HomeMy WebLinkAboutHDP 97-11; Golnick Residence; Hillside Development Permit (HDP) (2)c h ..- ut
August 1 I , 1997
Lon Gulnick
291 6-C Luciernaga Street
Carlsbad, CA 92009
SUBJECT: HDP 97-11 - GULNICK RESIDENCE
Thank you for applying for Land Use Permits in the City of Carlsbad. The Planning
Department has reviewed your Hillside Development Permit, application no. HDP 97-
1 I , as to its completeness for processing.
The application is incomplete, as submitted. Attached is a list of the item@) which must
be submitted to complete your application. No processing of your application can
occur until the application is determined to be complete. When all required materials
are submitted the City has 30 days to make a determination of completeness. If the
application is determined to be complete, processing for a decision on the application
will be initiated. In addition, please note that you have six months from the date the
application was initially filed, July 14, 1997, to either resubmit the application or submit
the required information. Failure to resubmit the application or to submit the materials
necessary to determine your application complete shall be deemed to constitute
withdrawal of the application. If an application is withdrawn or deemed withdrawn, a
new application must be submitted.
Please contact your staff planner, Greg Fisher, at (760)438-1161, extension 4328, if
you have any questions or wish to set up a meeting to discuss the application.
Sincerely,
Planning Director
MJH:GF:kr
c: Gary Wayne File Copy The Midglen Studio
Brian Hunter Data Entry William Arthur Patrick, AIA
Clyde Wickham Planning Aide 831 Midglen Way
Bobbie Hoder Woodside CA 94062
2075 Las Palmas Dr. - Carlsbad, CA 92009-1576 (61 9) 438-1161 0 FAX (61 9) 438-0894 @
LIST OF ITEMS NEEDED
TO COMPLETE THE APPLICATION
NO. HDP 97-11
Planning:
1. Provide area and acreage of grading. ’ See Page 2 of 5, (F3) of the Hillside
Development Permit application for further explanation.
2. Provide three copies of a preliminary title report (current within the last six
months) from date of application.
Engineering:
1. The engineering comments are not available at this time and will follow this
letter. Please contact Clyde Wickham, at (760) 438-1 161 , extension 4353, if you
have any questions.