July 28, 2011
Shea Homes
c/o Sarah Beckman
9990 Mesa Rim Road
San Diego, CA 92121
RE: CDP 10-14 - POINSETTIA PLACE BORROW SITE
The City has completed a review of the application for a Minor Coastal Development Permit for
the removal of approximately 65,500 cubic yards of dirt from a 3.77 acre portion of a 20 acre R-
1 zoned property located within and adjacent to the right-of-way for the easterly extension of
Poinsettia Lane south of Cassia Road and east of Poinsettia Lane within an area previously
disturbed for agricultural purposes.
This proposed grading is part of the implementation of the Poinsettia Place development which
was approved on the adjacent property to the north. The intent of this Minor Coastal
Development Permit is to supplement the Coastal Development Permit approved for the
Poinsettia Place project (CDP 04-23A) for offsite grading and acquisition of fill material needed
to construct the easterly Poinsettia Lane extension.
It is the Planning Director's determination that the project CDP 10-14 - POINSETTIA PLACE
BORROW SITE, is consistent with the applicable City's Coastal Development Regulations
(Chapters 21.201 - 21.205); and with all other applicable City ordinances and policies. The
Planning Director, therefore, APPROVES this request based upon the following:
1. That the total cost of the proposed development is less than $60,000.
2. That the proposed development requires no other non-administrative discretionary
approvals other than a Minor Coastal Development Permit.
3. That the development is in conformity with the public access and public recreation
policies of Chapter 3 of the Coastal Act, in that the property is not located adjacent to
the shore and therefore no opportunities for coastal access are available from the
subject site, nor are public recreation areas required of the project.
4. The proposed development will have no adverse effect on coastal resources, in that no
current Williamson Act agricultural activities or significant agricultural land
designated on Map X, sensitive resources, geological instability, flood hazard or
coastal access opportunities exist onsite; and the removal of 65,500 cubic yards
of dirt will not obstruct views of the coastline as seen from public lands or public
right-of-way or otherwise damage the visual beauty of the coastal zone.
1635 Faraday Avenue, Carlsbad, CA 92008-7314 T 760-602-4600 F 760-602-8559 ®
CDP 10-14 - POINSETTIA PLACE BORROW SITE
July 28, 2011
PAGE 2
5. The project is consistent with the provisions of the Coastal Resource Protection
Overlay Zone (Chapter 21.203 of the Carlsbad Municipal Code) in that the project
will adhere to the City's Master Drainage Plan, Grading Ordinance, Storm Water
Ordinance, Standard Urban Storm Water Mitigation Plan (SUSMP), and
Jurisdictional Urban Runoff Management Program (JURMP) to avoid increased
urban runoff, pollutants, and soil erosion. No natural vegetation is located within
the subject area and it is not prone to landslides or susceptible to accelerated
erosion, floods or liquefaction. The project site includes natural slopes greater
than or equal to 25%, however pursuant to Section 21.203.040(A)(1)(a) and
21.203.040(A)(3) of the Carlsbad Municipal Code grading within these slopes may
occur in that the proposed grading is within the right-of-way for the future
construction of Poinsettia Lane which is a City of Carlsbad Circulation Element
Roadway, no structures are proposed with this application; project grading is
essential to obtaining the necessary fill material for Poinsettia Lane; the site is not
within a major wildlife habitat or native vegetation area; and the site is not located
within a wildlife corridor.
6. That the proposed development is in conformance with the Mello II Segment of the
Certified Local Coastal Program and all applicable policies in that the site is located
within and adjacent to the right-of-way of the future extension of Poinsettia Lane
and the site is designated on the Land Use Map as Residential Low-Medium
Density (RLM) for the future development of single family residential uses. The
proposal to borrow fill material from this site is consistent with the Mello II RLM
Land Use designation.
7. That the request for a minor coastal development permit was adequately noticed at least
fifteen (15) working days before the date of this decision pursuant to Section
21.201.080(8) and (C) of the Carlsbad Coastal Development Regulations.
8. The Planning Director of the City of Carlsbad does hereby find:
a. The Planning Director has reviewed, analyzed, and considered the Negative
Declaration and the environmental impacts therein identified for this project and any
comments thereon prior to ADOPTING the project; and
b. the Negative Declaration has been prepared in accordance with requirements of the
California Environmental Quality Act, the State Guidelines and the Environmental
Protection Procedures of the City of Carlsbad; and
c. it reflects the independent judgment of the Planning Director of the City of
Carlsbad; and
d. based on the EIA Part II and comments thereon, there is no substantial evidence the
project will have a significant effect on the environment.
9. The project is not located in the Coastal Agricultural Overlay Zone, according to
Map X of the Land Use Plan, certified in September 1990, and therefore, is not
subject to the provisions of the Coastal Agricultural Overlay Zone (Chapter 21.202
of the Carlsbad Municipal Code).
10. The Planning Director has reviewed each of the exactions imposed on the Developer
contained in this approval, and hereby finds, in this case, that the exactions imposed to
CDP 10-14 - POINSETTIA PLACE BORROW SITE
July 28, 2011
PAGE 3
mitigate impacts caused by or reasonably related to the project, and the extent and the
degree of the exaction is in rough proportionality to the impact caused by the project.
Conditions:
1. The Planning Director does hereby APPROVE the Minor Coastal Development Permit,
CDP 10-14, for the project entitled POINSETTIA PLACE BORROW SITE (Exhibit A),
dated July 20, 2011, on file in the Planning Division and incorporated by this reference,
subject to the conditions herein set forth.
2. If any of the following conditions fail to occur; or if they are, by their terms, to be
implemented and maintained over time, if any of such conditions fail to be so
implemented and maintained according to their terms, the City shall have the right to
revoke or modify all approvals herein granted; deny or further condition issuance of all
future building permits; deny, revoke or further condition all certificates of occupancy
issued under the authority of approvals herein granted; record a notice of violation on the
property title; institute and prosecute litigation to compel their compliance with said
conditions or seek damages for their violation. No vested rights are gained by Developer
or a successor in interest by the City's approval of this Minor Coastal Development
Permit.
3. Staff is authorized and directed to make, or require the Developer to make, all
corrections and modifications to the Minor Coastal Development Permit documents,
as necessary to make them internally consistent and in conformity with the final action
on the project. Development shall occur substantially as shown on the approved
Exhibits. Any proposed development different from this approval, shall require an
amendment to this approval.
4. The Developer shall comply with all applicable provisions of federal, state, and local laws
and regulations in effect at the time of building permit issuance.
5. If any condition for construction of any public improvements or facilities, or the payment
of any fees in-lieu thereof, imposed by this approval or imposed by law on this Project
are challenged, this approval shall be suspended as provided in Government Code
Section 66020. If any such condition is determined to be invalid this approval shall be
invalid unless the City Council determines that the project without the condition complies
with all requirements of law.
6. The Developer/Operator shall and does hereby agree to indemnify, protect, defend and
hold harmless the City of Carlsbad, its Council members, officers, employees, agents,
and representatives, from and against any and all liabilities, losses, damages, demands,
claims and costs, including court costs and attorney's fees incurred by the City arising,
directly or indirectly, from (a) City's approval and issuance of this Minor Coastal
Development Permit, (b) City's approval or issuance of any permit or action, whether
discretionary or non-discretionary, in connection with the use contemplated herein, and
(c) Developer/Operator's installation and operation of the facility permitted hereby.
7. This approval shall become null and void if a grading permit is not issued for this project
within 24 months from the date of project approval.
8. Developer shall pay the citywide Public Facilities Fee imposed by City Council Policy
#17, the License Tax on new construction imposed by Carlsbad Municipal Code Section
CDP 10-14 - POINSETTIA PLACE BORROW SITE
July 28, 2011
PAGE 4
5.09.030, and CFD #1 special tax (if applicable), subject to any credits authorized by
Carlsbad Municipal Code Section 5.09.040. Developer shall also pay any applicable
Local Facilities Management Plan fee for Zone 21, pursuant to Chapter 21.90. All such
taxes/fees shall be paid at issuance of building permit. If the taxes/fees are not paid, this
approval will not be consistent with the General Plan and shall become void.
9. Prior to the issuance of a grading permit, Developer shall submit to the City a Notice of
Restriction to be filed in the office of the County Recorder, subject to the satisfaction of
the Planning Director, notifying all interested parties and successors in interest that the
City of Carlsbad has issued a Minor Coastal Development Permit on the property.
Said Notice of Restriction shall note the property description, location of the file
containing complete project details and all conditions of approval as well as any
conditions or restrictions specified for inclusion in the Notice of Restriction. The Planning
Director has the authority to execute and record an amendment to the notice which
modifies or terminates said notice upon a showing of good cause by the Developer or
successor in interest.
10. Approval of this request shall not excuse compliance with all applicable sections of the
Zoning Ordinance and all other applicable City ordinances in effect at time of building
permit issuance, except as otherwise specifically provided herein.
11. Prior to hauling dirt or construction materials to or from any proposed construction site
within this project, Developer shall apply for and obtain approval from, the City Engineer
for the proposed haul route.
12. This approval is subject to all of the conditions of approval adopted for the
Poinsettia Place project CT 04-1OA incorporating by reference all of the conditions
contained in City Council Resolution No. 2010-027 and Planning Commission
Resolutions No. 6650 (CT 04-1 OA), 6651 (CP 04-05A), 6653 (CDP 04-23A), 6193
(HDP 04-05), and 6196 (HMP 06-08).
13. Prior to issuance of a Grading Permit, the Developer must execute a Pre-
Excavation Agreement with the San Luis Rey Band of Mission Indians that
reasonably achieves appropriate treatment of human remains and cultural items;
requires a good faith effort by the parties to agree on what is "appropriate
treatment and dignity" when addressing human remains and cultural items;
requires the return of any human remains or cultural items recovered during the
construction process to the San Luis Rey Band of Mission Indians; and,
reasonably requires a Native American monitor to be present during ground-
disturbing activity.
NOTICE
This decision may be appealed by you or any member of the public to the Planning Commission
within ten days of receipt of this letter. Appeals must be submitted in writing to the Planning
Commission at 1635 Faraday Avenue in Carlsbad, along with a payment of $613.00. The filing
of such appeal within such time limit shall stay the effective date of the order of the Planning
Director until such time as a final decision on the appeal is reached. If you have any questions
regarding this matter, please feel free to contact Christer Westman at (760) 602-4614.
CDP 10-14 - POINSETTIA PLACE BORROW SITE
July 28, 2011
PAGES '
Please take NOTICE that approval of your project includes the "imposition" of fees, dedications,
reservations, or other exactions hereafter collectively referred to for convenience as
"fees/exactions."
You have 90 days from date of final approval to protest imposition of these fees/exactions. If
you protest them, you must follow the protest procedure set forth in Government Code Section
66020(a), and file the protest and any other required information with the City Manager for
processing in accordance with Carlsbad Municipal Code Section 3.32.030. Failure to timely
follow that procedure will bar any subsequent legal action to attack, review, set aside, void, or
annul their imposition.
You are hereby FURTHER NOTIFIED that your right to protest the specified fees/exactions
DOES NOT APPLY to water and sewer connection fees and capacity charges, nor planning,
zoning, grading or other similar application processing or service fees in connection with this
project; NOR DOES IT APPLY to any fees/exactions of which you have previously been given a
NOTICE similar to this, or as to which the statute of limitations has previously otherwise expired.
CITY OF CARLSBAD
CHRIS DeCERBO
Principal Planner
CD:CW:sm
Don Neu, Planning Director
Chris DeCerbo, Principal Planner
Steve Bobbett, Project Engineer
Glen Van Peski, Senior Civil Engineer
File Copy
Data Entry/DMS
California Coastal Commission (NoFA)