with the project civil engineer.
BACKFILL: All backfill soils should be compacted to at least 90 percent relative compaction.
Expansive or clayey soils should not be used for backfill material. The wall should not be backfilled
until the masonry has reached an adequate strength.
LIMITATIONS
REVIEW, OBSERVATION AND TESTING
The recommendations presented in this report are contingent upon our review of final plans and
specifications. Such plans and specifications should be made available to the Geotechnical Engineer
and Engineering Geologist so that they may review and verify their compliance with this report and
with the 2007 edition of the California Building Code.
It is recommended that Christian Wheeler Engineering be retained to provide continuous soil
engineering services during the earthwork operations. This is to verify compliance with the design
concepts, specifications or recommendations and to allow design changes in the event that subsurface
conditions differ from those anticipated prior to start of construction.
UNIFORMITY OF CONDITIONS
The recommendations and opinions expressed in this report reflect our best estimate of the project
requirements based on an evaluation of the subsurface soil conditions encountered at the subsurface
exploration locations and on the assumption that the soil conditions do not deviate appreciably from
CWE 2180124.02 August 7, 2018 Page No. 17
those encountered. It should be recognized that the performance of the foundations and/ or cut and
fill slopes may be influenced by undisclosed or unforeseen variations in the soil conditions that may
occur in the intermediate and unexplored areas. Any unusual conditions not covered in this report
that may be encountered during site development should be brought to the attention of the
Geotechnical Engineer so that he may make modifications if necessary.
CHANGE IN SCOPE
This office should be advised of any changes in the project scope or proposed site grading so that we
may determine if the recommendations contained herein are appropriate. It should be verified in
writing if the recommendations are found to be appropriate for the proposed changes or our
recommendations should be modified by a written addendum.
TIME LIMITATIONS
The findings of this report are valid as of this date. Changes in the condition of a property can,
however, occur with the passage of time, whether they are due to natural processes or the work of
man on this or adjacent properties. In addition, changes in the Standards-of-Practice and/ or
Government Codes may occur. Due to such changes, the findings of this report may be invalidated
wholly or in part by changes beyond our control. Therefore, this report should not be relied upon
after a period of two years without a review by us verifying the suitability of the conclusions and
recommendations.
PROFESSIONAL STANDARD
In the performance of our professional services, we comply with that level of care and skill
ordinarily exercised by members of our profession currently practicing under similar conditions and
in the same locality. The client recognizes that subsurface conditions may vary from those
encountered at the locations where our borings, surveys, and explorations are made, and that our
data, interpretations, and recommendations are based solely on the information obtained by us. We
will be responsible for those data, interpretations, and recommendations, but shall not be responsible
for the interpretations by others of the information developed. Our services consist of professional
CWE 2180124.02 August 7, 2018 Page No. 18
consultation and observation only, and no warranty of any kind whatsoever, express or implied, is
made or intended in connection with the work performed or to be performed by us, or by our
proposal for consulting or other services, or by our furnishing of oral or written reports or findings.
CLIENT'S RESPONSIBILITY
It is the responsibility of the Client, or her representatives, to ensure that the information and
recommendations contained herein are brought to the attention of the structural engineer and
architect for the project and incorporated into the project's plans and specifications. It is further their
responsibility to take the necessary measures to insure that the contractor and all subcontractors
carry out such recommendations during construction,
Appendix A
Data from CWE 201.116 Geotechnical Report
j '
LIGENQ
-~~TFiiTPEM::tit..OC,.f,0,,,
~COHfACr --Qt
w ::v~~'l~vrtn•
Tsa r 1.nt~IIX:N1'-'L.MCl,A.1:1 .. r"""""'1< 1-O:,.t,11-Q.l
~~ '°'""' 1 •••• ,
LOG OF TEST TRENCH NUMBER T-1
Date Excavated: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 313 feet Depth to Warer: l/A
Proposed E levation: 328 feet Bucket Size: 24 inches
(.J g ,.., ...., ,....
:r:: ~ E-< p. ii: ~ Cl 2 (.J
.... I . . .. .... •·· ., . ..
2 .... -.. .. .... •· -.. .,. .. -3 ... ... .. ·• ... . .. , .. -4 . ,··
... •··· ...
.. •···,.•· -5 ... .. ... .. ..•· .•· -6 ... .. ... •···· .... •·· -7 ... __ .,
.•· ... . .. .. ..
8 ... -
-9
.,_ 10
SAMPIFS
..; :?: 'u' 'o' > c ~ ·c '-' -0 ~ ::::: .... ~ < 0
SUivfNURY OF SUBSURFACE CONDITIONS ~ ..... E: ~ ;::) .-l ;:) f--, p. co :I! ';;;-C/1 ~ z ~ c < ~ 0
~ e ~
Topsoil: Dark brown, SIL TY S.-\ND (SJ\.1), moist, loose, fine-to medium-
grained.
Subsoil: Medium brown, CL'\ YEY SAND (SC), moist, loose to medium
dense fine-to medium-Qrained .
Terrace Deposits (Ot): Orangish-browo, CL:\ YEY SAND (SC), moist,
dense, fine-to coarse-grained . CK 7-1
CK 6.4
Terminated at 8 feet.
·w PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, California
Q u ~
~
t: z ;::)
>-, p:,:
Cl
II I.I
115.5
~
0 (/) E-< r' ~ (/)
0~ co :5
S,\
m
MD
DS
CHRISTIAN WHEELER BY: SCC DA IB: February 27, 2001
Engi ne e rin g OBNO.: 201.116 PU .TE NO.: 2
LOG OF TEST TRENCH NUMBER T-3
Dace Ei.cavared: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 317 feet Depth to Water: /A
Proposed Elevation: 314 feet Bucket Size: 24 inches
SAMPLES
c., 0 u ,...._ 0 P:.l z "" 'o' ...e, ~ $ .....l ~ > ~ g ·t:; ~ :r: ;d 'U gJ C II) ::.: ......
f--< ::i:: ~ 0 f--< t-<
0... SU~L\RY OF SUBSURFACE CONDITIONS >Il .....l ..::: ::i f--< ~ U) Ul 0... ,-l ::i ~ -0 ~ e: CQ ~ ....... $ 0 I=:
(j ~ z 3 0 ilO ..:; ~ 0 >-< ~ :,_ e ~ ~ .....l
0
Topsoil: Dark brown, SIL1Y SAND (Si\1), moist, loose, fine-to medium-
I !!rained. -.. .. ... Subsoil: Medium brown, CL-\ YEY SA D (SC), moist, loose to medium ...
.... 2
.... •····· dense, fine-co medium-grained. . . ... •· -.. •· .. •·
3 ...... Terrace Deposits (Ot): Orangish-brown, CLAYEY SAND (SC), moist, -... .. •···· dense to very dense, fine-to coarse-grained with occasional 3 inch cobble. , . .. • .. CK -4 ~·· ... .. •,; ..... . . ..... •·
-5 .. ...... .. •·
-6 Santiago Formation (Tsa): Light brown to white, SIL 1Y SAND (S:VI),
moist, dense to very dense, fine-to medium-grained.
-7 CK 11.0 111.9
-8
.... 9
-10
Terminated at 10 feet.
PROPOSED 5-LOT RESIDENTIAL PROJECT w West of Faraday Road, Carlsbad, California
C HR ISTIAN WHEELER BY: sec D:\TE: February 27, 2001
E n ginee r ing JOBNO.: 201.116 PLATE NO.: 4
LOG OF TEST TRENCH NUMBER T-4
Date Excavated: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 317 feet Depth to Water: N I A
Proposed Elevation: 314 feet Bucket Size: 24 inches
SAMPI.F.S
l? c;:;--u g 0 !I.! z '<>' 'o' .E:, ~ +--< ~ > ~ ~ ·i: ....; ::c u .,, ~ ~ 0 {/) ~ ~ .... t""' 5:: C i--, r-' 11.. SU~Th1ARY OF SUBSURFACE CONDITIO s ~ ...:i ,i ;:) i--, ~ {/) w p., +--< :J SJ ti z 0~ 0 ~ ~ .a ....__
V, ~ z ~ 5 ::> QO l'.) Ji ~ ;e, ?-~ j
0
~ Topsoil: Dark brown, SIL 'TY SAJ\.TD (SM), moist, loose, fine-ro medium-
1 grained. I-... .... • Subsoil: Medium brown, CL-\ YEY S,-\ND (SC), moist, loose to medium .. . . .. .. • dense, fine-to medium-grained . -2 .. • .. ... -... •· .. .. .. • Terrace Deposits (Ot): Orangish-brown, CLAYEY SAND/SIL 'TY SAND 3 .. • -..... ~···· (SC/S;\'I), moist, dense co very dense, occasional gravel and cobble . .... ..
-4 .. •·
..... .... •· ....
CK .. .. ,-5 .. .,..
~
... ~·' .. .. ...
,-6 ··••• 1111111 ... •······
.... 7
... •······
-8 Terminated at 7 feet.
-9
._ 10
w PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, California
CHRISTIAN WHEELER BY: sec D:\TE: February 27, 20()1
En gineer i ng JOB NO.: 201.116 PL-\TE J\:O.: 5
LOG OF TEST TRENCH NUMBER T-5 (Continued)
Date Excavated: 2/15/01 Logged by: ORR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 290 feet Depth to Water: N/A
Proposed Elevation: 306 feet Bucket Size: 24 inches
SAMPLES
l'.) = g ,-_ tI.l z ~ ~ ~ >-..., > ....l t: 0 ·c e..., ~ p,: -u ::: -0 ~ 0 E 5: ~ ~ '; r<~ SUNIMARY OF SUBSURFACE CONDITIONS !Il ....l ~ :J t: ~ (/) tI.l Po. --l :J t.... t; 0~ a ~ Cl., i:Q ~ ....... z ~ z ~ c :J i:Q l'.) ~ :I: 0 ~ j './: Q.. e ::E
0 .. .. Santiago Formation (Tsa): Light brown to light orangish~brown, .~ ..
·•· .... CLAYEY SAND (SC), moist, very dense . .. ..... 11 . ,
.. ~···· ... ' .. ... -~
-12 ... .. ·•' .. .... r:.'' .. . . •·
... 13 .. •· ... .... • ..
_ .. ,.•
-14 .... •· .. .. .. •· .. ..... ~···· CK 15.5 113.2 .,__ 15
.,__ 16 Terminated at 15 feet .
-17
-18
,-19
.. 20
PROPOSED 5-LOT RESIDENTIAL PROJECT ·w West of Faraday Road, Carlsbad, California
CHRISTIAN WHEELER BY: sec DATE: February 27, 2001
E n g i neer in g TOB NO.: 201.116 PL'\TENO.: 7
LOG OF TEST TRENCH NUMBER T-8
Date Excavated: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 314 feet Depth to Water: N/A
Proposed Elevation: 315 feet Bucket Size: 24 inches
SA.~IPLES
C) c:::-u g '"' w z <i' ,-... --9, >-....., .. ~ ...... ~ C :g ~ ~ i:.::
l: u ~ ~ 'o ~ e u: f--, :2 < ~~ ::i., SUM},L\RY OF SUBSURFACE CONDITIONS Jl.l ...... e: ,±: ~ t: w ~ i--l :::i /:l.. C!'.l : .... ...... z C E--Q ~ -"' C) ?-z 3 0 :::i ~ < i 0 >-j u:: e ?-i:.::
Q
Topsoil: Dark brown, SIL TY S,u'\lD (Sl'vl), moist, loose, fine-to medium-
I-1 l?[ained. .. .. •· Subsoil: Medium brown, CLAYEY SAND (SC), moist, loose to medium ... ..
-2
, ..... •·· dense, fine-to medium-grained. .. . •· .... .... •
.. ...... Terrace Deposits (Ot): Orangish-brown, CLAYEY SAND (SC), moist, 3 ... .... . . .. .... ·• dense to very dense, fine-to coarse-grained, occasional 2½ inch gravel.
CKlilllllll
•' .. .. ,
6.0 113.0 ..... 4 ... ..•· ..
: .. ·• .. .. .. .. -5 .. ..... .. .. •· .. •·
111111111
..
6 ... • -.... .. CK .... . .
7
...... •~· -
I-8 Terminated at 7 feet.
-9
-10
PROPOSED 5-LOT RESIDENTIAL PROJECT w West of Faraday Road, Carlsbad, California
CHRISTIAN WHEELER BY: sec DATE: February 27, 2001
Engineering TOB NO.: 201.116 PLATE NO.: 11
-
...
...
-
-
t-
...
....
-
-
-
LOG OF TEST TRENCH NUMBER T-9
Date Excavaced: 2/15/01 Logged by: DRR
Eguipment: Backhoe Project Manager: CI-IC
Existing Elevation: 314 feet Depth co Water: N/,-\
Proposed Elevation: --Bucket Size: 24 inches
g Cl 0 .....l
::r: ~ !--< P-, ::i::
ttl P-,
Q ;:z
(.'.)
.. . •· .. ...
.. •··· ..
1 ..
.... •··
... •· ...
2 .. •··· . . .. .. ....
·' ..
3 ~-···· , . .. .. •· .. ...
4 .... •· .. .. .. • ...
... ~··
5 ... .... ,• ... ., .
6
.... •··
. .. •······ .. .. ..
7 .. •·
..•· .... ·••
8
.... •····
..... •···
.... ·••
9 .. • ... .... •··
10 ... •·····
SAMPLES
Cil z <I'" ;€' > ~ C :.g ~
~ ._ ~ < C SUMMARY OF SUBSURFACE CONDITIONS Cil .....l ;:::: J:: ;:) ...., ;:) !;; ~ ;!:I ;.,
----6 ; a < 0 3:: e ::2 (/J
Subsoil: Medium brown, CL-\ YEY SA..i"JD (SC), moist, loose to medium
dense, fine-to medium-grained .
Terrace Deposits (Ot): Orangish-brown, CL-\. YEY SAND (SC), moist,
very dense, fine-to coarse-grained, abundant gravel and cobble . CK 5.7
Santiago Fonnation (Tsa): Light olive brown, CL:\ YEY SAND (SC), • moist, dense to very dense, fine-to medium-grained .
CK 15.8
11111111
CK
CKIIIIIIIII
Terminated at 10 feet.
w PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, California
C u __e:,
~
t: z ::,
>-~ Q
122.8
111.0
~ ,...,
V V) !--< !--< ~ (/J
i:<l O!--< ;!l :s
CHRISTIAN WHEELER BY: SCC DATE: February 27, 2001
En ginee ring OBNO.: 20l.116 PLATE NO.: 12
LABORATORY TEST RESULTS
PROPOSED FIVE-I.OT RESIDENTIAJ, PROJECT
\X'EST OF FAR.ADAY ROAD
PO\'{' A Y CA.LIFOR:\lIA
MAXIMUM DENSITY/ OPTIMUM MOISTURE CONTENT
Sample :\lumber
Description
Maxunum Density
Optimum Moisture Content
DIRECT SHEAR TEST
Sample Number
Description
Angle of Internal Faction
Apparent Cohesion
GRAIN SIZE DISTRIBUTION
Sample Nwnber T-1@ 2'-8'
Sieve Size Percent Passmg
#4 100
#8 93
#15 78
#30 59
#50 37
#100 22
#200 19
0.05 mm 18
0.005 mm 11
0.001 mm 8
Classification SC
EXPANSION INDEX TESTS
Sample Number:
Initial Moisture:
Initial Dn· Density:
Final :\fo1sture:
Expansion Index:
CW'E 201.116.1
Trench T-1 @ 2'-8'
Orangish-bto\lm, clayey sand (SC)
127.1 pcf
8.5 percent
Trench T-1@ 2'-8'
Rcmolded To 90 Percent
33 degrees
100 psf
T-2 @4'-6'
Percent Passing
T reneh T-8 @ 2' -8'
8.0 percrcnt
108.3 pcf
17.7 percent
6 (very low)
l\farch 14, 2001
100
99
98
97
87
70
60 ,, _,
18
CL
Trench T-6@ 3'-12'
Brown, sandy clay (CL)
106.0 pcf
18.S pcf
Trench T-6 @ 3'-12'
Remolded to 90 Percent
21 degrees
300 psf
T-6@ 3'-12'
Percent Passing
100
699
98
96
84
69
55
21
' '
CL
Trench T-6@3'-12'
13.7 percent
101.4 pcf
29.5 percent
85 (medium)
Plate No. 13
Appendix B
References
CWE 2180124.02 August 7, 2018 Appendix B•l
REFERENCES
Bryant, W. A. (compiler), 2005, Digital Database of Quaternary and Younger Faults from the Fault
Activity Map of California, version 2.0: California Geological Survey Web Page,
http://www.consrv.ca. gov/ CGS/information/ publications/ Quaternary Faults_ ver 2.htm
Christian Wheeler Engineering, Updated Geotechnical Investigation Report, Kirgis Subdivision,
Carlsbad Tract 02-06", dated October 10, 2013, Report CWE 2110148.0lR
Historic Aerials, NETR Online, historicaerials.com
Jennings, C.W. and Bryant, W. A., 2010, Fault Activity Map, California Geological Survey, Geologic
Data Map No. 6, http:/ /www.quake.ca.gov/gmaps/F AM/faultactivitymap.html
Kennedy, Michael P. and Tan, Siang S., 2007, Geologic Map of the Oceanside 30'x60' Quadrangle,
California, California Geologic Survey, Map No. 2.
Tan, S.S., 1995, Landslide Hazards in the Northern Part of the San Diego Metropolitan Area, San
Diego County, California, California Division of Mines and Geology Open-File Report 95-04.
U.S. Geological Survey, U.S. Seismic Design Maps Web Application,
http://geohazards.usgs.gov/ designmaps/ us/ application. ph p
U.S. Geological Survey, Quaternary Faults in Google Earth,
http://earthquake.usgs.gov/hazards/ qfaults/ google.php
•
Appendix C
Recommended Grading Specifications -General Provisions
CWE 2180124.02 August 7, 2018 Appendix C, Page C-1
RECOMMENDED GRADING SPECIFICATIONS -GENERAL PROVISIONS
GENERAL INTENT
CARLSBAD TRACT CT-15-07
TWAIN A VENUE
CARLSBAD, CALIFORNIA
The intent of these specifications is to establish procedures for clearing, compacting natural ground,
preparing areas to be filled, and placing and compacting fill soils to the lines and grades shown on the
accepted plans. The recommendations contained in the preliminary geotechnical investigation report
and/or the attached Special Provisions are a part of the Recommended Grading Specifications and
shall supersede the provisions contained hereinafter in the case of conflict. These specifications shall
only be used in conjunction with the geotechnical report for which they are a part. No deviation
from these specifications will be allowed, except where specified in the geotechnical report or in other
written communication signed by the Geotechnical Engineer.
OBSERVATION AND TESTING
Christian Wheeler Engineering shall be retained as the Geotechnical Engineer to observe and test the
earthwork in accordance with these specifications. It will be necessary that the Geotechnical Engineer
or his representative provide adequate observation so that he may provide his opinion as to whether
or not the work was accomplished as specified. It shall be the responsibility of the contractor to assist
the Geotechnical Engineer and to keep him appraised of work schedules, changes and new
information and data so that he may provide these opinions. In the event that any unusual conditions
not covered by the special provisions or preliminary geotechnical report are encountered during the
grading operations, the Geotechnical Engineer shall be contacted for further recommendations.
If, in the opinion of the Geotechnical Engineer, substandard conditions are encountered, such as
questionable or unsuitable soil, unacceptable moisture content, inadequate compaction, adverse
weather, etc., construction should be stopped until the conditions are remedied or corrected or he
shall recommend rejection of this work.
•
•
CWE 2180124.02 August 7, 2018 Appendix C, Page C-2
Tests used to determine the degree of compaction should be performed in accordance with the
following American Society for Testing and Materials test methods:
Maximum Density & Optimum Moisture Content -ASTM D1557
Density of Soil In-Place -ASTM D1556 or ASTM D6938
All densities shall be expressed in terms of Relative Compaction as determined by the foregoing
ASTM testing procedures.
PREPARATION OF AREAS TO RECEIVE FILL
All vegetation, brush and debris derived from clearing operations shall be removed, and legally
disposed of. All areas disturbed by site grading should be left in a neat and finished appearance, free
from unsightly debris.
After clearing or benching the natural ground, the areas to be filled shall be scarified to a depth of 6
inches, brought to the proper moisture content, compacted and tested for the specified minimum
degree of compaction. All loose soils in excess of 6 inches thick should be removed to firm natural
ground which is defined as natural soil which possesses an in-situ density of at least 90 percent of its
maximum dry density.
When the slope of the natural ground receiving fill exceeds 20 percent (5 horizontal units to 1 vertical
unit), the original ground shall be stepped or benched. Benches shall be cut to a firm competent
formational soil. The lower bench shall be at least 10 feet wide or 1-1/2 times the equipment width,
whichever is greater, and shall be sloped back into the hillside at a gradient of not less than two (2)
percent. All other benches should be at least 6 feet wide. The horizontal portion of each bench shall
be compacted prior to receiving fill as specified herein for compacted natural ground. Ground slopes
flatter than 20 percent shall be benched when considered necessary by the Geotechnical Engineer.
Any abandoned buried structures encountered during grading operations must be totally removed.
All underground utilities to be abandoned beneath any proposed structure should be removed from
within 10 feet of the structure and properly capped off. The resulting depressions from the above
CWE 2180124.02 August 7, 2018 Appendix C, Page C-3
described procedure should be backfilled with acceptable soil that is compacted to the requirements of
the Geotechnical Engineer. This includes, but is not limited to, septic tanks, fuel tanks, sewer lines or
leach lines, storm drains and water lines. Any buried structures or utilities not to be abandoned
should be brought to the attention of the Geotechnical Engineer so that he may determine if any
special recommendation will be necessary.
All water wells which will be abandoned should be backfilled and capped in accordance to the
requirements set forth by the Geotechnical Engineer. The top of the cap should be at least 4 feet
below finish grade or J feet below the bottom of footing whichever is greater. The type of cap will
depend on the diameter of the well and should be determined by the Geotechnical Engineer and/ or a
qualified Structural Engineer.
FILL MATERIAL
Materials to be placed in the fill shall be approved by the Geotechnical Engineer and shall be free of
vegetable matter and other deleterious substances. Granular soil shall contain sufficient fine material
to fill the voids. The definition and disposition of oversized rocks and expansive or detrimental soils
are covered in the geotechnical report or Special Provisions. Expansive soils, soils of poor gradation,
or soils with low strength characteristics may be thoroughly mixed with other soils to provide
satisfactory fill material, but only with the explicit consent of the Geotechnical Engineer. Any
import material shall be approved by the Geotechnical Engineer before being brought to the site.
PLACING AND COMPACTION OF FILL
Approved fill material shall be placed in areas prepared to receive fill in layers not to exceed 6 inches
in compacted thickness. Each layer shall have a uniform moisture content in the range that will allow
the compaction effort to be efficiently applied to achieve the specified degree of compaction. Each
layer shall be uniformly compacted to the specified minimum degree of compaction with equipment
of adequate size to economically compact the layer. Compaction equipment should either be
specifically designed for soil compaction or of proven reliability. The minimum degree of compaction
to be achieved is specified in either the Special Provisions or the recommendations contained in the
preliminary geotechnical investigation report.
•
•
CWE 2180124.02 August 7, 2018 Appendix C, Page C-4
When the structural fill material includes rocks, no rocks will be allowed to nest and all voids must be
carefully filled with soil such that the minimum degree of compaction recommended in the Special
Provisions is achieved. The maximum size and spacing of rock permitted in structural fills and in non-
structural fills is discussed in the geotechnical report, when applicable.
Field observation and compaction tests to estimate the degree of compaction of the fill will be taken
by the Geotechnical Engineer or his representative. The location and frequency of the tests shall be at
the Geotechnical Engineer's discretion. When the compaction test indicates that a particular layer is
at less than the required degree of compaction, the layer shall be reworked to the satisfaction of the
Geotechnical Engineer and until the desired relative compaction has been obtained.
Fill slopes shall be compacted by means of sheepsfoot rollers or other suitable equipment.
Compaction by sheepsfoot roller shall be at vertical intervals of not greater than four feet. In
addition, fill slopes at a ratio of two horizontal to one vertical or flatter, should be trackrolled.
Steeper fill slopes shall be over-built and cut-back to finish contours after the slope has been
constructed. Slope compaction operations shall result in all fill material six or more inches inward
from the finished face of the slope having a relative compaction of at least 90 percent of maximum dry
density or the degree of compaction specified in the Special Provisions section of this specification.
The compaction operation on the slopes shall be continued until the Geotechnical Engineer is of the
opinion that the slopes will be surficially stable.
Density tests in the slopes will be made by the Geotechnical Engineer during construction of the
slopes to determine if the required compaction is being achieved. Where failing tests occur or other
field problems arise, the Contractor will be notified that day of such conditions by written
communication from the Geotechnical Engineer or his representative in the form of a daily field
report.
If the method of achieving the required slope compaction selected by the Contractor fails to produce
the necessary results, the Contractor shall rework or rebuild such slopes until the required degree of
compaction is obtained, at no cost to the Owner or Geotechnical Engineer.
CWE 2180124.02 August 7, 2018 Appendix C, Page C-5
CUT SLOPES
The Engineering Geologist shall inspect cut slopes excavated in rock or lithified formational material
during the grading operations at intervals determined at his discretion. If any conditions not
anticipated in the preliminary report such as perched water, seepage, lenticular or confined strata of a
potentially adverse nature, unfavorably inclined bedding, joints or fault planes are encountered during
grading, these conditions shall be analyzed by the Engineering Geologist and Geotechnical Engineer
to determine if mitigating measures are necessary.
Unless otherwise specified in the geotechnical report, no cut slopes shall be excavated higher or
steeper than that allowed by the ordinances of the controlling governmental agency.
ENGINEERING OBSERVATION
Field observation by the Geotechnical Engineer or his representative shall be made during the filling
and compaction operations so that he can express his opinion regarding the conformance of the
grading with acceptable standards of practice. Neither the presence of the Geotechnical Engineer or
his representative or the observation and testing shall release the Grading Contractor from his duty to
compact all fill material to the specified degree of compaction.
SEASON LIMITS
Fill shall not be placed during unfavorable weather conditions. When work is interrupted by heavy
rain, filling operations shall not be resumed until the proper moisture content and density of the fill
materials can be achieved. Damaged site conditions resulting from weather or acts of God shall be
repaired before acceptance of work.
RECOMMENDED GRADING SPECIFICATIONS -SPECIAL PROVISIONS
RELATIVE COMPACTION: The minimum degree of compaction to be obtained in compacted
natural ground, compacted fill, and compacted backfill shall be at least 90 percent. For street and
•
•
•
•
CWE 2180124.02 August 7, 2018 Appendix C, Page C.6
parking lot subgrade, the upper six inches should be compacted to at least 95 percent relative
compaction.
EXPANSIVE SOILS: Detrimentally expansive soil is defined as clayey soil which has an expansion
index of 50 or greater when tested in accordance with the Uniform Building Code Standard 29-2.
OVERSIZED MATERIAL: Oversized fill material is generally defined herein as rocks or lumps of
soil over 6 inches in diameter. Oversized materials should not be placed in fill unless
recommendations of placement of such material are provided by the Geotechnical Engineer. At least
40 percent of the fill soils shall pass through a No. 4 U.S. Standard Sieve.
TRANSITION LOTS: Where transitions between cut and fill occur within the proposed building
pad, the cut portion should be undercut a minimum of one foot below the base of the proposed
footings and recompacted as structural backfill. In certain cases that would be addressed in the
geotechnical report, special footing reinforcement or a combination of special footing reinforcement
and undercutting may be required.