created a 2 1/2 acre pond which is kept stocked with fish by the owner.
A tributary to Agua Hedionda Creek, this 700 foot wide valley also con-
tains several underground springs.
The remainder of the site is comprised of two foothills separated
by a gentle saddle. Rising from the valley floor at 10-15% slopes is the
western peak at elevation 447 feet and the eastern peak at 555 feet. It
is from these vantage points that the entire project can be seen. Los Manos
Canyon and Squires Dam further to the north are also visible.
2. Geology
There are six geologic units on the site in addition to the minor
manmade fill areas. These units are from the youngest to the oldest;
Quaternary Alluvium, Pleistocene Terrace Deposits, two Teritiary units
within the Del Mar Formation, Cretaceous Age granite rocks. On the basis
of rock type, the site can further be divided into two s.eparate areas.
The northern half of the site is underlain by highly weathered granitic rock,
the bed rock of the area. Locally, there is a thin layer of Pleistocene
Terrace material over the granitic rock. The southern half of the site is
underlain by Tertiary Age sedimentary materials which appear to be hor-
izontally stratified.
A general description of each geologic unit and their general area of
occurance is given below:
Alluvium --Alluvial deposits are confined to the bottoms of mature
canyons and their tributaries, and consist of brown, porous, silty to sandy
served, the soil mantle and vegetation cover on the lower slopes of the
southern region suggests its presents. Experience with this unit in near-
by areas indicates that it is moderately to highly expansive both in its
natural state and when recompacted as fill.
Granitic Rock --The northern region of the property is underlain
by moderate to highly weathered granitic rock. In outcrops on the lower
canyon slopes, the weathered material has the appearance of cemented
sandstone. The excavation characteristics of the granitic materials
and their stability for use in fills vary dependant upon the degree of
decomposition and will require special study during the soils investi-
gation. The decomposed granitic rock has the consistency of silty-sand
and is generally suitable for use as nonexpansive select fill. Where
blasting is ne·eded, some oversized rock will be generated which may
require special provisions in the earthwork specifications with regard to
their placement in fills.
••
B. URBAN ELEMENTS
1. Circulation
Vehicular access to Valle Verde will be provided by Palomar Air-
port Road and Melrose Drive, both designated as major roads on the Cir-
culation Element of the County General Plan. Palomar Airport Road, an
existing County road, will be improved to a 126 foot wide right-of-way
as development occurs in Valle Verde, which will provide for four traveled
lanes and a median strip. Melrose Drive is a proposed 126 foot wide
right-of-way road which lies partially within the City of Carlsbad and par-
tially in an unincorporated area of San Diego County. The County has not
scheduled improvements for Melrose within the next six years, however,
that portion in the County will soon be annexed to the City of Vista who
will there be responsible for its design and construction.
Regional traffic corridors, Interstate 5 and State Highway 78 are
easily reached via Palomar Airport Road. Interstate 5 provides access to
San Diego, Los Angeles, and coastal communities, while State Highway
78 links the North County areas. Both of these routes are now under study
by the Comprehensive Planning Organization (CPO) as possible public
mass transit corridors which will ultimately reach the entire San Diego
County region. In addition, Palomar Airport will serve the needs of gen-
eral aviation aircraft and non-commercial jets of the area with an estimated
practical annual capacity of 435,000 operations by 1990.
•
2. EDUCATIONAL FACILITIES
The Valle Verde project is located within the Carlsbad Unified
School District. According to the District's Estimate of School-Age Stu-
dents, the student population generated by Valle Verde is as follows:
Unit Type
Multi-family
Single-family
Grade Level
K-6 (Elementary)
7-8 (Junior High)
9-12 (High School)
K-6 (Elementary)
7-8 (Junior High)
9-12 (High School)
Number of Students
60
60
84
114
66
117
To accommodate the increase in school-age students, a new ele-
mentary school will be needed. A ten-acre elementary school site ad-
joining the central open space area near the projects eastern boundary
has been proposed. As yet, the State School Board has not formally
accepted the site.
Mira Costa College, located approximately four miles northwest
of the subject property, will serve the proposed development. With a
daytime student enrollment of 1,370 and a daytime capacity of 2,500,
Mira Costa College will be able to adequately accommodate the number
of new community college students generated by the proposed project.
3. WATER
Based on an anticipated population of 4,500 residents and an av-
erage consumption factor of 10 0 gallons per person per day, it is estimated
that Valle Verde residents will require 450,000 gallons of water on a
·.;.
... ··:'.:.
daily basis. Water service is available to the project through an existing
27-inch line in Palomar Airport Road at a minimum pressure of 76 psi. •
Valle Verde is presently within the Carlsbad Municipal Water District
boundaries, therefore, no annexation is necessary .
. .
5. OTHER UTILITIES
San Diego Gas and Electric Company reports that 5, 700 kilowatt
hours of electricity per year are consumed by the average San Diego
County residence. Using this rate of consumption, the proposed project
will require· 23,400 kilowatt hours of electricity per day. According
to the Oceanside branch of San Diego Gas and Electric Company, a 12 kv
3 phase primary line would be required from the intersection of El Camino
Real and Palomar Airport Road to the project site.
The average San Diego County home also consumes 86,000 cubic
feet of gas per year. Using this rate of consumption, the proposed pro-
ject will require 353,500 cubic feet of gas per day. A 2 1/2 inch high
pressure gas line exists in Palomar Airport Road which will be enlarged
to an 18-inch line to serve North County. At present, however, a tap
into the existing 30 inch high pressure line in El Camino Real would be
required.
The Escondido branch of Pacific Telephone has stated that sufficient
services are available nearby and that they will extend the required lines
to the project boundary.
6. COMMUNITY SERVICES
Police Services --Police service will be provided by the City of .
Carlsbad Police Department, located at 1200 Elm Avenue. At present,
there are approximately 45 members on the police staff, or one member
for each 385. 8 population. Accordingly, with an anticipated population
of 4,500, the project will require the addition of 11 new staff members.
The northwest portion of the site and central valley is planned
for medium-low density dwelling units. Gardez:i homes, townhomes and
condominiums are arranged in appropriate clusters to create a continuous
open space and preserve the natural vegetation of the site. Each area
is served by its own internal circulation system of private drives and
parking bays linked to the primary Valle Verde circulation system at con-
trolled access points. Meandering foot paths allow pedestrian access to
major centers of community activity and open spaces. The intent is to
design the residential areas on the valley's lower slopes to preserve
the natural beauty of the creek bed and aligning coastal live oaks.
Both residential areas are physically separated by distance and topo-
graphy from Palomar Airport Road giving a feeling of seclusion and added
community identity. Incremental development minimizes the impact of
construction to residents as the project is built-out. Valle Verde is planned
to be complete in siX approximately equal phases over a six-year period.
All improvements, facilities and services required of the development will
be provided concurrent with need.
2. Neighborhood Commercial, Recreation and Open Space
A feature of the planned residential community is a centrally located
general store, designed to provide Valle Verde residents with essential
' food and convenience items. The close proximity of this small commercial
area eliminates the need for many long-distance shopping trips. It is
located at the major cross roads of the project allowing easy access by
automobile and pedestrian access via foot paths and bicycle trails.
The focal point of the residential community is the creek, lake and
oak trees of the central valley. This area is retained as recreational
open space, both active and passive, for the residents of Valle Verde.
A building forfeiture easement will be recorded with the first phase of
development to permanently commit this area to open space uses. Hiking
and riding trails will link small park areas and vista points to allow en-
joyment of the natural areas. Two small community recreation centers
compliment this open space by providing additional facilities such as a
swimming pool, club house, fishing lake (existing) and equestrian stables
and ring.
The planned community concept allows for a maximum of open space.
The numerous greenbelt areas which lace the site provide the necessary
buffers between developed areas and integrate them with existing natural
features. The greenbelts will be maintained by the residents of Valle
Verde through a homeowner's association.
3. Industrial Park
The southern portion of the development site is comprised of two
plateaus of sufficient size to allow the large pad areas required of indus-
trial parks. The approach zone of Palomar Airport, passing over the pla-
' tea us, is unconducive to residential uses or commercial us es involving
large assemblies of people. A planned industrial use with its required
deep setbacks and low percentage of lot coverage is a more appropriate
use. The greenbelt areas surrounding the industrial area and the land-
scaping required by the PM Zone will buffer the site from adjoining land
uses and create a park-like visual impression.
Lots within the industrial area are to be sold, or developed and leased
to individual companies for professional office, light manufacturing, research
and product development. It is estimated that employment for 400 to 600
individuals will be created, some of which will live in the Valle Verde
area. Loop streets provide access from Palomar Airport Road to the in-
dustrial site. This eliminates potential conflicts between residential
and non-residential traffic. Each company will provide onsite parking
for their employees and customers in adequately landscaped areas. Dev-
elopment will be in six phases over the same six year period for residen-
tial development. All required improvements, facilities and senrices
will be provided concurrent with need.
FLORA: On the· slopes w,.ch have not .been cult·i.vatl~ the-dominant
vegetation i~; Black Sage (Salira Hel·J_ifera) und Buckwheat (Eriogonum
Fa s c-i c u 1 a· tum ) . Th ·j s c o a s t a l s a g f· s c r u b • 11 a b i ta t i s g e n e r a 1 l y d r y
and sparsely vegetated, with other typical species as follows:
' Adenostoma fasciculatum
Quercus durnosa
Rhus 1aurina
R. Integrifol ia
Heteromeles Arbutifolia
Yucca Schcliqera
~ylococcus bicolor
Opuntia littoralis
Mimulus puniceus
·Lotus Scoparius
• ·Eriophyllurn sp.
Chamise
Scrub Oak
Laurel-leaved sumac
Lemonade berry
Toyon
Spanish Dagger
Mission Mar:iganta
Coa~tal Tuna Cact~s
Red monkeyf1ower
Bird's foot trefoil
Yarrow
There are also annual wildflowers which are characteristic ·of this
type of l1ab i tat.
• "FAUNA: The coastal sage scrub habitat hosts a variety of reptiles_,
·rqdents and avifauna. Among common species: Western fenc~ lizard,
side-blotched lizard, _the ~outhern alligator lizard, striped racer,
red racer, gopher snake, three species of rabbit, the California
. ground squirrel, agile kangaroo rat, and the cactus mouse. •
Also the following birds: California quail) roadrunner, scrub jay,
common bushtit, wrentit, bewicks wren, California thrasher, blue-
gray gnatcatcher, .loggerhead shrike, hou.sefinch, brown towhee, and
• Nhite-crowned sparrow. •
The animals sighted ;·n the cultivated or fallow-field habitats in-
cluded these additional species: Botta 1 s pocket gopher, the Coyote,
kildeer, mourning dove, poor-0ill horned lark, mockingbird, robin,
water pipit, western meadowlark, savannah sparrow, oregon junco,
. golden-crowned sparrow, foi sparrow, and song sparrow.
II. • "ENVIRONMENTAL IMPACTS
Agriculture -The site has been agriculturally produ£tive for
·approximately 20 years. Unfortunately, the costs of sustaining
·that use (in terms of taxes, margin~l profits, and deferred
development) dp not stimulate long term agricultural use.
Th.e property was, at one time, designated as an_ Agricultural Preserve.
The Preserve Contract was never finalized and subsequently was
dissolved.
...
.. 2 ..
Impacts associated wilt the development of agr~ltltura1 land
a re:
(1) Depletion of tomato and ~quash cultivation acreage by
s o rn e 1_ 5 0 .a c r e s ;
~2) Displacement of agricultural workers;
(3) Loss of open space;
(4) Inducement for the dev~lopment of other agricultural
propert·ies in ·the same vicinity.
AESTHETIC IMPACT·.
The natural rise of.the property above Palomar Airport Road and
El Camino Real n1ake it conspicuous to traffic. In its present
state, the site presents a pleasing vista of gently_sloping, op~n
• land.
Proper site design can help preserve and enhance this vista .
. Elaborat"ion. is provided under mitigating measures.
·TRAFFIC AND CIRCULATION
Estimated traffic· volumes for light industrial use on the property
is 16,073 trips per d~y. Both Palomar Airport Road ahd E1 Camino
·Real have very low traffic levels at present and will be abl~ to
adequately accomodate the additiona1 .trip generated.
"The .proposed Master Plan shows a north/south 6.0' road bisecting -
the proposed industrial sector-at its intersection with P~lomar
Airp0rt Road. A 60 1 east/west road is shown at the northern
perimeter.
•. 'AIR 'QUALITY
Incremental air quality impacts are ~s fallows:
1 .
-.
. 2.
From mobile (~utomobile) sources;
·ca·rbon Monoxide 388 1 b/day
• i ..
' I • ,
. Hydro Carbons 704 1 .b/ day --... . . . ... ..
Nitrogen Oxides .. •· .. 472" •• 1 .b/ day
,. ~ a ·rt i c u 1 a t es 23 l bl day
. .....
:.__ Oxides of Sulfur 14 l .b/ day
Stationaty· ~ources are more complex to project without
the exact ·uses proposed for the site .. · Emis~·1on levels
partially controlled through restrictidns·on levels of
·and emissions in the P.M. Zone.
kno\·li rig
u.re
pollution
3. Secondary factors such as population_ generation and increased
--3-
..
n e c d for f o s ~ i l f ~ic 1 • n er a t e cl e· n e r 9 y to s ~ r v e 91 du s t r.y
will also impact the air quality of the region. •
NOISE
The site's proximity to Palomar Airport.makes it particularly .
-suscGpt·ible to aircraft noise. The preliminary Comprehensive
Land Use Plan for Palomar Airport, prepared by Wilsey & Ham
for the Comprehensive Planning Organization, indicates that
present noise levels on the subject property are within
acceptable ranges for all types of development. However, pro-
jected.bperatiun levels for 1990 show that noise levels will be
margina11y. unacceptable for ·residential use in this· area, when considered
_,-fo,relation•to cr:ash haza·rd .. F.igures."1-11-3·-:.and ·111-4-·taken from the Wilsey and
• • 1-l_g_fll_}_j rport. Study _jJ 1.u stra te this. ..
: ~IRPORT HAZARD
. ..
Existing Hazard Zones for Palomar Airport with acci~enf data
are illustrated in FJgure 111-3 from the Wilsey and H~m study,
Hazard ·on the subject prop~rty, at the present time is limited.
The study -lists land use comp~tibility in the limited hazard
areas as:
. .
No reside~iial construction except for very low density or
agricurtural/open space uses. No uses invo1ving large
assemblages of people at times \'then .aircraft are. in operation.
The 199·0 projections for the Hazard Area for air traffic '(Figure
111-4) cover the. majority of the property-proposed for industrial
use. Compatible. types of.development are shown in Figur~ 111-6.
. .
'ELIMIHATION OF OPEN SPA·CE
The project will cause. the elimination of so~e 214 acres of
open land in the City of Carlsbad .
• 'HILLSIDE· DEV°ELOPMENT
Approximately 50% of the site has an average slope of 15% or
-greater. Depending on coverage, types of facilities de~~loped
• and specific soil conditions, certain mitigating measures·will
be required to minimize _any adverse impacts associated with
. gradi_ng. --
• -. ·ECON OM I C ·IMPACTS
.The applicant projects that when developed, this industrial s£ctor
will generate some 400-600 jobs. While the .demand of industry
_on municipal services is proportionately less than that of
residential development, it shou·ld be noted that an employment
g e n c. r a t i o n • o f t h i s ma g n i tu cl e i s g r o \·I th i n d u c· i n g . . Th u s , i t i s
·•indirectly impacting public services: ' •
. . -
-4-
BIOLOGY
The Valle Verde industrial area has been largely disturbed
-by agricultural cultivation Qver the iears. For this reason
the flora and fauna do not represent particularly valued
natural resources. Most of the bird, reptile and rodent
species can co-exist with industrial development, depending,
of course, on the scale and intensity of that development.
Certain other species (such as th~ Coyote) will be disperseci
by the deve1op1nen_t, but none are rare or endangered.
The effects of displacing animals from their habitats is
modified or intensified by the amount of development in
surrounding areas. Certainly provision for large open areas
in close proximity to the subject property will mitigate
this effect.
IV: "ANY ADVERSE ENVIRONMENTAL EFFECTS WHICH CANNOT BE AVOIDED
SHOULD THE PRo·vcYsAL BE IMPLEMENTED
Unavojdable adverse effects which will result from the in-
dustrial ·development.of the· proposed projects:ite ate p.S f_6Jlpv1s:
1.
2.
.3 .•
.. 4 ..
Decrease
acres.·
Decrease.
Displace.
In.crease
the open space i n San
agricultural land by
and/or reduce native
exhaust emissions in
Diego County by some
about 150 acres.
flora ·and wildlife:.
San Di~go County.
5. Increase.the level of noise in the ar~a.
• 6. Increase dernand for utilities and public services~
7.-Cha~ge the natural landforms of.the site.
214
~-Alte~ natural run off and percolation and diminish ground-
water quality.
3. Decrease employment in the agricultural sact~r.
1-0. Increase. traffic co~gestion in the area.
11. Increase. dust and erosion potential, especially during
co ns.truc.t ion.
12. Increase the hazard and loss of life should an airplane
accident occur on the site.
V. MITIGATION MEASURES PROPOSED TO MINIMIZE ADVERSE IMPACTS
The following measures are proposed to mitigate adverse en-
vironmental impacts associated with industrial development:
-5-
e
content irrigatip~ water.
(2) Indigenous animal communities will suffer
less disruption if provided·.with plant
communities similar t6 their native habitat.
ALTERNATIVES TO THE PROPOSED ACTION
1. No project-· maintain project site in i~s present-
a g r i c u l t u r a. 1 s t a t e_: Th i s a 1 t e r n a t i v e \'lo u l d e 1 i m i n a t e
al 1 of the expected adverse ·impacts should the project
Q cc u r . H o \·/ e v e r , t h e p r e s e n t ta x a t i o n s tr u c tu re a n d
:"limi:Ced financial yield of agr-iculturu.1 production
does not stimulate conti~ued agricultural use.
2 . Re ta i n S i t e f or O ~-n S p ace / Re c r ea t i o n a 1 U s e : H h i 1 e
th i s i s a des ·i r ab ·1 e use for the property and . one w hi ch
would benefit the community at ·large, it wpuld require
public purchase of the property. Inasmuch ·~s purchases
of this nature are dictated by public priorities and econo-
~ics, it does not appear likely that such a purchase
would occur. ~
3. Private Recreational Develobment:
Present land values and tax assessments would require
a high yield, fairly intensive recreational use of the
property to make it economically biable .. The li-k.eli-
hood of such a use occurring is very limited.
4 . D e v e l a p.JD I'-'> n t A s Es ta t e l.o.t·!-D.an.s.il¥--~O -2 d , n . / a. c re ) :
This alternative would be compatible with the airport
1 a rid . re.co in m e i1 d a t i o n s co n ta ·i n e d i n th e p r e 1 i m i n a r y
Wilsey and Ham study. However, the cost of land and
services to such low density uses would tend to be
_prohibitive and certainly would not serve a particularly
large or deficient market. •
. ' ·.5. • Sub·d-tv·ision of Property for Medi urn or High Density • •
• Residential Use (Over 7 d.u./acre): This use wou1d be
·1 n comp at; b 1 e !'flt 1n he 1-1 n J 1 n gs o t • the Ai r port La ,nsl_ use
Study. Air tfaffic accident hazards and noise impacts
make a use of this intensity undesirable.
V. RELATIONSHIP BETWEEN LOCAL SHORT TERM USES OF MAN'S
ENVIRONMENT AND ENHANCEMENT OF LONG-TERM PRODUCTIVITY
The thort term effects of the project will be· those associ-
. ated with the conversion of 214 acres of land~-most of
which is suitable for agricultural production --into a
planned industrial develop~ent. These short term effects
inclu~e t~~ elimination or displacement of native vegetation
and H~l.ctl11·e,. the depletion of natural .resources, and the
• noise and dust associated with construc_tion.
-7-
The 1Qng term effects include the loss of open space,
the loss of approximately 150 acres of cultivated lDnd
and additional agriculturally suitable-soils, increased
air•~ollution, increased .traffic, loss of natural habitat
for wildlife, degradation of ground water, consumption
of natural resources) and the increased possibility of
damage and loss of life associated with an airplane
accident .
. .
VI. • -··• ANY IRR EVERS I 13 LE EN V I RO !'1 MENTAL C ii ,L\ MG ES 1-J O UL D ""t'f E I NV O L VE D
Tr-r-=n:1 E PRO ro S ED AC l l Oil SH OlTCTi1rrrf:'.-n1 PL Ei·i ENT[ D:
The following irreversible changes would occur should the
pi~operty· be converted to ind,ustr-ial u·se:
1. Construction of buildings, pavement and
roadways would permanently commit the site
to industrial or non-open space uses.· . .
2. • The natur~.1 lu.nd form wil 1 be i treversibly
changed by the moving of approximately l million
cubic yards of excavation materials.
3 .. Native wildlife will be permanently displaced
by destruction of habitat and proximity to
human popul·ations.
4. As long as internal combustion vehicles ~re used
to provide transportation to the site and foisil
fuel plants are used to supply energy for the
proposed project, ajr quality will be irreversibly
_impacted by the project. •
5. An .irreversible committment of raw materials,
public utilities and natural resources will be
made with the approval of the project.
VII .• GROWTH INDUCING IMPACT OF THE PROPOSE □• ACTIVITY:
Developments which provide employment are growth inducing -to
the extend that t~~y induce persont to move into the.area .
. Stat·istics sho\•l that areas \vhich are co_nsidered to be desirable
living environments such as San Diego County, tend to sustain
higher unemployment rates than those areas which are less
d~sirable. • What this would indicate is that areas with higher un-
employment are often effected by the influx of people who
saGrifice deferred employment in order to relocate in a desirable
environment .
. Thus, unemployment rates (not withstanding regional effects
of unemployment in specific sectors) tend to -~tabilize
.proportionate to· overall unemployment levels. According to
this model, the creation of additional jobs in labor market
with high unemployment levels will tend to draw a higher .
percentage of outside persons than of the existing local labor
force.
Population growth is dependent, of ~ours~, on a c~mbination
of factors (such as housing availability, transportation,
. e t c . ) a n d -i t i s ha rd to ex t r i c a t e a s o 1 i ta r y fa_ c to r s u c h a s
the creation of jobs) and assign it a numerical value of
··growth inducement. However, it is fair to-say that extending
the urbanized portion of the City, as would be the case in
this project,. would stimulate urbanization of adjacent properties.
-9-
r
VI.I I. BOUNDARIES OF THE /\REA l·JHIC!l M/\Y BE SIGNIFICANTLY EF 1=ECTED
BY TH E P RO PO S ED l\ CT l V rrr:--· ~ .
The·effects of chnnges in the land .form, .d_isr(Jption tp • •
natural habitats, and impacts asso~iated with co~struction
phases will generally be confined to the project site.
Population impacts and impilct on services and public
utilities will generally be confined to the district bound-
aries of those ag~ncies providing services to the project.
The· effects of additional runoff and decreased groundwater
q u a 1 d t y vri 1 1 g e n e. r a 1 ·1 y b e c o n f i n e d-• t o th e i mm e d i a t e pr o j e c t
area, but may marginally impact the Agua Hedionda Lagoon,
which will receive additiona1 run off. •
The effect of ·the project on air quality will be shared by
the entire North County Air Basin.
IX. AGENCIES CONSULTED:
Copi~s of this report have been sent to the following
agencies for review. Written cqmments are to be received
by April 8, 1~74.
··AGENCIES CONSULTED:
U. S. Agricultural Department
Local Agency Formation Commis~ion .
County Parks & Recreation Department
State Division of Highways . •
County Parks and Recreation Department--District 6
.San Di~go ~egional Water Quality Control Board
·comprehensive Planning Organization
Stcite Department of Fish & Game
Department of Public Health
San Diego County Air Pollution Control District
San ,Diego County Sanitation & Flood Control
..... ; •. ··. . :-_. . _ .... ,.... . '
: .•,--:
-10-
AMENDMENT TO E.I.R. # 234
(GENERAL PLAN AMENDMENT FOR LOKER INDUSTRIAL SECTOR)
Back~round: At their meeting of April 9, 1974, the Planning·
Commission indicated that they wanted the following information
and ·elaboration included ·in the preliminary E.I.R. for the Valle
Verde General Plan Amendment:
1. The rel~tionship of the project to impacts on vegetation
and wildlife;
. .
2. The relationship of the project to the areas shown to the
north on the existing General Plan as Estate Low-density
Res i .den ti a 1 ;
3. An an~lysis of the market demand and local capacity to support
additional industrial land;
4. The environmental effects associated with timing of the
pro.j ect;
5. The elimination of open space; and, _
6. Alternatives and mitigating measures.
Corrections:
Page 2, third paragraph under FAUNA heading, first line:
11 animals 11 should read instead 11 vertebrates 11 •
Page 4, 1LIMINATION OF OPEN SPACE, should:·read:The project will
;· :. •• : • t es Li l t i n de v e 1 op men to v~ some 21 4 acres of o p e n 1 an d w i th i n
the Car1 sbad Sphere,"cif:· Influence.
Amendments:
1. The ~elationship of the· project to ~mpacts on vegetation
and wild.life:
A vegetation map which was attached to the preliminary
E.I.R. shows that a majority ~~proximately 90%) of the·
site is either presently under tomato cu1tivation or is
fallow·field which had at some time been used for
-1-
•,.
• agricultural purposes. Because ·the natural vegetation has
• been removed to allow for cultivation, the resident
vertebrate species which exist on the site are generally
rodents, reptiles, and birds. Vegetative cover in the
fallow, coastal sage, and cultivated habitats is generally
sparse; the resident species tend to be-foragersand burrowers
due to the lack of cover.
A Southern Oak Woodland habitat is located directly north of
the sector under consideration for the Planned Industrial
Land Use Amendment. Thi-s hab·itat is expected to support 27
species· of non-avian vertebrates. Species in addition to
those hoted in the coastal sage habitit are: the Slender
Southern Salamander, Broad-footed mole, a variety of rodents,
the Coyote, an occasional grey fox, Bobcat, and Mule Deer.
Additional avian vertebrates seen or heard in.this habitat are:
The White-tailed Kite, Cooper's Hawk, Sparrow Hawk, Common
Snipe, Barn Owl, Great Horned Owl, Costa's Hummingbird, Anna's
Hummingbird, Rufous Hummingbird, Red-shafted Flicker, Acorn
i,J o o d p e c k er , N u t ta 1 ·1 1 s ~Joo d p e c k e r , Em p i d o n ax F 1 y c a t c h e r , T re e
Swallow, Common Raven, Commbn Crow, Plain Titmouse, House Wren,
Hermit ·Thrush, Mountain Bluebird, Ruby-crowned Kinglet, Cedar
Waxwing, Phainopepla, Starling, Hutton's Vireo, Orange-crowned
Warbler, Nashville Warbler, Wilson's Warbler, Brewer's Blackbir<l,
Brown-headed Cowbird, Lesser Goldfinch, Rufous-sided Towhee,
Oregon Junco, Chipping Sparrow, and Song Sparrow.
Although this habitat is not within the_project area, it would
certainly be impacted by any adjacent development. • All of the
non-avian vertebrates are relatively intolerant to human
populations. The larger predator avian species would likely
• be displaced or ·eliminated by adjacent development. The
secondary effects of the resulting ecological imbalance between
predatorss foragers and vegetation could possibly reduce
other species.
2. Relationship Qf the Project to General Plan Designation of
Estate Low-Density Shown to the North:
It i~ not anticipated· that industrial lan~ use on the subject
si·te will impact nearby areas shown as residential. A green-
belt, open spac~ area separates the industri~l area to the
north. The Airport instrument landing system (strobe lighting)
separates the site to the west, Palomar Airport Road bounds
the site to the south, and Carlsbad Raceway is generally
·1otated to the east. Additionally, the property is topographi-
cally isolated by a valley to the north.
• 3 •. Analysis· of Market-Demand and Lmcal ·capac·ity to Support
Additional Industrial Land: This analysis is based on the
following ~ssumptions:
-2-
, • a. Laissez-faire economics alone cannot determine
the amount of industry which a city can support.
Marketing projections to a certain extend rely on
stimulated demand (i.e.,growth inducement and in-
creased consumptiori).
b. Although a market for certain industrial uses can be,•
justified as being economically viable, the social costs
and environmental costs of the use may outweigh the
benefits. ••
c. Marketing projections do not always reflect saturation
conditions. For instance, a City may grant a certain
property. General Plan and Zoning designations en-
abling industrial development on that property without
insuring immediate development plans. A subsequent
property owner might request industrial zoning (even
if the total industrial area in the City is greater
than what market conditions could support) based on
the marketing projection that this subsequent project
has a competitive edge --through location, land
costs, topography, etc.--in attracting industrial
tenants. The original property would thereby be tied
up by a land use designation for which there is no
peed. Worse yet, piecemeal or scattered development
could occur.
d. As a very general rule, the optimum percentage of land
devoted to industrial use in a balanced City is 10%.
This, of course, is a simple estimate; factors such as
available work force, the amount of land suited to
industrial use, population density and the ~bility
of the local environment to absorb adverse impacts
sustained through industrial use can effect the
optimum level for industrial land.
Analysis
There are presently approximately 20?5.48 acres within
the Carlsbad City limits which are zoned for industrial
type uses. The zoning is broken down as follows:
C-M (Heavy Co~mercia1 light industrial) ·_ :392.22 Acres
M (Manufacturing) 322.25
P-M (Planned Manufacturing) 582.87
P-U (Public Utilities) 788.11
TOTAL 2085.48
. /.3/4 This acreage accounts for "RW of total acreage
within the City boundaries. However, this figure is
somewhat misleading inasmuch as the bulk of potential
:industrial property within the Carlsbad sphere of
: influence has not been annexed.
-3-·
II
II
II
ii
• • ~ventual development of the Valle Verde project_·
would probably induce a population growth in the
realm of 600+ persons (assuming that 50% are locally
employed, and including additional family members
plus induced support population in the estimate.)
A final factor to consider in evaluating the need
for additional industrial land within the Palomar
Airport torrider is the.possibility th~t this area
will become a regional industrial center as suggested
by the Comprehe~sive Planning Organization. The logic
of this regional designation is based on several
factors:
a. The centrality of the area and access
through Palomar Airport Road and El
Cami no Rea 1 ;
b. The immediate influence of the Airport;
c. The av~ilability of large amounts of vacant
l~nd; and,
d. The physical suitability of the area for in-
dustr·i a 1 uses.
4. The Environmental Effects Associated with Timing of
The Project
A General Plan designation indicates an overall
concept for the ultimate future use of a propertj.
The General Plan cannot necessarily guarantee that
s~rvices or public facilities.will be available
coin~idental to the developers construction time-table~
Accordingly) these factors related to timing must
be evaluated at the Master Plan and Specific Plan
phases of development.
s.· The Elimination of Open Space -The project will
enable the eventual elimination of 214 acres of open
land within the Carlsbad Sphere of Influence. The
impact of this loss of open space wi_ll be determined
by (l)· The treatment of structures and open areas as a
part of any development, and, (2) The public's value
placed on this parcel as open_ land.
The site is certainly within -one of the more aestheti-
cally pleasing areas of Carlsbad. It is surrounded on
all sides by gently sloping, vegetated hills. The
only development within the immediate area of the
site is the Carlsbad Raceway.
6. ·Alternat·ives and Mitigating.-Measu.res:
1. No General Plan Amendment
Using this alternative, the project would main-
tain its present General Plan designation
-5-
·• f
as open space, parks or semi-public land. _
The benefit of this alternative would be that
it would allow the Staff, the Planning
Commission, C,ity Council and various citizen
groups additional time to review the appropriate
land use for this property in relation to the
overall land use revision. The disadvantage o(
this proposal is tbat it would extend the review
t·irne for the appl·icant's proposal-by approxi-
mately 2 months.
2. AJ?plicat·ion of Aqricultural Preserve General
Plan Desiqnation and A-P Zoninq: This alter-
native is one whith is up to the discretion of
the applicant. Economic incentives (in terms •
of tax relief and high profit from agri~ultur~l
use) certainly do not encourage the owner to
seek this option. However, if the property were
ma i n ta i n e d i n i ts p r e s en t a g r i c u 1 t u r a 1 s t a te ,
none of the adverse environmental impacts
discussed would occur. •
3. Publi·c Purchase of the Property for Recreational/
Open Space Purposes
This alternative has been explored by City
officials as a part of the Conservation Operi Space
and Parks and Recreation Element programs. Be-
cause of other high priority park acq~isition
projects and the fact that the Oak woodland
to the north of the subject property is proposed
for a park dedication, the possibility of ac-
quisition is not very l·ikely at. this.time. Public
priorities could change however, and this alterna•
•tive should not be eliminated. altogether.
-6-
.. . ,• ·•
/: _,,,,,,.,,.
-2-• A proposed 84-foot wide road is to provide access to the project
site from an easterly and westerly direction. It is proposed
that this road will connect to El Camino Real on the west and
Melrose Avenue on the east. As the road enters the project
site from the west, it divides to form two parallel 60-foot wide
roads which traverse either side of the open space. Access from.
the south will be provided by an 84-foot wide road connecting
to Palomar Airport Road. This road will traverse the central
portion of the site in a north-south direction, connecting to
Melrose Avenue near the northeast corner of the site.
II. ENVIRONMENTAL SETTING WITHDUT THE PROJECT
Land Use
The project site comprises the eastern portion of· Rancho Agua
Hedionda, totaling an area of 608 acres. The subject property is
located in northern San Diego County, 0.5 miles south of Oceanside,
2.2 miles west of San Marcos~ 33 miles north of San Diego, and 4. 1
miles east of the Southern California coastline.
Approximately eight percent of the property is located within the
City of Carlsbad, while the remaining 92 percent of the site lies
within an unincorporated area of San Diego County. It is an-
ticipated that the entire property will ultimately be located
within the corporate boundaries of Carlsbad as a result of future
annexation.
The project_ site is composed of vacant land, with approximately
150 acres devoted to squash and tomato crops. While the north-
east portion of the site has been previously brushed, only the
southern portion of the site is presently under cultivation.
The property is zoned A-1-8 in the 561 .1 acre County portion,
while the 46.9 acres located within the City of Carlsbad is
zoned R-A-10. Upon approval of the proposed pre-annexational
zone change, the property would have a PC and PM zoning designation.
Under the· existing Carlsbad General Plan, the so·uthern portion of
the project site is designated as park land, semi-public land, or
open space, while the northern portion of the site is designated
as estate low density residential. at a density of 0-2 d.u./net
acre.
The City of Carlsbad is currently processing a General Plan
Amendment which would change the designation on the southern
portion of the property from open space and estate low density to
Planned Industrial. This amendment would enable the zone change
to P-M ·as proposed by the applicant.
North of the project site is Los Monos Canyon, beyond which lies
Squires Dam·and the University of California Natural land and
Water Reserve System. East of Valle Verde is ·the Carlsbad Raceway
(zoned C-2) and the Carrillo Rancho Planned Community. South of
the proposed project site, beyond Palomar Airport Road is an un-
incorporated area of San Diego County, lies the Bressi Ranch
(zoned A-3-8).
-3-
Air Q1rnlity
The San Diego County Air Pollution Control District's Oceanside-
Carlsbad Air Monitoring Station is located at 100 South Cleveland
in Oceanside, approximately six miles northwest of the project site.
This station measures oxidant, carbon monoxide, nitrogen dioxides;
oxides of Qitrogen~ Total Hydrocarbon, methane and non-methane· hydrocarbon levels. -•
Oxidant levels for the Oceanside monitoring station ~qualed or ex-
ceeded Federal standards for the first half of 1972 on 48% and
26% of the days respectively. It should be notep that the subject
site is nearly five miles inland and does no~efit from the
dispersing offshore breezes which may be reflected in these levels.
Archaeology
An archeological survey was conducted on the subject site.on
October 31, November 1, 4, and 6, 1973.
In the prehistoric period, the area in proximity to the subject
property was occupied by at least three major cultures. From
approximately 10,000 years ago to 4,000 years ago, the San Dieguito
culture was the sole inhabitor of this area. Beginning about·
3,000 years ·ago, and·extending to 1,000 years ago, the La Jollan
culture was in existence. Commencing around 900 AD, and extending
into the period of Anglo occupation, the Luiseno and/or the
Diegueno (Kumayay) lived and hunted in the area. There exists
some doubt·as to whether the Luiseno or Diegueno (Kumayay) in-
habited the area, though for this analysis .it is assumed that tbis
area is primarily Luiseno. The San Dieguito River is generally
understood as the boundary between these two linguistically
different, but culturally similar groups of people.
The following are brief descriptions and analysis of the various
sites based on knowledge currently known. After the.site designation,
A categorical judgment is given. These judgments are defined as
follows:
CRITICAL: Must be excavated --great amount of data is re-
trievable, the site 1s unique, extensive, or
otherwise ·valuable for its research potential; AK-8.
MAJOR: Must be trenched, post-holed. or surface collected
and mapped, Data is available but is partially
destroyed, a surface site, or otherwise limited
potential for excavating purposes; AK-2.
MODERATE: Must be further mapped and surface collected.
Little or no excavation potential though a limited
amount of research.potential exists; AK-9.
MINOR~ Very limited in potential --usually already ex-
hausted by virtue of surface collection and mapping;
AK-1, AK-4, AK·5.
-4-• INSIGNIFICANT: Of no value though scattered material of in-
consequential nature may exist. Resources
are exhausted by surface collection and
mapping; AK-3, AK-6, AK-7, AK-10.
Site l: Minor. This site is a single unit Luiseno grinding,
area used to prepare acorns, seeds, and other edibles. This
form of food preparation (utilizing mortars, metates, and
basins) is indicative of the Luiseno culture rather than of
the earlier San Dieguito or La Jolla Cultures. Postholing
and a surface collection of this site proved negative. A
comprehensive map has been completed, as well as a completed
measurement and analysis of the depth, width, and length of
the mortars and slick.
Site 2: Major. This site is a San Dieguito II and possibly
San Dieguito III flaking area. A vast amount of heavily
patinated flakes and debitage litter the hillside. Repre-
sentative artifacts were recovered.
A surface collection was not completed nor was postholing,
based on the belief that these measures come under mitigation
rather than primary surveying. The approximate area of this
site is_ 1,000 square feet.
Site 3: Insignificant. This area cannot justifiably be called
a -site. No indication of habitation was found. However,
scattered artifacts associated with tool manufacturing were
located in an area roughly 25 feet by 10 feet. These arti-
facts appear to be random and without contextual matrix.
Site 4: Minor. Primarily a La Jollan food preparation area,
this half acre site is the remnant of an area that has been
plowed and badly eroded. Surface artifacts indicate that
the area was used to grind and/or prepare foods. A complete
surface collection was completed. Such a collection of these
highly disturbed materials has exhausted the scientific value
of tbis site.
Site 5: Minor. This badly disturbed site contains a mixture
of San Dieguito II and La Jollan material, including a minor
shell midden consisting primarily of chione. As a result of
cultivation and grading, little value is ascribed to this site.
An intensive surface collection was completed with the results
being recorded in the Appendix.
Site 6: Insignificant. This 200-square foot area is comprised
of a sprinkling of San Dieguito and La Jollan material.
Plowing, erosion, and the relatively small size of this site
explains the paucity of artifacts and edible shell material.
The surface collection and mapping of this quasi-site has
exhausted its· potential.
Site 7: Insignificant. A surface collection of this Luiseno
trail site has exhausted· the potential of this badly disturbed,
isolated, and randomly distributed site. The size of this
site is indeterminate due to random scattering.
-5-
Site 8: Critical. This site of approximately 1,000 square
feet contains elements of all three cultures: San Dieguito,
La Jollan, and Luiseno. The surface of this site is littered
with artifacts and traces of an extensive La Jollan shell
midden. Postholes indicated the presence of sub-surface fire
hearths, shell deposits, pottery, and burnt bone. Such
material was in evidence as deep as 36 11 • The artifactual
material, soil texture, and color would indicate that this
site saw repeated use as a food preparation area, if not as
a camp site.
Biology
Approximately 150 acres of the broad southern ridge portion
of the site are presently in tomato cultivation, and 125 acres
of the northcentral and northeastern portions of the site have
been recently plowed. Large portions of the remaining property
have been either plowed or burned, and are now covered with
ruderal weed species or early successional stages of the nati~e
coastal sage scrub community.
Despite recent agricultural activities, Valle Verde does contain
some important natural areas. The floor of the stream valley is
occupied by riparian and southern oak woodland communities (about
30 acres). ·A large number of coast live oaks (Quercus agrifolia)
make this portion of the property an important forage and cover
area for many animals. Large birds of prey (white-tailed kites
and red-tailed hawks) were observed perched in the huge oaks or
flying above the surrounding fields. A 2.8 acre man-made lake
is located in the western portion of the stream valley. This
lake provides habitat and cover for many organisms which inhabit
riparian and aquatic areas. Finally, a considerable portion of
the property is still covered with coastal sage scrub.
The following are general descriptions of the characteristic
habitats of the Valle Verde site. Full species list~ are on file
in the City Planning Department.
Coas~al Sage Scrub Habitat
Much of the northern half of the property has a ·cover of mature
coastal sage scrub, which consists of dry, low-growing shrubby
vegetation one to three feet in height. In small canyons, and on
certain north-facing slopes, a more lush plant community composed
of more mesic· species prevails. Hence the coastal sage scrub
community has a varied species composition depending on ~lope, ex-
posure (south-facing slopes are drier and generally more sparsely
vegetated than north-facing slopes), soil type, and current or
past land use.
On the.higher hills and south-facing slopes;· Black Sage (Salvia
·mellifera) ~nd Buckwheat(Eriogonum fasciculatum) were the dominant
species, w~ile the less exposed areas were dominated by Scrub Oak
(Quercus dumosa) and -Toyon (Heteromeles arbutifolia)~ A number
-6-
of annuals (wildfl,ers, grasses and forbs) a" also character-
istic of this habitat. The dominant species of this type is·
tarweed (Nemizonia sp.)
Riparian Habitat
The riparian habitat surrounds a lake near the western bound 9ry
of the site. The pond is surrounded by willows (Salix laevigata)
and cattails. (Typha cf. dominguensis). A cattail marsh extends
eastward approximately 1,000 feet. Directly to the north of the
pond, Willows and Giant Rye Grass (Elymus condensatus) occur along
a small ravine. Spring seeps appear to occur here throughout the
year, and apparently water runs down the ravine and maintains the
lake at its existing level.
The lake appears to have been formed by dozing an earthen dam
across the ravine. The surrounding area is extremely dry and is
covered with Buckwheat (Eriogonum fasciculatum) and Black Sage
(Salvia Mellifera). Some of the area south of the pond has been
plowed at one time and is now covered with dry grasses (Avena;
Bromus, and Polypogon) and mustard (Brassica).
Lake (Aquatic Habitat)
The lake has a maximum depth of ten feet with an average
depth of approximate1y six to eight feet.
The water was quite transparent (secchi disc reading of six feet)
and an aquatic plant (Pondweed, Potamazeton sp.) was quite abundant.
The lake was approximabely isothermal surface temperature, 67°F;
bottom temperature, 69 F) which would be expected for a clear,
shallow lake. The dissolved oxygen concentration was quite high
throughout the water column.
Mosquitofish (Gambrisia affinis) were quite common in the shallow
water near the pond's margin. Largemouth bass.(Micropterus
salmanoides) are apparently present, as the head and entrails
of a large fish (two to three pounds) were observed in shallow
water near shore. A plankton haul yielded a large number of
zooplankton. Zooplanktonic species included Co~epods Diaptomus
sp. and Cyclops sp., and Cladocera Bosmina sp. and Daphnia sp.
Fauna The characteristic animal and bird populations were surveyed
and categorized according to their habitats. A. species list, which
includes all animals and birds which would be expected to occur on
the site based on habitat availability, is on file in the Planning
Department.
Lake Aquatic Habitat -The site contains a variety of habitats,
and it probably supports a diverse and dense vertebrate fauna.
Hunters were observed on one occasion, and empty shotgun shells·
littered much of the property. Large numbers of brush and
Audubon's rabbits, as w~ll as jack rabbits, are evidently present,
as their fe~es cover much of the open $Oil in ·the coastal sage
scrub habitat. Hunters probably shoot these rabbits and the ducks
which undoubtedly use the ponps during spring and fall migration.
--7--
Coastal Sage Scrub -Based on evidence such as burrows, feces,
tracks, etc., it would be expected that a total of 36 species of
amphibians, reptiles, and mannals might use this habitat. Common
residents of this habitat would include the Western fence lizard
the Side-blotched lizard, the Southern alligator lizard, Striped
racer, Red racer, Gopher snake, three species of rabbit, the
California ground squirrel, the agile kangaroo rat and the
cactus mouse.
Birds observed or heard in this habitat were the California Quail,
Roadrunner, Scrub Jay, Common Bushtit, Wrentit, Bewick's Wren,
California Thrasher, Blue-gray Gnatcatcher, Loggerhead Shrike, House
Finch, Brown Towhee, and White-crowned Sparrow.
Southern Oak Woodland -This habitat could be expected to
27 species of non-avian vertebrates. Species in addition
those in the Coastal Sage Scrubs habitat are as follows:
Southern Slender Salamander, Broad-footed Mole, a variety
the Coyote, an occasional grey fox, Bobcat and Mule Deer.
support
to
The
of rodents,
Additional avian vertebrates seen or heard in this habitat are:
The White-tailed Kite, Cooper's Hawk, Sparrow Hawk, Common Snipe,
Barn Owl, Great Horned Owl, Costa's Hummingbird, Anna's Humming-
bird, Rufous Hummingbird, Red-shafted Flicker, Acorn Woodpecker,
Nuttall Is Woodpecker, Empidonax Flycatcher, Tree Swallow, Common
Raven, Common Crow, Rlain Titmouse, House Wren, Hermit Thrush,
Mountain Bluebird, Ruby-crowned Kinglet, Cedar Waxwing, Phainopepla,
Starling, Hutton's Vireo, Orange-crowned Warbler, Nashville Warbler,
Wilson's Warbler, Brewer's Blackbird, Brown-headed Cowbird, Lesser
Goldfinch, Rufous-sided Towhee, Oregon Junco, Chipping Sparrow,
and Song Sparrow.
Riparian Habitat -The riparian habitat could be expected to host
a total of 24 non-avian vertebrates, including three amphibians,
eight reptiles, and 13 mammals. Species common to this type
habitat are the Western Toad, the Pacific Treefrog, the Western
Fence Lizard, the Side-blotched Lizard, the Southern Alligator
Lizard, four members of the Family Colubridae, two species of
rabbit, and the Desert Wood Rat.
Bird species seen or heard in this habitat were the Eared Grebe,
·Piedbilled Grebe, Green Heron, Snowy Egret; .. Black-cr.owned Night
Heron, Mallard, Pintail, Cinnamon Teal, Shoveler,· Ruddy Duck,
American Coot, California Gull, Belted Kingfisher, Black Phoebe,
Scrub Jay, Long-billed Marsh Wren, Yellow Throat, Redwinged Black-
bird, Brewer's Blackbird, White-crowned Sparrow, and Song Sparrow.
Cultivated, Plowed or Fallow Field Habitat -Species which were
sighted or for which evidence was found include: Side Blotched
Lizard, rabbits, ground squirrels, Botta's Pocket Gopher and the
Coyote.
Birds seen br heard in cultivated sections include: The birds
seen or heard on the cultivated sectiqns were the Killdeer,
Mourning Dove, Poor-will Horned Lark, Mockingbird, California
Thrasher, Robin, Water Pipit, Loggerhead Shrike, Western Meadow-
lark, House Finch, Brown Towhee, Savannah Sparrow, Oregon Junco,
White-crowned Sparrow, Golden-crowned Sparrow, Fox Spartow and
-8-
Song Sparrow. In addition, Anna 1 s Hummingbird would be ex-
pected at other seasons of the year.
The birds seen or heard in the grassland sections were the Marsh
Hawk, Sparrow Hawk, Burrowing Owl,· Cassin•~ Kingbird, Say 1 s
Phoebe, Mockingbird, Western Meadowlark, House Finch, American
Goldfinch and Lesser Goldfinch.
Geolog1 -The geologic study shows portions of tha project site
to be underlain by the soft rocks of the La Jolla Group. These
rocks are fine-grained, friable, and poorly cemented, making
them highly susceptible to accelerated erosion. In areas where
overlying soils and vegetation may be removed, and where these
rocks may be exposed to high intensity rainfalls, a11 badlands 11
topography could develop. When La Jolla rocks are used as fill
material, they are also subject to accelerated erosion. Down-
stream silt traps and settling basins are necessary for any La
Jollan grading operation.
The rocks in the La Jolla Group can be excavated with ordinary
earth-moving equipment, and they lend themselves readily to mass
grading projects. As these soils are susceptible to accelerated
erosion, surface water should be diverted away from cut and fill
slopes. Silt traps and settling basins should be provided down-
stream of any grading and construction in the La Jolla Group.
In the alluvial soils, (found in the central portion of the pro-
ject site) shallow groundwater occurs. Adequate drainage would
have to be provided for any excavation or construction in these
areas. Also, provisions would have to be made for control of
surface water, including the possibility of flooding in the
lower alluvial valleys. The existence of these soft compressible
soils would cause any fills to be subject to settlement. It has
been a customary engineering practice to strip shallow terrace
deposits during grading thereby exposing the underlying La Jolla
Group rocks.
The northern and southeast portions of the proj~ct site is under-
lain by h~rd igneous and metamorphic rocks. These rocks are
generally hard and require ripping and blasting to excavate.
Trenching for utility lines is difficult and costly, and mass
grading is usually not feasible.
Seismology -The Inglewood-Rose Canyon Fault, located five miles
offshore from the City of Carlsbad, is the only active fault
within a 25 mile radius of the project site. The earthquake
of 1812, which destroyed San Juan Capistrano, is believed to have
had its epicenter on this fault. The Long Beach earthquake of
1933 was caused by movement on this fault .. Any earthquake with
its epicenter on the Inglewood-Rose Canyon Fault could pose a
serious threat to the City of Carlsbad.
There are four major fault zones withi~ a radius of 100 miles of
the project site. They are the Elsinore, Agua Caliente, San Jacinto
and San Andreas Fault Zones .. The effect of even a high magnitude
--9--
earthquake would be greatly attenuated by the time it reached
the subjest property. Approximately 85 percent of the properly
designed structures within the City Limits probably will not
sustain damage. However, structures in areas underlain by soft
saturated soils could be subj~ct to damate from the secondary
effects of liquification, lurch cracking, lateral spreading,
landslides, and structural damage due to ground vibration.
III. ENVIRONMENTAL IMPACTS
Impacts Associated With Pre~ent Agricultural Use·
1. The elimination of Agricultural Open Space.
2. The reduction of tomato and squash.cultivation.
3. The displacement of agricultural workers.
4. The acceleration of conversion of other agricultural
lands.
Aesthetic Impacts
l. The covering of open vegetated slopes with industrial
and residential structures.
2. The change in the prominent vista from El Camino Real
and Palomar Airport Road from open to developed land.
3. The alteration of natural landforms.
Drainage and Water Quality Impacts
l. Depletion of ground water from the coverage of land
with inpenetrable surfaces.
2. Reduction of groundwater quality through the introduction
of hydrocarbons, rubber, fertilizer, high mineral
content domestic water, etc.
Impacts Associated With Palomar ·Airport
l. CNEL levels (California Noise Level Equivalent) probably
do not exceed 55 decibels for the project site. This
is within acceptable limits for residential and in-
d~strial uses at the densities proposed ·for the Valle
Verde project. Noise level projections to 1990 do not
indicate unacceptable levels for the site.
2. Approximately 50% of the project site i~ within a
limited air traffic hazard zone, as defined by the C.P.O.
Palomar Airport Land Use Study prepared by Wilsey and
Hamm. Compatible uses in the limited hazard zone are
those which avoid concentrations of people in single
areas. Since this hazard effects only the industrial
and green belt areas, mitigation should be proposed
at the time specific plans for the industrial sector are
considered.
Air Quality Impacts
Approximately 28,000 automobile trips per day will be
generated from the project. The attached chart esti-
mates increases in emissions based on this projection.
Pollutant
Carbon
Monoxide
Hyr--
Ca; ns
N.Ltroge n
Oxides
Pc.:t.iculates
O:-::ides 0£
Sulfur
Estimate of Increase in Em.i.ss.ions
Moblle Stationary Total Project
Factor Usage Rate2 Tota( Factor 1 Usage Rate3 Total 'Combined
lb/mile miles/day lb/day _lb./106ft3 1 o6£t3/day lb/day Total
tons/da
0 .109 86}600 9439.4 20 .0002356 7.05 4. 72
0.02 86,600 1732.0 8 .0002356 2.85 0.87
0.0134 86,600 1160.4 50 .0002356 17. 7 0.59
0.00065 86~600 56.3. 19 .0002356 . 6. 75 0.03
0.00039 • 86~600 33.7 0.6 .0002356 0.21 0.017
1 Env.lronmental Protection Agency, 11Comp.ilation of Air Pollutant Emi~sion Factors, 11
AP-42 (revised February 19 72) , P .1-9.
2Der.i.ved by cons.Ld·er.i.ng the average mlleage of 12 .5 m.lles/gal (EPA-1972, P. 2-3),
the gallons of gasoline consumed, 500 x 106 gal/year, £or an automob.lle population
of 750,000 (ARB-1972 1 P. VII-8). • This usage rate is to be used unless more specific
informat.Lon is suppl.led in the tra££.i.c analysis.
3san Diego Gas & Elcctr.ic Company 11Average Gas and Electr.lc usage rates of Res.Ldences 11
unpublished data 1972.
S.D. Basin
Tor.al
tons/day
1685. 7
381.6
189.3
188 .-7
33.2
-10-
A secondary_air quality effect will be to increase de-
mand for fossil fuel generated energy, which in turn will
impact air quality.
A third source -of potential emissions would be from in-
dustrial/ manufacturing uses on the site. These will be
partially controlled by prohibition in the P-M Zone of
uses which create air pollution detectable by human
senses outside·the bounds of the site or emissions
which endanger human health, or cause· damage to animals,
veg~tation or property outside the site boundaries.
Impact on Public Service .
1. The major problem in extending public services to
the project is that the site is some 5 miles removed
from the central urbanized portion of the City of
Carlsbad and is additionally removed by 2 miles
from the nearest residential development. There
is an inherent inefficiency in extending services
in this manner. It is wasteful in terms of time
and cost, especially for .services which must be
provided on site (such as police, .fire, utilities,
etc.)
2. School facilities will be required on site for the
purposes of accomodating children generated by-the
project. Student population breakdown 1s estimated
as follows:
Grade Level
3.· Public Utilities
K-6
7-8
9-12
No. of Students
174
126
201
Development of the subject property will create an
increased demand for public utilities. Water,~elec-
tricity, natural gas, telephone, and sewer facilities
must be extended into the project area in order to
accommodate the proposed development.
Based on an anticipated population of 4,500 residents
and an average consumption factor of 100 gallons
per person per day, it is estimated that 450,000
gallons of water will be required by the proposed
• project on a daily basis. Water is available through
an existing 27-inch line in Palomar Airport Road.
The subject property is located within the Carlsbad
Municipal Water District boundaries. According to
the C.M.W.D., water service is available at a minimum
pressure of 76 psi.
-11--• San Diego Gas and Electric Company specifies that
5700 kilowatt hours of ele~tricity per year are con-
sumed by the average San Diego residence. Using this
rate of consumption, the propose9 project will require
23,400 kilowatt hours of electricity per day. According
to the Oceanside branch of San Diego Gas and Electric
Company, a 12KV 3 phase primary line would be required
from the intersection of El Camino Real and Palomar
Airport Road to the project site.
The average San Diego home also consumes 86,000 cubic
feet of gas per year. Using this rate of consumption,
the proposed project will require 352,000 cubic feet
of ga~ per day. A 2 1/2 inch H.P. gas line exists in
Palomar Airport Road, which the San Diego Gas and
Electric Company is proposing to enlarge to 18 inches
for the North County area. At present, a tap into the
existing 30-inch H.P. line at the intersection of Palomar
Airport Road and El Camino Real would be required.
According to the California Regional Water Control Board,
80 gallons of effluent are generated per person per day.
At' the above rate, 360 ;ooo ga 11 ans of effluent would
be discharged by the proposed development on a daily
basis.
A force main belonging to the Buena Sanitation District
runs through the center of the site. This main is
presently near capacity. The Carlsbad Sanitary Sewer
Map shows a proposed 15" gravity main running south-
easterly through the valley portion of the site.
Economics .
The applicant estimates that property taxes generated
by the project will be $2,021,250 per year for total
residential and $1,031,250 per year for total industrial.
Generally speaking, residential developments do not pay
their own way in terms of municipal service expenditures.
This is especially true when development occurs outside
the urban fringe and additional expenditure is necessary
to extend services.
The proposed industrial sector will presumably be self-
supporting. The applicant anticipates that some 400 to
600 jobs will be generated.
Archeology
Three of the known archeological sites described under
the project setting will be significantly disturbed.
They are sites 2, 8 and 9.
Site 2: This site is a rather extensive San Dieguito
flaking area. Unlike many sites on the property, this
one appears to be pure, i.e. no other cultures have in-
truded upon it. Its scientific value lies within the
-12-•
fact that little is known about the cultures defined
as San Dieguito II and III and in the fact that this
site is undisturbed.
It is suggested that this site be mapped, surface
collected, and postholed for possible sub-surface material.
Its general appearance indicates little or no depth to
the site, and-postholing would be a means of verifying
the lack of depth. If no depth is found, then the
mapping and surface collection are sufficient to achieve
mitigation. If depth is revealed, then it is suggested
that the area nearest the centei of the site is excavated
by trenching. This should achieve adequate mitigation.
Site 8: This site contains elements of all three cultures;
·the San Dieguito, La Jollan, and Luiseno. Evidences of
s he 11 mi d de n ( L a J o 11 a n ) , p o t t e r y ( lu i s e n o ) , . a n d h ea v i 1 y
patinated flakes (San Dieguito) indicates that this area
saw repeated use as a food preparation area. Although
plowing and cultivation have damaged the upper six inches
of the site(s), much df-the area appears undi~turbed
below the six-inch level. Postholes revealed sub-surface
artifacts (pottery, fire hearth, shell) and a midden
depth of up to thirty-six inches.
It is recommended that this site, or series of sites, be
excavated by means of a controlled grid system, utilizing
a Tor L trenching system. It is doubtful if a complete
excavation is necessary, due to partial damage by
plowing and erosional factors. However, an intensive
trench, or trenches, should be excavated to allow for
further salvage· of the site. Furthermore, a Carbon
14 dating of charcoal remains would greatly enhance
the results of the excavation and of the accompanying
analysis.
The valu~ of this site lies in the fact that many cultures
utilized the area~ As such, there exists the possibility
of excavating data which will enable archaeologists and
scientists to fill in gaps which ~urrently exist in
regard to the early pre-history of San Diego County. If
such a site were destroyed without proper excavation and
analysis, important cultural data would be lost. This
is especially true in the North County area, where little
analytical work has been accomplished.
Site 9: This extensive site covers two separate knolls and
represents the La Jollan and San Dieguito cultures. It
is suggested that a complete surface collection and mapping
be conducted on this site. Postholes revealed no signs
of depth or of sub-surface artifacts. No excavation or
further work beyond collection and mapping is necessary.
-13-
Biology
Valle Verde contains a mixture of disturbed and natural
habitats, each of which support wildlife. ·Those areas of the
property which have been greatly disturbed by agricultural
activities over the years do not represent a particularly
valuable natural resource. Southern oak woodland and
riparian habitats are substantially more valuable from an
environmental viewpoint. These two habitats are particularly
important for the following reasons: a) they are much
less abundant than other habitats in the San Diego area;
b) they provide valuable cover for the native fauna: c) they
support a· diverse animal population~ and d) they supply an
important water source for faunal populations in the area.
A decline in resident faunal populations would be expected
as a result of intensive use of this site. Specifically,
the following bird populations would be reduced:_ Green
Heron, White-tailed Kite, Marsh Hawk, Roadrunner, Griat
Horned Owl, Burrowing Owl, Nuttall Is Woodpecker, Common
Raven, and Phainopepla. With a reduction of food and cover,
many of the other species·would also show population declines.
Since this area has been relatively free from intensive
human use, it ha~ been an ideal breeding area for birds.
Certain species, such as the Green Heron, Ruddy Duck, White-
tailed Kite, Marsh Hawk, Roadrunner, Great Horned Owl,
Burrowing Owl, Poor-will, Nuttal1 1 s Woodpecker, Phainopepla,
and Lazuli Bunting would probably cease breeding here as
a result of intensive human occupation. Although some of
these species are experiencing declining numbers, none of
them are apprQaching the rare or endangered status.
The other vertebrates which currently occupy the site would
experience similar population declines as a result of habitat
removal. Human Rressures would most certainly eliminate
the presence of Coyote, Fox, Bobcat, and Deer. The species
in question.are neither rare nor endangered, however they
are somewhat unique in their proximity to an urban area.
Cert a i n po p u 1 a t i o n s , s u c h a s me m be rs o f t h e O rd e r Ro d e~n t i a
(Mockingbirds, Starlings, and Mourning Doves), which are
well adapted to human occupation, will probably increase in
number. Other birds, such as Rock Doves and House Sparrows
will probably be introduced into the area as a result of
development.
Geology
The potential geologic impacts of the project relates to
the following:
1. Compressible Soils -The alluvial soils are generally
in a loose state and may be potentially compressible in some
areas. The applicant proposes that the-alluvium be covered
to varying depths by fill, that in turn will support structures.
-14-
• --2. Expansive Soils Potentially expansive soils are present
within the soil mantle and within the formational materials
on the south si~e of the major c~nyon. These soils usually
have adequate strength to support fills an9 structures, but
because of their potential expansiv~ characteristics they
may adversely affect structures when they are exposed or
placed within 2 to 3 feet of finished grade, in either cut
or fill areas.
3. Landslides -The preliminary study indicates that there
are landslides on the property that will require special
stabilization measures. Most of the landslides extend to or
below· the alluvium, thus placing fiJl in the canyons as in-
dicated on the plans will improve stability. However, in
cut slopes as planned the applicant may find it necessary
to propose, remove or replace major portions of these slides.
4. Qesign of Slopes -The geologic reconnaissance nf the
property and review of the proposed plans indicate that most
of the slopes will be within the grantic rock and Del Mar
Formation. The siltstones and claystones of the Del Mar
Formation have proven to be the most troublesome geologic
formation in the northern· part of the county in regard to
slide susceptability. It can be .anticipated that hillside
development of the southern half of this site will un-
doubtedly requi~e some special buttress construction, sub-
surface drain installation and slope height and inclination
limitations. These limitations may not only apply in areas
of landslides, but probably on some of the advacent slopes.
5 •. _Excavation Characteristi~s -Based on the recorinais~ance and experience w1th s1m1 lar geolog1c units in nearby areas, 1t
appears that·the sedimentary rock units on the property may
be excavated with conventional excavating equipment.: Ex-
cavation within the granitic rock unit can generally be
made to moderate depths without the need of blasting. Where
outcrops or boulders of decomposition are encountered,
blasting may be required prior to excavation.
6:· S~ismolog,Y_
There is a generally moderate potential for structural~ damage
in alluvial soils. However, the La Jolla Group soils and the
alluvial soils on the subject property have only a minor
potential for damage from liquification, lurch cracking, lateral
spreading, and landslides.
-7. Jlood Control
A narrow strip of the Valle Verde Property is wi·thin the
limits of a 100-year flood. This area is located within
the central valley adjacent .to the intermitten stream bed.
The quantity of flow estimated for a 100-year flood in this
area is 1000 cubic feet per second. •
As proposed in the Valle .Verde Masterpla-n, this area would
be retained as open space. Development of homes will be
restricted to higher elevations.
-15-
IV. ANY ADVERSE ENVIRONMENTAL EFFECTS WHICH CANNOT BE AVOIDED
SHOULD THE PROPOSAL BE IMPLEMENTED
Unavoidable adverse effects which wi.11 rest:1lt from develop-
ment of the proposed project s i t e w i 11 be: -·· •
1. Decrease the amount of open space in San Diego
County by approximately 430 acres.
2. Decrease the amount of cultivated land in San
Diego County by 150 acres.
3~ Displace agricultural workers.
4. Reduce the amount of native flora and wildlife
habitat by approximately 430 acres.
5. Increase exhaust emissions in the County of· San
Diego by 0.002 percent.
6. Increase traffic congestion in the surrounding area.
7. Increase the level ·of noise in the area.
8. Increase the demand on schools, public utilities
and municipal services.
9. Al.ter the natural landforms found within the boundaries
of the project site.
10. Increase dust and erosion potential.
11. Decrease the quality of groundwater and storm runoff.
12. Extend· urbanized portion of the City to the eastern
fringe of its sphere of influence.
13. Increase hazard and potential loss· of life should an
airplane accident occuf on the site.
-16-
v. MITIGATION MEASURES PROPOSED TO MINIMIZE THE IMPACT
The following measures will be implemented in order to mitigate
the adverse environmental i~pacts of the proposed development.
1. Open space will be retained by utilizing the 11 cluster 11
method of development in the northwestern and· central
portions of the property. Also, the major east-west
valley crossing the central portion of the ~ite will
remain as natural open space to be used for park purposes.
This area, as well as other numerous landscaped green-
belt areas will provide corridors for wildlife passage
through the property.
2. The dis~lacement_of agricultural workers will be partially
mitigated through the employment generated in construction
and industrial uses.
3. The reduction in native flora will be minimized by
preserving the Coast Live Oaks and riparian vegetation
located within the major east-west trending valley.
Similarly, vegetative species found within Los Monos
Canyon will be preserved. Grassland and chaparral
vegetation removed by grading will be replaced by in-
trod~ced trees, shrubs, and ground cover.
4. Increased traffic will be partially minimized by pro-
viding recreational and commercial facilities within the
proposed community.
5. The quality of acoustics within the proposed project
could be significantly improved by utilizing insulated
walls and other noise abatement measures. This will
help mitigate impacts of both internal and external
noise.
6. Grading operations w11~ be confined to building pads and
roads in the areas proposed for residential development.
In. the industrial area, development will _be limited to
the meias to minimize the amount of grading.
7. • Mitigating measures proposed to minimize dust include the
watering of excavation materials, installation of
sprinklers, planting of vegetative cover, or other dust
suppression measures deemed necessary. Drainage facilities
will be designed in such a manner as to prevent erosion
of cut and fill surfaces. Wherever necessary, energy
dissipators will be included in the design in order to
reduce the velocity of water flowing into existing canyons.
8. A zone change to PC and PM would partially mitigate the
impa~ts associated with development of the site. These
zon~s are holding zones used until a Master Development
P 1 a n, S p e ci f i c P 1 a n , a n d Te n ta t i -v e Ma p h a v e b e e n a p p r o v e d .
It is at the Master Plan and Specific Plan stages that
developmental criteri~ is determined. Therefore, a zone
change would only represent an intention by the City
of Carlsbad to consider a more specific proposal at a
-17-
later time.
9. Reductions in water quality can be partially mitigated by
planting the area with trees and shrubs native to the
coastal region of San Diego County. Since these trees are
adapted to survive during the dry summer months, only small
amounts of domestic irrigation water ·need be applied. A
reduction i~ the use of mineralized irrigation water will
reduce the rate of water quality deterioration.
10. Geologic studies should be made to mitigate grading/ seismic
impacts. These should include:
a. A detailed erosion control study -(drainage control,
landscaping, er~sion rates, siltation control).
b. Routine Engineering/ Geologic Study
c. Routine slope stability study
d. Routine Seismic Hazard study (potential primary and
secondary effects).
e. Routine soil and foundation study (groundwater, drainage,
expansiveness, soil strength, etc.)
f. Geophysical (hard rock excavation.)
11. The impacts on public services can be mitigated by establish-
ment of a reasonable time schedule for phased construction
of the project which is in step with service expansions and
area wide development trends.
12. The industrial sector should be planned to avoid concentrations
of persons in single areas.
-20-
Residential Sector
The proposed Planned Community Sector will consist
of some 1500 housing units. There is not presently
a deficiency of single family units within this
uppermiddle income price range. In fact statistics
indicate that a large portion of housing starts
from 1970-1973 will be serving this market. Marketing
projects for single family units in thi~ range are
based on the assumption that people can be· induced
to move into the Carlsbad area.
The Carlsbad Unified School District estimates that
some 650-700 school age children will be generated
by the project. An additional $000-3500 adult popu-
lation could be -expected a$ :a result of the project. Non-School aged children should range from 30Q to
500. Thus a potential population generat1on of
approximately 4,500 could be expected.
IX. BOUNDARIES OF THE AREA WHICH MAY BE SIGNIFICANTLY EFFECTED
BY THE PROPOSED ACTIVITY:
The effects of changes in the land form, disruption to
natural habitats, and impacts associated with construction
phases will generally be confined to the project site.
Population impacts and impact on services and public
utilities will generally be confined to the district bound-
aries of those agencies providing services to the project_.
The effects of additional runoff and decreased groundwater
quality will generally be confined to the immediat~ project
area, but may marginally impact the Agua Hedionda Lagoon,
which will receive additional run off.
The effect of the project on air quality will be shared by
the entire North County Air Basin. Traffjc and circulation
impacts will be generally localized.
Xw AGENCIES CONSULTED:
Copies of this report have been sent to the following
• agencies for review:
U. S. Agricultural Department
Loca1 Agency Formatio'-n Commission
County Parks & Recreation Department
State Division of Highways
County Parks and Recreation Department -District 6
San Diego Regional Water ·Quality Control Board
Comprehensive Planning Organization
State Department of Fish & Game
Department of Public· Health
San Diego County Air Pollution Control District I
San Diego County Sanitation & Flood Control .
!
e -21-•
XI. RELATIONSHIP BETWEEN LOCAL SHORT TERM USES OF MAN'S ENVIRON-
MENT AND ENHANCEMENT OF LONG TERM PRODUCTIVITY
The short term effects of the project will be those
associated with the conversion of the property from open
and agricultural land to a planned industrial and planned
residential development. The short term effects of the
project include the elimination and displacement of native
vegetation and wildlife, the depletion of natural resources,
the elimination of agricultural land,-and the noise and dust
associated with construction.
The long term effects will include an increased demand on
public services, stimulation of population growth, irrever-
sible loss of agriculturally suitable soils, degradation of
air quality, consumption of natural resources, and the
increased possibility of damage and loss of life associated
with an airplane accident.
The relationship of the long and short term effects depends,
to a large degree, on the intensity and rapidity with which
these changes take place. Should the conversion occur with-
in the next few years, the impacts on public services, growth
inducement and Drderly development of the city are likely
to be severe. A more gradual conversion will lessen these
effects.
XII. This ?raft E.I.R. has been prepared by the City of Carlsbad
Plan~1ng Department, utilizing information supplied by t~e
applicant's c?nsultant, Rick [ngineering Company, and
comments received from those reviewing agencies have been attached. •
Mr.· Don Agatep
January 23, 1974
Page 2
·•
The environmental consequences of the project appear to be in conflict with the
following interim regional goals and objectives of the local governments which
comprise CPO. •
'Encourage growth within the present limits of urbanization rather
than extending the urban area to encourage more efficient utilization
of existing schools, sewer lines, and other public and private facilities. 11
'Discourage extension of urbanized areas until all public services and
facilities have been planned, programmed and financed. 11
Another important environmental effect of the project would be to eliminate the 275
acres of cultivated to1natoes and plowed agricultural land that now exist on the pro-
perty. This can significantly reduce the economic viability of neighboring tomato
crops by introducing conflicting urban uses, raising the expectations of surrounding
landowners about the value of their property, and possibly increasing local property
taxes. These three factors, ,taken together, will most likely result in the loss of
agricultural production in the area as urban development continues to take its place.
Again from an agricultural resource standpoint, the following CPO Goals and
Objectives are not compatible:
'Preserve as open space lands the agricultural c:r:-op lands of the
region, 11 and 'to give equal protection to these lands regardless of
their size or proximity to urban areas. 11
'Encourage the preservation of agricultural land and recreational
uses between communities through land use regulations and tax
policieso· 11
Intensity of Development
The draft EIR points out that the project area contains significant natural areas
consisting of a waterway, -associated riparian habitat including oak trees and a man-
made pond. Natural limitations on development mentioned are the flood area of
Agua Hedondia Creek and the steep slopes and unstable soils conditions occurring
on a major portion of the property. The draft EIR does not demonstrate that the
planned development of l, 500 housing units, related commercial and recreational
areas, 155 acres of light industrial uses and alteration to natural land forms in-
cluding excavatim!. of 3 million cubic feet of material adequately considers the
nai-u.ral values and limitations to development inherent in the site.
Mr .. Don Agatep
January 23, 197•1
Page 3
The CPO Board has adopted the following interim regional goals and objectives
related to the conditions mentioned above.
'Integrate urban growth with the natural environment, ra_ther than
superimposing development upon it. 11
"Preserve open space land needed to protect public health, safety,
and welfare, including: beaches, cliffs, lagoons, wooded areas,
desert vistas, vistas, areas of significant wildlife or vegetation. 11
The development of the property at the intensity proposed will significantly alter
natural landforms rather than be integrated with them and may result in the degra-
dation of the proposed undeveloped riparian areas through increased erosion and
changes in hydrology. Public safety on the sloped areas can only be achieved at
high cost and degradation of the environment under the proposed intensity of use.
For these reasons the project appears to conflict with regional goals and objectives.
Reductions in the intensity of use guided by these goals could mitigate the problems
of integrating natu3?al and manmade environments.
Relationship to Palomar Airport
The entire project area is within the interim influence area for Palomar Airport
adopted by the Airport Land Use Commission in 1972. The property is directly
east of the normal visual landing pattern, while the southern 1/3 lies directly •
under the new instrument landing pattern. It can be anticipated that parts of the
property will be subjected to noise hazard. The extent of this hazard and its
impact in terms of appropriate land uses has not been determined at this time.
The problem is being studied by CPO staff, a consultant and an advisory committee.
The initial report detailing airport expansion, noise impacts and suggested land
use measures to mitigate these impacts will be available in mid-February, 1974.
It is suggested that this information be considered as part of the final EIR in taking
action on this project. CPO will make this report available as soon as it is com-
pleted.
CPO staff appreciates the opportunity to comment on this and other regionally
significant projects. ¥le trust that the above comments will be useful in evaluating
the Valle Verde draft Environmental Impact Report.
Sincerely,
~~
ARTHUR LETTER
Intergovernmental Relations Coordinator
AL:gi
·•
By Telephone from Dept. of Fish & Game -Bruce Elias
January 3, 1973 L. Estel
Re: Specific Plan No. 155 Pacesetter Homes
No Specific Comments on project -Advises that no answer by
required date does not mean they endorse project.
Re: Master Plan No. 15Z Loker Development
Possible alteration to be made to waterway, course, etc. indicated
on map by roadway would be in violation of Fish & Game Code
Section 1602 -Would suggest that sponsor contact the Fish and