TABLE OF CONTENTS
INTRODUCTION
PROJECT DESCRIPTION
STORM WATER MANAGEMENT SYSTEM DESIGN
EROSION AND SEDIMENT CONTROL
BEST MANAGEMENT PRACTICE
DOWNSTREAM ANALYSIS
EXECUTIVE SUMMARY
LIST OF TABLES:
Table 1-Summary of gutter spread calculations
Table 2-Storm water runoff calculations -10-year storm
Table 3-Storm water runoff calculations -100-year storm
Table 6-Basin intake capacity calculations
Table 4-Storm drainage pipe flow calculations -10-year storm
Table 5-Storm drainage pipe flow calculations-1 00-year storm
LIST OF FIGURES:
Exhibit A -Location map
Exhibit B -Pre-development drainage map
Exhibit C -Post-development drainage map
Exhibit D -Schematic drainage diagram
Exhibit E -City Master Drainage Plan
Exhibit F-FIRM Flood Insurance Map
ATTACHMENTS
Hydraulic calculations
-----.. --------------
---
----------
-
INTRODUCTION
This drainage study report is being submitted to the City of Carlsbad as a reference to the LOS
Church located at Camino De Los Coches and Via Caliendo, a part of the NW 114 Quarter of
Section 6, Township 13 South, Range 3 West, City of Carlsbad, County of San Diego, California.
The square footage of the said development is 6.82 acres.
The site is in a Zone X (outside the 100 & 500 year flood plan) according to FEMA Flood
Insurance Rate Map, Community Panel No. 1053 of 2375, dated June 19, 1997. According to site
investigation there is no historical significance on or near the site, and no environmental liability
was found at the site. The site after development will be used for community service purpose.
Therefore, there will be no on-site industry activities and their associated discharge.
This report intends to present the existing storm water drainage conditions and the proposed
storm water management for this development. Control measures and detailed calculations are
included in the report.
PROJECT DESCRIPTION
Existing Conditions:
The site is currently undeveloped vacant land. There is a creek (an unnamed tributary of Encinitas
Creek) along the west boundary of the site. Runoff released from a 24" RCP pipe across Camino
De Los Coshes drains into the creek through the project site. Storm water from the site drains
directly into the creek. There is no existing on-site storm water management system.
Post-Development Conditions:
The proposed development consists of a LOS Church located on 6.82 ac site. The total acreage of
impervious surface areas is 3.23 acres or 47.4% total acreage.
Runoff from the controlled drainage areas drains into five catch basins and discharges into the
creek through underground storm sewers. A 24" RCP storm drain is installed by connecting to the
existing 24" RCP to divert drainage into the creek. Exhibit D shows a schematic drainage
diagram for the project site.
--------------------
-
-
-----------
-
EROSION & SEDIMENT CONTROL
Erosion and sediment control measures are designed and installed to prevent the escape of
sediment from the site during the construction of the proposed development. Site Erosion Control
Plan shows the erosion and sediment control measures and specifications. Sediment control
measures shall be installed and maintained per local jurisdictional requirement and specifications.
Sequence o(Major Activities:
1. Install stabilized construction entrance
2. Install silt fence
3. Site clearing
4. Remove and stockpile topsoil
5. Perform site grading operations
6. Stabilize denuded areas and stockpiles
7. Install curb inlets and storm drains
8. Install sediment filters
9. Begin building construction
10. Install utilities, curb and gutter
11. Complete grading and install permanent sodding and planting
12. Complete final pavement
13. Remove structural controls and re-seed any areas disturbed by the removal after all
construction activity and the site is stabilized.
BEST MANAGEMENT PRACTICE
The proposed project/site incorporates a combination of Best Management Practice (BMP)
measures to handle the storm water runoff and pollution mitigation requirements. The BMP
measures meet the requirements of the National Pollutant Discharge Elimination System
(NPDES), the San Diego Regional Water Quality Control Board (SDRWQCB) and the City of
Carlsbad.
Some of the BMP measures implemented include: Installing stormceptors to remove pollutants
and sediments. Directing runoff through vegetated areas. Developing and enhancing vegetation
and wildlife habitat areas along the existing drainage channel. Protecting the drainage channel
embankment from erosion by seeding, vegetation and rip rap. Controlling storm water discharge
velocities by using energy dissipators.
------------------
......
-
-
-
-
---------
-
increase downstream of 0.04 inch. Therefore, the impact of this development upon down stream
would be negligible.
Table 2. Summary of Storm Water Runoff Calculations (10-yr Storm)
Drainage Controlled Runoff Tc Intensity Peak discharge
structure drainage area coefficient (min) (inlhr) (cfs)
(ac)
1 (inlet) 0.11 0.85 5 8 0.75
2 (inlet) 0.54 0.85 5 8 3.67
2A (inlet) 0.13 0.85 5 8 0.88
4 (stormceptor) 0.54 0.85 5 8 3.67
5A 2.25 0.85 5 8 15.30
(stormceptor)
None 3.25 0.35 7 7 7.96
(Uncontrolled)
Note: see Post-Development Map (Exhibit C) for drainage layout and controlled drainage areas.
Table 3. Summary of Storm Water Runoff Calculations (100-yr Storm)
Drainage Controlled Runoff Tc Intensity Peak discharge
structure drainage area coefficient (min) (inlhr) (cfs)
(ac)
1 (inlet) 0.11 0.85 5 11 1.03
2 (inlet) 0.54 0.85 5 11 5.05
2A (inlet) 0.13 0.85 5 11 1.22
4 (stormceptor) 0.54 0.85 5 11 5.05
5A (stormceptor) 2.25 0.85 5 11 21.04
None 3.25 0.35 7 10 11.38
(Uncontrolled)
Note: see Post-Development Map (Exhibit C) for drainage layout and controlled drainage areas.
Table 4. Summary of Inlet Intake Capacity Calculations
Inlet structure Drainage area Discharge (cfs) Discharge (cfs) Inlet size *Basin intake
# (ac) (10-yr storm) (100-yr storm) cllJ)acity (cfs)
1 (inlet) 0.11 0.65 0.92 15" dia. grate 1.8
2 (inlet) 0.54 3.21 4.59 1-grate inlet 10.9
2A (inlet) 0.13 0.77 1.10 15" dia. grate 1.8
4 (stormceptor) 0.54 3.21 4.59 1-grate inlet 10.9
5A (stormceptor) 2.25 13.39 19.12 1-grate inlet 21.7
Note: see Post-development Map for drainage structure layout and controlled drainage areas.
*Assuming 20% clogging factor and 0.6 foot water depth.
----Table 5. Storm Drainage Pipe Calculations (10-yr Storm) -Storm Drain Controlled Runoff Tc Intensity Peak Pipe drainage ... drainage coefficient (min) (inlhr) discharge capacity
area (ac) (cfs) (cfs) -P-1 0.11 0.85 5 8 0.75 3.61 -P-2 0.65 0.85 5 8 4.41 5.89 -P-2A 0.13 0.85 5 8 0.88 8.07
P-3 0.78 0.85 5 8 5.10 7.47 -P-4 1.32 0.85 5 8 8.97 23.80 -P-5 -----6.08 ... P-5A 2.25 0.85 5 8 15.30 23.80 -P-6 -33.89 --Note: see Post-Development Map for drainage layout and controlled drainage areas. ---Table 6. Storm Drainage Pipe Calculations (100-yr Storm) -Storm Drain Controlled Runoff Tc Intensity Peak Pipe drainage -drainage coefficient (min) (inlhr) discharge capacity
area (ac) (cfs) (cfs) -P-1 0.11 0.85 5 11 1.03 3.61 -P-2 0.65 0.85 5 11 6.06 5.89
-P-2A 0.13 0.85 5 11 1.21 8.07 -P-3 0.78 0.85 5 11 7.01 11.27
P-4 1.32 0.85 5 11 12.33 20.43
P-5 - -- --4.90 -P-5A 2.25 0.85 5 11 21.04 20.43 -P-6 33.89 ---Note: see Post-Development Map for drainage layout and controlled drainage areas.
--------
---------
------
-
-
-----------------
ATTACHMENT
HYDRAULIC CALCULATIONS
---..
-..
----------
---
-
-
-
---------
07/06/01
Creek Cross Section A-A: Pre-development
Worksheet for Irregular Channel
(/po-yr)
Project Description
Project File
Worksheet
Flow Element
Method
c:\mz\haestad\fmw\lds-carl.fm2
Creek Cross Section A-A
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.030000 ft/ft
Elevation range: 211.00 ft to 219.00 ft.
Station (ft) Elevation (ft)
0.00 219.00
10.00 217.00
20.00 215.20
30.00 213.50
40.00 212.00
47.00 211.00
53.00 212.00
77.00 219.00
Discharge 999.76 cfs
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 215.46 ft
Flow Area 110.31 ft2
Wetted Perimeter 47.22 ft
Top Width 46.29 ft
Height 4.46 ft
Critical Depth 215.52 ft
Critical Slope 0.027871 fVft
Velocity 9.06 fVs
Velocity Head 1.28 ft
Specific Energy 216.73 ft
Froude Number 1.04
Flow is supercritical.
Start Station
0.00
End Station
77.00
Roughness
0.050
,.. 12:23:16 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666 -
FlowMaster v5.13
Page 1 of 1
------------------
-
---
-----------
07/06/01
Cross Section A-A (pre-development)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
c:\mz\haestad\fmw\lds-carl.fm2
Creek Cross Section A-A
Irregular Channel
Manning's Formula
Solve For Water Elevation
Section Data
Wtd. Mannings Coefficient
Channel Slope
Water Surface Elevation
Discharge
219. ,...
~
0.050
0.030000 ft/ft
215.46 ft
999.76 cfs
0 \ ~ 0
218.
217.
216.
c
.Q 215. 1ii > (!)
jjj
0
0
1\ ~
\ /{)()-)/!';
\
\.
\
I~ I '<V 2,/ S"; t/-6
~ 1F
~
,...
I 1/
I
I
I
I
0 \ I~
0 "'
214.
213.
212. 0
0 211.
0.0 10.0 20.0
\ I
\; I
30.0 40.0 50.0
Station (ft)
~
~
60.0 70.0 80.0
-12:28:55 PM Haestad Methods. Inc. 37 Brookside Road Waterbury. CT 06708 (203) 755·1666
FlowMaster v5.13
Page 1 of 1 -
---
-
----------
-
-
-
-
-
..... ---------
07/06/01
Creek Cross Section A-A: Post-development
Worksheet for Irregular Channel
{!Po-yr.}
Project Description
Project File
Worksheet
Flow Element
Method
c:\mz\haestad\fmw\lds-carl.fm2
Creek Cross Section A-A
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.030000 ft/ft
Elevation range: 211.00 ft to 219.00 ft.
Station (ft) Elevation (ft)
0.00 219.00
10.00 217.00
20.00 215.20
30.00 213.50
40.00 212.00
47.00 211.00
53.00 212.00
77.00 219.00
Discharge 1,023.81 cfs
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 215.50 ft
Flow Area 112.26 ft2
Wetted Perimeter 47.61 ft
Top Width 46.67 ft
Height 4.50 ft
Critical Depth 215.57 ft
Critical Slope 0.027779 ftlft
Velocity 9.12 ft/s
Velocity Head 1.29 ft
Specific Energy 216.79 ft
Froude Number 1.04
Flow is supercritical.
Start Station
0.00
End Station
77.00
Roughness
0.050
-12:24:08 PM Haestad Methods. Inc. 37 Brookside Road Waterbury. CT 06708 {203) 755-1666 -
FlowMaster v5. 13
Page 1 of 1
------------------------
-
-
-------
-
Cross Section A-A (post-development)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
c:\mz\haestad\fmw\lds-carl.fm2
Creek Cross Section A-A
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0.050
0.030000 ft/ft
Water Surface Elevation
Discharge
219. ~
~ ~
215.50 ft
1,023.81 cfs
0 \ ~ 0
218.
217. ~ ~ 0 \ ~ /t?t?-YJ•,
216.
c
.Q 215.
iii > Q) w
214.
213.
212.
0
0
0
0
0
\ ~ \.
\
\
f\
\
~ 21.5:5: ~ ..
~
N
7
1\; l7
,...
I
I
I
I
I r
I~
'~
211.
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0
07/06/01
12:28:03 PM
Station (ft)
Haestad Methods. Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FfowMaster v5.13
Page 1 of 1
---------...
--------
---
......
-
-----------
07/03/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-1: 10• PVC@ 2% SLOPE
.Worksheet for Circular Channel
c:\mz\haestad\fmw\lds-carl.fm2
Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.012
0.020000 ft/ft
0.83 ft
Diameter 10.00 in
Results
Discharge 3.45 cfs
Flow Area 0.55 ft2
Wetted Perimeter 2.51 ft
Top Width 0.11 ft
Critical Depth 0.78 ft
Percent Full 99.60
Critical Slope 0.018232 ft/ft
Velocity 6.32 ft/s
Velocity Head 0.62 ft
Specific Energy 1.45 ft
Froude Number 0.49
Maximum Discharge 3.61 cfs
Full Flow Capacity 3.36 cfs
Full Flow Slope 0.021097 ft/ft
Flow is subcritical.
02:56:25 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5. 13
Page 1 of 1
--------------------
---------------
07/03/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-2: 12• HOPE @ 2.01% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\lds-carl.fm2
Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.012
0.020100 ft/ft
1.00 ft
Diameter 12.00 in
Results
Discharge 5.47 cfs
Flow Area 0.79 ft2
Wetted Perimeter 3.14 ft
Top Width 0.3e-7 ft
Critical Depth 0.94 ft
Percent Full 100.00
Critical Slope 0.017370 ft/ft
Velocity 6.97 ft/s
Velocity Head 0.75 ft
Specific Energy 1.75 ft
Froude Number 0.24e-3
Maximum Discharge 5.89 cfs
Full Flow Capacity 5.47 cfs
Full Flow Slope 0.020100 ft/ft
Flow is subcritical.
-02:57:22 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666 -
FlowMaster v5.13
Page 1 of 1
---
--------------------
-
-
-------
-
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-4: 15• HOPE @ 10% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\lds-carl. fm2
Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.012
0.1 00000 ft/ft
1.25 ft
Diameter 15.00 in
Results
Discharge 22.13 cfs
Flow Area 1.23 ft2
Wetted Perimeter 3.93 ft
Top Width 0.00 ft
Critical Depth 1.25 ft
Percent Full 100.00
Critical Slope 0.095960 ft/ft
Velocity 18.03 ft/s
Velocity Head 5.05 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 23.80 cfs
Full Flow Capacity 22.13 cfs
Full Flow Slope 0.1 00000 ft/ft
07/03/01
03:09:33 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
--------------------
-----------------
07/03101
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-5: 1 o• PVC @ 5.68% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\lds-carl.fm2
Stonn Drain
Circular Channel
Manning's Fonnula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.012
0.056800 ft/ft
0.83 ft
Diameter 10.00 in
Results
Discharge 5.66 cfs
Flow Area 0.55 ft2
Wetted Perimeter 2.62 ft
Top Width 0.00 ft
Critical Depth 0.83 ft
Percent Full 100.00
Critical Slope 0.052401 ft/ft
Velocity 10.37 ft/s
Velocity Head 1.67 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 6.08 cfs
Full Flow Capacity 5.66 cfs
Full Flow Slope 0.056800 ft/ft
03:31:44 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755·1666
FlowMaster v5.13
Page 1 of 1
--------------------
-
-
-
-----------
·~------·~---------------------------···---···------
07/03/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-SA: 15" HOPE @ 1 0% SLOPE
Worksheet f9r Circular Channel
c:\mz\haestad\fmw\lds-carl.fm2
Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.012
0.1 00000 tvft
1.25 ft
Diameter 15.00 in
Results
Discharge 22.13 cfs
Flow Area 1.23 ft2
Wetted Perimeter 3.93 ft
Top Width 0.00 ft
Critical Depth 1.25 ft
Percent Full 100.00
Critical Slope 0.095960 tvft
Velocity 18.03 tvs
Velocity Head 5.05 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 23.80 cfs
Full Flow Capacity 22.13 cfs
Full Flow Slope 0.1 00000 tvft
03:11:09 PM Haestad Methods. Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5. 13
Page 1 of 1
-.. -.. ----------------
-
---
-
-------
-
•
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P·6: 24" RCP@ 1.94% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\lds~arl.fm2
Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
0.013
0.019400 ft/ft
Depth 2.00 ft
Diameter 24.00 in
Results
Discharge 31.51 cfs
Flow Area 3.14 ft2
Wetted Perimeter 6.28 ft
Top Width 0.00 ft
Critical Depth 1.88 ft
Percent Full 100.00
Critical Slope 0.016769 ftlft
Velocity 10.03 ftls
Velocity Head 1.56 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 33.89 cfs
Full Flow Capacity 31.51 cfs
Full Flow Slope 0.019400 ftlft
07/03101
03:12:28 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755·1666
FlowMaster v5.13
Page 1 of 1
-------------------• --• -
-------• ---
STORM DRAINAGE STUDY REPORT
for
LDSCHURCH
City of Carlsbad
County of Leucadia
State of California
Project No. 45001000
Engineer of Record: Mark Thompson, PE
One West Third Street, Suite 100
Tulsa, Ok 74103
918-295-4413
Date: February 23, 2001
----
---• --------
---
-----.. ---• •
-
TABLE OF CONTENTS
INTRODUCTION
PROJECT DESCRIPTION
STORM WATER MANAGEMENT SYSTEM DESIGN
EROSION AND SEDIMENT CONTROL
BEST MANAGEMENT PRACTICE
DOWNSTREAM ANALYSIS
EXECUTIVE SUMMARY
LIST OF TABLES:
Table 1 -Summary of gutter spread calculations
Table 2-Storm water runoff calculations -10-year storm
Table 3-Storm water runoff calculations -100-year storm
Table 6-Basin intake capacity calculations
Table 4-Storm drainage pipe flow calculations -10-year storm
Table 5-Storm drainage pipe flow calculations -100-year storm
LIST OF FIGURES:
Exhibit A -Location map
Exhibit B -Pre-development drainage map
Exhibit C -Post-development drainage map
Exhibit D -Schematic drainage diagram
Exhibit E -City Master Drainage Plan
Exhibit F-FIRM Flood Insurance Map
ATTACHMENTS
Hydraulic calculations
----.. --• ------.. -•
• •
• • -• -•
• • -• -• -•
• • .. -
INTRODUCTION
This drainage study report is being submitted to the City of Carlsbad as a reference to the LDS
Church located at Camino De Los Coches and Via Caliendo, a part of the NW 1/4 Quarter of
Section 6, Township 13 South, Range 3 West, City of Carlsbad, Leucadia County, California. The
square footage of the said development is 6.82 acres.
The site is in a Zone X (outside the 100 & 500 year flood plan) according to FEMA Flood
Insurance Rate Map, Community Panel No. 1053 of 2375, dated June 19, 1997. According to site
investigation there is no historical significance on or near the site, and no environmental liability
was found at the site. The site after development will be used for community service purpose.
Therefore, there will be no on-site industry activities and their associated discharge.
This report intends to present the existing storm water drainage conditions and the proposed
storm water management for this development. Control measures and detailed calculations are
included in the report.
PROJECT DESCRIPTION
Existing Conditions:
The site is currently undeveloped vacant land. There is a creek (an unnamed tributary of Encinitas
Creek) along the west boundary of the site. Runoff released from a 24" RCP pipe across Camino
De Los Coshes drains into the creek through the project site. Storm water from the site drains
directly into the creek. There is no existing on-site storm water management system.
Post-Development Conditions:
The proposed development consists of a LDS Church located on 6.82 ac site. The total acreage of
impervious surface areas is 2.42 acres or 35.5% total acreage .
Runoff from the controlled drainage areas drains into five catch basins and discharged into the
creek through underground storm sewers. A 24" RCP storm drain is installed by connecting to the
existing 24" RCP to divert drainage into the creek. Exhibit D shows a schematic drainage
diagram for the project site .
--.. -.. -• .. ----
---• -• -• -• -• -• -• ..
• -• ----
EROSION & SEDIMENT CONTROL
Erosion and sediment control measures are designed and installed to prevent the escape of
sediment from the site during the construction of the proposed development. Site Erosion Control
Plan shows the erosion and sediment control measures and specifications. Sediment control
measures shall be installed and maintained per local jurisdictional requirement and specifications .
Sediment Yield Calculations:
The universal soil loss equation (USLE) was used to estimate annual sediment yield from the
disturbed areas.
Sediment Yield (A) = R x K x LS x C x P x (AREA)
Total disturbed area (AREA)= 3.9 ac
Rainfall erosion index (R) = 200
Soil erodibility factor (K) = 0.32
Length-slope factor (LS) = 1.3
Cover factor (C) = 0.45
Erosion control factor (P) = 1.0
A= (200)(0.32)(1.3)(0.45)(1.0)(3.9) = 146 tons/year
The estimated annual soil loss from the total disturbed area is about 146 tons .
Sequence o(Major Activities:
1. Install stabilized construction entrance
2. Install silt fence
3. Site clearing
4. Remove and stockpile topsoil
5. Perform site grading operations
6. Stabilize denuded areas and stockpiles
7. Install curb inlets and storm drains
8. Install sediment filters
9. Begin building construction
10. Install utilities, curb and gutter
11. Complete grading and install permanent sodding and planting
12. Complete final pavement
13. Remove structural controls and re-seed any areas disturbed by the removal after all
construction activity and the site is stabilized.
---• .. -..
• .. ---
-..
•
• •
• • -•
• •
• •
• •
• •
•
IIIII ---
BEST MANAGEMENT PRACTICE
All waste contaminants during the construction activities shall be managed per the City of
Carlsbad and County of San Diego requirements. The contractor shall periodically water the site
to control dust. The contractor and developer shall contact the proper government agencies for
any environmental emergencies and take proper actions per city, county and state specifications
and procedures .
DOWNSTREAM ANALYSIS
The site is located in a Zone X (outside the 100 & 500 year flood plan) according to FEMA Flood
Insurance Rate Map, Community Panel No. 1053 of 2375, dated June 19, 1997 (see attached. The
FEMA Flood Insurance Map). The 100-year peak runoff flow rate will increase from 24.8 cfs to
35.5 cfs after development.
Based on the Drawing No 296-5 in the Master Drainage and Storm Water Quality Management
Plan of the City of Carlsbad dated March 1994, the controlled drainage area by the creek at
Section A-A is about 400 acres (see attached Master Plan Map). The drainage from the 400-acres
watershed passes through the creek with an estimated flow rate of about 1000 cfs from 100-year
storm (assuming intensity of 5 inches and runoff coefficient of 0.5). The study indicated that
increased flow due to this development results in a negligible water surface increase downstream
of 0.25 inch (see attached hydraulic calculations). Therefore, the impact of this development upon
down stream would be negligible .
EXECUTIVE SUMMARY
The proposed development consists of a LDS Church located on an approximately 6.82 acres site.
The total acreage of impervious surface areas is about 2.42 acres or 35.5% of the site .
Storm water management system for the site consists of drainage water collection system and on-
site underground drainage pipes. Drainage from an existing storm sewer underneath the Camino
De Los Coches is diverted away from the development area using a 24" RCP storm sewer and
discharged into the creek. The total pre-development peak discharge from the site for a 10-year
and 100-year storm is 14.3 cfs and 20.7 cfs, respectively. The post-development peak discharge
from the site from 10-year storm and 100-year storm is 24.9 cfs and 31.9 cfs, respectively. The
-• -.. -..
Ill -• -.. ------•
• •
• •
• • ..
Ill::
• -• -•
• • -
Table 5. Storm Drainage Pipe Calculations (10-yr Storm)
Storm Drain Control Runoff Tc Intensity Peak
drainage coefficient (min) (inlhr) discharge
area (ac) (cfs)
P-1 0.11 0.85 5 8 0.75
P-2 0.65 0.85 5 8 4.41
P-3 0.13 0.85 5 8 0.88
P-4 0.78 0.85 5 8 5.10
P-5 1.32 0.85 5 8 8.97
P-6 - ----
P-7 2.25 0.85 5 8 15.30
P-8 - ----
P-9 -----
P-10 - --- -
Note: see Post-Development Map for drainage layout and controlled drainage areas.
Table 6. Storm Drainage Pipe Calculations (100-yr Storm)
Storm Drain Control Runoff Tc Intensity Peak
drainage coefficient (min) (inlhr) discharge
area (ac) (cfs)
P-1 0.11 0.85 5 11 10.3
P-2 0.65 0.85 5 11 6.06
P-3 0.13 0.85 5 11 1.21
P-4 0.78 0.85 5 11 7.01
P-5 1.32 0.85 5 11 12.33
P-6 - --- -
P-7 2.25 0.85 5 11 21.04
P-8 -----
P-9 -----
P-10 - ----
Note: see Post-Development Map for drainage layout and controlled drainage areas .
Pipe drainage
capacity
(cfs)
2.19
6.17
3.10
11.27
20.43
4.90
20.43
31.99
31.99
31.99
Pipe drainage
capacity
(cfs)
2.19
6.17
3.10
11.27
20.43
4.90
20.43
31.99
31.99
31.99
------------------------
--
----• • -• -•
ATTACHMENT
HYDRAULIC CALCULATIONS
---------------
-• ..
•
• • ..
•
• •
• •
• • .. ..
• • ..
•
02/23/01
Creek Flow Capacity
Worksheet for Irregular Channel
( /(ltl-'fl" sro~tH -PilE-J)&-l/.iU.Pf'tH~7)
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
c:\mz\haestad\fmw\wal-mart. fm2
channel
Input Data
Irregular Channel
Manning's Formula
Discharge
Channel Slope 0.030000 fVft
Water Surface Elevation 215.08 ft
Elevation range: 211.00 ft to 219.00 ft.
Station (ft) Elevation (ft)
0.00 219.00
42.00
47.00
53.00
77.00
Results
Wtd. Mannings Coefficient
Discharge
Flow Area
Wetted Perimeter
Top Width
Height
Critical Depth
212.00
211.00
212.00
219.00
0.035
999.76
84.10
40.92
40.04
4.08
215.75
cfs
ft2
ft
ft
ft
ft
Critical Slope 0.013658 fVft
Velocity 11.89 fVs
Velocity Head 2.20 ft
Specific Energy 217.28 ft
Froude Number 1.45
Flow is supercritical.
Start Station
0.00
End Station
77.00
Roughness
0.035
-11 :06:54 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
•
FlowMaster v5.13
Page 1 of 1
--------------
•
• • -• -• -
•
• -• -
•
•
fill
Creek Cross Section A-A
Cross Section for Irregular Channel
( pll.e-.P~f/~t-u~t~t~/.17)
Project Description
Project File
Worksheet
Flow Element
Method
c:\mz\haestad\fmw\wal-mart. fm2
channel
Solve For
Section Data
Irregular Channel
Manning's Formula
Discharge
0.035 Wtd. Mannings Coefficient
Channel Slope 0. 030000 ft/ft
Water Surface Elevation
Discharge
219. .....
~
215.08 ft
999.76 cfs
0 \ ~ 0
218.
217 .
216.
£ -
c
.Q 215.
<a > Q)
ijj
214.
213.
212.
0 \ ~
\
\ /tiP
0 \ 0
0
0
0
~
\
\
-.::7 ;;us;.
~
[\
\;
~a
I~
I v
.....
I
I
I
I
I
·~
~ 211.
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 • •
02123/01
-11 :07:07 AM
•
Station (ft)
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
---• ---• ---• -----• -• -• -•
• • -• -•
• •
• • -• -•
02/23/01
Creek Flow Capacity
Worksheet for Irregular Channel
( f>C)_$-r -Pl!VcUf'Mefl/1')
Project Description
Project File
Worksheet
Flow Element
Method
c:\mz\haestad\fmw\wal-mart. fm2
channel
Solve For
Input Data
Irregular Channel
Manning's Formula
Discharge
Channel Slope 0.030000 tvtt
Water Surface Elevation 215.1 0 ft
Elevation range: 211.00 ft to 219.00 ft.
Station (ft) Elevation (ft)
0.00 219.00
42.00
47.00
53.00
77.00
Results
Wtd. Mannings Coefficient
Discharge
Flow Area
Wetted Perimeter
Top Width
Height
Critical Depth
212.00
211.00
212.00
219.00
0.035
1,012.53
84.90
41.11
40.23
4.10
215.77
Start Station
0.00
cfs
ft2
ft
ft
ft
ft
Critical Slope 0.013635 tvtt
Velocity 11.93 tvs
Velocity Head 2.21 ft
Specific Energy 217.31 ft
Froude Number 1.45
Flow is supercritical.
End Station
77.00
Roughness
0.035
11:04:33AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 {203) 755-1666
FlowMaster v5. 13
Page 1 of 1
---• -• ---• -• ---• ..
• -• ---------• -• -• -•
02/23/01
Creek Cross Section A-A
Cross Section for Irregular Channel
(_pos-r -Pl::Vt:"Wf'Mc~T)
Project Description
Project File
Worksheet
Flow Element
Method
c:\mz\haestad\fmw\wal-mart. fm2
channel
Solve For
Section Data
Irregular Channel
Manning's Formula
Discharge
Wtd. Mannings Coefficient
Channel Slope
0.035
0.030000 ft/ft
Water Surface Elevation
Discharge
219. "" ~
215.10 ft
1,012.53 cfs
0 \ ~ 0
218.
217 .
216.
£ -
c
.Q 215. a; > G)
ijj
0
0
\ I~
\
1\ /M
\
~ ~:PIS"· /0
~
"' I
I
I
I
I
0 \ ~ 0
214.
213.
212 . 0
0 211.
0.0 10.0 20.0
\ I ~ \
\; v ~
30.0 40.0 50.0 60.0 70.0 80.0
Station (ft)
-11 :05:27 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1 ..
---• --• ..
• ..
• -.. -• -• ..
•
[II
• -1111
• •
• • .. ..
• •
• •
• • 02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-1: 10" PVC@ 1% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.010000 ft/ft
0.83 ft
Diameter 10.00 in
Results
Discharge 2.19 cfs
Flow Area 0.55 ft2
Wetted Perimeter 2.62 ft
Top Width 0.00 ft
Critical Depth 0.66 ft
Percent Full 100.00
Critical Slope 0.010604 ft/ft
Velocity 4.02 ft/s
Velocity Head 0.25 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 2.36 cfs
Full Flow Capacity 2.19 cfs
Full Flow Slope 0.010000 ft/ft
• 11:14:55AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
--• -• -• ..
• ..
• -.. -• -• -• ..
• -• -----• -• -• .. • ..
•
02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-2: 12" RCP @ 3% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.030000 ft/ft
1.00 ft
Diameter 12.00 in
Results
Discharge 6.17 cfs
Flow Area 0.79 ft2
Wetted Perimeter 3.14 ft
Top Width 0.00 ft
Critical Depth 0.96 ft
Percent Full 100.00
Critical Slope 0.026131 ft/ft
Velocity 7.86 ft/s
Velocity Head 0.96 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 6.64 cfs
Full Flow Capacity 6.17 cfs
Full Flow Slope 0.030000 ft/ft
11:51:25 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
---
---•
Ill
• -• ---• -• ..
-•
• -..
• •
• •
• • 02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-3: 1 0" PVC @ 2% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.020000 ft/ft
0.83 ft
Diameter 10.00 in
Results
Discharge 3.10 cfs
Flow Area 0.55 ft2
Wetted Perimeter 2.62 ft
Top Width 0.00 ft
Critical Depth 0.76 ft
Percent Full 100.00
Critical Slope 0.017456ft/ft
Velocity 5.68 ft/s
Velocity Head 0.50 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 3.33 cfs
Full Flow Capacity 3.10 cfs
Full Flow Slope 0.020000 ft/ft
• 11 :26:34 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
-•
• --..
• -• -
• -• -.. -
-
--------
"' •
• • -•
02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-4: 12" RCP @ 10% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.1 00000 ft/ft
1.00 ft
Diameter 12.00 in
Results
Discharge 11.27 cfs
Flow Area 0.79 ft2
Wetted Perimeter 3.14 ft
Top Width 0.00 ft
Critical Depth 1.00 ft
Percent Full 100.00
Critical Slope 0.094943 ft/ft
Velocity 14.34 ft/s
Velocity Head 3.20 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 12.12 cfs
Full Flow Capacity 11.27 cfs
Full Flow Slope 0.1 00000 ft/ft
11:51:07 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
--.. -• ..
• ..
• -• --
• -• ----
-
-
----• -•
• • -.. 02/23101
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-5: 15" RCP @ 10% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.1 00000 ft/ft
1.00 ft
Diameter 15.00 in
Results
Discharge 19.97 cfs
Flow Area 1.05 ft2
Wetted Perimeter 2.77 ft
Top Width 1.00 ft
Critical Depth 1.25 ft
Percent Full 80.00
Critical Slope 0.090842 ft/ft
Velocity 18.97 ft/s
Velocity Head 5.59 ft
Specific Energy 6.59 ft
Froude Number 3.26
Maximum Discharge 21.97 cfs
Full Flow Capacity 20.43 cfs
Full Flow Slope 0.095544 ft/ft
Flow is supercritical.
11:53:33AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
•
•
.. -... -• ..
..
• -• -.. ..
• -II
!Ill
II
--
-• -•
•
• •
02123/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-6: 1 0" PVC @ 5% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.050000 ft/ft
0.83 ft
Diameter 10.00 in
Results
Discharge 4.90 cfs
Flow Area 0.55 ft2
Wetted Perimeter 2.62 ft
Top Width 0.00 ft
Critical Depth 0.82 ft
Percent Full 100.00
Critical Slope 0.045096 ft/ft
Velocity 8.98 ft/s
Velocity Head 1.25 ft
Specific Energy FULL ft
Froude Number FULL
Maximum Discharge 5.27 cfs
Full Flow Capacity 4.90 cfs
Full Flow Slope 0.050000 ft/ft
• 11 :56:35 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
ill
FlowMaster v5.13
Page 1 of 1
---... -----------• -• -------
--•
• -•
• •
02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-7: 15" RCP @ 10% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart. fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.1 00000 ft/ft
1.25 ft
Diameter 15.00 in
Results
Discharge 20.43 cfs
Flow Area 1.23 ft2
Wetted Perimeter 3.93 ft
Top Width 0.33e-7 ft
Critical Depth 1.25 ft
Percent Full 100.00
Critical Slope 0.095288 ft/ft
Velocity 16.65 ft/s
Velocity Head 4.31 ft
Specific Energy 5.56 ft
Froude Number 0.48e-3
Maximum Discharge 21.97 cfs
Full Flow Capacity 20.43 cfs
Full Flow Slope 0.1 00000 ft/ft
Flow is subcritical.
-11 :55:57 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
•
FlowMaster v5.13
Page 1 of 1
-..
• -• -• -• -• -•
• • -
-• --..
iill ..
• -•
• • .. ..
02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-8: 24" RCP @ 2% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart.fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.020000 ft/ft
2.00 ft
Diameter 24.00 in
Results
Discharge 31.99 cfs
Flow Area 3.14 ft2
Wetted Perimeter 6.28 ft
Top Width 0.6e-7 ft
Critical Depth 1.89 ft
Percent Full 100.00
Critical Slope 0.017296 ft/ft
Velocity 10.18 ft/s
Velocity Head 1.61 ft
Specific Energy 3.61 ft
Froude Number 0.25e-3
Maximum Discharge 34.41 cfs
Full Flow Capacity 31.99 cfs
Full Flow Slope 0.020000 ft/ft
Flow is subcritical.
1!11111 11 :58:40 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
-.. -•
.. ..
• ---.. -• -• --.. -----------•
• • -• --02/23101
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-9: 24" RCP @ 2% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart.fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.020000 ft/ft
2.00 ft
Diameter 24.00 in
Results
Discharge 31.99 cfs
Flow Area 3.14 ft2
Wetted Perimeter 6.28 ft
Top Width 0.6e-7 ft
Critical Depth 1.89 ft
Percent Full 100.00
Critical Slope 0.017296 ft/ft
Velocity 10.18 ftls
Velocity Head 1.61 ft
Specific Energy 3.61 ft
Froude Number 0.25e-3
Maximum Discharge 34.41 cfs
Full Flow Capacity 31.99 cfs
Full Flow Slope 0.020000 ft/ft
Flow is subcritical.
11:58:51 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.13
Page 1 of 1
-----
• -•
• ...
• -• -• -•
..
• ..
• ---• .. ---..
02/23/01
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
P-1 0: 24" RCP @ 2% SLOPE
Worksheet for Circular Channel
c:\mz\haestad\fmw\wal-mart.fm2
CMP Storm Drain
Circular Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
Depth
0.013
0.020000 fVft
2.00 ft
Diameter 24.00 in
Results
Discharge 31.99 cfs
Flow Area 3.14 ft2
Wetted Perimeter 6.28 ft
Top Width 0.6e-7 ft
Critical Depth 1.89 ft
Percent Full 100.00
Critical Slope 0.017296 fVft
Velocity 10.18 fVs
Velocity Head 1.61 ft
Specific Energy 3.61 ft
Froude Number 0.25e-3
Maximum Discharge 34.41 cfs
Full Flow Capacity 31.99 cfs
Full Flow Slope 0.020000 fVft
Flow is subcritical.
-11 :59:00 AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666 -FlowMaster v5.13
Page 1 of 1