HomeMy WebLinkAboutPIP 98-05; Cornerstone Corporate Center; Planned Industrial Permit (PIP) (18)March 17, 1998
TO: VAN LYNCH, PLANNING TECHNICIAN II
FROM: Associate Engineer Quon
COMPLETENESS REVIEW AND INITIAL ISSUES STATEMENT
CORNERSTONE CORPORATE CENTRE - BUILDING A, PIP 98-05
The Engineering Department has completed its review of the subject project for application
completeness. The application and plans submitted for this project are complete and suitable
for continued engineering review.
In addition, the Engineering Department made a preliminary review of the project for
Engineering issues. Engineering issues which need to be resolved or adequately addressed
prior to conditioning of the project are as follows:
1. The applicant should consider adding a section of raised curb at the project entrance or
devise some other alternative to avoid an awkward 5-legged intersection.
Attached is a redlined check print set of the project. Please forward this plan set to the
applicant for corrections and changes as noted. The applicant must return this plan set with the
corrected plans to assist us in our continued review. If you have questions regarding any of the
comments above, please contact me at extension 4380.
KENNETH W. QUON
Associate Engineer
C: Public Works Director
Bob Wojcik, Principal Civil Engineer
COMMUNITYCORNERSTONE LOT A ENG COMPLETE MEMO