NOTICE OF PRELIMINARY DECISION ON TENTATIVE PARCEL MAP
Project ID: MS 05-23
Project Name: HILTON CARLSBAD BEACH RESORT AND SPA
Applicant Name: Hofman Planning and Engineering
Per City of Carlsbad Municipal Code Section 20.24.115, the City is required to send this
notice and the enclosed copy of the preliminary decision letter to all persons who requested
to be heard in response to the Notice of Filing for this minor subdivision. After a final
decision has been made on the project, you will also receive a notice and copy of that
decision.
If you have concerns or comments, you may request a review of this preliminary decision.
Per Carlsbad Municipal Code Section 20.24.120, such request must be in writing and
received by the City Engineer within 10 calendar days after the date of this preliminary
decision. Following the completion of a requested review or if no request for review was
made within the time prescribed, the City Engineer will issue a final decision.
If you have no remaining issues to discuss with us, there is no need to respond to this notice.
However, if you have any questions or comments, please contact the Project Engineer, Frank
Jimeno, at 760-602-2758 or via email at Frank.jimeno@carlsbadca.gov.
Sincerely,
Robert T. Johnson, Jr., PE
City Engineer
a.
by: David A. Mauser, PE
Deputy City Engineer
Enclosure(s): Reduced tentative parcel map exhibit
Preliminary Decision Letter
cc: Project Engineer, then file
Doc DR-06-25
1635 Faraday Avenue • Carlsbad, CA 92008-7314 • (760) 6O2-2720 - FAX (76O) 6O2-8562
i"tT"'t^1"-t"'i~TT'T"r"T^"j:~l:'37t"r' i )~"—'""•••*"'-*.»-B.»
tt::»4*l:*TM:::t::»*3^^ff^ta^eKKiff^^S'&^S^^^&S^SSS'S'^^^^^
1**^
^s^rr:;.,.,
i ^---..-^-T.-^vm —ci" ^c^v
rE3&Z
O i S *Q_i:
- "
s-^^^
City of Carlsbad
Public Works - Engineering
September 25, 2009
Hofman Planning and Engineering
3152 Lionshead Avenue
Carlsbad, California 92010
TENTATIVE PARCEL MAP
MS 05-23: HILTON CARLSBAD BEACH RESORT AND SPA
The City Engineer has completed a review of the application for a tentative parcel map located
at the southeast corner of Carlsbad Boulevard and Ponto Drive and more particularly described
as a portion of the south 2/3rd of Lot 4 (southeast quarter of the southeast quarter) of Section 29,
Township 12 South, Range 4 West, San Bernardino Meridian in the City of Carlsbad. The City
Engineer has made a preliminary decision pursuant to Section 20.24.120 of the City of Carlsbad
Municipal Code to approve this tentative parcel map based on the findings and subject to the
conditions listed below.
Please review the following findings and conditions for this tentative parcel map. If you have
concerns or comments, you may request a review of this preliminary decision in writing. Such
request must be received by the City Engineer within 10 calendar days of the date of this
preliminary approval. Upon receiving such written request, the City Engineer will arrange a time
and place for such review. If after 10 days no request is made, or following a requested review
of this preliminary approval, the City Engineer will issue a final approval letter for this tentative
parcel map.
Findings:
1. The Planning Director has determined that:
a. the project is a subsequent activity of the Ponto Beachfront Village Vision Plan
for which a program EIR was prepared, and a notice for the activity has been
given, which includes statements that this activity is within the scope of the
program approved earlier, and that the program EIR adequately describes the
activity for the purposes of CEQA) [15168( c)(2) and (e)]; and
b. this project is consistent with the Vision Plan cited above; and
c. EIR 05-05 was certified in connection with the prior plan; and
d. the project has no new significant environmental effect not analyzed as
significant in the prior EIR; and
1635 Faraday Avenue • Carlsbad, CA 92008-7314 • (760) 602-2720 • FAX (760) 602-8562
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
e. none of the circumstances requiring a Subsequent EIR or a Supplemental EIR
under CEQA Guidelines Sections 15162 or 15163 exist; and
f. all feasible mitigation measures or project alternatives identified in the Ponto
Beachfront Village Vision Plan EIR 05-05 which are appropriate to this
Subsequent Project have been incorporated into this Subsequent Project.
2. The City Engineer has determined that:
a) The proposed map and the proposed design and improvement of the subdivision,
as conditioned, is consistent with and satisfies all requirements of the General
Plan, any applicable specific plans, Titles 20 and 21 of the Carlsbad Municipal
Code and the State Subdivision Map Act, in that the lots being created satisfy all
minimum requirements of Title 20 regarding lot sizes and configuration and have
been designed to comply with all other applicable regulations; and,
b) The design of the subdivision and improvements are not likely to cause serious
public health problems, and the discharge of storm water from the subdivision
complies with current California Regional Water Quality Control Board
requirements and the City of Carlsbad Standard Urban Stormwater Mitigation
Plan (SUSMP) requirements, in that the Developer has prepared a preliminary
Storm Water Management Plan to identify pollutants of concern and incorporate
best management practices to either avoid contact with storm water or filter
pollutants to the maximum extent practicable; earth drainage swales and bio
retention areas are incorporated into the subdivision design for filtration of
stormwater runoff; the project is conditioned to incorporate Low Impact Design
(LID) techniques: and,
c) The design of the subdivision or the type of improvements will not conflict with
easements of record or easements established by court judgment, or acquired by
the public at large, for access through or use of property within the proposed
subdivision, in that the developer shall delineate on the parcel map all existing
easements of record; and,
d) The property is not subject to a contract entered into pursuant to the Land
Conservation Act of 1965 (Williamson Act);
e) The exactions imposed on the Developer are imposed to mitigate impacts
caused by or reasonably related to the project, and the extent and the degree of
the exaction is in rough proportionality to the impact caused by the project.
Page 2 of 8
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
CONDITIONS:
Unless specifically stated in the condition, all of the following conditions, upon the approval of
this tentative parcel map, must be met prior to approval of a parcel map, building permit, or
grading permit, whichever is first.
General
1. This approval is granted subject to all conditions of approval of SDP 05-14, RP 05-11,
CDP 05-43 and CDP 09-04.
2. Developer shall submit to the City Engineer a reproducible 24" x 36" photo mylar of the
tentative parcel map reflecting the conditions approved by the final decision-making
body. The reproducible shall be submitted to the City Engineer, reviewed, and, if
acceptable, signed by the City's project engineer and project planner prior to submittal of
the building plans, or parcel map.
3. Unless a standards variance has been issued, no variance from City Standards is
authorized by virtue of approval of this tentative parcel map.
4. Developer shall comply with all applicable provisions of federal, state, and local laws and
regulations in effect at the time building permits are issued.
5. If any conditions for construction of any public facilities or payment of any fees in-lieu
thereof, imposed by this approval or imposed by law on this project are challenged, this
approval shall be suspended as provided in Government Code Section 66020. If any
such condition is determined to be invalid, this approval shall be invalid unless the City
Engineer determines that this project without this condition complies with the
requirements of the law.
6. Developer shall and does hereby agree to indemnify, protect, defend and hold harmless
the City of Carlsbad, its Council members, agents, officers, and representatives, from
and against any and all liabilities, losses, damages, demands, claim and costs, including
court costs and attorney's fees incurred by the City arising, directly or indirectly, from (a)
City's approval and issuance of this tentative parcel map, (b) City's approval or issuance
of any permit or action, whether discretionary or non-discretionary, in connection with the
use contemplated herein, including an action filed within the time period specified in
Government Code Section 66499.37 and (c) Developer's installation and operation of
the facility permitted hereby, including without limitation any and all liabilities arising from
the emission by trie facility of electromagnetic fields or other energy waves or emissions.
7. Developer shall prepare, submit and process for City Engineer approval a parcel map to
subdivide this project. There shall be one parcel map recorded for this project.
Developer shall pay processing fees per the City's latest fee schedule.
8. Developer shall install sight distance corridors at all street intersections and driveways in
accordance with City Engineering Standards. The property owner shall maintain this
condition.
Page 3 of 8
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
9. The project is approved with the express condition that building permits will not be
issued for the development of the subject property unless the City Engineer determines
that sewer facilities are available at the time of application for such sewer permits and
will continue to be available until time of occupancy. This note shall be placed on the
non-title sheet of the parcel map.
Fees/Agreements
10. Developer is required to pay all required fees and deposits prior to approval of the parcel
map.
11. Developer shall pay the Planned Local Drainage Area Fee prior to approval of the parcel
map.
12. Developer shall pay the citywide Public Facilities Fee imposed by City Council Policy
#17, the License Tax on new construction imposed by Carlsbad Municipal Code Section
5.09.030, and CFD #1 special tax (if applicable) subject to any credits authorized by
Carlsbad Municipal Code Section 5.09.040. Developer shall also pay any applicable
Local Facilities Management Plan fee for Zone 22, pursuant to Chapter 21.9. All such
taxes/fees shall be paid at issuance of building permits. If the taxes/fees are not paid,
this approval will not be consistent with the General Plan and shall become void.
13. Prior to issuance of a building permit for the project, owner shall agree to pay a fair
share contribution to the cost of improvements to the intersections and intersection
approaches of La Costa Avenue with Vulcan Avenue and Coast Highway 101 located
within the City of Encinitas. The intersection and associated intersection approach
improvements include widening and/or replacement of the La Costa Avenue bridge over
the North County Transit District railroad tracks and are more specifically described in
Appendix G-2 to the Ponto Beachfront Village Vision Plan EIR 05-05 ("Intersection
Improvements"). The aggregate fair share contribution from all the Ponto Beachfront
Village Vision Plan area landowners/developers is fifty percent (50%) of the cost to
design and construct Intersection Improvements including any required right-of-way
acquisition and environmental mitigation costs. The fair share contribution for each
separate land owner/developer shall be determined based upon the ratio of the
respective traffic generation resulting from a particular development to the overall traffic
generation resulting from the aggregate development of all the properties located within
the Ponto Beachfront Village Vision Plan area times the fifty percent (50%) share of
Intersection Improvements. The owner shall pay the estimated fair share contribution, or
submit an irrevocable instrument of credit in a form acceptable to the Finance Director
and City Attorney from one or more responsible financial institutions regulated by the
state or federal government and approved by the Finance Director and City Attorney,
prior to building permit issuance and, enter into an agreement with the City to be
recorded against the property that provides for adjustment of the fair share payment
amount, up or down, based upon a revision to the costs to construct Intersection
Improvements or a revision to the amount of traffic generated by the project or the
overall traffic generation resulting from the aggregate development of all the properties
located within the Ponto Beachfront Vittage Vision Plan area.
Page 4 of 8
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
14. Developer shall cause property owner to apply for, execute, and submit to the City
Engineer for recordation an Encroachment Agreement covering private Fire Access lane
located over existing Carlsbad Boulevard public right-of-way or easements as shown on
the tentative parcel map. Developer shall pay processing fees per the City's latest fee
schedule.
15. Prior to approval of any grading or building permits for this project, Developer shall
cause Owner to give written consent to the City Engineer for the annexation of the area
shown within the boundaries of the subdivision into the existing City of Carlsbad Street
Lighting and Landscaping District No. 1 and/or to the formation or annexation into an
additional Street Lighting and Landscaping District. Said written consent shall be on a
form provided by the City Engineer.
Grading
16. Developer shall comply with the latest version of the City's Stormwater Regulations and
shall implement best management practices at all times. Best management practices
include, but are not limited to, pollution treatment practices or devices, erosion control to
prevent silt runoff during construction, general housekeeping practices, pollution
prevention and educational practices, maintenance procedures, and other management
practices or devices to prevent or reduce the discharge of pollutants to stormwater,
receiving water, or stormwater conveyance system to the maximum extent practicable.
Developer shall notify prospective owners and tenants of the above requirements.
17. Developer shall submit documentation, subject to City Engineer approval, demonstrating
how this project complies with Interim Hydromodification requirements per the latest
version of the City's SUSMP. Documentation shall be included within the Storm Water
Management Plan (SWMP).
Dedications/improvements
18. Developer shall cause Owner to dedicate to the City Ponto Drive for public street &
public utility purposes as shown on the tentative parcel map. The offer shall be made by
a certificate on the parcel map. All land so offered shall be free and clear of all liens and
encumbrances and without cost to the City. Streets that are already public are not
required to be rededicated. Additional easements may be required at final design to the
satisfaction of the City Engineer.
19. Developer shall prepare and process public improvement plans and, prior to City
Engineer approval of said plans, shall execute a City-standard Subdivision Improvement
Agreement to install and shall post security in accordance with C.M.C. Section
20.16.070 for public improvements shown on the tentative parcel map. Said
improvements shall be installed to City Standards to the satisfaction of the City
Engineer. These improvements include, but are not limited to:
A. Half-street improvements of Carlsbad Boulevard along the project frontage. Half-
street improvements shall include a 32-ft paved half-street width consisting of two
Page 5 of 8
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
12-ft traffic lanes, an 8-ft bike lane, curb and gutter, meandering sidewalk, street
lights, fire hydrants, median curb, median grading, parkway and median
landscaping and irrigation, , signing and striping, and street drainage facilities, all
to the satisfaction of the City Engineer.
B. Dedicated left-turn lane on north bound Carlsbad Boulevard at its intersection
with Ponto Drive, including modifications to the existing traffic signal, signing and
striping, all to the satisfaction of the City Engineer.
C. Complete half-street improvements of Ponto Drive along the project frontage
from Carlsbad Boulevard to the southerly property line south of the parking
structure easterly of Ponto Drive, as shown in the site plan. The improvements
shall consist of curb, gutter, sidewalk, five-ft bike lane, street lights, fire hydrants,
median curbs with full median hardscape, parkway and full median landscaping
and irrigation, street drainage facilities, signing and striping, and wayfinding
signage, all to the satisfaction of the City Engineer.
D. Temporary improvements to Ponto Drive from the improvements terminus listed
above to its intersection with Beach Way, including a transition, with safety
features, from the above improvements' elevations to the existing ground
elevation, and a transition to Beach Way's existing improvements, all to the
satisfaction of the City Engineer.
E. Construct an extension to the existing 8" potable water line in Ponto Drive from
its existing terminus southerly along the project frontage.
F. Construct an extension to the existing 8" recycled water line in Ponto Drive from
its existing terminus southerly along the project frontage.
G. Construct an extension to the existing 8" recycled water line in Carlsbad
Boulevard from its existing terminus southerly along the project frontage.
Developer shall pay the standard improvement plancheck and inspection fees. Improvements
listed above shall be constructed within 18 months of approval of the subdivision or
development improvement agreement or such other time as provided in said agreement.
20. Developer shall execute a City standard Development Improvement Agreement to
design and install, and shall post security in accordance with C.M.C. Section 20.16.070,
for full-width public improvements, within the project boundary, for the extension of
Ponto Drive from the improvements' terminus listed in condition 22C to its intersection
with Beach Way. The improvements shall consist of curb, gutter, sidewalk within the
project frontage, five-ft bike lane, street lights, fire hydrants, median curbs with full
median hardscape, parkway and full median landscaping and irrigation, street drainage
facilities, signing and striping, and wayfinding signage, all to the satisfaction of the City
Engineer.
Page 6 of 8
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
Non-Mapping Notes
21. Note(s) to the following effect(s) shall be placed on the parcel map as non-mapping
data:
A. Developer has executed a City-standard Minor Subdivision Improvement
Agreement and has posted security in accordance with C.M.C. Section
20.28.070 to install public improvements shown on the tentative parcel map.
These improvements include, but are not limited to:
1) Half-street improvements of Carlsbad Boulevard along the project
frontage.
2) Dedicated left-turn lane on north bound Carlsbad Boulevard at its
intersection with Ponto Drive.
3) Half-street improvements of Ponto Drive along the project frontage from
Carlsbad Boulevard to the southerly property line south of the parking
structure easterly of Ponto Drive.
4) Temporary improvements to Ponto Drive from the improvements terminus
listed above to its intersection with Beach Way.
5) Design and install full-width public improvements, within the project
boundary, for the extension of Ponto Drive from the improvements'
terminus listed in item 4 above to its intersection with Beach Way.
6) Construct an extension to the existing 8" potable water line in Ponto Drive
from its existing terminus southerly along the project frontage.
7) Construct an extension to the existing 8" recycled water line in Ponto
Drive from its existing terminus southerly along the project frontage.
8) Construct an extension to the existing 8" recycled water line in Carlsbad
Boulevard from its existing terminus southerly along the project frontage.
B. This subdivision contains a remainder parcel. No building permit shall be issued
for the remainder parcel until it is further subdivided pursuant to the provisions of
Title 20 of the Carlsbad Municipal Code.
C. Building permits will not be issued for development of the subject property unless
the appropriate agency determines that sewer and water facilities are available.
D. No structure, fence, wall, tree, shrub, sign, or other object may be placed or
permitted to encroach within the area identified as a sight distance corridor as
defined by City of Carlsbad Engineering Standards or line-of-sight per Caltrans
standards.
Code Reminders
The project is subject to all applicable provisions of local ordinances, including but not limited to
the following:
22. This tentative parcel map will expire thirty-six (36) months from the date of the final
Page 7 of 8
Preliminary Decision Letter
MS 05-23 Hilton Carlsbad Beach Resort and Spa
September 25, 2009
approval notice issued by the City Engineer.
23. Developer shall pay traffic impact and sewer impact fees based on Section 18.42 and
Section 13.10 of the City of Carlsbad Municipal Code, respectively. The Average Daily
Trips (ADT) and floor area shown on the tentative parcel map are for planning purposes
only.
NOTICE
Please take NOTICE that approval of your project includes the "imposition" of fees, dedications,
reservations, or other exactions hereafter collectively referred to for convenience as
"fees/exactions."
You have 90 days from the date of final approval to protest imposition of these fees/exactions.
If you protest them, you must follow the protest procedure set forth in Government Code Section
66020(a) and file the protest and any other required information with the City Manager for
processing in accordance with Carlsbad Municipal Code Section 3.32.030. Failure to timely
follow that procedure will bar any subsequent legal action to attack, review, set aside, void, or
annul their imposition.
You are hereby FURTHER NOTIFIED that your right to protest the specified fees/exactions
DOES NOT APPLY to water and sewer connection fees and capacity charges; to planning,
zoning, grading, or other similar application processing or service fees in connection with this
project; or to any fees/exactions of which you have previously been given a NOTICE similar to
this, or as to which the statute of limitations has previously otherwise expired.
If you have any questions regarding the above, please contact the Project Engineer, Frank
Jimeno at 760-602-2708. If you have any planning-related questions, please contact the Project
Planner, ChristerWestman, at 760-602-4614.
Sincerely,
Robert T. Johnson, Jr., PE
City Engineer
/ -1
By: David A. Hauser, PE
Deputy City Engineer
cc: Senior Civil Engineer Glen Van Peski
Project Engineer Frank Jimeno
Project Planner Christer Westman
Fire Department Jim Weigand
Senior Office Specialist Dev. Svcs.
MS File
Page 8 of 8
City of Carlsbad
Public Works — Engineering
October 30, 2009
Hofman Planning and Engineering
3152 Lionshead Avenue
Carlsbad, California 92010
FINAL APPROVAL OF TENTATIVE PARCEL MAP
Project ID: MS 05-23
Project Name: HILTON CARLSBAD BEACH RESORT AND SPA
Whereas no review of the Preliminary Approval letter dated September 25, 2009 was requested
within the required time, the subject tentative parcel map has been approved per the findings
and conditions set forth in said Preliminary Approval letter.
As required by Carlsbad Municipal Code Section 20.24.140(e), notice of this final decision will be
sent to all property owners within 300 feet of the project. Per Carlsbad Municipal Code Section
20.24.140(b) and the California Subdivision Map Act Section 66452.5, any interested person
adversely affected by this decision of the City Engineer may appeal the decision to the City
Council. Such appeal must be filed in writing with the City Clerk within 10 calendar days of the
date of this notice. At the time of filing the appeal, the appeal fee as listed in the current
Carlsbad Development Fees schedule must be paid. If you have questions regarding the appeal
process, please contact the City Clerk's office at (760) 434-2808.
If you have any project-related questions, please contact the Project Engineer, Frank Jimeno, at
760-602-2758 or via email at frank.jimeno@carlsbadca.gov. If you have any planning-related
questions, please contact the Project Planner, Christer Westman, at 760-602-4614.
Sincerely,
Robert T. Johnson, Jr., PE
City Engineer
by: David A. Mauser, PE
Deputy City Engineer
cc: Engineer of Work
Project Engineer, then file
Christer Westman, Planner
Planning Senior Management Analyst
Senior Office Specialist, Dev. Svcs.
Doc DR-06-27
01/05/2009
1635 Faraday Avenue • Carlsbad, CA 92008-7314 - (760) 602-272O • FAX (760) 602-8562
City of Carlsbad
Public Works - Engineering
October 30, 2009
NOTICE OF APPROVAL OF TENTATIVE PARCEL MAP
Project ID: MS 05-23
Project Name: HILTON CARLSBAD BEACH RESORT AND SPA
Applicant Name: Hofman Planning and Engineering
Notice is hereby given that a tentative parcel map has been approved subject to conditions on
property generally located at the southeast corner of Carlsbad Boulevard and Ponto Drive and
more particularly described as a portion of the south 2/3rd of Lot 4 (southeast quarter of the
southeast quarter) of Section 29, Township 12 South, Range 4 West, San Bernardino Meridian
in the City of Carlsbad.
The project involved is described as the consolidation nine existing lots into one parcel and a
remainder parcel.
Per Carlsbad Municipal Code Section 20.24.140(b) and the California Subdivision Map Act
Section 66452.5, any interested person adversely affected by this decision of the City Engineer
may appeal the decision to the City Council. Such appeal must be filed in writing with the City
Clerk within 10 calendar days of the date of this notice. At the time of filing the appeal, the
appeal fee as listed in the current Carlsbad Development Fees schedule must be paid. If you
have questions regarding the appeal process, please contact the City Clerk's office at (760)
434-2808.
If you have any project-related questions, please contact the Project Engineer, Frank Jimeno, at
760-602-2758 or via email at frank.jimeno@carlsbadca.gov.
Sincerely,
Robert T. Johnson, Jr., PE
City Engineer
by: David A. Mauser, PE
Deputy City Engineer
Enclosure(s): Reduced tentative parcel map exhibit
Final Decision Letter (included only to Notice of Filing respondents)
cc: Applicant
Engineer of Work
Project Engineer, then file
Doc DR-06-29
01/05/2009
1635 Faraday Avenue - Carlsbad, CA 92008-7314 • (76O) 602-272O • FAX (76O) 602-8562