SUBJECT: HADLEY PROPERTY - CT 98-171CDP 98-74/HDP 98-19
Thank you for applying for Land Use Permits in the City of Carlsbad. The Planning
Department has reviewed your development application no. CT 98-17/GDP 98-741HDP 98-
19 as to its completeness for processing.
Due to the fact that legislative actions (Zone Change and Local Coastal Program
Amendment) are being processed concurrently with quasi-judicial actions the Planning
Department has determined that the site development plan, coastal development permit,
special use permit, and hillside development permit must remain incomplete until the
legislative actions are approved by the City Council. Please contact your staff planner,
Jeff Gibson, at (760) 438-l 161, extension 4455, if you have any questions or wish to set
up a meeting to discuss the application.
Sincerely,
MICHAEL J. HOLZMILLER
Planning Director
MJH:JG:vd
C: Gary Wayne
Adrienne Landers
Steve Jantz
Bobbie Hoder
File Copy
Data Entry
Planning Aide
2075 La Palmas Dr. l Carlsbad, CA 92009-1576 l (760) 438-l 161 l FAX (760) 438-0894 @
LIST OF ITEMS NEEDED
FOR STAFF REVIEW OF THE APPLICATION
No. CT 98-17ICDP 98-74/HDP 98-19
Planning:
1. The tentative map and associated application exhibits should be at scale no smaller
than 1 n = 40” (use multiple cut sheets and match lines where applicable).
2. The “constraints map notes” need to be corrected to reflect the fact that the site
contains .2 acres of oak woodland and an archaeological site (Sdi 6819). The
density calculation table must also include the oak woodland and this area must be
subtracted from the project’s gross acreage for purposes of density calculation.
3. The site has been historically utilized for agricultural purposes, therefore, the Final
Program EIR for SP 203A, which covers this property, requires the submittal of a
pesticide/soil testing report prior to approval of the tentative map.
4. The biological mitigation section of Final Program EIR for SP 203A requires the
incorporation of building setbacks/buffer zones to separate development areas from
dedicated open space boundaries to protect the native habitat area. A 60 foot
wide buffer/setback is recommended, and in this project, the 60 foot setback
would prohibit the development of several of the proposed lots. The exact location
of the buffer area should be delineated on the tentative map and discussed and
justified in the biological report.
5. Please revise the biological report to include a biological impact assessment and
mitigation plan for the impacts associated with the selective clearing of native
habitat for purposes of fire suppression in Zone 3. Prior to your next re-submittal
the Planning Department recommends that you consult with the resource agencies
concerning the project’s biological impacts and the appropriate mitigation measures
for the impacts.
6. A site visit to the property and. the review of orthophoto maps indicates that
vegetation on a portion of the site has been cleared without an approved grading
permit from the City. The areas that have been cleared must be surveyed and
reflected in the impact section of the project’s biological report. If deemed a
significant impact, applicable mitigation would be required for the clearing of
sensitive native habitat. The appropriate state and federal wildlife agencies should
also be notified by your biologist of the removal of native habitat.
7. The project is subject to inclusionary housing requirements, therefore, if you
propose to purchase affordable housing credits from Villa Loma there is an
application process that must take place before this project can proceed to Planning
Commission. The City’s Combined Project Review Committee must review the
proposal in accordance with City Council Policies No. 57 and 58 and make a
recommendation to the Housing Commission. For more information on how to
proceed when proposing an affordable housing credit purchase from Villa Loma,
please contact the City’s Housing and Redevelopment Department.
8. The pesticide residue section of Final Program EIR for SP 203A requires a minimum
25-foot-wide open space easement be provided between open field agricultural
operations (Tabata parcels) and the lot lines of all individual residential lots located
within future developable area on-site. This buffer area may be located on the
adjacent agricultural property so long as evidence of an easement agreement is
presented at the time of project application.
ISSUES OF CONCERN
Planning:
1. The project’s landscape plans do not comply with the landscape requirements of
Specific Plan 203(A). Street tree requirements -70% of homes must have 1 - 24”
box tree and 2 -15 gallon trees/ 30% from the theme palette and 70% from the
accent palette (See Page 90 of SP 203 (A)).
2. R-l-7500 is the proposed zoning, therefore, Lot 18 must be increased in size to at
least 7500 sq. ft. or a Planned Development Permit application must be submitted.
3. After structure setbacks for fire suppression and habitat purposes are taken into
consideration for Lots No. 19 and 20, there is not enough development area to plot
a reasonably sized dwelling unit. These lots should be either expanded or
eliminated.
4. When creating a panhandle lot that have less than 10,000 sq. ft. of area in the
buildable area of the lot, exclusive of the access portion of the lot, the applicant is
required to process a site plan showing that all requirements of the panhandle
section of the R-l-Zone are met. Part of this site plan review process should
include the establishment of the front, year and side yards of the panhandle lot for
purposes of building setback from property lines.
5. See the attached redlined marked plans for additional comments. Please return all
marked redlined plans with the next re-submittal of the application.
Engineering:
Traffic and Circulation
1. The access (Street “A”) with Black Rail Road must be coordinated with the other
undeveloped parcels along Black Rail. According to the approved Specific Plan,
joint access between this parcel to the north is proposed with one access roadway.
The applicant should prepare an appropriate circulation plan which will provide
access to all parcels in compliance with the appropriate intersection spacing
outlined in the Engineering Design standards.
2. Street “G” in the Aviara Phase Ill area traverses parallel to the southerly boundary of
this project. The applicant should consider utilizing this roadway as access.
Sewer and Water
3: Both sewer and water facilities to serve the proposed development will be required.
Coordinate design standards and utility locations with CMWD.
Gradinq
4. A grading permit will be required.
5. A permission to grade letter will be required for the area outside the project
boundaries.
Drainaue
6. Rip rap will be required at the end of the 18” storm drain.
7. Due to the proposed grading, a ponding effect occurs at the boundary with Tabata.
Please propose a solution.
Miscellaneous
8. Attached is a red-lined check print of the proposed project for the applicants use in
making the requested revisions. This check print must be returned with the project
revisions to facilitate continued staff review.