HomeMy WebLinkAbout2026-04-30; Beach Access Repairs and Upgrades Project Update (District 1); Gomez, PazTo the members of the:
ITY COUNCIL
Dat CA/ CC✓
CM _ACM ✓ocM (3) ✓
Council Memorandum
April 30, 2026
To: Honorable Mayor Blackburn and Members of the City Council
From: Paz Gomez, Deputy City Man~g ,:Rp lie Works
Via: Geoff Patnoe, City Manager GfY
Re: Beach Access Repairs and U r Project Update (District 1)
{city of
Carlsbad
Memo ID#2026022
This memorandum provides an update to a previous Council Memorandum dated April 9, 2026,
which is provided in Attachment A, on the Beach Access Repairs and Upgrades Project,
Capital Improvement Program (CIP) Project No. 3896.
Background
The Beach Access Repairs and Upgrades Project (project) includes repairs and work for improved
access, mobility and aesthetics. Project elements include:
• Widening the upper sidewalk westward, with an additional foot of supported sidewalk
over the bluffs for more space to walk
• Removing the metal beam and timber post guardrail on the east side of the sidewalk to
gain an additional foot of sidewalk space1
• Replacing existing streetlights with light fixtures on double-masts (i.e., one east and one
west), to improve street and sidewalk lighting
• Extending the lower sidewalk's eastern retaining walls a short distance to help maintain
the slope at the base of the stairways
• Replacing four sets of stairs from the upper sidewalk to the lower seawall
• Replacing the upper sidewalk platforms
The project has been under construction since late October 2025 on two of the four beach access
stairways: Hemlock Avenue and Cherry Avenue. The other two access stairways have remained
open and are part of the second phase: Maple Avenue and Sycamore Avenue, which will start in
Fall 2026. The intent is to have only two of the stairways closed at any given time.
Attachment A, which is the Council Memorandum dated April 9, 2026, provides additional
background information on the project.
1 This guardrail is not required based on the American Association of State Highway and Transportation
Officials (AASHTO) Roadside Design Guide.
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
April 30, 2026
Page 2
Discussion
The City Council adopted Resolution No. 2025-079, accepting bids and awarding a contract to
De La Fuente Construction, Inc. (contractor), on April 15, 2025. The Notice to Proceed was issued
on October 27, 2025, and the contractor started construction shortly thereafter. Construction of
the project has been phased for a period of over 20 months to minimize the associated impacts
along Carlsbad Boulevard and Tamarack State Beach during the summer season from Memorial
Day through Labor Day. The previous memorandum in Attachment A details the delay of the
Cherry Avenue stairway.
Unfortunately, the contractor confirmed that they are unable to open the Hemlock Avenue
stairway by the summer because stair stringers and handrails cannot be fabricated in time due to
procurement delays caused by its subcontractor. Until these components are fabricated and
installed, the stairway cannot be completed or made accessible. Therefore, the contractor will
focus on completing the upper sidewalk and railings between Maple Avenue and Tamarack
Avenue before Memorial Day.
The contractor will then demobilize from the construction site before Memorial Day and return
after Labor Day to immediately complete the Cherry Avenue and Hemlock Avenue beach access
stairs. Once the Cherry Avenue and Hemlock Avenue beach access stairs are opened, the
Sycamore Avenue and Maple Avenue beach access will be closed for demolition and
construction.
In summary, the status of each beach access is as follows:
• Hemlock Avenue: In construction, complete installation of the stairs and rails in Fall 2026
• Cherry Avenue: In construction, complete installation of the stairs and rails in Fall 2026
• Maple Avenue: Start construction when Cherry Avenue and Hemlock Avenue work is
completed in Fall 2026 with completion in spring 2027
• Sycamore Avenue: Start construction when Cherry Avenue and Hemlock Avenue work is
completed in early Fall 2026 with completion in spring 2027
Next Steps
Ongoing construction will continue until shortly before Memorial Day 2026. The contractor will
then demobilize until after Labor Day. The remaining work is expected to be completed in spring
2027.
Attachment: A. Council Memorandum dated April 9, 2026
cc: Sheila Cobian, Assistant City Manager
Cindie McMahon, City Attorney
Jeff Murphy, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1}
April 30, 2026
Page 3
Christie Calderwood, Police Chief
Michael Calderwood, Fire Chief
Tim Lyons, Assistant City Attorney
Dalton Sorich, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
Zach Korach, Finance Director
Kyle Lancaster, Parks & Recreation Director
Mike Strong, Community Development Director
Amy Ventetuolo, Communication & Engagement Director
Eric Lardy, Assistant Director of Community Development
Sarah Reiswig, Risk Manager
John Kim, City Traffic Engineer
Emily Hasegawa, Engineering Manager
Mariel Cairns, Acting Engineering Manager
To the members of the:
CITY COUNCIL
Date: 4/912026 CA_x_ cc_x_
CM_x_ ACM_x_ DCM (3)_x_
April 9, 2026
Council Memorandum
To:
From:
Honorable Mayor Blackburn and Members of the City Council
Paz Gomez, Deputy City Manager, Public Works
Sheila Cobian, Assistant City Managers C Via:
Re: Beach Access Repairs and Upgrades Project Update (District 1)
Attachment A
{city of
Carlsbad
Memo ID#2026015
This memorandum provides an update to a previous Council Memorandum dated February 8, 2024,
which is provided in Attachment A, on the Beach Access Repairs and Upgrades Project, Capital
Improvement Program (CIP) Project No. 3896.
Background
The Beach Access Repairs and Upgrades Project includes repairs and work for improved access,
mobility and aesthetics. Project elements include:
• Widening the upper sidewalk westward, with an additional foot of supported sidewalk
over the bluffs for more space to walk
• Removing the metal beam and timber post guardrail on the east side of the sidewalk to
gain an additional foot of sidewalk space1
• Replacing existing streetlights with light fixtures on double-masts (i.e., one east and one
west), to improve street and sidewalk lighting
• Extending the lower sidewalk's eastern retaining walls a short distance to help maintain
the slope at the base of the stairways
• Replacing four sets of stairs from the upper sidewalk to the lower seawall
• Replacing the upper sidewalk platforms
Discussion
The City Council adopted Resolution No. 2025-079, accepting bids and awarding a contract to De
La Fuente Construction, Inc. (contractor), on April 15, 2025. The notice to proceed was issued on
October 27, 2025, and the contractor started construction shortly thereafter. Construction of the
project has been phased for a period of over 20 months to minimize the associated impacts
along Carlsbad Boulevard and Tamarack State Beach during the summer season from Memorial
Day through Labor Day.
1 This guardrail is not required based on the American Association of State Highway and Transportation
Officials (AASHTO) Roadside Design Guide.
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
April 9, 2026
Page 2
During demolition of the Cherry Avenue upper foundation and platform supports, the contractor
discovered unforeseen field conditions that required the Engineer of Record to redesign the
upper foundation wall and reinforce the platform supports. Due to the sequence of construction,
reinforcement of the platform supports will not be ready in time for the stairs and rails to be
installed before the summer moratorium. Therefore, the contractor will focus on completing the
Hemlock Avenue beach access stairs and the upper sidewalk and railings between Maple Avenue
and Tamarack Avenue before Memorial Day.
The contractor will then demobilize from the construction site before Memorial Day and return
after Labor Day to immediately complete the Cherry Avenue beach access stairs and start
demolition on the Maple Avenue location. Once the Cherry Avenue beach access is opened, the
Sycamore Avenue beach access will be closed for demolition and construction.
In summary, the status of each beach access is as follows:
• Hemlock Avenue: in construction, completion scheduled for May 2026
• Cherry Avenue: in construction, complete installation of the stairs and rails in Fall 2026
• Maple Avenue: start construction in Fall 2026 with completion in early 2027
• Sycamore Avenue: start construction when Cherry Avenue is completed in early Fall 2026
with completion in early 2027
Next Steps
Ongoing construction will continue until shortly before Memorial Day 2026. The contractor will then
demobilize until after Labor Day. The remaining work is expected to be completed in early 2027.
Attachment: A. Council Memorandum dated February 8, 2024
cc: Geoff Patnoe, City Manager
Cindie McMahon, City Attorney
Jeff Murphy, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Christie Calderwood, Police Chief
Michael Calderwood, Fire Chief
Tim Lyons, Assistant City Attorney
Dalton Sorich, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
Zach Korach, Finance Director
Kyle Lancaster, Parks & Recreation Director
Mike Strong, Community Development Director
Amy Ventetuolo, Communication & Engagement Director
Eric Lardy, Assistant Director of Community Development
Sarah Reiswig, Risk Manager
John Kim, City Traffic Engineer
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
April 9, 2026
Page 3
Todd Reese, Parks Services Manager
Emily Hasegawa, Engineering Manager
Mariel Cairns, Acting Engineering Manager
To the members of the:
CITY COUNCIL
oa:~~ \~~ CA✓ cc✓
CM ACM LocM {3~/
Council Memorandum
February 8, 2024
To:
From:
Honorable Mayor Blackburn and Members of the City Council
Paz Gomez, Deputy City Manager, Publi~orks
Via: Geoff Patnoe, Assistant City Manager ~
Re: Beach Access Repairs and Upgrades Project Update (District 1)
Attachment A
{city of
Carlsbad
Memo ID# 2024010
This memorandum provides an update on the Beach Access Repairs and Upgrades Project,
Capital Improvement Program (CIP) Project No. 3896.
Background
The city is working on a project to make necessary repairs and upgrades to the stairs and
walkway on the west side of Carlsbad Boulevard between Pine Avenue and approximately
30 feet north of Tamarack Avenue. The project includes structural repairs and improvements to
the concrete sidewalks, retaining walls and beach access stairways located along Carlsbad
Boulevard. These existing features would be replaced with similar materials and designs except
for the walkway, which would be widened to better accommodate the large number of walkers,
runners, joggers and other users.
The sidewalks and stairways were built in the 1980s. The sidewalk between Pine Avenue and
Maple Avenue is elevated and cantilevered over the bluff. There are four stairways to the lower
sea wall within the project area. Repairs are needed due to deterioration of the sidewalk
structure, exposed and rusted steel reinforcements, cracked and broken concrete, and rusting of
stairway components.
Discussion
The repair project was originally considered a maintenance project, but the scope has expanded
into an improvement project to address the current engineering standards and building code
requirements and to account for increased demand for beach access.
Overall, the repairs and additional work for improved access, mobility and aesthetics include:
• Widening the upper sidewalk westward, with a further foot of cantilever over the bluffs
for more space to walk
• Removing the metal beam and timber post guardrail on the east side of the sidewalk to
gain a foot of additional sidewalk space (this guardrail is not required based on the
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
February 8, 2024
Page 2
American Association of State Highway and Transportation Officials (AASHTO) Roadside
Design Guide -see below)
• Replacing existing streetlights with light fixtures on double-masts (i.e., one east and one
west), to improve street and sidewalk lighting
• Extending the lower sidewalk's eastern retaining walls a short distance to help maintain
the slope at the base of the stairways
• Replacing four sets of stairs from the upper sidewalk to the lower seawall
• Replacing the upper sidewalk platforms
Safety along Carlsbad Boulevard
As the city implements the policies in the General Plan Mobility Element, approved by the City
Council in 2015, safety along Carlsbad Boulevard is a top priority. In the same area as the beach
access project, the following changes have been made or are planned:
• Improved crosswalks with curb extensions to shorten the walking distance, center
medians to provide a place for pedestrians to stop, if needed, and flashing lights to alert
drivers when pedestrians are present
• Creating buffered bike lanes
• Slowing down traffic through restriping lanes and installing curb extensions
These changes work together to promote safer behavior among all road users.
Guardrail considerations
While it may seem counterintuitive to remove a guardrail in an area where we are making safety
improvements, there are several reasons why this design is preferred:
• The AASHTO Roadside Design Guide, which is used by transportation planners to
determine recommended street designs and features based on several factors, including
location, traffic, speeds and visibility, does not require a guardrail
• The existing guardrail was installed in the 1980s when Carlsbad Boulevard served as
Pacific Coast Highway with high speeds, prior to construction of Interstate 5
• Removing the guardrail will provide another foot of space to the walkway, which is one of
the most heavily used walkways in the region
• Removing the guardrail will make this segment of Carlsbad Boulevard consistent with
other similar segments