HomeMy WebLinkAboutCDP 02-42; 2200 HIGHLAND DR; UPDATE TO GEOTECHNICAL INVESTIGATION; 2003-10-01I
I
I
I
I
I
I
I
I
I
I
I
I
I
·I
I
I
I
I
Plan Review Geotechnical Update Report
Lot at the North Terminus of Highland Drive
Carlsbad, California
(A.P.N. #156-051-24)
HDP ();2.-ID
October 1, 2003 RECEIVED
Prepared For:
MR. JIM DUNN, JR
4316 Cassanna Way, #305
Oceanside, California 92057
Prepared By:
OCT O 6 2003
CITY OF CARLSBAD
PLANNING DEPT.
VINJE & MIDDLETON ENGINEERING, INC.
2450 Vineyard Avenue, Suite 102
Escondido, California 92029
Job #03-387 -P
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONTENTS
PAGE NO.
I. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
II. SITE DESCRIPTION / HISTORY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Ill. PROPOSED DEVELOPMENT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
IV. GEOTECHNICAL CONDITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
A. Slope Stability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
8. Seismic Response Coefficients . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
V. CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
VI. RECOMMENDATIONS ......................................... ~ . . . 6
A. Remedial Grading and Earthworks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
B. Foundations and Interior Floor Slabs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
C. Exterior Concrete Slabs / Flatworks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
D. Soil Design Parameters .... _. ... ~-. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
E. Asphalt and PCC Pavement Design .............................. 15
F. General Recommendations ............... •. . . . . . . . . . . . . . . . . . . . . . 16
VII. LIMITATIONS ................................................... 18
TABLE NO.
Site Seismic Parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
PLATE NO.
Regional Index Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Site Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Cross-Section at Proposed Storm Drain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Geologic Cross-Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Typical Slope Rec_onstruction Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Test Boring and Test Pit Logs ........................................ 6-14
Retaining Wall Drain Detail . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Isolation and Re-entrant Corner Reinforcement . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Slope Reinforcement Installation Guide ........................ APPENDIX A
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
LOT AT THE NORTH TERMINUS OF HIGHLAND DRIVE
CARLSBAD, CALIFORNIA
I. INTRODUCTION
_ The property investigated in this work includes 2.54 acres of undeveloped land located at
the northern terminus of Highland Drive within the City of Carlsbad. The property location
is depicted on a Regional Index Map included herein as Plate 1. Existing topographic
conditions and proposed development at the site are shown on a Site Plan, Plate 2.
A storm drain pipe traverses the property transporting storm water from an inlet box at the
northend of Highland Drive into canyon terrain and the Buena Vista Lagoon to the north.
The storm drain is buried within a descending slope which marks the northern margins of
the property. The existing pipe has failed and resulted in high levels of erosion and related
failures within lower slope terrain. We understand that the u·pper nearly level areas atop
the existing project descending slope is planned for the support of a single-family residence
to the east and a detached garage/shed structure to the west. Consequently, The purpose
of this work was to review all available pertinent geotechnical reports and documents and
provide update recommendations that are consistent with the proposed site development.
Previous soils and geotechnical investigations at or in the vicinity of the study property
have resulted in the following technical reports:
1. "Preliminary Geotechnical Report, Storm Drain Reconstruction, North End of
Highland Drive, Carlsbad," Job #03-262-P, prepared by Vinje & Middleton
engineering, Inc., dated June 17, 2003.
2. "AssE?ssment of Fill Slope Regression, 2202 Highland Drive, Carlsbad, California,"
prepared by Taylor-Hunter Associates, Inc., THA Project No. G02-00199, dated
December 5, 2002.
3. "Geotechnical Investigation, Proposed Lot Split, Three-Acre Site, 2022 Highland
Drive, Carlsbad, California," by Ron Gutier (C.E.G.) and Erik J. Nelson (P.E.), Job
#GN-1, dated February 17, 1989.
The referenced reports are on file wit_h our firm and copies can be obtained upon request.
Logs of the exploratory Test Borings and Test Pit Trenches completed in connection with
the preparation of the 1989 investigation (Reference 3) are enclosed herein as Plates 6
through 14. Boring and trench locations are shown on the enclosed Site Plan, Plate 2.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
II. SITE DESCRIPTION / HISTORY
PAGE 2
OCTOBER 1, 2003
The irregular-shaped parcel is located at the north terminus of Highland Drive in a
residential section of the City of Carlsbad. The property currently supports a moderate
covering of native plants and weeds. Site topography ranges from nearly level in the upper
southeasterly reaches of the property to steeply sloping, and locally vertical, canyon terrain
within the northwestern margin of the property with more than 50 feet of vertical relief.
Slope gradients at and adjacent the study property generally approach 2: 1 to 1: 1
(horizontal to vertical).
Existing site topography was achieved by placing undocumented fills atop natural ground
surfaces more than 36 years ago (Reference 3). Approximate fill limits as determined in
the field is shown on Plate 2. Site existing fills, as outlined in Reference 3, consist of silts
and sands with a considerable amount of deleterious material and no evidence of benching
into bedrock.
We understand that plans for reconstruction of the failed storm pipe within the lower
reaches of the northern descending slope are near completion. We further understand
that the City of Carlsbad is planning to carry out the storm drain repairs and realignment
with the associated grading repairs of lower canyon terrain erosion resulting from the pipe
failure.
Ill. PROPOSED DEVELOPMENT
As depicted on Plate 2, a new residential dwelling with detached garage and associated
improvements are planned for the upper reaches of the subj~ct property. Moderate to
significant grade alterations using cut-fill grading techniques are proposed to achieve
design grades and construct level surfaces for the support of the planned structures and
improvements. The planned grade alterations primarily consist of minor cutting of the
higher areas to the southwest and placing fills over the existing northern slope to new
design configurations. Modular (sequential) retaining walls are also incorporated into the
designs to accommodate ground level transitioning and allow 2: 1 slope gradients.
The existing 24-inch storm drain pipe crossing the site will be abandoned and replaced with
a 36-inch pipe installed along a new alignment. The new alignment extends from the lower
terrain over the ascending slope and crosses the project property to the existing inlet box
north of Highland Drive as shown on Plate 2. The storm drain installation will be
performed as a part of the City of Carlsbad storm drain reconstruction project which also
includes reconstruction of the failure scrap within the lower slope terrain. New storm drain
profile with respect to existing terrain ·and proposed grading is depicted on the enclosed
Cross.:section at Proposed Storm Drain, Plate 3.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION l'ERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I·
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 3
OCTOBER 1, 2003
Construction details are unknown. However, it is anticipated that conventional wood-frame
and stucgo buildings supported on shallow stiff continuous strip and spread pad concrete
footings with slab-on-grade floor foundations will be utilized.
IV. GEOTECHNICAL CONDITIONS
Geotechnical conditions at the site remain substantially unchanged since the preparation
of the referenced reports. The study property is underlain by Formational rock units that
range from Pleistocene age Terrace Deposits at the near surface to Eocene age
sandstone units at depth (Reference 3). Project slopes are mantled by an undetermined
thickness of undocumented fills. The upper, southeast portion of the property consists of
nearly level terrain that gives way to steep canyon topography to the northwest. A
subsurface profile as determined from available geotechnical data is depicted on the
enclosed Geologic Cross-Section, Plate 4.
A. Slope Stability
Site topographic conditions are depicted on Plate 2. Near vertical slope conditions
mark the lower canyon terrain where a recent storm drain failure has occurred. No
indications of deep-seated instability were noted; however, rotational-type slope
failures within the existing lower near-vertical slopes may be expected under
current site conditions. We understand the City of Carlsbad is developing plans for
the replacement of the storm drain and repair grading of the lower slope failure
areas within the impacted areas.
The existing northern embankment is a fill over natural slope type construction.
The embankment was created by placing undocumented fill deposits over the pre-
grading _sloping natural terrain. The fills were placed without engineering
observation and compaction testing control. It is reported that lower keyways or
adequate benching of sloping ground receiving fill were also not provided.
Furthermore, existing fills are generally loose deposits and contain trash and
organic debris. Based on the available information, the existing northen graded fill
slope is considered marginally stable (low safety factor) and subject to failure upon
saturation, surcharging or a significant seismic event.
B. Seismic Response Coefficients
For design purposes, site specific seismic parameters were determined as part of
this investigation in accordance with the Uniform Building Code. The following
parameters are consistent with the indicated project seismic environment and may
be utilized for project design work:
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 4
OCTOBER 1, 2003
TABLE 1
... ..
•. s~1~mic-. aeismic; Response Coefffcients Site :Soil. • • -aeisinic:
Profile -Seismic '. · Zone~· _ ~~,µrce. :_ -N~ I Nv-,. : Ca:'.·,·J.· .:_o~::.:--1---: :.Ts : : --1· TY:pe-Zon~ F~~tdi<· --.-.·Type ,. T.9 ' '; -•. ' . ' ', , .. -'. '
I SD I 4 I 0.4 I B I 1.0 I 1.1 I 0.44 I 0.68 I 0.614 I 0.123 I
Accordinq to Chapter 16, Division IV of the 1997 Uniform Buildinq Code.
V. CONCLUSIONS
Based upon our review of the referenced technical reports and recent site inspection,
development of the property for residential purposes, substantially as proposed, is
considered feasible from a geotechnical viewpoint. The site is underlain by loose
undocumented fills within_ the pad and northern slope areas over Formational sandstone
units which are exposed in an overly steepened slope condition within the lower terrain
below the proposed building areas.
Geotechnical factors presented below are unique to the project site and will influence
grading procedures and the associated development costs:
* A recent storm drain failure in the lower slope areas below the property has
resulted in high levels of erosion and near vertical slopes. The lower slope failure
has not yet impacted the upper graded slope along the project northern boundary.
However, future local impacts within the existing storm drain alignment is
considered likely, particularly in an event of heavy rainfall.
* Existing slope areas of the property were developed by placing loose
undocumented fills over sloping natural terrain. The fills also contain an
abundance of trash debris and deleterious materials (Reference 3). The northern
slope is marginally stable and should be removed and properly reconstructed as
recommended in following sections. •
* The replacement of the storm drain and repair grading of the lower slope failure
within the impacted areas are planned by the City of Carlsbad. The new storm
drain alignment crosses the property as shown on Plate 2. The remaining portions
of the existing pipe at the project site should also be removed as part of the site
remedial grading and/or appropriately abandoned per the approved plans.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 5
OCTOBER 1, 2003
* Site existing fills and upper weathered Terrace Deposits/Formational rock are not
suitable for support of planned structures and improvements in their present
condition. The entire section of existing fills, topsoils and upper weathered Terrace
Deposits/Formational rock should be removed and properly recompacted using
remedial grading techniques as recommended in a following section. Added
excavations of cut ground will be required in the case of cut/fill pads in order to
eliminated non-uniform bearing soils transitioning.
* The overall stability of graded building surfaces developed over sloping terrain is
most dependent upon adequate keyjng and benching of fills into the undisturbed
bedrock during grading operations. At the project site, added care should be given
to proper construction of keyways and benching during regrading.
* In general, reconstruction of the northern slope and regrading of the site to design
elevations may be considered difficult overall. Portions of the project regrading and
reconstruction within the storm drain alignment may be coordinated wi_th the City ·
of Carlsbad, a_nd installation of the new drain pipe. Proposed modular transition
walls near the lower slope areas may also be difficult to construct due to necessary
deepened foundations for setback requirements and adequate clearance from t_he
top of the new storm drain pipe to bottom of the wall foundations. Appropriate
recommendations are given in the following sections.
* Import soils, if required to complete grading and achieve final design grades,
should conform to the requirements of this report as specified in the following
sections.
* Finish grade soils are expected to consist of sandy deposits (SP/SM) with very low
expansion potential (El less than 21). Actual classification and expansion
characteristic of finished grade soil mix can only be provided in the final as-graded
compaction report based on appropriate testing. Final foundation and slab
subgrade soils should be tested at the completion of pad construction to confirm
expansion characteristics of bearing soils which will govern final foundations and
slab design.
* Adequate site surface, subsurface and slope face drainage control are critical
factors in the future stability of the developed property as planned. Drainage
facilities should be designed and installed for proper control and disposal of
surface and subsurface water.
* Liquefaction and seismically induced settlements will not be a factor in the
development of the project site provided our remedial grading recommendations
are followed.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADlNG SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 6
OCTOBER 1, 2003
* Post construction settlements are not expected to be factors in the construction of
··the planned buildings at the project site provided our remedial grading and
foundation recommendations are implemented during the construction phase of the
project.
* Soil collapse will not be a factor in the constructions of the planned buildings at the
study site provided our recommendations are followed.
VI. RECOMMENDATIONS
The following recommendations are consistent with the indicated geotechnical conditions.
at the project site and should be reflected on the final plans and implemented during the
construction phase. Added or modified recommendations may also be appropriate and
can be provided at the final plan review phase:
A. Remedial Grading and Earthworks
Cut/fill and remedial grading techniques may be used in order to achieve final
design grades and construct a stable ground for supporting the planned structures
and improvements. All grading and earthworks should be completed in
accordance with Appendix Chapter 33 of the Uniform Building Code, City of
Carlsbad Grading Ordinances, the Standard Specifications for Public Works
Construction, and the requirements of the following sections wherever applicable:
1. Clearing and Grubbing -Remove surface vegetation, trash, debris and other
unsuitable/deleterious materials from all areas of proposed new fills,
improvements, and structures plus 10 feet minimum, or as directed in the field.
The prepared ground should be inspected and approved by the project
geotechnical engineer or his designated representative.
All irrigation lines, abandoned pipes and undergrounq structures should be
properly removed from the construction areas. Existing underground utilities in
the construction areas Should also be pot-holed, identified and marked prior to
the actual work. Inactive lines should be properly removed or may be
abandoned as approved in the field. Voids created by the removals of the
underground pipes or structures should be properly backfilled with compacted
fills as recommended herein.
2. Removals and Remedial Grading -Remedial techniques should be used in
order to construct safe and stable ground and building pad surfaces suitable for
the support of the proposed structures and improvements. The entire section
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION l'ERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 7
OCTOBER 1, 2003
of existing site fills, topsoils and weathered soft sandstone units in the areas to
receive new fills, structures and improvements plus 10 feet where possible, and
as directed in the field should be removed to the underlying competent bedrock
and placed back as properly compacted fills. Actual limits and depths of
removals should be given in the field by the project geotechnical consultant.
However, approximate depths may be obtained from the enclosed Test Borings
and Test Pit Logs (Plates 6-14).
Project grading operations may be coordinated with the City of Carlsbad_ to
concur with the lower slope repairs of the impacted areas, as well as the
planned trenching and new storm drain installation within the proposed
realignment.
3. Cut-Fill Transition / Undercuts -Ground transition from excavated cut to
placed fill should not be permitted underneath the proposed structures and
improvements. Building foundations and floor slabs should be uniformly
supported on undisturbed cut ground or entirely founded on compacted fills.
Transition areas will require special treatment. The cut portion of the cut/fill
pads plus 10 feet should be undercut to a sufficient depth to provide for a
minimum of 3 feet of compacted fill mat below rough finish grades, or at least
12 inches of compacted fill beneath the deepest footing whichever is more. In
the roadways, driveway, parking and on-grade slabs/improvement transition
areas there should be a minimum of 12 inches of compacted soils below rough
finish subgrade.
4. Fill Materials and Compaction -Soils generated from the excavation of site
weathered sandstone will predominantly consist of good quality sandy materials
which will work well in compacted fills. Soils generated from the removals of
the project existing fills will include trash debris and deleterious materials. All
trash debris and deleterious material should be selectively separated from the
existing project fills to the satisfaction of the project geotechnical consultant
prior to reuse as new site fills. Separated trash debris and unsuitable materials
should be properly removed and exposed of. Clay bearing soils, if
encountered,-should be selectively buried in deeper fills at a minimum of 4 feet
below rough. finish pad grades and 15 feet away from the finish slope face.
Project new fills shall be clean deposits free of vegetation, organic matter,
deleterious materials, trash and debris consisting of minus 6-inch particles as
approved in the field. •
Uniform bearing soil conditions should be constructed at the site by the grading
operations. Site fills should be adequately processed, thoroughly mixed,
moisture conditioned to near optimum moisture levels as directed in the field,
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 8
OCTOBER 1, 2003
placed in thin uniform horizontal lifts and mechanically compacted to a
minimum of 90% of the corresponding laboratory maximum dry density per the
ASTM D-1557, unless otherwise specified.
. .
5. Shrinkage and Import Soils -Based upon our analysis, on-site soils may
shrink approximately 5% to 15% on volume basis when compacted to a
minimum of 90% compaction levels. Import soils, if required to complete repair
grading or achieve final design grades, should be clean sandy deposits
( expansion index less than 21) and approved by the project geotechnical
engineer prior to delivery to the site. Non-expansive sandy import soils, if any,
should be used for wall backfills and placed within the upper finish subgrade
levels.
6. Reconstruction of Existing Slope and New Graded Slope -The existing
northern fill slope should be removed and reconstructed as a part of the project
remedial grading operations in accordance with the requirements of this report.
Slope reconstruction is depicted on the enclosed Typical Slope Reconstruction
Details, Plate 5.
The new reconstructed fill slope shall be provided with a lower keyway. The
keyway should maintain a minimum depth of 2 feet into the competent bedrock
with a minimum width of 20 feet as approved by the project geotechnical
engineer or his designated representative. The keyway should expose
competent bedrock throughout, with the bottom heeled back a minimum of 5%
into the natural hillside and inspected and approved by the project geotechnical
engineer. Additional level benches should be constructed into the natural
hillside as the fill slope construction progresses·. The slope should be
reconstructed to achieve existing and/or flatter slope design gradients. Provide
slope reinforcement consisting of Tensar UX-1400 (or greater from the same
series) at approximately 4 vertical feet for slope gradients steeper than 2:1 as
shown on the enclosed Plate 5. Slope reinforcement should be placed 1 ½ feet
from the finish slope face to the back side heel of excavated benches within the
compacted embankment fills for additional stability. Intermediate slope face
reinforcement consisting of Tensar BX-1100 (or greater from the same series),
should be provided to enhance surficial stability as shown. Slope reinforcement
shall be placed in conformance with the enclosed Slope Reinforcement
Installation Guide enclosed herein as Appendix A.
Reconstructed slopes should be compacted to a minimum of 90% of the
corresponding laboratory maximum density value in accordance with ASTM D-
1557 out to the slope face. Back rolling at a minimum of 4-foot vertical
VINJE & MIDr:>LETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1.
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 9
OCTOBER 1, 2003
increments and track-walking the completed slope is recommended. Field
density tests should be performed to confirm adequate compaction levels within
the slope face.
New project graded slopes should be programmed for 2:1 gradients maximum.
Graded slopes constructed at 2:1 gradients will be grossly stable with respect
to deep seated and surficial failures for the anticipated design maximum vertical
heights. All fill slopes shall be provided with a lower keyway as specified, and
compacted to 90% (minimum) of the laboratory standard out to the slope face.
Cut slopes should ·be inspected and approved by the project geotechnical
consultant during the grading to confirm stability. In the event loose existing
fills/topsoils are encountered at the cut surfaces or portions thereof, the
impacted slope face may require reconstruction as stability fill slope or the
slope face may be moisture conditioned and compacted in-place by track-
walking with heavy construction equipments. Specific recommendations should
be provided by the project geotechnical consultant in the field based on actual
cut slope face exposures.
7. Wall Back Drainage -A wall back drainage system should be provided behind
all project retaining walls. The wall back drainage system should consist of a
minimum 18-inches wide trench excavated to the depths of the wall foundation
level w~th a minimum 4-inch diameter, Schedule 40 (or SOR 35), perforated
pipe surrounded with a minimum 2.25 cubic feet per foot of ¾-crushed rocks
wrapped in filter fabric (Mirafi 140 N), or Caltrans Class 2 permeable aggregate
installed at suitable elevations to allow for adequate fall via a non-perforated
solid pipe to an approved outlet. Protect pipe outlet as appropriate. Filter fabric
can be eliminated if Class 2 permeable material is used. Typical wall back
drain system is depicted on the enclosed Plate 15. Provide appropriate
waterproofing as indicated on the approved project drawings.
8. Storm Drain Trenching and Backfilling -All trenching and backfill operations
associated with the new storm drain installation should be completed as
specified in the "Preliminary Geotechnical Investigation, North End of Highland
Drive," prepared by this office, Job #03-262-P, dated June 17, 2003 (Referertce
1), and subsequent Grading Plan Review letter, dated October 1, 2003. The
referenced report and plan review letter should be considered and utilized in
conjunction with this report where appropriate and applicable.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 10
OCTOBER 1, 2003
9. Surface Drainage and Erosion Control -A critical element to t~~ continued
stability of the building pads and slopes is an adequate surface drainage
system and protection of the slope face. This can most effectively be achieved
by appropriate vegetation cover and the installation of the following systems:
* Drainage swales should be provided at the top and toe of-the slopes per
project civil engineer design.
* Building pad surface run-off should be collected and directed away from the
planned buildings and improvements to a selected location in a controlled
manner. Area drains should be installed.
* The finished slope should be planted soon after completion of grading in
accordance with the project approved landscape plans. Unprotected slope
faces will be subject to severe erosion and should not be allowed. Over-
watering of the slope faces shall not be allowed. Only the amount of water
to sustain vegetation should be provided. Native broad-leaf grasses which
require minimal amounts of water to sustain vegetation life are
recommended.
* Temporary erosion control facilities and silt fences should be installed during
the construction phase periods, and until landscaping is fully established as
indicated and specified on the approved project grading/erosion plans.
10. Engineering Inspections -All grading operations including removals,
suitability of earth deposits used as compacted fill, and compaction procedures
should be continuously inspected and tested by the project geotechnical
-consultant and presented in the finar as-graded compaction report. The_ nature
of finish subgrade soils should also be confirmed in the final compactic;m report
at the completion of grading.
Geotechnical engineering inspections shall include but not limited to the
following:
* Initial Inspection -After the grading/brushing limits have been staked but
before grading/brushing starts.
* Keyway/bottom of over-excavation inspection -After the bottom of over-
excavation is exposed and prepared to receive fill but before fill is placed.
* Cut slope/excavation inspection -After the excavation is-started but before
the vertical depth of excavation is more than 5 feet. Local and CAL-OSHA
safety requirements for open excavations apply.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION l'ERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I.
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 11
OCTOBER 1, 2003
* Fill/wall backfill inspection -After the fill/wall backfill placement is started but
before the vertical height of fill/backfill exceeds 2 feet. A minimum of one
test shall be required for each 100 lineal feet maximum with the exception of
wall backfills where a minimum of one test shall be required for each 25
lineal feet maximum. Wall backfills shall also be mechanically compacted
to at least 90% compaction levels unless otherwise specified. Finish rough
and final pad grade tests shall be required regardless of fill thickness.
* Foundation trench inspection -After the foundation trench excavations but
before steel placement.
* Foundation bearing/slab subgrade soils inspection -Prior to the placement
of concrete for proper moisture and specified compaction levels.
* Geotechnical foundation/slab steel inspection -After the steel placement is
completed but before the scheduled concrete pour.
* . Subdrain/wall back drain inspection -After the trench excavations but during
the actual placement. All material shall conform to the project material
specifications and approved by the project geotechnical engineer.
* Underground utility/plumbing trench inspection -After the trench excavations,
but before installation of the underground facilities. Local and CAL-OSHA
·safety requirements for open excavations apply. Inspection of the pipe
bedding may also be required by the project geotechnical engineer.
* Underground utility/plumbing trench backfill inspection -After the backfill
placement is started above the pipe zo"ne, but before the vertical height of
backfill exceeds 2 feet. Testing of the backfill within the pipe zone, may also
be required by the governing agencies. Pipe bedding and backfill materials
shall conform to the governing agencies requirements and project soils
report if applicable. All trench backfills shall be mechanically compacted to
a minimum of 90% compaction levels unless otherwi~e specified. Plumbing
trenches more than 12 inches deep maximum under the interior floor slabs
should also be mechanically compacted and tested for a minimum of 90%
compaction levels. Flooding or jetting techniques as a means of compaction
method shall not be allowed.
* Pavement/improvements subgrade and basegrade inspections -Prior to the
placement of concrete or asphalt for proper moisture and specified
compaction levels.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION l'ERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
8. Foundations and Interior Floor Slabs
PAGE 12
OCTOBER 1, 2003
The following preliminary recommendations are consistent with very low expansive
(expansion index less than 21) sandy (SP/SM) foundation bearing soils. Final
foundation and slab design will depend on expansion characteristics of finish grade
soils and the actual fill differential thickness underneath the proposed buildings.
All recommendations should be confirmed and/or revised as necessary in the
rough grading compaction report based on-site as-graded geotechnical conditions
and actual testing of the foundation bearing soils. Individual building sites may
require specific foundation/slab design and may be anticipated. Additional specific
recommendations may also be necessary and should be given at the time of the
final plan review phase when detailed grading and structural/architectural drawings
are available:
1. All building and retaining wall foundations planned on or near the top of
descending slopes should be adequately deepened to provide a minimum
horizontal distance of 7 feet or one-third of the slope height, whichever is
greater (need not exceed 40 feet maximum) between the bottom outside edge
of the footing and face of slope. Actual construction details should be provided
by the project structural engineer.
2. Continuous strip and perimeter wall foundations should be sized at least 15
inches wide and 18 inches deep for single and two-story structures. Spread
pad footings should be at least 30 inches square and 12 inches deep. Footing
depths are measured from the lowest adjacent ground surface, not including
the sand/gravel beneath floor slabs. Exterior continuous footings should
enclose the entire building perimeter. •
3. Continuous interior and exterior foundations should be reinforced by at least
four #4 reinforcing bars. Place a minimum of 2-#4 bars 3 inches above the
bottom of the footing and a minimum of 2-#4 bars 3 inches below the top of the
footing. Reinforcement details for spread pad footings should be provided by
the project architect/structural engineer. •
4. All interior slabs should be a minimum of 4 inches in thickness, reinforced with
#3 reinforcing bars spaced 16 inches on center each way, placed mid-height
in the slab. Slabs should be underlain by 4 inches of clean sand (SE 30 or
greater) which is provided with a 6-mil plastic moisture barrier placed mid-height
in the sand. In the case of good quality sandy subgrade soils, as approved by
the project geotechnical engineer, the 6-mil plastic moisture barrier may be laid
directly over the slab subgrade and covered with a minimum of 2 inches of
clean sand (SE 30 or greater).
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-034"3
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 13
OCTOBER 1, 2003
5. Provide "softcut" contraction/control joints consisting of sawcuts spaced. 10 feet
on center maximum each way for all interior slabs. Cut as soon as the slab will
support the weight of the saw, and operate without disturbing the final finish
which is normally within 2 hours after final finish at each control joint location
or 150 psi to 800 psi. The sawcuts should be a minimum of 1-inch in depth but
not to exceed 1 ¼-inches in depth maximum. Anti-ravel skid plates should be
used and replaced with each blade to avoid spalling and raveling. Avoid
wheeled equipments across cuts for at least 24 hours.
6. Provide re-entrant corner reinforcement for all int~rior slabs. Re-entrant
corners will depend on slab geometry and/or interior column locations. The
enclosed Plate 16 may be used as a general guideline.
7. Foundation trenches and slab subgrade soils should be inspected and tested
for proper moisture and specified compaction levels and approved by the
project geotechnical consultant prior to the placement of concrete.
C. Exterior Concrete Slabs / Flatworks
1. All exterior slabs (walkways, and patios) should be a minimum of 4 inches in
thickness -reinforced with 6x6/10x10 welded wire mesh carefully placed mid-
height in the slab.
2. Provide "tool joint" or "softcut" contraction/control joints spaced 10 feet on
centers (not to exceed 12 feet maximum) each way. Tool or cut as soon as the
slab will support weight, and can be operated without disturbing the final finish
which is normally within 2 hours after final finish at each control joint location
or 150 psi to 800 psi. Tool or softcuts should be a minimum of 1-inch but
should not exceed 1 ¼-inches deep maximum. In the case of softcut joints,
anti-ravel skid plates should be used and replaced with each blade to avoid
spalling and raveling. Avoid wheeled equipments across cuts for at least 24
hours.
3. All exterior slab designs should be confirmed in the final as-graded compaction
report.
4. Subgrade soils should be tested for proper moisture and specified compaction
levels and approved by the project geotechnical consultant prior to the
placement of concrete.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
D. Soil Design Parameters
PAGE 14
OCTOBER 1, 2003
The following preliminary soil design parameters are based on the tested
representative samples of on-site earth deposits. All parameters should be re-
evaluated when the characteristics of the final as-graded soils have been
sp.ecifically determined:
* Design wet density of soil = 124.3 pcf.
* Design angle of internal friction of soil= 31 degrees.
* Design active soil pressure for retaining structures = 40 pcf (EFP), level backfill,
cantilever, unrestrained walls. •
* Design active soil pressure for retaining structures = 62 pcf (EFP), 2: 1 sloping
backfill surface, cantilever, unrestrained walls.
* Design at-rest soil pressure for retaining structures = 60 pcf (EFP), non-
yielding, restrained walls.
* Design passive soil pressure for retaining structures = 388 pcf (EFP), level
surface at the toe.
* Design passive soil pressure for retaining structures = 156 pcf (EFP), 2:1
sloping down condition at the toe.
* Design coefficient of friction for concrete on soils = 0.38.
* Net allowable foundation pressure for on-site compacted fills (minimum 15
inches wide by 18 inches deep footings) = 2000 psf.
* Allowable lateral bearing pressure (all structures except retaining walls) for on-
site compacted fill = 150 psf/ft.
Notes:
* Use a minimum safety factor of 1.5 for wall over-turni!7g and sliding stability.
However, because large movements must take place before maximum passive
resistance can be developed, a safety factor of 2 may be considered for sliding
stability where sensitive structures and improvements are planned near or on
top of retaining walls. •
* When combining passive pressure and frictional resistance the passive
component should be reduced by one-third.
* The net allowable foundation pressure provided herein was determined for
footings having a minimum width of 15 inches and depth of 18 inches. The
indicated values may be increased by 20% for each additional foot of depth and
20% for each additional foot of width to a maximum of 4500 psf, if needed. The
allowable foundation pressure provided herein also applies to dead plus live
loads and may be increased by one-third for wind and seismic loading.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 15
OCTOBER 1, 2003
* The allowable lateral bearing earth pressures may be increased by the amount
of the designated value for each additional foot of depth Jo a maximum of 1500
pounds per square foot.
* Construction plans, details and profile for the modular (sequential) retaining
walls incorporated into the northern slope construction, should be reviewed and
approved by the project geotechnical consultant. Additional recommendations
should be given at that time if necessary.
E. Asphalt and PCC Pavement Design
Specific pavement designs can best be provided at the completion of rough
grading based on R-value tests of the actual finish subgrade soils; however, the
following structural sections may be considered for cost estimating purposes only
(not for construction):
1. A minimum section of 3 inches asphalt on 6 inches Caltrans Class 2 aggregate
base may be considered for on-site asphalt paving surfaces. Actual design will
also depend on the design Tl and approval of the City of Carlsbad.
Base materials should be compacted to a minimum of 95% of the
corresponding maximum dry density (ASTM D-1557). Subgrade soils beneath
the asphalt paving surfaces should also be compacted to a minimum of 95%
of the corresponding maximum dry density within the upper 12 inches.
2. Residential PCC driveways and parking supported on non-expansive to very
low expansive ( expansion index of less than 21) granular subgrade soils should
be a minimum of 5 inches in thickness, reinforced with #3 reinforcing bars at 18
inches on centers each way, placed mid-height in the slab. Subgrade soils
beneath the PCC driveways and parking should be compacted to a minimum
of 90% of the corresponding maximum dry density. •
Provide "tool joint" or "softcut" contraction/control joints spaced 1 0 feet on
center (not to exceed 15 feet maximum) each way. Tool or cut as soon as the
slab will support weight, and can be operated without disturbing the final finish
which is normally within 2 hours after final finish at each control joint location
or 150 psi to 800 psi. Tool or softcuts should be a minimum of 1-inch but
should not exceed 1 ¼-inches deep maximum. In case of softcut joints, anti-
ravel skid plates should be used and replaced with each blade to avoid spalling
and raveling. Avoid wheeled equipments across cuts for at least 24 hours.
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 16
OCTOBER 1, 2003
3. Subgrade and basegrade soils should be tested for proper moisture and the
. specified compaction levels and approved .by the project geotechnical
consultant prior to the placement of the base or asphalt/PCC finish surface.
4. Base section and subgrade preparations per structural section design, will be
required for all surfaces subject to traffic including roadways, travelways, drive
lanes, driveway approaches and ribbon (cross) gutters. Driveway approaches
within the public right-of-way should have 12 inches subgrade compacted to a
minimum of 95% compaction levels, and provided with a 95% compacted Class
2 base section per the structural section design. Base section may not be
required under curb and gutters, and sidewalks in the case of non-expansive
subgrade soils (expansion index less than 21). Appropriate recommendations
should be given in the final as-graded compaction report.
F. General Recommendations
1. The minimum foundation design and steel reinforcement provided herein are
based on soil characteristics and are not intended to be in lieu of reinforcement
necessary for structural considerations. All recommendations should be further
evaluated in the site specific study for each individual lot and confirmed by the
project architect/structural engineer.
2. Adequate staking and grading control is a critical factor in properly completing
the recommended remedial and site grading operations. Grading control and
staking should be provided by the project grading contractor, or surveyor/civil
engineer, and is beyond the geotechnical engineering services. Inadequate
staking and/or lack of grading control may result in unnecessary additional
grading which will increase construction costs.
3. Footings located on or adjacent to the top of slopes should be extended to a
sufficient depth to provide a minimum horizontal distance of 7 feet or one-third
of the slope height, whichever is greater (need not exceed 40 feet maximum)
between the bottom edge of the footing and face of slope. This requirement
applies to all improvements and structures induding fences, posts, pools, spas,
etc. Concrete and AC improvements should be provided with a thickened edge
to satisfy this requirement.
4. Expansive clayey soils should not be used for backfilling of any retaining
structure. All retaining walls should be provided with a 1: 1 wedge of granular,
compacted backfill measured from the base of the wall footing to the finished
surface.
VINJE & MIDDLETQN ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
PAGE 17
OCTOBER 1, 2003
5. All underground utility and plumbing trenches should be compacted to a
minimum of 90% of the maximum dry density of the soil unless otherwise
specified. Care should be taken not to crush the utilities or pipes during the
compaction of the soil. Non-expansive, granular backfill soils should be used.
6. Site drainage over the finished pad surfaces should flow away from structures
onto the street in a positive manner. Care should be taken during the
construction, improvements, and fine grading phases not to disrupt the
designed drainage patterns. Roof lines of the buildings should be provided with
roof gutters: Roof water should be collected and directed away from the
buildings and structures to a suitable location. Considerations should be given
to adequately damp-proof/waterproof the basement walls/foundations and
provide the planter areas adjacent to the foundations with an impermeable liner
and a subdrainage system.
7. Final plans should reflect preliminary recommendations given in this report.
Final foundations and grading plans may also be reviewed by the project
geotechnical consultant for conformance with the requirements of the
geotechnical investigation report outlined herein. More specific
recommendations may be necessary and should be given when final grading
and architectural/structural drawings are available.
8. All foundation trenches should be inspected to ensure adequate footing
embedment and confirm competent bearing soils. Foundation and slab
reinforcements should also be inspected and approved by the project
geotechnical consultant.
9. The amount of shrinkage and related cracks that occurs in the concrete slab-
on-grades, flatworks and driveways depend on many factors the most important
of which is the amount of water in the concrete mix. The purpose of the slab
reinforcement is to keep normal concrete shrinkage cracks closed tightly. The
amount of concrete shrinkage can be minimized by reducing the amount of
water in the mix. To keep shrinkage to a minimum the following should be
considered:
* Use the stiffest mix that can be handled and consolidated satisfactorily.
* Use the largest maximum size of aggregate that is practical. For example,
concrete made with %-inch maximum size aggregate usually requires about
40 lbs. more (nearly 5 gal.) water per cubic yard than concrete with 1-inch
aggregate. •
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, Escondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PLAN REVIEW GEOTECHNICAL UPDATE REPORT
HIGHLAND DRIVE, CARLSBAD
* Cure the concrete as long as practical.
PAGE 18
OCTOBER 1, 2003
The amount of slab reinforcement provided for conventional slab-on-grade
construction considers that good quality concrete materials, proportioning,
craftsmanship, and control tests where appropriate and applicable are provided.
10. A preconstruction meeting between representatives of this office, the property
owner or planner, the grading contractor/builder, and the city inspector is
recommended in order to discuss grading/construction details associated with
site development.
VII. LIMITATIONS
The conclusions and recommendations provided herein have been based on available
data obtained from pertinent reports and plans, as well as our experience with the soils and
Formational materials located in the general area. The materials encountered on the
project site and utilized in our laboratory testing are believed representative of the total
area; however, earth materials may vary in characteristics between excavations.
Of necessity we must assume a certain degree of continuity between exploratory
excavations and/or natural exposures. It is necessary, therefore, that all observations,
conclusions, and recommendations are verified during the grading operation. In the event
discrepancies are noted, we should be contacted immediately so that an inspection can
be made and additional recommendations issued if required.
The recommendations made in this report are applicable to the site at the. time this report
was prepared. It is the responsibility of the owner/developer to ensure that these
recommendations are carried out in the field.
It is almost impossible to predict with certainty the future performan·ce of a property. The
future behavior of .the site is also dependent on numerous unpredictable variables, such
as earthquakes, rainfall, and on-site drainage patterns.
The firm of VINJE & MIDDLETON ENGINEERING, INC., shall not be held responsible for
changes to the physical conditions of the property such as addition of fill soils, added cut
slopes, or changing drainage patterns which occur without our inspection or control.
The property owner(s) should be aware that the development of cracks in all concrete
surfaces such as floor slabs and exterior stucco are associated with normal concrete
shrinkage during the curing process. These features depend chiefly upon the condition of
concrete and weather conditions at the time of construction and do not reflect detrimental
ground movement. Hairline stucco cracks will often develop at window/door corners, and
VINJE & MIDDLETON ENGINEERING, INC. 2450 Vineyard Avenue, facondido, California 92029-1229 • Phone (760) 743-1214 • Fax (760) 739-0343
GEOTECHNICAL INVESTIGATIONS GRADING SUPERVISION PERC TESTING ENVIRONMENTAL INVESTIGATION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
DATE OBSERVED:
LOGGED BY: R.G. -:::
I-Q w ~ w
I.. 2 ....
:r: !:!: ... (I)
0. en
... Q
0 w
0 mw
"" C:..J -::>a.
(I) t--:
~ (I)-_-c
0 ocn
w < ...J z
0 ..J m ::,
.... 80 CJ
-
-
-
-
85 ~ .
.
-.
90· .
.
-.
95-.
.
.
.
100· .
.
.
105.
.
.
.
110-
-
115 -
.
120-
JOB NO.: GN-l
w ...J a.
:E < (I)
!.:: ...J ::, m.
11/7 /87 METHOD OF DRILLING: 30 inch bucket auger
4113 lbs to 25', 2981 lbs to 41', 2168 lbs to 70'
GROUND ELEVATION: -155± LOCATION: See Geotechnical Map
.... >-~
w~ c:o
Qc.. a:.,_ .... :::,_ w t--o>-Cl)W _.., < ...
0% ..JC/)
::::o. a.z
zW 0 -c
BORING NO. B-1
(CONTINUED)
DESCRIPTION
White fine SANDSTONE, slightly moist,
·sOIL TEST
dense contacts: horizontal, undulatory, gradational
@ 83' clayey siltstone, 7" thick
Total ·nepth 85'
No water
,
LOG OF BORING !FIGURE: B-J
PLATE 8
:
DATE OBSERVED: __ .... I 0""-(2=,.3...,_lw.8 .. 7 ____ METHOD OF OR ILL ING: Hatachi Trac~ka:.....:H~o~e~------,--
OGGED BY: R.G.
;:: --I-0 .... C 1/J
UJ I-0 UJ _,
.u < 0 alw a.
LI. 0 I.. c:: -I :I --::> C. <
:I: I.. C') .... :::E CD
I-C') ~ !!'.!< ~ a. C') 0 ea, w < -l
C -l -' -::> m ::> m -0 -
--
--
-
-
10-.
--
15-.
-
I .OGGE0 BY: • RIG I
--
I .
.
.
&-
.
I -.
1~
[> --< . t> "'.: >
'«.S > 0-
-
-
JOB NO.: GN-1
I
GROUND ELEVATION: 150+ LOCATION: See Geotechnical Map
....
w!
ct I-
~% c,W -1-oz
:EC
(.)
>-u:-a:u Cc. -TEST PIT NO. ___ 3 ___
w u>-<t: -' en a.z -w DESCRIPTION ::c
Fill: Red brown medium SAND, moist,
"-.. loose
"'--1-,,,.c_o-:n...;t_a...;c~t...;:_..;.N..:6;..;0;;.;Ee-',:.....6:..0:..0..:N~...,,,.--------~---4
Bedrock: Linda Vista Formation; Red.
.
brown coarse SANDSTONE, slightly
moist, dense
bedding: horizontal
below 6' grades to light brown medium
sandstone
NOTE: Fill exposed in northern half
of test pit to bottom
@ 12' concrete pieces in fill
Total Depth 14'
No water
SOIL TEST
GROUND ELEV I. TION: 1!?0+ LOCATION: See Geo technical Ma:e
TEST PIT NO. 4
~ Fill: Red brown silty medium SAND, --slightly moist, loose
Bedrock: Linda Vista Formation; Red
brown ~oarse SANDSTONE, slightly·
moist, dense
NOTE: Fill exposed in western portion
of test pit to bottom
Fill/bedrock
contact: N35W, 50°W
.
contact: horizontal, undulatory
Santiago formation; white brown fine to
medium SANDSTONE." slightl v moist. dense
T~tal Depth 21'
No water
l LOG OF TEST PIT jFIGURE: TP-2
.. PLATE 11
~ DATE OBSERVED:
LOGGED BY:
r r r r r
f
'
' '
' r
--t-
UJ
LIJ I.I. -::: I-Q,.
UJ 0 --
. .
-
'5-
---.
10-
---
1S-· -
-
;.;_
0 I--0 I-< 0
0 I.I. -I.I. a,
"' :t "' 0 < ..I ..J Cl u
r r r
LOGGED BY:
' I
I'
--
.
-
·s-
-.
-
t.0-
-
-
·-
15-
-
-
Rz!:.i1
Q w w ...I
CJUJ A.
:I C:::..,1 :::> Q,. <
I-:f ID
!!? < ~ gen ...I :::> ::) m
rx
.
R.G.
I
I
I JOB NO.: CN-l
10/23/87 METHOD OF DRILLING: Eatai::b;i I:cack Hee
GROUND ELEVA TIOH: lSQ+ LOCA 'r 10N: See GectecbDjcal l:fap -,.. u:-
LI.I! a:u TEST PIT NO. 9 0 Q,. a: I--::) :::z: uJ ... w u>-SOIL TEST ~ ... <t: oz ...I er,
:lO c.z DESCRIPTION -UJ c., =c
Fill: Dark brown silty medium SAND, --moist, loose contact: E-W, 60°S
Bedrock: Santiago Formation; white
brown medium SANDSTONE, slightly
moist, dense·
crossbedding: horizontal
Total Depth 11'
No water
·r
GROUND ELEVATION: 150+ LOCATION: See GeotechnicaJ Map
TEST PIT NO. 10
Dark brown silty medium SAND, Fill: --moist, loose contact: N40W. 75°W
Bedrock: Linda Vista Formation; Red
brown medium to coarse SANDSTONE,
slightly moist·, dense
fracture plane: N35W, 78°W
Total Depth 11'
INo water
I LOG OF TEST PIT !FIGURE: TP-5
PLATE 14
I
I
I
I
I
I
I
I
I APPENDIX A
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
·' I
I
I
I
I
I
I
I
I
I
forcement
lnstallat,On Gui e
TENSAR® Geog rids are a proven technique for
building steep reinforced slopes without steep
prices-for better and more profitable land use in
a wide number of applications.
This guide covers the recommended steps for
instailation of TEN SAR Geogrids in reinforced slopes.
Figure 1: A Tensar Reinforced Slope
This guide is for illustration and not for design or specification pur-
poses. See disclaimer on page 6.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
f ntroduction
The guideline covers: (a) tools required; (b) cutting
geogrid strips to the required lengths; (c) site
excavation; (d) drainage; (e) placement of uniaxlal
geogrids; (f) fill placement and compaction; (g)
intermediate reinforcement; (h) protection of the
finished slope against erosion; and (i) special
instructions for biaxial geogrids.
Tools
~ Circular saw.
fii:;'J Sawhorses and plywood to construct a work
table to cut geog rids. •
~ Steel pipe for unrolling geogrids on work table.
~] Hog ringer with boxes of hog rings-optional.
~ Steel "U" pins for securing geogrid to ground-
optiona/.
~ Spray paint (one color for each type of geogrid,
if more than one grade is used).
Step 1-Cut Geogrid
~ Color code the ends of the geogrid rolls if more
•• ,:;:•:. 't:."• •.j• • r •
Figure 2: Color Coding Geogrid Rolls
t.~,, ~ ,>?), 'A'i:w •
~ -~ , ',
~ ~
~~,..n-·u,.. ....... ,.,~,. •. ,,...,.,,,.,.
Figure 3: Cutting Geogrids 2
than one type of geogrid is specified (FIGURE 2).
~ Cut geogrids to lengths shown on the construc-
tion drawings. Never cut the heavy ribs that span
the width of the roll.
!;Ji An easy way to cut the geog rid is on a work
table using a circular saw (FIGURE 3).
~ As each length of material is cut, mark and tag it
according to length and type, and stockpile it for
later use.
~ You may want to join several precut geog rid
strips together side-by-side using hog-rings
(FIGURE 4). This step can increase the speed
of subsequent geog rid pf acement and is most
often used on large projects. Tagging strips or
units of joined strips with the elevation and
station can also speed construction.
. The correct geogrid type and lengths must be used
at each lift level according to the project design.
Figure 4: Joining Geogrid Strips .
Biaxial Uniaxial