HomeMy WebLinkAboutCT 98-16; Worthing Subdivision; Tentative Map (CT) (13)February 10, 1999
TO: ANNE HYSONG, ASSOCIATE PLANNER
FROM: Ken Quon, Associate Engineer
PROJECT ISSUES STATEMENT
WORTHING SUBDIVISION, CT 98-1 6
The Engineering Department has completed its review of the resubmitted project application for
completeness and/or engineering issues. The project application is now or was previously
found complete for the purpose of continued engineering review. The project application does
contain some engineering issues or concerns which remain to be resolved by the applicant. All
engineering issues should be fully resolved or addressed prior to resubmitting the project for
our review. The outstanding engineering issues or concerns are as follows:
1. Before the Engineering Department can proceed any further with its review, the
horizontal alignment of James Drive must be established along the project frontage. As
proposed on the tentative map, establishment of this road alignment is dependent upon
the applicant to obtain a triangular shaped piece of right-of-way from the adjacent
property to the north. Once the applicant demonstrates that this right-of-way is secured
through submittal to the City of an application for right-of-way dedication, the
Engineering Department will continue with review of this project.
If you have questions regarding any of the comments above, please contact me at extension
4380.
KENNETH W. QUON
Associate Engineer
c: Public Works Director
Bob Wojcik, Principal Civil Engineer
COMMUNITY: WORTHING ENG ISSUES MEMO