HomeMy WebLinkAboutPRE 2025-0032; 2045 CORTE DE NOGAL PICKLEBALL; Admin Decision Letter{city of
Carlsbad
VIA EMAIL AND MAIL
July 21, 2025
Andrew Slipka
7105 Corintia Street
Carlsbad, CA 92009
SUBJECT: PRE 2025-0032 (DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
APN: 213-061-09-00
Thank you for submitting a preliminary review application to convert a 35,407-square-foot (SF) light
industrial building into a 14-court indoor/outdoor pickleball recreation facility at 2045 Corte del Nagai, a
2.59-acre site located in the Planned Industrial (P-M) zone. The existing building was permitted pursuant
to Planned Industrial Permit PIP 85-04 and the lot was created pursuant to Tentative Tract Map CT 80-34.
The scope of the conceptual project includes the following:
• Conversion of 30,000 SF warehouse use into 8 indoor courts and 5 indoor warm-up/practice
courts and the conversion a portion of the existing parking lot into 6 outdoor courts. Exclusive of
the warm-up courts, a total of 14 courts are proposed. No spectator seating is proposed.
• New accessible restrooms
• The facility will be open to the public with membership options available
• 5,150 square feet of office and storage will remain for use by the employees
• 52 parking spaces will remain. The following calculation was included as part of the site plan:
PARKING CALCULATIONS
USE NUMBER OF PARKING RATIO PARKING SPACES
14 STND. PICKLEBALL COURTS (8-INDOOR/ 6-OUTDOOR) 42 3 PARKING SPACES PER COURT'' 6
PRE/POST PLAY PLAYER AREA (CIRCULATION AREA) 05 1 PARKING SPACE PER 3 USERS 36
EMPLOYEE AREA 0-l 1 PARKING SPACE PER 250 S.F. GROSS FLOOR AREA •
GROUND FLOOR OFFICE 01 1 PARKING SPACE PER PRIVATE OFFICE 5
NOTES:
I. Pict.lebol C~t ratio cf 3 poMg ;poce! Pfl }tondord court bo!ed on ratio used for 11·~ Poin:ettio Tu,r.i: to Picklebol Court: prtject ICD 20'2~41 bo.:t·d on Fkk~bol covni U·,ot do not hove
spKtoto, s•otirlg.
2. S ...,-o,m-vp/p,actice courts o,+ not proaQrom,.,.,.d for 11-ogu., ploy. public re:ervotion. or spectolo, everJs. The-'r v!e is e.-;d,.11ive~ lmited to scheduled coocting and plc:lyer tronsifi.on beM-•eer'I mote hes.
toth of ...,hich o.re incorpo1ot•d if',lo the use pattern: of the-14 1tondo,-d covrt1.A1 tvch. the:e covts do no1 rep,ean1 indeP4"ndenl t,ip ,;teMrotio" or,equife odOrtionol po ming. cofl:1:tent ,,,.;,1, City
p,ec♦deflt vnd~ CD 2023-0004.
3. Pre/po:t p-'oy otea iJ APPROX .. 3,327 SF anal i: Intended a: a horulent s,ag:flg zor~ fer ploye,: arriving 1horHy bcefore Ot-leoving :hertly after =cl'!Mv"-.-d co~ time1. ea.1ed on standard grovp p!oy situ of 4-
p'oyer: and COVl'I sc~ul.rv,i. v,,,e anticipate r.o mot• than IS p'aye,1 occupying lhe 1pace at peak. U1in9 th• Cltv-op~oved pt..::edent c,f 1 space per J vser:, we popo!e a maximum potking
aloco1':on of S spocu fcf' thi:s a,eo. .. Crovnd floe, emp>:iyee o,.a, ii. approximolfft' 950 SF. v.\l serve 01 employ-bteok oreo and re;hoorru and not fCl pub1'c v:e. Upper r.oOf' -...!I not be oc:cu~ and plonMd u1e f04' gen.ral facrty
stOfage.
S. G,ovnd floe, office a1eo ~ o,-,. p,iYale office. •1,•e ~peel one panting :pace tor the private office d~ ncrrnoib1,1:inea t'.01,1n. '· Pe, Carl!bad ~\urieipolCod~ (CMCJ Hl!Ction 21.44.030 . ...,hete ti-.. po1king ,eqvJ'en",t!nb for o vie a,e not 1peofieo.'ly def.n•d herein. !he porJ:ir-,a reqlitement: fo, such use :hal et! delerrrinN by the city
p'Qnner.
TOTAL PARKING SPACES REQUIRED: 52
TOTAL PARKING SPACES PROVIDED: 52
Community Development Department
Planning Division [ 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032{DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
July 21, 2025
Pa e 2
In response to your application, the Planning Division has prepared this comment letter. Please note that
the purpose of a preliminary review is to provide you with direction and comments on the overall concept
of your project. This preliminary review does not represent an in-depth analysis of your project. It is
intended to give you feedback on critical issues based upon the information provided in your submittal.
This review is based upon the plans, policies, and standards in effect as of the date of this review. Please
be aware that at the time of a formal application submittal, new plans, policies, and standards may be
in effect and additional issues of concern may be raised through a more specific and detailed review.
Planning:
General
1. General Plan and zoning designations for the property are as follows:
a. General Plan: Pl, Planned Industrial
b. Zoning: P-M, Planned Industrial
c. Specific or Master Plan: N/ A
2. The project requires the following permits:
a. Minor Conditional Use Permit (MCUP). Pursuant to the permitted use matrix of the P-M zone,
Carlsbad Municipal Code Section 21.34.020, recreation facilities such as the proposed pickleball
facility require an MCUP, which is an administrative/City Planner-level decision.
b. Building permit
3. New requirements related to the city's goals to reduce greenhouse gas (GHG) emissions will likely
impact development requirements of this project. A formal application submittal will need to include
a completed Climate Action Plan Checklist (Form P-30) to determine what requirements will apply to
the project. New GHG reduction requirements are related to energy efficiency, photovoltaic, electric
vehicle charging, water heating and traffic demand management requirements, as set forth in the
California Green Building Standards Code and in Carlsbad Municipal Code Chapters 18.21, 18.30 and
18.51 which is available on the city's website at the following address:
http://www.qcode.us/codes/carlsbad/view.php?topic=18&frames=on
To the extent that new GHG reduction requirements are in effect at the time of application for
grading or building permits, the project will be required to comply with the effective requirements
even if different than what is proposed in the project's planning approvals. GHG reduction
requirements may impact, but are not limited to, site design and local building code requirements.
If incorporating new GHG reduction requirements results in substantial modifications to the project
after planning approvals are obtained, then prior to issuance of grading or building permits, the
applicant may be required to submit and receive approval of a Consistency Determination or an
Amendment application for the project through the Planning Division .
4. Parking. CMC Chapter 21.44, the Parking Ordinance, does not specify a parking requirement for
pickleball courts. In addition, there is not a similar use that could be used to apply a parking ratio.
Pursuant to CMC Section 21.44.030 -Parking Requirements for Uses Not Specified, the City Planner
Community Development Department
Planning Division I 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032(DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
July 21, 2025
Pa e 3
has the authority to determine the appropriate parking ratio for the use. The determination shall be
based upon the following:
a. The parking requirement for the most comparable use specified in this chapter; and/or
b. A parking study or other evidence satisfactory to the City Planner.
Since there is not a use comparable to a pickleball court in the Parking Ordinance that can be used
to determine the appropriate parking ratio, the City Planner can consider other evidence. Based on
research completed regarding parking requirements for pickleball courts throughout California, it is
common to apply a ratio of 4 parking spaces per pickleball court. Your concept project proposes 3
parking spaces per pickleball court. Given the possibility that not all courts will be occupied at any
given time as well as the potential for the ride sharing, the City Planner is preliminarily supportive of
the proposal to provide 3 spaces per court. However, please be advised that the warm up courts are
required to be parked. Exclusive of the office and storage uses, the concept project includes 19
courts; therefore, a minimum of 57 parking spaces are required for the pickleball courts and 52
spaces are proposed.
In addition, the site plan includes a note that the existing office is "not a part of proposed project."
The gross floor area of this part of the building is required to be included in the parking calculation.
The required parking ratios for office and storage uses are 1 space per 250 square feet and 1 space
per 1,000 square feet of gross floor area, respectively. Please include a detailed floor plan of this
area with the submittal and factor the additional parking spaces required in the parking calculation.
As currently proposed, adequate parking is not provided to account for the mixture of uses. If
adequate parking cannot be provided, please reduce the number of proposed courts.
5. Setbacks. Pursuant to CMC Section 21 .34.070.B, the project is required to comply with the following
setbacks :
• Front (collector street, shortest of the two street frontages is Corte Del Abeta): average setback
of 35 feet; however, the setback shall not be less than 25 feet, entirely landscaped.
• Front-street side (collector street, Corte Del Nagai): average setback of 35 feet; however, the
setback shall not be less than 25 feet, entirely landscaped.
• Side (south property line): 10 feet, entirely landscaped
• Rear (west property line): 20 feet, minimum 10 feet landscaped
Please update the plans to demonstrate compliance with the above-noted setbacks. Preliminarily, it
appears the project complies; however, please include setback dimensions between the parking
spaces and the property lines, the exterior courts and the property lines and demonstrate
compliance with the minimum setbacks. In addition, please demonstrate compliance with the 35-
foot average setback and landscaped setback requirements.
6. Lighting/fencing. With the submittal, please include details regarding any proposed fencing and/or
outdoor lighting. Please ensure all outdoor lighting is shielded to prevent impacts to the residential
area to the south and to prevent spillover onto the adjacent lot.
7. Hours of operation. With the submittal, please include details regarding the proposed hours of
operation.
Community Development Department
Planning Division I 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032(DEV 2025-0040) -2045 CORTE DE NOGAL PICK LEBALL
July 21, 2025
Pa e 4
8. Converted parking area . Please clarify if the pavement for the parking spaces will be replaced with
the new pickleball courts and if so, what the material will be (i.e., rubber, synthetic turf, etc.).
9. Landscaping. Please consider adding additional trees, specifically evergreen trees with large
canopies to provide shade adjacent to the outdoor pickle ball courts.
10. Change in occupancy. Prior to occupancy, a Certificate of Occupancy Permit for a change of use shall
be issued pursuant to Carlsbad Municipal Code Section 21.60.010.
11. McClellan-Palomar Airport. The subject property is located within the boundaries of the McClellan-
Palomar Airport Land Use Compatibility Plan (ALUCP). Preliminary review of the conceptual project
against the ALUCP revealed the following:
a. Exhibit 111-1-Compatibility Policy Map: Noise . The project site is located outside of the 60 db
CNEL noise exposure range per Exhibit 111-1. Pu rsuant to the ALUCP Section 3.3 .3(a) on page 3-
19: "The threshold for evaluation is the projected 60 dB CNEL contour. This contour defines
the noise impact area of the Airport. All land uses located outside of this noise contour are
consistent with the noise compatibility policies."
b. Exhibit 111-2 -Compatibility Policy Map: Safety. The project site is located within Safety Zone
6, Traffic Pattern Zone. Pursuant to Table 111-2 (Pgs. 3-45 through 3-52) of the ALUCP, "Indoor
Small Assembly Room (capacity 50 to 299 people)", "Office" and "Non-Group Recreation" uses
are compatible with airport uses when located within Safety Zone 6 with no F.A.R. restrictions.
c. Exhibit 111-3 -Compatibility Policy Map: Part 77 Airspace Protection. The project site is located
outside the 7:1 Transitional Surface contour of Exhibit 111-3. As the building is existing and
located outside of this area, approval from the Federal Aviation Administration is not required.
d. Exhibit 111-4 -Compatibility Policy Map: Overflight. The project site is located within the
Overflight Notification Area. Pursuant to the ALUCP Policy 3.6 -Overflight Compatibility
Policies for McClellan-Palomar Airport, real estate disclosures and overflight notification
documents are not required for non-residential land uses.
e. Exhibit 111-5 -Compatibility Policy Map: Airport Influence Area. The project site is located
within Review Area #1 of the Airport Influence Area. Review Area #1 consists of locations
where noise and/or safety concerns may necessitate limitations on the types of land use
actions. Please see discussions above in subsection a) and b).
f. Exhibit 111-6 -Compatibility Policy Map: Avigation Easement Area. The project site is located
outside of the Avigation Easement Area.
12. Noise. To analyze the project's compliance with the California Environmental Quality Act (CEQA),
the Noise Element of the city's General Plan and the Noise Guidelines Manual, please submit a noise
analysis prepared by a registered professional. As part of the study, please include current ambient
noise measurements and distances between the proposed exterior pickleball courts and existing
buildings in all directions as well as the closest residential development. Please be advised that
Community Development Department
Planning Division I 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032(DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
July 21, 2025
Pa e 5
additional design features such as a sound-absorbing fence, acoustic panels and/or padded paddles
may be required to adequately mitigate the noise generated from the exterior pickleball courts.
Please see link below for additional information:
https://www.carlsbadca .gov/home/showpublisheddocument/238/637425974092370000
13. Please consider providing outdoor bicycle parking for electric bikes to encourage alternative modes
of transportation.
All necessary application forms, submittal requirements, and fee information are available at the Planning
counter located in the Faraday Building at 1635 Faraday Avenue or online at
https://www.carlsbadca.gov/departments/community-development/planning. You may also access the
General Plan Land Use Element and the Zoning Ordinance online at the website address shown. Please
review all information ca refully before submitting.
Land Development Engineering:
Land Development Engineering Division staff have completed a preliminary review of the above-
referenced project. Prior to formal application for the project permit submittal, the following items must
be adequately resolved/addressed, unless otherwise noted:
1. Contact Nick Gorman in the Transportation Division at Nick.Gorman@carlsbadca.gov, a division of
the Public Works Department, to determine if a Scoping Agreement is required. Scoping Agreements
are used to determine if a Local Mobility Analysis (LMA) is required and the scope of analysis. If an
LMA is deemed necessary, first, work with Transportation Division staff to obtain an approved
scoping agreement. After the scoping agreement has been approved, submit the approved Scoping
Agreement as an appendix within the LMA that is to be prepared pursuant to the most recent
Transportation Impact Analysis Guidelines.
2. After the scoping agreement has been approved or deemed not necessary by the Transportation
Division, submit a completed Transportation Analysis Need Statement Form P-42 to Land
Development Engineering at LandDev@carlsbadca .gov prior to discretionary application submittal.
If an LMA has been deemed not necessary by the Transportat ion Division, please provide
correspondence from the Transportation Division indicating one is not required.
3. A Transportation Demand Management (TOM) plan may be required depending on the number of
employee vehicle trips the project will generate. Calculate the gross employee ADT using the
generation rates from Table 2-2 of the TOM Handbook
at: https://www.carlsbadca.gov/home/showpublisheddocument/310/637425981338370000
Show calculations on the Climate Action Plan checklist, Form P-30. If applicable, submit a TOM plan
with your application for discretionary permits.
4. Depending on the CEQA determination, which is determined after the application for discretionary
permits is submitted, a Vehicle Miles Traveled (VMT) analysis may be required per the Vehicles Miles
Traveled Analysis Guidelines at https://www.ca rlsbadca .gov/home/showdocument?id=312.
Community Development Department
Planning Division [ 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032(DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
July 21, 2025
Pa e 6
5. Complete a Stormwater Standards Questionnaire Form E-34. This questionnaire will guide you and
the city in determining what type of reports and storm water mitigation must be completed to satisfy
state and City storm water quality requirements.
6. Based on this project's general land use, Pl, this project may be subject to the City of Carlsbad trash
capture requirements. If trash capture is required based on Form E-34, either a Trash Capture Storm
Water Management Plan (TCSWQMP) Form E-35A or a SWQMP with trash capture Form E-35 is
required.
7. Provide a Preliminary Title Report (current within the last six (6) months).
8. Plot all existing easements and encumbrances listed in the Title Report on the site plan.
9. Is the existing driveway on Corte Del Abeta to be removed and relocated? The driveway on the site
plan does not match the alignment of the existing driveway but there's no statement that the
driveway is to be re-located.
10. Clearly show and identify all existing surface improvements (screened back) and proposed
improvements (heavier line weight) for curb, gutter, sidewalk, paving, striping, inlets, adjacent
driveways, transformers, etc. on the project site to differentiate existing vs. proposed site
improvements.
11. It is unclear if there are any proposed improvements to the existing parking lot. Are portions of the
existing parking lot just to be re-striped for the new pickleball courts? Or will the existing AC and
PCC paving be removed, re-graded, replaced and re-striped?
12. If portions of the existing parking are to be removed, re-graded and replaced:
a. Plot and label the limits of disturbance/grading.
b. Indicate the earthwork quantities (cut, fill, import, export, remedial) in cubic yards.
c. Provide existing and proposed contours and spot elevations using vertical datum NGVD29.
13. Show bearings and distances of the existing lot line.
14. Provide typical street cross sections for existing frontage streets. Provide existing right-of-way width
and existing improvements and proposed improvements.
15. Delineate and annotate all driveways and driveway widths.
16. Show all existing utilities and callout size for: water, sewer, laterals, meters, storm drain,
underground utilities, streetlights in Corte Del Nagai and Corte Del Abeta and on the property.
17. Address the comments on the attached redlined plan.
18. Please be advised that a more in-depth review of the proposed development will occur with the
discretionary permit application when a more complete design of the project is provided.
Community Development Department
Planning Division I 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032(DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
July 21, 2025
Pa e 7
Fire & Life Safety:
1. Change of use/occupancy will be required for converting the use of the space from warehouse
(Storage occupancy) to Pickleball (Assembly).
2. Egress is adequate.
3. Provide sprinkler system design and density to confirm adequacy for Assembly occupancy.
Utilities/CMWD:
1. Privatize existing water main and fire hydrant.
2. Quitclaim existing water easement.
3. Relocate existing domestic water and fire services, meters and backflow devices to meet current
standards.
4. Single check backflow preventer is out of compliance; replace to meeting current city engineering
standards (W-9).
5. Please see attached redlines.
Traffic:
Transportation Planning and Mobility staff have completed a review of the above-referenced project for
application completeness. The Transportation Department has reviewed the 2045 Corte Del Nogal -
Pickleball Republic submittal and have provided the comments below.
1. Please submit a Scoping Agreement per the latest City of Carlsbad Transportation Impact Analysis
Guidelines. The scoping agreement is provided in Appendix A of the TIA guidelines.
2. The project should consider providing pedestrian enhancements along the property frontage to
allow for safe access to the proposed site for users that park on-street given the limited proposed
parking on the project site.
Community Development Department
Planning Division I 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600
PRE 2025-0032(DEV 2025-0040) -2045 CORTE DE NOGAL PICKLEBALL
July 21, 2025
Pa e 8
If you would like to schedule a meeting to discuss this letter with the commenting departments, please
contact Shannon Harker at the number below. You may also contact each department individually as
follows:
• Planning: Shannon Harker, Senior Planner, at (442) 339-2621
• Land Development Engineering: Tim Carroll, Project Engineer, at (442) 339-2737
Sincerely,
ERIC LARDY, AICP
City Planner
EL:SH:CF
Enc: Utilities redlines
c: Phillip Teyssier, 3200 Highland Avenue B4-2, National City, CA 91950
Tim Carroll, Project Engineer
Fire & Life Safety
Laserfiche/File Copy
Data Entry
Community Development Department
Planning Division I 1635 Faraday Avenue I Carlsbad, CA 92008-7314 I 442-339-2600