HomeMy WebLinkAboutSDU 99-29; Centerstone at Tamarack Lot 2; Second Dwelling Unit (SDU) (7)TO: Assistant Planner, Paul Goodwin
FROM: Associate Engineer, Clyde Wickham
DATE: July 27, 1999
RE: SDU 99 - 29: Centerstone 2"d Dwelling Permit
Engineering Department staff has completed a review of the above-referenced project for
application completeness. The application and plans submitted for this proposed project
are from an Engineering standpoint considered complete. Additionally, staff has conducted
a review of the project for engineering issues of concern. Engineering issues have been
addressed as part of the Final Map and development plan process. We have no conditions
to add at this time. We support the application as submitted
If you or the applicant have any questions, please contact me at extension 4353.
n
Asskiate Engineer
Land Development Division
c: Bob Wojcik
Principal Civil Engineer, Land Development Division