HomeMy WebLinkAboutCT 2021-0005; CHINQUAPIN COASTAL HOMES; FINAL SOILS REPORT; 2025-07-11 11 July 2025 Rincon Real Estate Group Job No. 21-13506 5315 Avenida Encinas, Suite 200 Carlsbad, CA 92008 Attn: Mr. Kevin Dunn Subject: Final Report of Grading Observations and Soil Testing Chinquapin Coastal Homes 330 Chinquapin Avenue Carlsbad, California Dear Mr. Dunn: Per the request of Mr. Clay Hatch with Rincon Homes and as required by the City of Carlsbad, Geotechnical Exploration, Inc. hereby presents this final report of grading observations and soil testing performed on subject property. Our firm previously issued a Report of Rough Grading Observations and Soil Testing for the subject project on October 17, 2023. For the location of the project, refer to the Vicinity Map, Figure No. I. Our firm also prepared a Report of Preliminary Geotechnical Investigation dated October 28, 2021 and the following additional supplementary documentation: 1.) Permeable Pavers Unlined Cross Section letter dated May 04, 2022; 2.) Response to Third Party Review, 1st Review dated September 16, 2022; 3.) Revised Permeable Pavers Unlined Cross Section letter dated September 19, 2022; 4.) Grading Plan Review letter dated October 11, 2022; 5.) Foundation Plan Review letter dated October 11, 2022; 6.) Response to Land Development Engineering dated February 03, 2023; Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 2 7.) Response to Reviewers Comments for Curb and Gutter Daylight Requirements dated February 06, 2023; 8.) Response to Third Party Review Comments: First Review City Permit No.: PC2022-0056 dated February 06, 2023; 9.) Grading and Shoring Plan Review Letter dated March 30, 2023; 10.) Report of Rough Grading Observations and Soil Testing dated October 17, 2023. PREVIOUS FIELD OBSERVATIONS As previously stated, Geotechnical Exploration, Inc. had previously prepared a Report of Rough Grading Observations and Soil Testing for the project. In summary, our representative observed during rough grading the soil removals down to competent soil material and soil recompaction of the building pad soils. The drilling for the shoring soldier piles were also observed, and the removal of blocks and cistern located in the middle of the most southern portion of the lot near Chinquapin Avenue. For more detailed information on the work performed between August 09, and October 04, 2023, refer to our report dated October 17, 2023. FIELD OBSERVATIONS 1. The following observations and soil testing during final grading were performed between October 11, 2023 and June 24, 2025. The earthwork was performed in accordance with the recommendations presented in our report dated October 28, 2021 and additional supplementary documentation. Our representative observed the bearing soils for the new retaining wall footings located on the east property line, followed by the north and south retaining wall footing excavation bottom soils. The observed footing Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 3 excavations were observed to be founded in suitable recompacted fill or dense formational soils. A footing memo was issued to the contractor/ contractor’s representative on October 11, 2023. 2. Our representative was requested to observe the backfill placement for the east property line and north retaining walls. When our representative arrived, the contractor had completed the backfill placement of both retaining walls. Our representative was informed by the contractor that the backfill consisted of ¾-inch diameter sized crushed rock with an 8 to 10-inch soil cap. Our representative was also informed by the contractor that waterproofing and a French subdrain system was placed behind the retaining wall on November 7, 2023. It should be noted that it is not within the scope of our services to provide quality control oversight for surface or subsurface drainage construction or retaining wall sealing and base of wall drain construction. It is the responsibility of the contractor to verify proper wall sealing, geofabric installation, protection board installation (if needed), drain depth below interior floor or yard surfaces, pipe percent slope to the outlet, etc. 3. The sewer utility trench backfill placement and recompaction for the project driveway was observed and tested on November 28, 2023, January 26 and 29, 2024. The sewer utility trench backfill located on Chinquapin Avenue was also observed and tested periodically between December 28, 2023 and January 09, 2024. The sewer utility trenches were backfilled with the on-site soil material. 4. The backfill placement for a water service utility located in Chinquapin Avenue was observed and tested on January 29, 2024 and again on March 7. 2024. Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 4 Backfill placement for the fire water line was also observed and tested on February 29 and March 01, 2024. 5. The backfill placement for the sewer tie-ins going into the units were observed and tested between April 3 and May 21, 2024. The sewer utility trench that runs underneath the paver driveway on the north side of the lot and parallel to units 1 through 9 was observed and tested by our representative on May 20, 2024. 6. The bearing soils for the interior and exterior footing excavations of units 1 through 9 were observed to be founded in dense/ suitable recompacted fill soils on April 15, 2024. A field memo was issued to the contractor/ contractor’s representative for the observed footing excavations bottom soils. 7. Backfill placement of the gas utility trench located near the north side property line was observed and tested on July 01 and 03, 2024. 8. A utility trench located on Chinquapin Avenue was observed and tested on July 09, and 11, 2024. Temporary road base located in the driveway was also observed and tested on July 26, 2024. 9. A rectangular utility patch located on Chinquapin Avenue near the driveway entrance was observed and tested on August 28, 2024. 10. The backfill placement for the electrical utility trench located parallel to the sidewalk the runs along Chinquapin Avenue and perpendicular to Chinquapin Ave. center line and into the rectangular utility trench was observed and tested on August 29, 2024. 11. The sewer utility located parallel Chinquapin Avenue and the street patchwork perpendicular to Chinquapin Ave. center line and the subject lot was observed and tested on September 18 and 19, 2024. Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 5 12. The subgrade for the ribbon gutter located on the north side of the paver driveway was observed and tested on April 23, 2025. The curb subgrade that runs on the south side of the driveway adjacent to the units was observed and tested on May 07, 2025. The driveway soil subgrade was also tested on May 07, 2025. The curb and gutter soil subgrade located near Chinquapin Avenue was observed was observed and tested between June 02 and June 06, 2025. 13. The water utility trench located on Chinquapin was observed and tested on June 11, 2025. The Chinquapin asphalt street pavement was also observed and tested on June 12, 2025, also the curb and gutter excavations on the east side of the curb inlet for the driveway were also observed to be founded in very dense recompacted fills. The soil subgrade near the driveway entrance was observed and tested along with a portion of side walk near unit 1 on June 19, 2025. 14. The gravel layer placed in the area of the paver driveway was observed between June 20 and June 24, 2025. The gravel layer probed very dense with the hand probe. SOIL TESTING Representative soil samples were collected during grading to determine laboratory maximum dry density of the soils per ASTM D1557-12e1. Field density tests were performed at approximate locations shown on Figure Nos. IIa-c, Plot Plan and Site- Specific Geologic Map, and are in accordance with ASTM D6938-17a. The complete list of density tests results is shown as Table A on Figure Nos. IIIa-g, and laboratory soil compaction test results are shown as Table B on Figure No. IIIh. Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 6 Equipment used for soil compaction consisted of a mini-excavator with sheep’s foot compaction wheel and vibratory plate. Water was added, when needed, to increase soil moisture. Field density tests yielded a relative compaction of at least 90 percent or 95 percent, at certain locations, of the maximum laboratory dry density at the tested locations. Areas with failed tests were brought to the awareness of the grading contractor and recompacted until the recommended compaction was achieved. In general, the on-site used during grading consisted of brown silty sand and the imported soils consisted of brown well-graded gravel and dark grayish-brown recycled crushed miscellaneous base. The on-site and imported soils used during the grading were classified to have very low expansion potential (E.I.) with EI values less than 20 per ASTM D4829. Asphalt concrete was imported to the site and the Hveem number provided by the asphalt concrete supplier was used to determine the compaction of the asphalt concrete. Proper finish drainage for the site is to be implemented by the general contractor prior to completing construction. Any future or pending earthwork should be observed by our field representative prior to form, steel reinforcing placement, and just prior to concrete placement. Any pending utility trenches, or retaining wall backfill should also be performed under the observation and testing of our firm as well as any finished subgrade testing for any pending exterior flatwork or driveway. SITE SUITABILITY AND COMPLIANCE The observed and tested areas of the project site are, in our professional opinion, suitable for their intended use. The adequate formational soils are suitable to support the recompacted fill for the new structures to be built and adjacent related exterior improvements. Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 7 We certify that the geotechnical engineering aspects of the grading reported herein are in compliance with the approved geotechnical report and approved grading plans. LIMITATIONS The findings and opinions presented herein have been made in accordance with currently accepted principles and practice in the field of geotechnical engineering in the City of Carlsbad. No warranty, either expressed or implied, is made. All statements in this grading report are applicable only for the grading operation observed and tested by our firm. The firm Geotechnical Exploration, Inc. shall not be held responsible for fill soils placed without our observations and testing at any other time, or subsequent changes to the site by others, which directly or indirectly cause poor surface or subsurface drainage, water erosion, and/or alteration of the strength of the compacted fill soils. As previously stated, it is not within the scope of our services to provide quality control oversight for surface or subsurface drainage construction or retaining wall sealing and base of wall drain construction. It is the responsibility of the contractor to verify proper wall sealing, geofabric installation, protection board installation (if needed), drain depth below interior floor or yard surfaces, pipe percent slope to the outlet, etc. In the event that any changes in the nature, design, or location of the building or improvements are planned, the conclusions and recommendations contained in this report should not be considered valid unless the changes are reviewed and the conclusions of this report modified or verified in writing. Rincon, 330 Chinquapin Homes Job No. 21-13506 Carlsbad, California Page 8 This opportunity to be of service is sincerely appreciated. If you have any questions regarding this letter, please contact our office. Reference to our Job No. 21-13506 will help expedite a response to your inquiry. Respectfully submitted, GEOTECHNICAL EXPLORATION, INC. _______________________________ ______________________________ Jaime A. Cerros, P.E. Richard A. Cerros, P.E. R.C.E. 34422/G.E. 2007 R.C.E. 94223 Senior Geotechnical Engineer VICINITY MAP Chinquapin Coast Homes 330 Chinquapin Avenue Carlsbad, CA. Figure No. I Job No. 21-13506 SITESITE Thomas Bros Guide San Diego County pg 1106-F6 Bottom of Excavation Elevation (feet) 47.0’ 47.0’ 47.0’ Approximate Limits of Grading Septic System Location 7 6 5 2 4 1 316 13 14 15 12 8 10 11 6 19 18 17 24 20 21 25 23 22 28 26292746.0’ 46.0’ 46.0’ 46.0’ 45.0’ 46.0’ N FIre Service Trench UtilityTrenchPatch Electrical Trench Curb and Gutter Observed 6-12-25 Sewer Trench Location 7 3 41 Burrito Drain Location Observed 1-7-23 Water Service Trench186 Approximate Location of Field Density Test 798084818785 86 33 3235 313034908988 9183 4748 55 104 58 59 60616362 65 66 67 69 68 707271 73 74 75 76777882 92 93 94 95 96 97 98 99 100 114 64 122 113 121 112 101 102 103 105 106 107 108 109111110 130 119 129 118 128 131 116 115 117 120 177 166 172 176 178 183 182 179 180 167 184 181 161 175 171 170 174 165 169 173 5153 5256 54 127 168 Artificial Fill Qop Qaf Old Paralic Deposits, Unit 6-7 GEOLOGIC LEGEND 159 Qaf 6-7 Qop6-7 Qaf Qop6-7 Qaf Qop6-7 Qaf Qop6-7 21-13506-PLOT-PLAN-IIA-7-9-25.ai REFERENCE: This Plot Plan was prepared from an existing undated GRADING PLAN by PASCO LARET SUITER & ASSOCIATES and from on-site field reconnaissance performed by GEI. NOTE: This Plot Plan is not to be used for legal purposes. Locations and dimensions are approximate. Actual property dimensions and locations of utilities may be obtained from the Approved Building Plans or the “As-Built” Grading Plans. Chinquapin Coast Homes 330 Chinquapin Avenue Carlsbad, CA. Figure No. IIa Job No. 21-13506 PLOT PLAN AND SITE SPECIFIC GEOLOGIC MAP July 2025 GRAPHIC SCALE: (FEET) CH I N Q U A P I N A V E N U E LEGEND 123-126 FIELD DENSITY TEST LOCATIONS Location of Temporary Shoring Ribbon Gutter 185 Approximate Location of Field Density Test 156 154 149 157 153 150 158 159 151 160 152 185 163 186 162 164 161 155 Artificial Fill Qop Qaf Old Paralic Deposits, Unit 6-7 GEOLOGIC LEGEND Qaf 6-7 Qop6-7 Qaf Qop6-7 Qaf Qop6-7 Qaf Qop6-7 21-13506-PLOT-PLAN-IIB-7-9-25.ai REFERENCE: This Plot Plan was prepared from an existing undated GRADING PLAN by SHORING DESIGN GROUP and from on-site field reconnaissance performed by GEI. NOTE: This Plot Plan is not to be used for legal purposes. Locations and dimensions are approximate. Actual property dimensions and locations of utilities may be obtained from the Approved Building Plans or the “As-Built” Grading Plans. Chinquapin Coast Homes 330 Chinquapin Avenue Carlsbad, CA. Figure No. IIb Job No. 21-13506 July 2025 GRAPHIC SCALE: (FEET) CH I N Q U A P I N A V E N U E LEGEND FIELD DENSITY TEST LOCATIONS PLOT PLAN AND SITE SPECIFIC GEOLOGIC MAP Street Patch Location Sewer Trench Location Water Trench Location 148 Approximate Location of Field Density Test 45 57 143 148 142 147 144 141 145 133 139 140 146 134 50 44 46 43 49 42 41 40 39 38 37 36 135 132 137 136138 Artificial Fill Qop Qaf Old Paralic Deposits, Unit 6-7 GEOLOGIC LEGEND Qaf 6-7 Qop6-7 Qaf Qop6-7 Qaf Qop6-7 Qaf Qop6-7 21-13506-PLOT-PLAN-IIC-7-9-25.ai REFERENCE: This Plot Plan was prepared from an existing IMPROVEMENT PLAN by PASCO LARET SUITER & ASSOCIATES dated 6/12/2023 and from on-site field reconnaissance performed by GEI. NOTE: This Plot Plan is not to be used for legal purposes. Locations and dimensions are approximate. Actual property dimensions and locations of utilities may be obtained from the Approved Building Plans or the “As-Built” Grading Plans. Chinquapin Coast Homes 330 Chinquapin Avenue Carlsbad, CA. Figure No. IIc Job No. 21-13506 FIELD DENSITY TEST LOCATIONS July 2025 GRAPHIC SCALE: (FEET) LEGEND PLOT PLAN AND SITE SPECIFIC GEOLOGIC MAP TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks 1 8/10/23 SEPTIC TANK BACKFILL 41.5 11.6 118.9 95 1 2 8/10/23 SEPTIC TANK BACKFILL 43.5 12.4 119.3 95 1 3 8/10/23 SEPTIC TANK BACKFILL 45.5 8.9 121.0 97 1 4 8/11/23 BUILDING PAD FILL UNIT #1 46 6.1 121.3 97 1 5 8/11/23 BUILDING PAD FILL UNIT #2 46 7.4 118.3 95 1 6 8/11/23 BUILDING PAD FILL UNIT #3 46 6.8 119.0 95 1 7 8/11/23 BUILDING PAD FILL UNIT #1 47 6.0 117.8 94 1 8 8/11/23 BUILDING PAD FILL UNIT #2 47 8.1 119.9 96 1 9 8/11/23 BUILDING PAD FILL UNIT #3 47.5 10.3 118.0 94 1 10 8/14/23 BUILDING PAD FILL UNIT #1 47.5 9.4 116.8 93 1 11 8/14/23 SEPTIC TANK BACKFILL 47 10.0 118.9 95 1 12 9/25/23 BUILDING PAD FILL UNIT #4 47 6.0 116.0 93 1 13 9/25/23 BUILDING PAD FILL UNIT #6 47 5.4 118.1 94 1 14 9/25/23 BUILDING PAD FILL UNIT #5 48 4.9 120.4 96 1 15 9/26/23 BUILDING PAD FILL UNIT #2 48 6.8 117.3 94 1 16 9/26/23 BUILDING PAD FILL UNIT #3 48 7.0 118.8 95 1 17 9/26/23 BUILDING PAD FILL UNIT #6 48 6.2 116.7 93 1 18 9/29/23 BUILDING PAD FILL UNIT #7 48 8.4 114.3 91 1 19 9/29/23 BUILDING PAD FILL UNIT #8 48 9.6 115.1 92 1 20 9/29/23 BUILDING PAD FILL UNIT #9 49 9.1 117.0 94 1 21 10/2/23 BUILDING PAD FILL UNIT #1 FSG 6.9 115.4 92 1 22 10/2/23 BUILDING PAD FILL UNIT #2 FSG 7.3 116.0 93 1 23 10/2/23 BUILDING PAD FILL UNIT #3 FSG 6.9 117.1 94 1 24 10/4/23 BUILDING PAD FILL UNIT #4 FSG 7.1 114.0 91 1 25 10/4/23 BUILDING PAD FILL UNIT #5 FSG 8.0 112.9 90 1 26 10/4/23 BUILDING PAD FILL UNIT #6 FSG 7.6 115.1 92 1 27 10/4/23 BUILDING PAD FILL UNIT #7 FSG 6.9 113.3 91 1 28 10/4/23 BUILDING PAD FILL UNIT #8 FSG 6.5 113.0 90 1 Job No. 21-13506 Figure No. IIIa SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) 29 10/4/23 BUILDING PAD FILL UNIT #9 FSG 6.0 114.8 92 1 30 11/28/23 SEWER TRENCH BACKFILL FSG -3.5 6.4 109.0 87 1 FAIL SEE #31 RETEST 31 11/28/23 SEWER TRENCH BACKFILL FSG -3.5 7.3 112.1 90 1 RETEST OF #30 32 11/28/23 SEWER TRENCH BACKFILL FSG -3 5.1 110.6 88 1 FAIL SEE #33 33 11/28/23 SEWER TRENCH BACKFILL FSG -3 7.8 113.4 91 1 RETEST OF #32 34 11/28/23 SEWER TRENCH BACKFILL FSG -2 8.6 112.3 90 1 35 11/28/23 SEWER TRENCH BACKFILL FSG -3.5 7.0 112.8 90 1 36 12/28/23 SEWER TRENCH BACKFILL FSG -4 6.8 116.1 93 1 37 12/29/23 SEWER TRENCH BACKFILL FSG -2 7.6 114.4 92 1 CHINQUAPIN AVENUE 38 12/29/23 SEWER TRENCH BACKFILL FSG -.5 8.1 112.6 90 1 CHINQUAPIN AVENUE 39 1/2/24 SEWER TRENCH BACKFILL FSG -3 8.4 118.1 94 1 CHINQUAPIN AVENUE 40 1/2/24 SEWER TRENCH BACKFILL FSG -1.5 6.9 113.4 91 1 CHINQUAPIN AVENUE 41 1/2/24 SEWER TRENCH BACKFILL FSG -.5 7.3 118.3 95 1 CHINQUAPIN AVENUE 42 1/5/24 SEWER TRENCH BACKFILL FSG -2 6.9 116.3 93 1 CHINQUAPIN AVENUE 43 1/5/24 SEWER TRENCH BACKFILL FSG -.5 7.8 118.8 95 1 CHINQUAPIN AVENUE 44 1/8/24 SEWER TRENCH BACKFILL FSG -1.5 6.9 114.3 91 1 CHINQUAPIN AVENUE 45 1/8/24 SEWER TRENCH BACKFILL FSG -.5 6.6 115.5 92 1 CHINQUAPIN AVENUE 46 1/9/24 SEWER TRENCH BACKFILL FSG 5.5 121.0 97 1 CHINQUAPIN AVENUE 47 1/26/24 SEWER TRENCH BACKFILL FSG -2.5 10.1 112.0 90 1 CHINQUAPIN AVENUE 48 1/26/24 SEWER TRENCH BACKFILL FSG -1.0(8.4)8.4 113.1 90 1 DRIVEWAY(POTHOLE) 49 1/29/24 SEWER TRENCH BACKFILL FSG -.5 7.8 119.6 96 1 DRIVEWAY(POTHOLE) 50 1/29/24 WATER TRENCH BACKFILL FSG -1 8.1 120.4 96 1 CHINQUAPIN AVENUE 51 2/29/24 FIRE WATER TRENCH FSG -1.0 8.0 115.3 92 1 CHINQUAPIN AVENUE 52 2/29/24 FIRE WATER TRENCH FSG -1.0 6.3 119.4 96 1 53 3/1/24 FIRE WATER TRENCH FSG -1.0 8.8 113.1 90 1 54 3/1/24 FIRE WATER TRENCH FSG -1.0 9.7 120.4 96 1 55 3/1/24 FIRE WATER TRENCH FSG -1.0 9.7 116.8 93 1 56 3/1/24 FIRE WATER TRENCH FSG -1.0 9.7 117.8 94 1 Job No. 21-13506 Figure No. IIIb Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) 57 3/7/24 WATER LINE TRENCH FG -1.5 10.1 119.9 96 1 ON CHINQUAPIN AVENUE 58 4/3/24 SEWER TIE IN BACKFILL FSG 9.8 117.8 94 1TRENCH BACKFILL 59 4/3/24 SEWER TIE IN BACKFILL FSG 7.4 124.0 99 1 60 4/3/24 SEWER TIE IN BACKFILL FSG 6.5 113.8 91 1 61 4/3/24 SEWER TIE IN BACKFILL FSG 8.2 117.9 94 1 62 4/3/24 SEWER TIE IN BACKFILL FSG 6.5 116.6 93 1 63 4/3/24 SEWER TIE IN BACKFILL FSG 7.4 119.4 96 1 64 4/4/24 INTERIOR SEWER TRENCHES FSG 18.0 109.1 87 1FAIL 65 4/4/24 INTERIOR SEWER TRENCHES FSG 12.3 107.6 86 1FAIL 66 4/8/24 INTERIOR SEWER TRENCHES FSG 5.9 116.2 93 1 RETEST of No. 64 67 4/8/24 INTERIOR SEWER TRENCHES FSG 6.4 118.3 95 1 RETEST of No. 65 68 4/8/24 SEWER TIE IN UNIT 8 FSG 6.5 119.4 96 1 69 4/8/24 INTERIOR SEWER UNIT 3 FSG 6.6 115.3 92 1 70 4/8/24 INTERIOR SEWER #4 FSG 7.5 119.4 96 1 71 4/8/24 INTERIOR SEWER #5 FSG 7.0 118.5 95 1 72 4/8/24 INTERIOR SEWER #6 FSG 7.8 116.4 93 1 73 4/8/24 INTERIOR SEWER #7 FSG 7.6 119.4 96 1 74 4/8/24 INTERIOR SEWER #8 FSG 6.2 117.2 94 1 75 4/8/24 INTERIOR SEWER #9 FSG 8.1 118.0 94 1 76 5/20/24 SEWER TRENCH BACKFILL FSG -1' 8.2 123.0 98 1 77 5/20/24 SEWER TRENCH BACKFILL FSG -1' 7.8 116.0 93 1 78 5/20/24 SEWER TRENCH BACKFILL FSG -1' 8.8 121.7 97 1 79 5/21/24 SEWER TRENCH BACKFILL FSG -1' 6.1 118.0 94 1 80 5/21/24 SEWER TRENCH BACKFILL FSG -1' 7.7 120.9 97 1 81 5/21/24 SEWER TRENCH BACKFILL FSG -1' 7.0 121.4 97 1 82 5/21/24 SEWER TRENCH BACKFILL FSG -1' 8.9 116.6 93 1 83 5/21/24 SEWER TRENCH BACKFILL FSG 6.1 123.2 99 1 84 5/21/24 SEWER TRENCH BACKFILL FSG 5.3 122.6 98 1 Job No. 21-13506 Figure No. IIIc Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) 85 5/21/24 SEWER TRENCH BACKFILL FSG 5.1 122.3 98 1 86 5/21/24 SEWER TRENCH BACKFILL FSG 5.5 122.9 98 1 87 5/21/24 SEWER TRENCH BACKFILL FSG 5.3 123.1 98 1 88 5/21/24 SEWER TRENCH BACKFILL FSG 5.6 123.8 99 1 89 5/21/24 SEWER TRENCH BACKFILL FSG 6.2 114.3 91 1 90 5/21/24 SEWER TRENCH BACKFILL FSG 5.2 123.0 98 1 91 5/21/24 SEWER #9 FSG -1' 6.9 116.2 93 1 92 5/21/24 SEWER #9 FSG 5.8 115.8 93 1 93 5/21/24 SEWER #8 FSG -1' 5.6 114.2 91 1 94 5/21/24 SEWER #8 FSG 4.9 123.4 99 1 95 5/21/24 SEWER #7 FSG -1' 5.8 119.4 96 1 96 5/21/24 SEWER #7 FSG 5.3 121.4 97 1 97 5/21/24 SEWER #6 FSG -1 9.3 113.9 91 1 98 5/21/24 SEWER #6 FSG 5.7 123.4 99 1 99 5/21/24 SEWER #5 FSG -1 7.7 114.2 91 1 100 5/21/24 SEWER #5 FSG 5.2 122.9 98 1 101 5/21/24 SEWER #4 FSG -1 7.8 123.0 98 1 102 5/21/24 SEWER #4 FSG 5.1 123.1 98 1 103 5/21/24 SEWER #3 FSG -1 7.2 122.7 98 1 104 5/21/24 SEWER #3 FSG 6.4 114.5 92 1 105 5/21/24 SEWER #2 FSG -1 8.6 123.0 98 1 106 5/21/24 SEWER #2 FSG 5.8 122.4 98 1 107 5/21/24 SEWER #1 FSG -1 6.2 120.3 96 1 108 5/21/24 SEWER #1 FSG 5.7 119.4 96 1 109 5/21/24 SEWER FSG -1 7.3 118.4 95 1 110 7/1/24 GAS TRENCH BACKFILL FSG -1 7.0 123.2 99 1 111 7/1/24 GAS TRENCH BACKFILL FSG 6.8 122.4 98 1 112 7/3/24 GAS TRENCH BACKFILL FSG 5.9 120.4 96 1 Job No. 21-13506 Figure No. IIId Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) 113 7/3/24 GAS TRENCH BACKFILL FSG 5.4 122.1 98 1 114 7/3/24 GAS TRENCH BACKFILL FSG 3.4 115.4 92 1 115 7/9/24 UTILITIES TRENCH BACKFILL ROAD FSG -0.5' 5.4 119.7 96 1 116 7/9/24 UTILITIES TRENCH BACKFILL ROAD FSG 7.0 119.3 95 1 117 7/9/24 UTILITIES TRENCH BACKFILL ROAD FSG 6.5 120.4 96 1 118 7/11/24 UTILITIES TRENCH BACKFILL ROAD FSG -1 8.1 120.5 96 1 119 7/11/24 UTILITIES TRENCH BACKFILL ROAD FSG 7.2 121.0 97 1 120 7/26/24 TEMP ROAD BASE FSG 5.9 117.2 96 3 BASE 121 7/26/24 TEMP ROAD BASE FSG 4.2 117.8 96 3 BASE 122 7/26/24 TEMP ROAD BASE FSG 5.7 119.3 98 3 BASE 123 8/28/24 TRENCH PATCH FG -1' 5.2 121.2 97 1 124 8/28/24 TRENCH PATCH FG -3' N/A 145.7 98 4 ASPHALT 125 8/28/24 TRENCH PATCH FG -1.25" N/A 140.8 95 4 ASPHALT 126 8/28/24 TRENCH PATCH FG N/A 140.9 95 4 ASPHALT 127 8/29/24 AC (ELE TRENCH PATCH) FG -3" N/A 141.2 95 4 CHINQUAPIN AVENUE 128 8/29/24 AC (ELE TRENCH PATCH) FG N/A 142.6 96 4 CHINQUAPIN AVENUE 129 8/29/24 AC (ELE TRENCH PATCH) FG N/A 141.0 95 4 CHINQUAPIN AVENUE 130 8/29/24 AC (ELE TRENCH PATCH) FG -3" N/A 141.7 96 4 CHINQUAPIN AVENUE 131 8/29/24 AC (ELE TRENCH PATCH) FG -3" N/A 140.8 95 4 CHINQUAPIN AVENUE 132 9/18/24 PATCH SEWER TRENCH FSG 5.4 119.3 95 1 CHINQUAPIN AVENUE 133 9/18/24 PATCH SEWER TRENCH FSG 5.0 120.1 96 1 CHINQUAPIN AVENUE 134 9/18/24 PATCH SEWER TRENCH FBG 13.1 116.4 95 3 CHINQUAPIN AVENUE 135 9/18/24 PATCH SEWER TRENCH FBG 10.8 117.9 96 3 CHINQUAPIN AVENUE 136 9/18/24 PATCH SEWER TRENCH FBG 11.9 115.9 95 3 CHINQUAPIN AVENUE 137 9/18/24 PATCH SEWER TRENCH FG -1.25 0.0 140.3 95 4 CHINQUAPIN AVENUE 138 9/18/24 PATCH SEWER TRENCH FG -1.25 0.0 141.0 95 4 CHINQUAPIN AVENUE 139 9/18/24 PATCH SEWER TRENCH FG -1.25 6.1 140.6 95 4 CHINQUAPIN AVENUE 140 9/19/24 STREET PATCH (TRENCH) FSG 5.4 120.4 96 1 Job No. 21-13506 Figure No. IIIe Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) 141 9/19/24 STREET PATCH (TRENCH) FSG 6.5 119.0 95 1 142 9/19/24 STREET PATCH (TRENCH) FSG 5.4 119.8 96 1 143 9/19/24 STREET PATCH (TRENCH) FBG 6.5 116.1 95 3 144 9/19/24 STREET PATCH (TRENCH) FBG 10.8 117.4 96 3 145 9/19/24 STREET PATCH (TRENCH) FBG 11.4 117.9 96 3 146 9/19/24 STREET PATCH (TRENCH) FG -1.25 11.8 140.8 95 4 147 9/19/24 STREET PATCH (TRENCH) FG -1.25 0.0 141.1 95 4 148 9/19/24 STREET PATCH (TRENCH) FG -1.25 0.0 140.1 95 4 149 4/23/25 RIBBON GUTTER IN DRIVEWAY FSG 0.0 119.1 95 1 150 4/23/25 RIBBON GUTTER IN DRIVEWAY FSG 6.9 120.3 96 1 151 4/23/25 RIBBON GUTTER IN DRIVEWAY FSG 8.1 119.3 95 1 152 5/1/25 CURB SUGRADE FSG 6.4 120.1 96 1 153 5/1/25 CURB SUGRADE FSG 8.1 119.0 95 1 154 5/1/25 CURB SUGRADE FSG 7.0 119.2 95 1 155 5/7/25 DRIVEWAY SUBGRADE FSG 8.0 118.1 94 1 156 5/7/25 DRIVEWAY SUBGRADE FSG 7.0 118.7 95 1 157 5/7/25 DRIVEWAY SUBGRADE FSG 7.8 119.1 95 1 158 5/7/25 DRIVEWAY SUBGRADE FSG 6.0 118.4 95 1 159 5/7/25 DRIVEWAY SUBGRADE FSG 7.2 118.6 95 1 160 5/7/25 DRIVEWAY SUBGRADE FSG 6.0 120.1 96 1 161 6/2/25 CURB & GUTTER SUBGRADE FSG 6.1 121.8 97 1 162 6/2/25 CURB & GUTTER SUBGRADE FSG 8.4 120.2 96 1 DRIVE APPROACH 163 6/6/25 CURB & GUTTER SUBGRADE FSG 6.4 119.3 95 1 164 6/6/25 RIBBON GUTTER FBG 11.8 117.0 96 3 165 6/11/25 WATER UTILITY TRENCH FSG 7.2 120.0 96 1 166 6/11/25 BACKFILL (STREET) FSG 6.9 118.5 95 1 167 6/11/25 BACKFILL (STREET) FSG 8.2 119.6 96 1 168 6/11/25 BACKFILL (STREET) FSG 7.4 120.3 96 1 Job No. 21-13506 Figure No. IIIf Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade TABLE A Approximate Moisture Dry Degree of Test Elevation Content Density Compaction Compaction No. Date of Test Test Location (Feet) (%) (pcf) (%) Curve No. Remarks SUMMARY OF FIELD DENSITY TEST RESULTS (ASTM D1556 and/or ASTM D6938) 169 6/11/25 BACKFILL (STREET) FBG 13.0 115.1 94 3 170 6/11/25 BACKFILL (STREET) FBG 12.5 115.3 94 3 171 6/11/25 BACKFILL (STREET) FBG 13.0 117.0 96 3 172 6/11/25 BACKFILL (STREET) FBG 14.0 115.6 95 3 173 6/11/25 BACKFILL (STREET) FPG N/A 140.7 95 4 174 6/11/25 BACKFILL (STREET) FPG N/A 143.1 97 4 175 6/11/25 BACKFILL (STREET) FPG N/A 144.6 98 4 176 6/11/25 BACKFILL (STREET) FPG N/A 141.5 96 4 177 6/12/25 STREET ASPHALT PAVEMENT FPG N/A 143.0 97 4 178 6/12/25 STREET ASPHALT PAVEMENT FPG N/A 142.1 96 4 179 6/17/25 STREET ASPHALT PAVEMENT FPG N/A 142.7 96 4 180 6/17/25 STREET ASPHALT PAVEMENT FPG N/A 144.0 97 4 181 6/17/25 STREET ASPHALT PAVEMENT FPG N/A 141.9 96 4 182 6/17/25 STREET ASPHALT PAVEMENT FPG N/A 140.8 95 4 183 6/17/25 STREET ASPHALT PAVEMENT FPG N/A 142.0 96 4 184 6/17/25 STREET ASPHALT PAVEMENT FPG N/A 143.7 97 4 185 6/19/25 DRIVEWAY SG FSG 7.0 118.2 95 1 186 6/19/25 SIDEWALK SG FSG 6.4 115.5 92 1 Job No. 21-13506 Figure No. IIIg Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade Job No. 21-13506 Figure No. IIIh TABLE B LABORATORY COMPACTION TEST RESULTS (ASTM D1557) Compaction Maximum Optimum Test Source of Dry Density Moisture Content E.I. Curve No. Description of Material Material (pcf) % C-1 Silty Sand (SM); Brown On-site 125.0 8.0 0 C-2 Well-Graded Gravel (GW); Brown Import 135.8 7.4 C-3 Recycled Base (CMB); Dark Grey Brown Import 122.3 11.0 C-4 ¾”-Diameter Asphalt Conc. (AC) Import 148.0 * *Asphalt Concrete is measured in wet density and do not require moisture content.