TO: VAN LYNCH, ASSOCIATE PLANNER
FROM: Ken Quon, Associate Engineer
PROJECT ISSUES STATEMENT
RANCHO CARRILLO VILLAGE L, CT 99-11/CP 99-08/MP 139(1)
The Engineering Department has completed its review of the resubmitted project application for
completeness and/or engineering issues. The project application is now complete for the
purpose of continued engineering review. The project application does contain some
engineering issues or concerns which remain to be resolved by the applicant. All engineering
issues should be fully resolved or addressed prior to resubmitting the project for our review.
The outstanding engineering issues or concerns are as follows:
1. The entrance street is to intersect Carrillo Way at a right angle for at least 50', as
measured from the extension of the curb face.
2. The plans are to include notes indicating the parties responsible for maintaining slopes
along all project boundaries.
3. It appears from the landscape plans that plant materials will encroach into the sight
distance triangle at the corner of Melrose Drive and Carrillo Way. Please note that this
triangle is to be free of any obstructions exceeding 30" in height.
4. The applicant is to submit a preliminary title report of the project site shown on this
application.
5. The geotechnical report submitted with this application discusses the project site prior to
mass grading of the Rancho Carrillo development. Since the mass grading has already
occurred, this report must be revised to address the project site conditions and feasibility
in its current state (after the mass grading of the Rancho Carrillo development).
If you have questions regarding any of the comments above, please contact me at extension
4380.
KENNETH W. QUON
Associate Engineer