HomeMy WebLinkAboutAV 03-01; Mier Residence; Administrative Variance (AV) (5)- 4-.
City of - Carlsbad - D-0,
February 3,2003
Monica Mier
P. 0. Box 2923
Lake Arrowhead, CA 92352
SUBJECT: AV 03-01 - Mier's Residence
Thank you for applying for Land Use Permits in the City of Carlsbad. The Planning Department
has reviewed your Administrative Variance, application no. AV 03-01, as to its completeness for
processing.
The application is incomplete, as submitted. Attached are two lists. The first list is information
which must be submitted to complete your application. This list of items must be submitted
directly to your staff planner by appointment. All list items must be submitted
simultaneously and a copy of this list must be included with your submittals, including
five (5) sets of plans. No processing of your application can occur until the application is
determined to be complete. The second list is issues of concern to staff. When all required
materials are submitted the City has 30 days to make a determination of completeness. If the
application is determined to be complete, processing for a decision on the application will be
initiated. In addition, please note that you have six months from the date the application was
initially filed, January 3, 2003, to either resubmit the application or submit the required
information. Failure to resubmit the application or to submit the materials necessary to
determine your application complete shall be deemed to constitute withdrawal of the application.
If an application is withdrawn or deemed withdrawn, a new application must be submitted.
Since re I y ,
Planning Director
MJH:BK:sn
C: Don Neu, Team Leader
David Rick, Project Engineer
File Copy
Data Entry
Planning Aide
@ 1635 Faraday Avenue Carlsbad, CA 92008-7314 (760) 602-4600 FAX (760) 602-8559 www.ci.carlsbad.ca.us
4
LIST OF ITEMS NEEDED
TO COMPLETE THE APPLICATION
No. AV 03-01 - Mier’s Residence
Planning:
1. Plot the location of structures on the adjacent properties and include dimensions
showing the setbacks to the common property lines.
2. Please submit two copies of the Preliminary Title ReRort (current within the last six
(6) months.
3. Please indicate the percentage of building coverage on the site plan.
4. Please include a floor plan of the garage showing the minimum interior dimensions
and the square footage of the garage.
Engineering:
1. Provide a letter from a registered soils engineer authorizing the narrow side yard
setback of three feet. City Standards (GS-15) require a five-foot distance at 2%
positive drainage between the building foundation and drainage swale. Two
percent positive drainage two feet from the property line is also required. The
soils engineer shall provide recommendations to mitigate any potential impacts to
the foundation.
ISSUES OF CONCERN
Planning :
1. Although staff can recommend approval of the administrative variance as proposed,
you are encouraged to explore revising the location of the garage so that it has a
“zero” setback on one side and a 4’ setback on the opposite side. This would enable
you to provide a garage which meets the City standards for a two-car garage with a
minimum interior dimension of 20’ x 20’ clear. If you elect to explore this option, the
soils engineer report (requested in Engineering item #I) should review the project as
designed with a “zero” setback. If the “zero” setback option is selected, the project
would require approval of a Variance (which requires Planning Commission
approval) rather than an Administrative Variance.
Engineering:
1. Plot the outline of the roof overhang. Drainage shall not discharge onto the
neighbor‘s property. Roof drains may be necessary and should be shown on
the plan.