One Single
Family Home:No Charge
All Other Applications.
Based on Project Site
Size:
PLANNING DEPARTMENT
HILLSIDE DEVELOPMENT PERMIT
APPLICATION FORM
0 -
0 -
10 -
1 Acres
10 Acres
TOO Acres
100 Acres
50.00
100.00
200.00
400.00
Complete Description of Project (attach additional sheets if necessary)
GRADING PLAN FOR A SINGLE FAMILY RESIDENCE (PE 2-89'10)
Location of Project
OBELISCO CIRCLE, CARLSBAD
Permit/File Numbers Associated with this Project
. PE 2-89-10
Legal Description (complete)
LOT 693 MAP 7367
La Costa Meadows Unit No. 4
Local Facility Management Zone
6
Zone General Plan
R-l-15 RL
Proposed Zone Proposed General Plan
Owner
Name (Print or Type)
JACK E. WILLIAMS ET. AL.
Mailing Address
7433 Solano Street
City and State Zip Telephone
Carlsbad, CA 92009 942-1209
1 CERTIFY THAT AM THE LEGAL OWNER
AND THAT ALL THE ABOVE INFORMATION
IS TRUE AND CORRECT TO THE BEST OF
MY KNOWLEDGE.
SIGNATURE , DATE
7~ te Application Kec'd. Received By
^. • 3> - ^^ £-Vlx7
Assessors Parcel Number
215-440-08
Existing Land Use
VACANT
Site Acreage
0.86 AC
Applicant
Name (Print or Type)
WAYNE PAS CO
Mailing Address
535 No. Hwy. 101, #A
City and State Zip
Solana Beach, CA 92075
Telephone
259-8212
1 CERTIFY THAT 1 AM THE OWNER'S
REPRESENTATIVE AND THAT ALL
THE ABOVE INFORMATION IS TRUE
AND CORRECT TO THE BEST OF
MY KNOWLEDGE.
SIGNATURE DATE
Fees Ripseived Re^c
• (2_3 /\y^o.
PROJECT NUMBER (S)
HILLSIDE DEVELOPMENT PERMIT
INFORMATION SHEET
GENERAL INFORMATION
This sheet generally explains how your Hillside Development
Permit (HDP) will be processed. If you have any questions after
reading this, please call Development Processing counter at 438-
1161 or review Chapter 21.95 of the Carlsbad's Municipal Code.
When a Hillside Development Permit is needed:
A Hillside Development Permit (HDP) is required when
development is proposed on land with a slope gradient of 15% or
greater and a slope height of greater than 15 feet. Development
means building, grading, subdivision or other modification of a
hillside area.
It is highly recommended that you, as an applicant, 1)
review Chapter 21.95 of the Carlsbad Municipal Code (The Hillside
Ordinance) and 2) discuss the Hillside Development with a City
Planner before submitting an application for a Hillside
Development Permit. The Hillside Development Permit should be
submitted concurrently with any permit or application for
development of a Hillside area.
How your Hillside Development Permit will be Processed
Generally the steps involved in reviewing your HDP application
are as follows:
1. A Hillside Development Permit application is submitted
to the Development Processing counter at 2075 Las
Palmas Drive. The application must be submitted with
and reference any other permit application such as a
building or grading permit, tentative map, etc. All
maps submitted shall be folded to 8-1/2" x 11".
Information items required:
(a) A completed Hillside Development
Permit Application Form
(b) Four copies of the slope analysis
(see Section 21.95.020 of
Carlsbad's Municipal Code)
Identify slopes 1. 0 to less than 15% slope
2. 15% to less than 25% slope
3. 25% to less than 40% slope
4. 40% or greater slopes
% Slope = Vertical Distance x 100
Contour interval!
Horizontal Distance
(Distance between contour intervals) ~
(c) Four copies of the slope profile(s)
(d) Assurance of slope analysis and slope profile
accuracy
(e) Show with a site plan, grading plan
and building plans and elevations
how development fulfills the
following Hillside Development and
Design Standards (21.95.060)
Submit four (f4) sets) of each plan.
1. Coastal Zone"Requirements (if applicable)
2 . Contour grading
3. Area or extent of grading
4. Screening graded slopes
5. View preservation and enhancement
,-, 6. Roadway design
. - fe*-7. Hillside architecture
Z - ^8. Hilltop architecture
9. Hillside drainage
10. Man-made slope height and
volume of grading cut or
fill
11. Potential development and
design standard
modification
(f) A completed "disclosure statement"
i—~ (g) Two copies of a preliminary title report.
2. A Development Services counter person generally checks
your application for completeness, if your application
is incomplete, it cannot be accepted. If your
application appears complete, it is accepted.
3. The Hillside Development Permit application is
typically reviewed, processed, and approved concurrent
with the first permit or application you may have with
the City for that hillside area.
4. For approval of a Hillside Development Permit the
following findings must be made:
-2-
(a) That hillside conditions and undevelopable areas
of the project have been properly identified.
(b) That the development is consistent with the
purpose, intent and requirements of the Hillside
Ordinance to:
(1) Assure hillside alteration will not result in
substantial damage or alteration of
significant natural resource areas, wildlife
habitats or native vegetation areas;
(2) Preserve the natural appearance of hillsides
by assuring that development density and
intensity relates to the slope of the land,
and is compatible with hillside preservation.
(3) Assure proper design is utilized in grading,
landscaping, and in the development of
structures and roadways to preserve the
natural appearance of hillsides.
(4) Preserve and enhance a healthful and
aesthetically pleasing environment by
assuring that hillside development is
pleasing to the eye, rich in variety, highly
identifiable, and reflects the City's
cultural and environmental values.
(5) Assure hillside conditions are properly
identified and incorporated into the planning
process.
(6) Implement the intent of the land use and open
space/conservation elements of the Carlsbad
General Plan.
(7) Prevent erosion and protect the lagoons from
excessive siltation.
(8) Encourage creatively designed hillside
development requiring a minimal amount of
grading.
(9) Reduce the intensity of development on
hillside areas to ensure all development that
does occur is compatible with the existing
topography.
-3-
(c) That hillside development is consistent with the
Hillside Development and Design Standards
(21.95.60) and substantially conforms to the
intent of the concepts illustrated in the Hillside
Development Guidelines Manual.
(d) That development is consistent with the provisions
of Section 21.53.230 and 240 of the Carlsbad
Municipal Code.
Appeal
If your Hillside Development Permit is denied, you may appeal the
decision of:
1. The Planning Director to the Planning Commission
2. The Planning Commission to the City Council
LBS:af
-4-
APPLICANT:
AGENT:
MEMBERS:
PISCLOSU REFORM
JACK E. WILLIAMS
Name (individual, partnership, joint venture, corporation, syndication
7A-^ QOTAMO ST. CARLSBAD, C.A 92009Business Address
942-1209
Telephone Number
WAYNE PASCO
Name
535 No. Hwy. 101, Solana Beach, CA 92075
Business Address
259-8212
Telephone Number
Name (individual, partner, joint
venture, corporation, syndication)
Home Address
Business Address
Telephone Number Telephone Number
Name Home Address
Business Address
Telephone Number Telephone Number
(Attach more sheets if necessary)
I/We understand that if this project is located in the Coastal Zone, I/we will apply
for Coastal Commission Approval prior to development.
I/We acknowledge that in the process of reviewing this application, it may be
necessary for members of City Staff, Planning Commissioners, Design Review Board
members, or City Council members to inspect and enter the property that is the
subject of this application. I/We consent to entry for this purpose.
I/We declare under penalty of perjury that the information contained in this disclosure
is true and correct and that it will remain true and correct and may be relied upon
as being true and correct until amended.
APPLICANT
BY
Agent, Owner, Partner