HomeMy WebLinkAbout2026-07-06; Traffic Safety and Mobility Commission; 01; Semiannual Transportation ReportMeeting Date: July 6, 2026 To: Traffic Safety & Mobility Commission From: Tom Frank, Transportation Director/City Engineer Staff Contact: Tom Frank, Transportation Director/City Engineer tom.frank@carlsbadca.gov, 442-339-2766 Subject: District Recommended Action Receive the Semiannual Transportation Report. Executive Summary In 2018, the City Council asked staff to present updates twice a year on coordinated policies, programs and projects that improve different ways people move around the city, whether by walking, biking, rolling, taking transit or driving. This report provides an update on the progress of these efforts over the last six months, Jan. 1, 2026, through June 30, 2026, and goals for the next six months. Staff have advanced several high-priority initiatives and projects to improve mobility conditions focusing on safety, cost-effectiveness and improving parking availability. Staff are making progress on approximately 60 projects in the five-year Capital Improvement Program, or CIP, that are in various stages of completion from early feasibility studies and planning to finishing up construction. Explanation & Analysis The Transportation Department manages the city’s roadways and drainage systems that keep streets, bike lanes and sidewalks usable in all weather, including rainstorms. The city’s Capital Improvement Program includes over 100 street and drainage projects, ranging from coordinating traffic signal timing and slowing down traffic in neighborhoods to redesigning streets to meet modern standards outlined in the Mobility Element in the city’s General Plan, the section focused on transportation. The following is an update on initiatives that address mobility, how people travel within the city, and how the city manages its roadways and drainage assets. TRAFFIC SAFETY & MOBILITY COMMISSION July 6, 2026 Item #1 Page 1 of 19 Transportation Department Initiatives Past six months (January to June 2026): •Addressed an emergency repair on El Camino Real and Carlsbad Village Drive •Addressed an emergency repair on the storm drain west of Carlsbad Boulevard and north of Solamar Drive •Completed construction of the El Camino Real Widening from Sunny Creek Road to Jackspar Drive •Presented the city’s Traffic Management Program for City Council adoption, formerly named the Carlsbad Residential Traffic Management Program, which was initially adopted in 2001 and updated in 2011 •Completed the traffic calming effort process for Celinda Drive •Began the traffic calming effort for Anillo Way, La Gran Via and Madrilena Way •Prepared and submitted several annual reports to various transportation agencies including the San Diego Association of Governments, or SANDAG, California Department of Transportation, or Caltrans, and California Transportation Commission to secure funding for transportation projects •Continued to update GIS asset inventory data associated with transportation, drainage, facilities, and parks and recreation assets •Completed annual monitoring and surveying for 13 Carlsbad employers that are required to comply with the city’s Transportation Demand Management ordinance, which is intended to reduce the number of single-occupant vehicle trips by businesses in Carlsbad •Received City Council approval of the Fiscal Year 2026-27 Traffic Safety and Mobility Commission Work Plan •Advanced the Drainage Master Plan Update and presented to the Planning Commission •Continued to provide drainage engineering and flood control support to the Land Development Engineering Division in the Community Development Department and •Continue required reporting to secure transportation project funding from a variety of transportation agencies including SANDAG, Caltrans, California Transportation Commission and federal agencies •Continue to provide updates to the city’s GIS inventory data associated with transportation, drainage, facilities, and parks and recreation assets •Reach out to Carlsbad area school districts to identify additional schools for FY 2026-27 Safe Routes to School Plans •Finalize the annual Growth Management Plan Circulation Section Report •Begin updates to the city’s Transportation Impact Analysis Guidelines •Continue evaluating the city’s Sustainable Mobility Plan, intended to support all forms of transportation while meeting the city’s climate action goals, a study on a transportation impact fee and possibly a vehicle miles traveled mitigation program •Prepare a nexus fee study and continue finalizing the Drainage Master Plan Update July 6, 2026 Item #1 Page 2 of 19 Updates on projects that improve ways that people move through the city: Consistent with the City Council’s Strategic Plan, the city’s CIP includes a more focused list of high-priority transportation and drainage projects. The following table highlights the progress of CIP projects that focus on improving the safety and convenience of all road users. Additional project information is included in the Transportation Department CIP Project Status Update as of June 30, 2026, provided in Exhibit 1. TRANSPORTATION IMPROVEMENT PROJECTS Project Name Past six months (January to June 2026) Next six months (July to December 2026) Project replace damaged sidewalks, curb and gutters and install Americans with Disabilities Act, or ADA, compliant Improvements ramps consistent with the city’s ADA bid and award contract Preventative Palomar Airport Road bridge railing bid and award contract Improvements bid and award contract Coastal Rail Trail and Pedestrian Improvements initiate construction Improvements Project, additional parking on Chestnut Avenue east of convert parking from parallel to perpendicular bid and award contract to review parking Council July 6, 2026 Item #1 Page 3 of 19 TRANSPORTATION IMPROVEMENT PROJECTS Project Name Past six months (January to June 2026) Next six months (July to December 2026) Avenue and Palm and Upgrades from Pine Avenue to Tamarack Avenue Labor Day and Tamarack Avenue Intersection Improvements initiated permitting permitting, prepare to bid and award contract Safety Improvements high-visibility crosswalks and speed permitting as required for Widening from Arenal Road to La obtaining permitting to bid and award contract Widening from Poinsettia Lane to Camino Vida Roble Widening from Sunny Creek Road to Jackspar Drive including new northbound travel lane, bike lane and sidewalk Improvements Veterans Memorial Park Project Parking convert parallel to diagonal parking bid and award contract Safe Routes to School plans for Tamarack Avenue with the initiate construction July 6, 2026 Item #1 Page 4 of 19 TRANSPORTATION IMPROVEMENT PROJECTS Project Name Past six months (January to June 2026) Next six months (July to December 2026) Jefferson Elementary School Safe Routes to School Plan safety and traffic calming improvements with Carlsbad Traffic permitting Drive Complete Street Improvements Kelly Elementary School and neighborhood communities School Plan identifying long- term street and mobility pedestrian and bike improvements, south of Palomar Airport eligibility for state grant funding School Safe Routes to School Plan on College Boulevard and Bobcat Boulevard with the Sidewalk Improvement Project. Initiated Improvements: Multi-use trail on College Boulevard between Bobcat Boulevard and Carlsbad Village Drive and Alga Road sidewalk east of El Coastal Improvements community input on street segments, received City Council Improvements at Maverick Way and Camino De Los bid and award contract Improvements permitting July 6, 2026 Item #1 Page 5 of 19 TRANSPORTATION IMPROVEMENT PROJECTS Project Name Past six months (January to June 2026) Next six months (July to December 2026) Project on State, Madison, Roosevelt and Washington bid and award contract DRAINAGE IMPROVEMENT PROJECTS Project Name Past six months (January to June 2026) Next six months (July to December 2026) Condition storm drains to identify locations in storm drain repair project improvements project environmental studies and contract documents to advertise for bids to construct replacement and repair systems throughout the city for replacement and/or repair based on previously completed drainage design Drainage design phase design and permitting for maintenance of the concrete-lined section of the Drainage environmental studies permitting Trash Capture Best Management engineering design, environmental and geotechnical studies studies, geotechnical and engineering design The city optimizes maintenance efforts on its transportation and drainage assets to preserve the systems and infrastructure that allow for safe and comfortable travel for all users. Ongoing Maintenance and Operations of Roadways and Drainage Systems • Logged nearly 17,000 individual inspection service requests of city street and storm July 6, 2026 Item #1 Page 6 of 19 •Removed and replaced approximately 60,000 square feet of asphalt and concrete on streets and sidewalks •Repaired about 800 street signs that were knocked down or faded and refreshed 520 street paint lines and legends •Replaced approximately 550 induction streetlights with efficient light-emitting diode, or LED, light fixtures •Completed over 5,500 utility mark-outs to locate underground utilities •Continued with concrete sidewalk slicing repairs •Worked with Caltrans to expand coordination hours between signals adjacent to the Interstate Highway 5 and Poinsettia Lane ramp signals and the Interstate Highway 5 and Palomar Airport Road ramp signals •Added midday traffic signal coordination timing on El Camino Real and Palomar Airport Road •Continued equipment upgrades at various traffic signals to replace old infrastructure and improve vehicle and bicycle detection •Continued audible pedestrian systems installations at several traffic signals to make them more ADA-accessible •Continued to evaluate data to better understand transportation patterns on city streets •Continued routine high-priority storm drain inspections and cleanings •Cleaned La Costa Avenue box culvert •Conducted inspections and cleaning of concrete-lined portions of Kelly Channel •Performed annual vegetation clearing and trash removal for the Buena Vista Creek Channel Maintenance District and coordinated with the California Department of Fish and Wildlife •Performed channel maintenance in the Agua Hedionda Creek between the bridges of Cannon Road and El Camino Real and coordinated with the California Department of Fish and Wildlife •Performed inspections to assess the drainage system at Gabbiano Lane outfall Next six months (July to December 2026): •Perform regular channel maintenance for the Buena Vista Creek Channel Maintenance District in coordination with the California Department of Fish and Wildlife •Perform regular channel maintenance in the Agua Hedionda Creek between El Camino Real and Cannon Road in coordination with the California Department of Fish and Wildlife •Continue to coordinate with the City of Oceanside and regulatory agencies to advance a long-term maintenance strategy for the Buena Vista Creek Channel Maintenance Project •Perform regular maintenance at the Gabbiano outfall, Tamarack Channel and Kelly Channel •Survey and repair sidewalks in high-pedestrian traffic areas such as the Village, along July 6, 2026 Item #1 Page 7 of 19 Fiscal Analysis This item is a presentation on the work related to management of the city’s transportation and drainage assets, and it has no fiscal impact. Next Steps The next semiannual transportation report will be presented in January 2027. Environmental Evaluation The proposed action is not a “project” as defined by the California Environmental Quality Act, or CEQA, Section 21065 and CEQA Guidelines Section 15378(b)(5) and does not require environment review under CEQA Guidelines Section 15060(c)(3) and 15061(b)(3), because the proposed action to receive the Transportation Semiannual Report is an organizational or administrative government activity that does not involve any commitment to any specific project which may result in a potentially significant physical impact on the environment. Any subsequent action or direction stemming from the proposed action may require preparation of an environmental document in accordance with CEQA or the CEQA Guidelines. Exhibit 1.Transportation Department Capital Improvement Program project status update as of June 30, 2026 July 6, 2026 Item #1 Page 8 of 19 Exhibit 1 Transportation Department Capital Improvement Program (CIP) Project Status Update as of June 30, 2026 The Transportation Department implements improvement projects and critical major maintenance for roadway and drainage infrastructure as part of the City of Carlsbad’s Capital Improvement Program (CIP). This update highlights the status of several high priority and critical need transportation and drainage projects. Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule 2025 Concrete Repair Project, Concrete Repair and Replacement Program, 6013: Concrete repairs to damaged sidewalks, curb and gutter, driveway aprons and cross gutters in need of repair at multiple locations citywide. Construction Construction to be completed fall 2026 2026 ADA Improvements Project, ADA Ramp Improvement Program, 6049 To advance the city’s ADA Implementation Plan, this project includes approximately 200 locations citywide for pedestrian ramp improvements. Design Bid fall 2026, award construction contract spring 2027 2026 Bridge Maintenance Project, Bridge Preventative Maintenance Program, 6066 This program performs preventative maintenance activities such as deck sealing, concrete patching and repairing spalls to increase the life of the bridge structures. This project includes repairs for three bridges located on Cannon Road (Macario Canyon Bridges), Rancho Santa Fe Road (San Marcos Creek Bridges) and the Palomar Airport Road Overcrossing spanning Interstate Highway-5 (I-5). Design and Permitting Bid late 2026, award construction contract spring 2027 2026 Parking Lot Improvements Project, Parking Lot Maintenance Program, 6052 This program plans for maintenance of the city’s parking lots and driveways to provide access to city parks, fire stations, libraries and facilities. Design Bid fall 2026, award construction contract early 2027 July 6, 2026 Item #1 Page 9 of 19 2 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule 2026 Sidewalk Improvements Project, Sidewalk/Street Construction Program, 6002 This is an ongoing program designed to complete sidewalk improvements throughout the city. Design and Permitting Bid fall 2026, award construction contract spring 2027 2026 Street Resurfacing Project, Pavement Management Program, 6001 This ongoing annual program is designed to extend the service life of city streets and maintain a smooth and safe driving surface for vehicles. The city utilizes a pavement management database to determine pavement management needs for the purpose of establishing which streets are to be slurry sealed, overlaid or reconstructed. On a periodic basis, the conditions of the roads are field surveyed, and the pavement management database is updated to reflect current conditions. Each year, specific pavement management projects are defined, funding is programmed and a CIP pavement project is budgeted. Design includes approximately 50 centerline miles of resurfacing Bid summer 2026, award construction contract fall 2026 with construction through first half of 2027 ADA Beach Access – Pine Avenue to Tamarack Avenue Project, 6065 This project will construct two ADA accessible ramps from street level on Carlsbad Boulevard, down to the beach near Pine Avenue and at Tamarack Avenue. Design and Permitting Bid early 2028, award construction contract mid-2028 Avenida Encinas Coastal Rail Trail and Pedestrian Improvements Project, 6004 This project will be completed in three phases or segments and provide multimodal improvements including new bike lanes, sidewalks and traffic calming features. Segments 1 and 2 are complete, and Segment 3 is located between Palomar Airport Road and Poinsettia Coaster Station. Design of Segment 3 Bid summer 2026, award construction contract fall 2026 July 6, 2026 Item #1 Page 10 of 19 3 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule Barrio Lighting Project, 4013 This project has two phases as part of the Village and Barrio Master Plan which recommends pedestrian scale lighting. Phase 1 is complete, and Phase 2 will install approximately 122 pedestrian lights in the Barrio area. Construction Target completion summer 2026 Barrio Parking Improvements, 6119 This project was approved by the City Council on Dec. 9, 2025, to implement new parking opportunities in the Barrio neighborhood. The first project is the final design of perpendicular parking spaces on Chestnut Avenue east of Madison Street. A study is also being finalized to evaluate parking opportunities on Palm Avenue, Pine Avenue and Madison Street, with results to be provided to the City Council in summer 2026. Design Bid fall 2026, award construction contract early 2027 Barrio Traffic Calming, 4015 This project includes traffic calming improvements such as additional stop signs, a raised crosswalk, high-visibility crosswalks at selected locations and a traffic circle at Pine Avenue and Harding Street, which will include public art at a future date; water and sewer utilities improvements are also included in this project. Construction Target completion spring 2027 Beach Access Repairs and Upgrades from Pine Avenue to Tamarack Avenue Project, 3896 This project will repair sidewalks, handrails, stairways, retaining walls and seawall along Carlsbad Boulevard. Construction began Oct 2025, paused for summer 2026 Restart construction after Labor Day 2026, target completion late spring 2027 Carlsbad Boulevard and Tamarack Avenue Intersection Improvements Project, 6058 This project will provide sidewalk, pedestrian ramp and crosswalk improvements to improve ADA access. The City Council approved a smaller scale project with limited improvements on April 29, 2025. Design and Permitting with the California Coastal Commission, State Parks and North County Transit District Bid early 2027, award construction contract spring 2027 July 6, 2026 Item #1 Page 11 of 19 4 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule Carlsbad Traffic Safety Improvements Project, 6116 The project will improve roadway and pedestrian safety by installing speed cushions near Jefferson Elementary School and upgrading existing crosswalks with high-visibility markings in school zones throughout the city. Conceptual Design Bid fall 2027, award construction contract spring 2028 College Boulevard Multi-Use Path and Alga Road Sidewalk Project, Sidewalk Improvements Project, 6002 This project includes a new Class I multiuse path along the east side of College Boulevard from Peninsula Dr. to Bobcat, which is part of Sage Creek High School Safe Routes to School Plan. Another sidewalk segment is included on Alga Road from El Camino Real east to Estrella del Mar Road. Design and Permitting Bid fall 2027, award construction contract spring 2028 College Boulevard - Reach A Extension, 3636 This project is a new segment of College Boulevard from Sunny Creek Road to Cannon Road, included in the City’s General Plan and Growth Management Plan, which was paused per City Council direction on June 7, 2022, and reactivated with the fiscal year 2026-27 budget approval on June 16, 2026. Funding for preliminary engineering studies and cost estimates included in the fiscal year 2026- 27 CIP budget Resume preliminary engineering and financing study summer 2026 El Camino Real Widening from Arenal Road to La Costa Avenue Project, 6051 This project will widen southbound El Camino Real from Arenal Road to La Costa Avenue to arterial standards, add sidewalk and widen bridge. It also involves utility relocations, right-of-way acquisitions, environmental mitigation and open space boundary adjustments. Design is complete. Permitting and right-of-way acquisitions Bid late 2026, award construction contract early 2027 July 6, 2026 Item #1 Page 12 of 19 5 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule El Camino Real Widening from Poinsettia Lane to Camino Vida Roble Project, 6072 This project will widen El Camino Real to city standards, provide an additional northbound through lane from Cinnabar Way to Camino Vida Roble to increase capacity and add new sidewalks, street lights, and medians. Construction Target completion spring 2027 El Camino Real Widening from Sunny Creek Road to Jackspar Drive Project, 6094 This project will widen El Camino Real to city standards and provide an additional northbound through lane to increase capacity and add new sidewalks. Roadway opened to traffic late May 2026 Construction closeout activities Faraday Avenue Improvements Project, 6099 This project includes roadway, driveway access and striping improvements associated with Veterans Memorial Park Project. Construction Target completion summer 2028 Grand Avenue Parking Improvements, 6079 The project proposes to convert parallel parking spaces into diagonal parking spaces and reduce westbound Grand Ave. between the Tyler St. Alley and Jefferson St. from two lanes to one lane. The project proposes to restripe existing parking spaces to gain 14 new parking spaces. Design and Permitting Bid fall 2026, award construction contract early 2027 Hope Elementary Safe Routes to School Combined roadway improvement plans for Tamarack Avenue with the 2026 Resurfacing Project. Design See 2026 Resurfacing Project, 6001 Jefferson Elementary Safe Routes to School Combined the proposed pedestrian safety and traffic calming improvements with Carlsbad Traffic Safety Improvements Project. Design See Carlsbad Traffic Safety Improvements Project, 6116 July 6, 2026 Item #1 Page 13 of 19 6 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule Kelly Drive and Park Drive Complete Street Improvements Project, 6075 This project will improve traffic safety, pedestrian access and connectivity for cyclists along Kelly Drive and Park Drive. On Dec. 9, 2025, the City Council selected the option to develop a Safe Routes to School, or SRTS, Plan for Kelly Elementary School to identify near-term and long-term improvements. Planning and Conceptual Design Present near-term and long-term improvements to Traffic Safety & Mobility Commission (TS&MC) and City Council approval early 2027 Paseo Del Norte Pedestrian and Bike Improvements Project, 6115 This project will enhance pedestrian and bike safety on Paseo Del Norte between Palomar Airport Road and Sea Gate Road with a potential pedestrian signal in the vicinity of Tip Top and Motel 6. This project was identified in the city’s Local Roadway Safety Plan as one of the priority safety improvement projects. Conceptual Design Pending Caltrans approval of project scope change request Sage Creek High School Safe Routes to School Plan Combined the proposed Class I trail on College Boulevard and Bobcat Boulevard with the Sidewalk Improvement Project. Design See College Boulevard Multi- use Path, 6002 Terramar Area Coastal Improvement Project, 6054 This project scope was revised by the City Council in October 2025 and refined in June 2026 based on community input, to include resurfacing and restriping on Carlsbad Boulevard in the Terramar area and on Cannon Road from Carlsbad Boulevard east to the railroad tracks. Conceptual Design Final design will be included with the 2027 Resurfacing Project Traffic Calming Unicornio Street, Residential Traffic Improvement Program, 6070 A traffic calming plan consisting of two speed cushions on Unicornio Street met the community support threshold and was supported by the TS&MC at its Oct. 6, 2025, meeting. The final traffic calming plan was supported by the TS&MC at its April 6, 2026, meeting. City Council adopted a resolution approving the traffic calming plan for implementation at its June 23, 2026, meeting. Final Design Solicit bids summer 2026, award construction contract fall 2026 July 6, 2026 Item #1 Page 14 of 19 7 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule Traffic Calming, Residential Traffic Improvement Program, 6070 This program implements improvements based on an evaluation process to determine whether a roadway is eligible for traffic calming measures. The 2026 program update was adopted by the City Council at its April 14, 2026, meeting and is renamed the Traffic Management Program. Celinda Drive: Staff completed Phase II for Celinda Drive with a neighborhood meeting conducted on Nov. 12, 2025, to present a traffic calming concept plan and to receive feedback from the community. Results from a mail survey to gauge community support for the proposed traffic calming plan for Celinda Drive did not meet the required threshold to proceed. This proposed project is not moving forward. Anillo Way, La Gran Via and Madrilena Way: A neighborhood meeting was conducted on June 3, 2026, to present a traffic calming concept plan and to receive feedback from the community. Planning and Conceptual Design Celinda Dr: No further action at this time Anillo Way/La Gran Via/ Madrilena Way: Present the final design to TS&MC late summer 2026 then City Council fall 2026 Traffic Signal Improvements at Maverick Way and Camino de los Coches Project, 6332 This project will upgrade traffic signal control hardware and detection, relocate signal poles and align left turn signal heads and replace pedestrian ramps to meet American with Disabilities Act standards. Design Bid late 2026, award construction contract early 2027 Tyler Street Sidewalk Improvements Project, 6103 This project reflects a revised scope of work that includes sidewalk and driveway aprons on the east side of Taylor Street from Oak Avenue to Chestnut Avenue. Design and Permitting Bid summer 2027, award construction contract fall 2027 July 6, 2026 Item #1 Page 15 of 19 8 Transportation Projects Project Name, Description, CIP Project No. Status Target Schedule Valley Street and Magnolia Avenue Sidewalk and Street Improvement Project, 6019 This project will construct sidewalks, bike facilities, green paint street features and road widening along a portion of Valley Street and Magnolia Avenue. Utility undergrounding and pole removals were completed by San Diego Gas & Electric (SDGE) in spring 2026. Construction is planned for summer 2028. Design Bid late 2027, award construction contract early 2028 Village Lighting Project, 4016 This project will provide decorative pedestrian lighting on State, Madison, Roosevelt, and Washington Streets, and replace tree twinkle lighting on a portion of State Street. This project is the first of several planned lighting projects in the Village. Design Bid summer 2026, award construction contract early 2027 Drainage Projects Project Name, Description, CIP Project No. Status Target Schedule 2026 Storm Drain Improvements, Storm Drain Repair and Rehab Program, 6607 Replace or repair damaged storm drain infrastructure at various locations throughout the city to proactively eliminate pipeline and channel failures. Design Bid fall 2026, award of construction contract spring 2027 2027 Storm Drain Improvements, Storm Drain Repair and Rehab Program, 6607 Replace or repair damaged storm drain infrastructure at various locations throughout the city to proactively eliminate pipeline and channel failures. Permitting Bid spring 2027, award of construction contract summer 2027 2027 Surface Drainage Improvements Project Phase 1, 6608 This project includes improvements to surface drainage conditions on several streets within the northwest quadrant area of the city, including installation of concrete curbs, gutters, swales and gravel to reduce erosion and improve drainage. Design Bid spring 2027, award construction contract summer 2027 July 6, 2026 Item #1 Page 16 of 19 9 Project Name, Description, CIP Project No. Status Target Schedule Agua Hedionda Creek Vegetation Maintenance Project, 6629 Project includes vegetation clearing and removal within the section of the Agua Hedionda Creek confined by the bridges of El Camino Real and Cannon Road. This maintenance improves flood capacity of the stream, thereby improving flood protection. The permitting agency confirmed in fiscal year 2020-21 that the creek can be cleared multiple times per year. Channel maintenance was performed in October 2025 and January/February 2026. Permitting In fiscal year 2026-27, this will be funded from the maintenance and operations budget Perform up to three clearings between Sept 2026 and Feb 2027 Submit notifications and reports to the California Department of Fish and Wildlife (CDFW) mid-2026 and early 2027 Buena Vista Creek Channel Maintenance Project, 6619 This project includes long-term channel maintenance of Buena Vista Creek between the bridges of South Vista Way and Haymar Drive with continued collaboration with the City of Oceanside for portions of channel within its jurisdiction. The CIP includes coordinating with jurisdictional agencies to determine the scope, environmental permitting and habitat mitigation requirements for long-term channel maintenance of the earthen section. Maintenance of the concrete portion of the channel will be funded by the maintenance and operations budget. Permitting with CDFW, Regional Water Quality Control Board and the U.S. Army Corps of Engineers Develop a white paper on partnering with the City of Oceanside for the earthen section of the channel, pending initial discussions, targeted late 2026 Drainage Master Plan Project BCB – Magnolia Avenue Drainage Improvements Project, Citywide Drainage Improvement Program, 6608 Phase I was completed in mid-2022 on Magnolia Avenue which installed a 30-inch diameter storm drain pipeline on Magnolia Avenue from Brady Circle to Monroe Street. Split into two separate construction phases during the summer months due to the proximity of nearby schools, Phase II will provide a storm drain lateral on Valley Street, planned for summer 2027. Design Bid fall 2026, award construction contract spring 2027 Construction summer 2027 during school break and complete before start of 2027 school year July 6, 2026 Item #1 Page 17 of 19 10 Project Name, Description, CIP Project No. Status Target Schedule Drainage Master Plan Update, 6623 This effort provides updates to the city’s 2008 Drainage Master Plan, including updating the list of master planned projects, creating an updated drainage impact fee schedule and amending existing Programmatic Environmental Impact Report document. Nexus fee study Sept 2026 to the City Council to amend agreement to conduct nexus fee study and complete DMP update Drainage Master Plan Project BFB-Upper Project, 6622 This project includes drainage improvements and slope stabilization to a city-owned earthen drainage channel on the east side of El Camino Real from Chestnut Avenue to Tamarack Avenue. The objective of the project is to restore the channel by stabilizing slopes to mitigate against erosion during storm events and help reduce sediment transport to the Agua Hedionda Lagoon. Design and Permitting Bid spring 2028, award construction contract summer 2028 Highland Ave. and Hoover Street Storm Drain Improvements, 6607 This project includes extension of a storm drain system from Highland Avenue to Hoover Street. Design Combined with CIP 5025 Adams-Cove water main replacement, bid late 2026 Kelly Drive Channel Repair, 6606 This project will address a long-term repair for the length of Kelly Channel. Scoping Initiate conceptual design 2027 Merwin Drive Storm Drain Improvements Project, 6608 This project will improve surface drainage conditions and reduce the potential for ponding on Merwin Drive during and following storm events. Review of design included analysis of alternate alignments that could result in reduced construction costs. Design and Permitting Bid spring 2027, award construction contract fall 2027 July 6, 2026 Item #1 Page 18 of 19 11 Project Name, Description, CIP Project No. Status Target Schedule State Street Regional Trash Capture Amendment Compliance Program, 6626 This program is to design and construct Trash Capture Best Management Practices (TCBMPs) to improve storm water quality, achieve compliance with watershed permit and reduce maintenance costs. Two planned locations for TCBMPs are State Street and Agua Hedionda. State Street: Design and Permitting State Street: Bid late 2026, award construction contract spring 2027 Agua Hedionda: Initiate design late 2026 July 6, 2026 Item #1 Page 19 of 19