HomeMy WebLinkAboutSDU 02-25; King Guest Unit; Second Dwelling Unit (SDU) (7).-
TO:
FROM:
DATE:
SUBJECT:
CHRIS SEXTON-PLANNING TECHNICIAN
Joanne Juchniewicz, Engineering Technician
April 9,2003
SDU 02-25; KING GUEST UNIT
COMPLETENESS REVIEW
The Engineering Department has completed its review of the above referenced project for
application completeness and has determined that the application and plans submitted for this
project are complete and suitable for continued review. Engineering staff does not have any
comments to add to the project. Please add the following conditions of approval to the approving
resolution:
1. Prior to building permit issuance, developer shall cause property owner to dedicate
10’ of frontage for future road widening. A copy of current Title Report and
processing fee will be required.
2. Prior to building permit issuance, developer shall cause property owner to enter into a
Neighborhood Improvement Agreement with the City for the future public improvement
of Laguna Drive along the property frontage for a half street width of 30 feet. Public
improvements shall include but are not limited to paving, base, sidewalks, curb and
gutter, grading, clearing and grubbing, under grounding or relocation of utilities, sewer,
water, fire hydrants, street lights and retaining walls. A copy of current Title Report and
processing fee will be required.
4. The developer shall pay all current fees and deposits required.
If you or the applicant has any questions, please either see or contact me at 602-2775.