HomeMy WebLinkAboutCT 99-01; Carlsbad Beach Estates; Tentative Map (CT) (43)z & --7y City of Carlsbad
February 5, 1999
Merit Group, Inc.
Suite 202
217 1 El Camino Real
Oceanside, CA 92054
SUBJECT: CT 99-Ol/SDP 99-OZ/PUD 99-Ol/CDP 99-02 - CARLSBAD BEACH ESTATES
Thank you for applying for Land Use Permits in the City of Carlsbad. The Planning
Department has reviewed your tentative tract map, site development plan, planned unit
development, and coastal development permit, application no’s. CT 99-01, SDP 99-02,
PUD 99-01, and CDP 99-02, as to its completeness for processing.
The application is incomplete, as submitted. Attached are two lists. The first list is
information which must be submitted to complete your application. This list of items must
be submitted directly to your staff planner by appointment. All list items must be
submitted simultaneously and a copy of this list must be included with your submittals. No
processing of your application can occur until the application is determined to be complete.
The second list is issues of concern to staff. When all required materials are submitted the
City has 30 days to make a determination of completeness. If the application is
determined to be complete, processing for a decision on the application will be initiated. In
addition, please note that you have six months from the date the application was initially
filed, January 5, 1999, to either resubmit the application or submit the required
information. Failure to resubmit the application or to submit the materials necessary to
determine your application complete shall be deemed to constitute withdrawal of the
application. If an application is withdrawn or deemed withdrawn, a new application must
be submitted.
Please contact your staff planner, Elaine Blackburn, at (7601 438-l 161, extension 4471, if
you have any questions or wish to set up a meeting to discuss the application.
Sincerh,
v Plann*&g Director
MJH:EB:mh
c: Gary Wayne
Dennis Turner
Ken Quon
Bobbie Hoder
File Copy
Data Entry
Planning Aide
2075 La Palmas Dr. l Carlsbad, CA 92009-1576 - (760) 438-l 161 - FAX (760) 438-0894
LIST OF ITEMS NEEDED
TO COMPLETE THE APPLICATION
No. CT 99-Ol/SDP 99-02/PUD 99-Ol/CDP 99-02
Planning:
1. The building coverage information should be shown for each proposed lot separately as
a percentage (%I.
2. The plan sheets show the maximum allowed density for the various areas as the top of
the General Plan range (e.g., 23 dwelling units per acre for RH and 15 dwelling units
per acre for RMH). Actually, the maximum allowed density under growth management
would be the growth control point for the ranges (i.e., 19 dwelling units per acre for
RH and 1 1.5 dwelling units per acre for RMH). Please correct the various plan sheets
as necessary.
3. Please call out the amount of the pop-outs/recesses on the architectural elevations.
4. Some of the architectural elevations appear to dimension the building height from the
& restrictive of either the existing or proposed grade. Building height must be
measured from the more restrictive of the two.
Engineering:
1. A hydrology study which analyzes pre and post development hydrology of the project
site.
ISSUES OF CONCERN