HomeMy WebLinkAboutCT 99-20; Carlsbad Airport Center Lot 10; Tentative Map (CT) (3)MCid.Qd l~--aq -qq
City of
November 23, 1999
Carl King
Smith Consulting Architects, Suite 200
12220 El Camino Real
San Diego CA 92 130
SUBJECT: CT 99-20/ PUD 99-09/ PIP 99-03 - CARLSBAD AIRPORT CENTRE LOT 10
Thank you for applying for Land Use Permits in the City of Carlsbad. The Planning Department has
reviewed your Tentative Map, Planned Unit Development, and Planned Industrial Permit, application
numbers CT 99-20 / PUD 99-09 / PIP 99-03, as to its completeness for processing.
‘The items requested from you earlier to make your Tentative Map, Planned Unit Development, and
Planned Industrial Permit, application no. CT 99-20 / PUD 99-09/ PIP 99-03 complete have been
received and reviewed by the Planning Department. It has been determined that the application is now
complete for processing. Although the initial processing of your application may have already begun,
the technical acceptance date is acknowledged by the date of this communication.
Please note that although the application is now considered complete, there may be issues that could be
discovered during project review and/or environmental review. Please see the attached list of issues of
concern. These issues should be resolved prior to scheduling the project for public hearing. In addition,
the City may request, in the course of processing the application, that you clarify, amplify, correct, or
otherwise, supplement the basic information required for the application.
Please contact your staff planner, Van Lynch, at (760) 438-l 161, extension 4447, if you have any
questions or wish to set up a meeting to discuss the application.
Planning Director
XIJH:VL:cs
c: Gary Wayne
Chris DeCerbo
Glen Van Peski
Bobbie Hoder
File Copy
Data Entry
Planning Aide
Attachment
2075 La Palmas Dr. l Carlsbad, CA 92009-1576 l (760) 438-l 161 - FAX (760) 438-0894
No. CT99-20 / PUD 99-09 / Pl’T! 99-03
November 23, 1999
Page 2
ISSUES OF CONCERN
Planning:
1. Please provide quantity of plants proposed on the landscape plan.
2. Provide an approval of a license agreement from S.D.G. & E. to allow improvements and parking
within the easement area.
3. Provide letter from the Carlsbad Airport Centre Owner’s association regarding the application and
review of the proposal.
Engineering:
1.
2.
3.
4.
5.
6.
7.
Previous lot line between Lots 1 and 10 is labeled “exist. Lot line” and “old lot line”. Tentative Map
would be clarified by deleting the previous lot line and labels.
The retaining walls on the Tentative Map are all shown using the Keystone wall symbol, but one of
the walls is labeled as a masonry wall. Symbols should be consistent with the Tentative Map.
One of the proposed retaining walls is labeled as a Keystone wall on the site plan, and a Keystone or
masonry wall on the Tentative Map. The Site Plan should be consistent with the Tentative Map.
The legal description on the Site Plan is incorrect.
The daylight line behind the proposed retaining walls should be revised to reflect the true limits of
grading necessary to construct the Keystone walls.
NPDES storm water pollution control plan will be required for this project. We suggest a
maintenance plan and program of prevention be developed instead of just adding a series of “Fossil
Filters” to catch basins. We recommend consideration of vegetation as an onsite filter and possibly a
detention basin to control downstream runoff.
A hydrology study will be required with the’ final engineering for this project. In addition to sizing
onsite drainage facilities, hydrology study will either have to show flows leaving the site that are
consistent with the previously approved hydrology reports, or check downstream facilities to prove
adequacy.
Attached are redlined check prints for your use. These check prints must be returned with the revised
plans to assist staff in the continued review of your project.