On April 7, 2009 the Housing and Redevelopment Commission and City Council
conditionally approved Tentative Tract Map No. CT 08-05, amendment to Major
Redevelopment Pennit No. RP 06-03, and amendment to Coastal Development Permit
No. 06-09, for property located at 560 Carlsbad Village Drive. Enclosed please find a
signed copy of the resolutions with final conditions of approval.
I congratulate you on the approval of the condominium conversion and I wish you much
success In your future endeavors. If you have any questions and/or comments
regarding this correspondence, please contact my office at (760) 434-2813.
Sincerely,
AUSTIN SILVA
Assistant Planner
Enclosures
C: Richard Woolsley, Richard and Richard Construction
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2397 • (760) 434-2810/2811 • FAX (760) 720-2037 ^
March 27,2009
TO: CiTY MANAGER
FROM: HOUSING AND REDEVELOPMENT DIRECTOR
ROOSEVELT CENTER TENTATIVE TRACT MAP - CT 08-05
Attached for information ofthe Housing and Redevelopment Commission is a letter I recently forwarded
to the developer of the Roosevelt Center project regarding the water meter issue discussed by the
Commission at the public hearing on March 17, 2009. Also attached Is a letter forwarded by the
developer indicating the motivation for the request for a master water meter and sub-meters. The
developer wanted to assure the Commission that he and his partners were not trying to work around
the process and to share their reasons for the master water meter request. The developer
correspondence Is attached for the purpose of sharing this additional information. A copy of the
Engineering staffs correspondence to the developer indicating its support for the master water meter
with conditions is attached for information purposes as well.
Engineering staff is currently researching Information on the operational Issue for the master water
meter raised by the Commission at their meeting on March 17^^ and will report on the findings through
a separate report. If there are questions or comments regarding the attached correspondence, please
contact me at X2935.
(IE FOUNTAIN
City Manager/Housing and Redevelopment Commission
City Attorney
Community Development Director
City Engineer
Deputy City Engineer
Senior Civil Engineer, Development Services
Public Works Director
Citv of Carlsbad
Housing & Redevelopment Department
March 27, 2009
RICHARD WOOLSEY
RICHARD & RICHARD CONSTRUCTiON CO.
234 VENTURE STREET, SUrTE 100
SAN MARCOS, CA. 92078
RE: 560 CARLSBAO VILLAGE DRIVE (ROOSEVELT CENTER); CT 08-05
Dear Mr. Woolsev:
Thank you for your letter dated March 18, 2009 regarding the tentative map approval for the Roosevelt
Center development at 560 Carisbad Village Drive In Carisbad. As you Indicated, at the Housing and
Redevelopment Commission meeting on March 17, 2009 there was some concern expressed about a
single master water meter and sub-meters and the impact It might have on future owners. The concern,
as I understand it, was related to the potential for one or more owners to refuse or not be able to pay
his/her water bill and then the obligation for that cost falling on the other owners to ensure continuous
water service. A request was made by the Commission for staff to research and provide information on
other condominium projects in Carisbad that have had a similar water service/meter arrangements and
share the owner collection/payment experiences to date. Staff is currently researching this information
and will present its findings to the Commission when the tentative map for your project is considered
again on April 7, 2009.
Although an inquiry was made by the Commission as to whether or not, as the developer, you were
aware of the requirement for separate water meters for a condominium and now were attempting to
work around the requirement by requesting the subject tentative map approval during construction of
the project, it is my personal belief that the motivation for, or timing of, your request is no longer a
concern or issue among the Commission. As you are aware, Engineering staff confirmed its support for
the master water meter and sub-meters with conditions noted in a letter to you dated November 25,
2008. This information was shared with the Commission during the hearing. However, because the
separate water meters was indicated as a condition of approval for a future tentative map in your
original project approval, the City Attorney indicated that only the Commission, not staff, was
authorized to change the condition and now allow the master meter rather than individual water
meters. The Commission is considering your request. However, it requested additional information on
operational matters related to the water meters before taking action.
To ensure that the Commission has all relevant information on this matter, I will share your letter with
the Commission members which Indicates that your request Is based only on limited physical space
within the alley to provide 10 individual water meters and the poor economic conditions which are
demanding flexibility In your ability to rent or sell the restaurant, retail, office and/or residential units
within your development. 1 will also provide them with a copy of the Engineering Staff letter outlining Its
conditions for support ofthe single master water meter with sub-meters.
2965 Roosevelt St., Ste. B • Carlsbad. CA 92008-2397 • (760) 434-2810/2811 • FAX (760) 720-2037 ^
R. Woolsey
March 27, 2009
Page 2
Thank you for your correspondence. If any additional information Is required from you to address the
Commission's concerns and/or questions, I will contact you again. If you have any additional questions
or comments for my office, please contact me at (760) 434-2815.
Sincerely, ^
DEBBIE FOUNTAIN
Housing and Redevelopment Director
C: City Manager/Housing and Redevelopment Commission
City Attorney
Community Development Director
City Engineer
Deputy City Engineer
Senior Civil Engineer, Development Services
Public Works Director
Citv of Carlsbad
Public Works - Engineerin
November 25,2008
RECEIVED
DEC 0 2 2008
BY: Mr. Richard Woolsey
Richard & Richard Construction Company, Inc
234 Venture Street
Suite 100
San Marcos, CA 92078
SUBJECT: CT 08-05 ROOSEVELT CENTER
REQUEST FOR WAIVER OF DEVELOPMENT SERVICES
POLICY DIRECTIVE NO. 2
Engineering Services reviewed your request for a waiver ofPolicy Directive No. 2 dated
September 25, 2008, requirement for a separate water service and meter to each
individually ovmed unit. A waiver has been granted subject to the folloving conditions:
a) A sub-meter shall be installed for each individually owned unit The sub-
meters shall be privately owned and maintamed by the Property Owners
Association (POA). It shall be the responsibility of the POA to apportion
the water bill to the sq>arate sub-metered ownership witiiin each building
served by a City water meter.
b) Prior to sale of any unit, the owner shall create an impound account to be
funded with an amount equal to an estimated three months of water bill
payments.
c) Owners and tenants of the units shall be notified that the City may shutoff
water service to the entire building if adequate payment of the water bill is
not made
d) The project CC&R's shall include wording satisfactory to the City
Engineer relating to the provisions of conditions a), b) and c) above. The
CC&Rs shali also include language stating that the CC&R provisions
related to water meters cannot be changed without the approval of the City
Engineer.
If you have further questions or comments regarding this matter, please feel fiee to write
or give me a call at (760) 602-2739.
David Hauser
Deputy City Engineer
Development Services
c Bob Johnson, Acting City Engineer
Glen Van Peski, Senior Civil Engineer, Development Services
1635 Faraday Avenue • Carlsbad, CA 92008-7314 • (760) 602-2720 • FAX (760) 602-8562 @
'ICHARD R &
Coiistmctioii '^SVO'a
Company, Inc. ^(His^oPi^S^
PICHARD Commercial. Industria
State Ucense
March 18,2009
Carlsbad Re-development department
Attn: Debbie Fountain
2965 Roosevelt Street, Suite B
Carlsbad, CA. 92008
Re: 560 Carlsbad Village Drive (Roosevelt Center) Track Map Approval
Ms. Debbie Fountain:
As you observed yesterday evening at the City Council and Housing and redevelopment
Commission Meeting ( AB # 19,749), there was concem over ownership utilizing one
city water meter along with individual tenant meters for reason of working around the
typical system. As expressed in the design review board meeting and again yesterday
evening in the City Counsel meeting, there could be nothing further from the truth. The
reasons are:l)To give the project versatility do to the crash in the economic conditions
and, 2)Physical space within the alley prohibited multiple water meters.
It is the intent of the ownership to maintain a minimum of 51 % of the real estate and
operate and be responsible for the HOA which will be billed and pay the monthly water
usage bills.
Please respond to this letter with any assistance or information necessary to help get the
track map approved at the next scheduled City Council Meeting. Last night's City
Council deferment of this issue could possibly result in our ability to sell the restaurant
element and rent the associated retail store which would create financial disaster to this
project.
Thank You for your assistance and timely response.
Richard A. Wdolse;!
Cc: Tom Hurley
Gene Lecher
David Wilkin/on, Counsel
234 Venture street • Suite 100 • San Marcos • CA 92078 • Phone 760-759-2260 • Fax 760-759-2269
Citv of Carlsbad
Housing & Redevelopment Department
November 17, 2008
SPEAR AND ASSOCIATES
ATTN: KEN GIFFORD
475 PRODUCTION STREET
SAN MARCOS, CA 92078
Subject: Roosevelt Center
RP 06-03A/CDP 06-09A/CT 08-05
Dear Richard:
The items requested from you eariier to make your application No. RP 06-03A/CDP 06-
09A/CT 08-05 complete have been received and reviewed by the Housing &
Redevelopment Department and all other appropriate departments. It has been
determined that the application is now complete for final processing. Although the initial
processing of your application may have already begun, the technical acceptance date is
acknowledged by the date of this communication. The City may, in the course of
processing the application, request that you clarify, amplify, correct, or otherwise,
supplement the basic information required for the application.
Please contact my office at (760) 434-2813, if you have any questions or wish to set up
a meeting to discuss the application.
Sincerely,
Austin Silva
Assistant Planner
Tecla Levy, Engineering Department
File
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2397 • (760) 434-2810/2811 • FAX (760) 720-2037 ®
Citv of Carlsbad
Housing & Redevelopment Department
August 27, 2008
SPEAR AND ASSOCIATES
ATTN: KEN GIFFORD
475 PRODUCTION STREET
SAN MARCOS, CA 92078
Subject: Roosevelt Center, Major Redevelopment Permit
CT 08-05/RP 06-03A/CDP 06-09A
Dear Ken:
Thank you for applying for a tentative parcel map and associated permits In the
City of Carlsbad. The Housing and Redevelopment Department, together with
other appropriate City departments, has reviewed your application No. CT 08-
05/RP 06-03A/CDP 06-09A, as to its completeness for processing.
The application is incomplete, as submitted. The attached list includes
information that must be submitted to complete your application. This list of
items must be submitted directly to the Housing & Redevelopment Office.
All list items must be submitted simultaneously and a copy of this list must
be included with your submittal. No processing of your application can occur
until the application Is determined to be complete. When all required materials
are submitted to the Redevelopment Office, the City has an additional thirty (30)
days to make a determination of completeness. If the application is determined
to be complete, processing for a decision on the application will be Initiated. In
addition, please note that you have six months from the date the applrcation was
initially filed, August 11, 2008, to either resubmit the application or submit the
required information. Failure to resubmit the application or to submit the
materials necessary to determine your application complete shall be deemed to
constitute withdrawal of the application. If an application is withdrawn or deemed
withdrawn, a new application must be submitted.
Please contact my office at (760) 434-2813, if you have any questions or wish to
set up a meeting to discuss the application.
Sincerely,
Austin Silva
Assistant Planner
Tecla Levy, Engineering
Debbie Fountain, Housing and Redevelopment Director
Rick Woolsley, Richard and Richard Construction
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2397 • (760) 434-2810/2811 • FAX (760) 720-2037 @
Roosevelt Center
08/27/2008
Page 2 of3
LIST OF ITEMS NEEDED
TO COMPLETE THE APPLICATION
No. CT 08-05/RP 06-03A/CDP 06-09A
Staff has completed a review of the subject project for application completeness.
The applications and plans submitted for this project are incomplete at this time.
Please resubmit sets of plans addressing the foitowing incomplete items:
Engineering:
Incomplete Items:
1. Please provide an updated preliminary title report that reflects the (Certificate
of Compliance for Adjustment Plat Doc. 2007-0723613 dated Nov. 16, 2007
and the new APN No. 203-292-22.
2. Please revise the site plan to agree with DWG 452-5A, including the
proposed plan changes currently in process with the City.
3. Please comply with Development Services Policy Directive No. 2: 'A separate
water service shall be provided to each separate ownership unit within any
proposed building structure unless specifically approved othenA/lse by the
District Engineer or designated representative'. The applicant may request a
waiver of the Policy Directive No. 2
4. If a waiver of Directive No. 2 is approved by the City Engineer, the design and
operation of the proposed water system shall comply with the following.
A. Sub-meters may be installed for portions of this project. The sub-meters
shall be privately owned and maintained by the Property Owners
Association (POA) or Operator of this facility. It shall be the responsibility
of the POA/Operator to apportion the water bill to the separate sub-
metered ownership within each building served by a City water meter.
B. Prior to issuance of building permits for this project, the owner shall create
an impound account to be funded with an amount equal to an estimated
three months of water bill payments for the entire pnDject.
C. Owners and tenants of the units shall be notified that the City may shutoff
water service to the entire building if adequate payment of the water bill is
not made.
D. The project CC&R shall include wording satisfactory to the City Engineer
relating to the provisions of conditions a), b) and c) above. The CC&Rs
shall also include language stating that the CC&R provisions related to
Roosevelt Center
08/27/2008
Page 3 of 3
water meters cannot be changed without the approval of the City
Engineer.
5. Developer will be required submit to the City Engineer CC&R's and/or other
recorded document, addressing the maintenance, repair, and replacement of
shared private improvements within this subdivision, and to distribute the
costs of such maintenance in an equitable manner among the owners of the
properties within this subdivision.
Enclosed is a redlined check-print of the project. This check print must be
returned with the revised plans to facilitate continued staff review. If you
have any questions regarding Engineering items, please contact Tecla Levy at
(760) 602-2733.
City of Carlsbad
ENGINEERING DEVELOPMENT SERVICES
MEMORANDUM
August 21, 2008
TO: Austin Silva, Housing and Redevelopment
FROM: Tecla Levy, Engineering
SUBJECT: RP 06-03(A); CDP 06-09(A); CT 08-05 ROOSEVELT CENTER
APN 203-292-22
Engineering Department staff has completed the first review ofthe application submittal
documents for application completeness. The application and plans submitted for this
project are complete. Prior to next submittal, it is suggested the following items are
adequately addressed.
Engineering Concerns:
General
1. Please provide an updated preliminary title report that reflects the Certificate of
Compliance for Adjustment Plat Doc. 2007-0723613 dated Nov. 16, 2007 and the
new APN No. 203-292-22.
2. Please revise the site plan to agree with DWG 452-5A, including the proposed
plan changes currently in process with the City.
3. Please comply with Development Services Policy Directive No. 2: 'A separate
water service shall be provided to each separate ownership unit within any
proposed building structure unless specifically approved otherwise by the District
Engineer or designated representative'. The applicant may request a waiver of
the Policy Directive No. 2
4. If a waiver of Directive No. 2 is approved by the City Engineer, the design and
operation of the proposed water system shall comply with the following.
A. Sub-meters may be installed for portions of this project. The sub-meters
. shall be privately owned and maintained by the Property Owners
Association (POA) or Operator of this facility. It shall be the responsibility
of the POA/Operator to apportion the water bill to the separate sub-
metered ownership within each building served by a City water meter.
RP 06-03(A); CDP Oe-oJP^; CT 08-05 ROOSEVELT CENTEI
August 22, 2008
Page 2 of 2
B. Prior to issuance of building permits for this project, the owner shall
create an impound account to be funded with an amount equal to an
estimated three months of water bill payments for the entire project.
C. Owners and tenants of the units shall be notified that the City may shutoff
water service to the entire building if adequate payment of the water bill
is not made.
D. The project CC&R shall include wording satisfactory to the City Engineer
relating to the provisions of conditions a), b) and c) above. The CC&Rs shall
also include language stating that the CC&R provisions related to water
meters cannot be changed without the approval of the City Engineer.
5. Developer will be required submit to the City Engineer CC&R's and/or other
recorded document, addressing the maintenance, repair, and replacement of
shared private improvements within this subdivision, and to distribute the costs
of such maintenance in an equitable manner among the owners of the properties
within this subdivision.
Enclosed is a redlined check-print of the project. This check print must be returned
with the revised plans to facilitate continued staff review. If you have any
questions, please call me at telephone (760) 602-2733.
Attachment
Red-lined Site Plan.
SDGc San Diego Gas & Electric
571 Enterprise Street
tscondido, CA 92029-1244
A Sempra Energy utility'
Project #745835-010
July 10,2008
City of Carisbad
1635 Faraday Avenue
Carisbad, CA 92008-7314
Subject: Roosevelt Street Center - 560 Carisbad Village Dr.
Gentlemen:
The above project will be supplied with electric meters based on the following
information:
• Suites: 100, 101, 103, 200. 201, 202, 203, 204 (commercial)
• Suites: 300 & 301 (residential)
Unit 103 is the only commercial suite with a gas meter. The two residential
suites will both have gas meters.
Should you have any questions, please do not hesitate to call me.
Sinc^ly. ^-N /^u
Mich'fete'laJeune|s^^
Senior Customer Project Planner
760-480-7651