HomeMy WebLinkAbout; As-Graded Report North Comml Pad Golf Course; As-Graded Report North Comml Pad Golf Course; 2008-02-28AS-GRADED REPORT OF ROUGH GRADING FOR THE NORTH COMMERCIAL
PAD AND CONSTRUCTION OF THE CRIBLOCK RETAINING WALL,
CARLSBAD MUNICIPAL GOLF COURSE, CARLSBAD, CALIFORNIA
Prepared for:
CITY OF CARLSBAD
c/o Dudek Engineering and Environmental
1645 South Rancho Santa Fe Road, Suite 202
San Marcos, California 92078
Project No. 841363-009
February 28, 2008
' 1 Leighton and Associates, inc.
I A LEIGHTON GROUP COMPANY
Leighton and Associates, Inc.
A LEIGHTON GROUP COMPANY
February 28, 2008
Project No. 841363-001
To: City of Carlsbad
c/o Dudek Engineering and Environmental
1645 South Rancho Santa Fe Road, Suite 202
San Marcos Califomia 92078
Attention: Mr. George Litzinger
Subject: As-Graded Report of Rough Grading for the North Commercial Pad and
Construction of the Criblock Retaining Wall, Carlsbad Municipal Golf Course,
Carlsbad, Califomia
hi accordance with the request and authorization of representatives of the City of Carlsbad, we have
performed geologic observation and documentation services during the rough grading of the north
commercial pad and geotechnical observation and testing services during the constmction activities
for the Criblock retammg wall at the Carlsbad Municipal Golf Course project in located in
Carlsbad, Califomia. The accompanying report summarizes our geologic and geotechnical
observations, field and laboratory test results, and the geotechnical conditions encountered during
the grading and/or construction operations for the north commercial pad and the associated
Criblock retaining wall, hi addition, the accompanying report presents our geotechnical conclusions
and preliminary recommendations concerning the future commercial development on the north
commercial pad.
The gradmg and constmction operations for the north commercial pad and the associated Criblock
retaining wall were performed in general accordance with the project geotechnical reports
(Appendix A), geotechnical recommendations made during grading, and the City of Carlsbad
requirements. As of the date of this report, the rough grading and constmction operations for the
north commercial pad are essentially complete. It should be noted that a site specific geotechnical
investigation should be performed for any proposed future development on the pad.
3934 Murphy Canyon Road, Suite B205 a San Diego, CA 92123-4425
858.292.8030 a Fax 858.292.0771
841363-009
If you have any questions regarding our report, please contact this office. We appreciate this
opportunity to be of service.
Respectfully submitted,
LEIGHTON AND ASSOCIATES, INC.
William D. Olson, RCE 45283
Associate Engineer
Randall K. Wagner
Principal Geologist
n—
r, qEG 1612
Distribution: (4) Addressee
Leighton
I 841363-009
TABLE OF CONTENTS
Page
l.OINTRODUCnON ^
1.1 PROJECT DESCRIPTION ^
2.0 SUMMARY OF GRADING AND CONSTRUCTION OPERATIONS 4
2.1 SITE PREPARATION AND REMOVALS 4
2.2 FILL SLOPE KEY 5
2.3 SUBDRAINS 5
2.4 FILL PLACEMENT AND COMPACTION 5
2.5 FIELD DENSITY TESTING s
2.6 LABORATORY TESTING 6
3.0 ENGINEERING GEOLOGIC SUMMARY 7
3.1 AS-GRADED GEOLOGIC CONDITIONS 7
3.2 GEOLOGIC UNITS 7
3.2.1 Previously-Placed Artificial Fill (Unmapped) 7
3.2.2 Topsoil (Unmapped) 7
3.2.3 Colluvium (Unmapped) 8
3.2.4 Santiago Formation (Map Symbol-Tsa) 8
3.3 GEOLOGIC STRUCTURE s
3.4 FAULTING !!!!!!!!!!!!!!!!!!!!!!!!! s
3.5 sasMicHY 9
3.6 GROUNDWATER """I."!"!!!!!!."!."!!.""!!!!.!."!!!!!!!!!]9
3.7 EXPANSION AND SULFATE CONTENT TESTING OF REPRESENTATIVE FINISH GRADE Soi'LS.'.'...'.."..".".".. 'io
4.0 CONCLUSIONS
5.0 RECOMMENDATIONS
5.1 ADDITIONAL GEOTECHNICAL INVESTIGATION 13
5.2 EXCAVATIONS 13
5.3 FILL PLACEMENT AND COMPACTION 13
5.4 SUBDRAIN OUTLET MAINTENANCE 14
5.5 SLOPE MAINTENANCE GUIDELINES 14
5.6 CONSTRUCTION OBSERVATION AND TESTING 15
6.0 QMITAnONS jg
Leighton
841363-009
TABLE OF CONTENTS rContinued^
FIGURE
FIGURE 1 - SITE LOCATION MAP - PAGE 2
PLATES
PLATE 1 - AS-GRADED GEOTECHNICAL MAP - IN POCKET
PLATES 2 AND 3 - CRIBLOCK WALL DENSITY TEST LOCATION MAP - IN POCKET
APPENDICES
APPENDIX A - REFERENCES
APPENDIX B - SUMMARY OF FIELD DENSITY TESTS
APPENDIX C - LABORATORY TESTING PROCEDURES AND TEST RESULTS
APPENDIX D - COMMERCIAL PAD COMPACTION TESTING REPORT BY TESTING ENGINEERS
APPENDIX E - GENERAL EARTHWORK AND GRADING SPECIFICATIONS
Leighton
841363-009
1.0 INTRODUCTION
hi accordance with the request and authorization of representatives of the City of Carlsbad, we have
performed geologic observation and documentation services during the rough grading of the north
commercial pad and geotechnical observation and testing services during the constmction activities
for the Criblock retaming wall at the Carlsbad Municipal Golf Course located m Carlsbad,
Califomia (Figure 1). This as-graded report summarizes our geologic and geotechnical
observations, geologic mapping, field and laboratory test results, and the geotechnical conditions
encountered during the course of our services for the project.
Based on the contract for the development of the Carlsbad Municipal Golf Course, Leighton
performed the duties of the geologic/geotechnical consultant of record while Testing Engineers
performed the all of the geotechnical services associated with the fill placement and compaction
operations. The only exception was that Leighton performed all of the geotechnical services related
to the constmction of the Criblock retainmg wall which included observation and testmg of the
retaining wall backfill.
As of this date, the grading activities for the north commercial pad are essentially complete.
However, the site is only sheet-graded and will still need to be fine graded in order to constmct the
future proposed commercial building pad(s), driveways/parking areas, and other anticipate site
improvements, hi addition, it should be noted that a site specific geotechnical investigation should
also be performed for any proposed future development (i.e., the design and constmction of
buildings and other site improvements) of the site as indicated in Section 5.0.
The grading plans and Criblock retaining wall constmction plans for the project, prepared by P&D
Consultants and Retaming Walls Company North, respectively, were utilized as the base maps to
present the as-graded geologic/geotechnical conditions and approximate locations of the field
density tests associated with the constmction of the retaining wall. The As-Graded Geotechnical
Map (Plate 1) and the Criblock Wall Density Test Location Map (Plates 2 and 3) are presented in
the pocket at the rear of the text.
1.1 Project Description
The Carlsbad Municipal Golf Course is bounded by Palomar Airport Road on the south.
Hidden Valley Road and the Grand Pacific Carisbad Resort on the west, Faraday Avenue
on the north, and the Palomar Airport and Business Park on the east in Carlsbad,
Califomia. College Boulevard bisects the golf course in an approximately southwest to
northeast direction. The subject site (i.e. the north commercial pad) is located on the
eastern side of the golf course and north of College Boulevard as indicated on Figure 1.
^ Leighton
Carlsbad Municipal
Golf Course
Carlsbad, California
SITE LOCATION
MAP
Project No.
841363-009
Date
February 2008 Figure 1
841363-009
Based on the project grading plans, the proposed grade of commercial pad ranges fi-om
approximately 257 feet mean sea level (msl) at the southwest comer of the pad to 266 feet
msl in the eastem portion of the pad. The original topography ranged from approximately
190 feet msl along the northwest side of the pad to approximately 310 feet msl in the
southwestern portion of the pad. In order to increase the size of the pad, a relatively large
fill slope (up to approximately 140 feet in height) and a Criblock retaining wall were
constmcted along the north side of the pad. The slope was constmcted at a 2:1 (horizontal
to vertical) slope inclination with 3 benches. The upper part of the slope was replaced
with a Criblock retaining wall that was approximately 1,325 feet in length and ranged
from approximately 20 to 40 feet in height. However, due to the recommended minimum
embedment depth of 5 to 10 feet, the exposed height of the retaining wall ranged from
approximately 15 to 30 feet.
-3-
Leighton
841363-009
2.0 SUMMARY OF GRADING AND CONSTRUCTION OPERATIONS
The grading operations for the north commercial pad were performed by SEMA Constmction
between November 2005 and June 2006. The grading operations, prior to constmction of the
Criblock retaming wall, were geologically observed and documented by Leighton while the fill
placement and compaction operations were observed and tested by Testing Engineers (TE, 2007).
Documentation related to Testing Engineers' observations and testing is presented in Appendix D of
this report, hi summary, during the rough grading operations. Testing Engineers' field technicians
were on site full-time durmg the grading operations while a Leighton field and/or project geologist
were on site on a periodic basis. During the Criblock retaining wall constmction operations, a
Leighton field technician was on site fiill time during the retaining wall backfill and compaction
operations.
Grading of the site included: 1) the removal of potentially compressible desiccated previously
placed artificial fill soils, topsoil, colluvium, and weathered formational material; 2) the excavation
of a fill slope key; 3) preparation of areas to receive fill; 4) the placement of canyon and retaining
wall subdrains; 5) excavation of formational material; 6) the placement of retaining wall backfill,
and 7) the placement of compacted fill soils. Up to approximately 50 feet of cut was excavated and
a maxunum of approximately 80 vertical feet of fill was placed within the grading limits of the site.
The as-graded geotechnical conditions are presented on the As-Graded Geotechnical Map (Plate 1).
2.1 Site Preparation and Removals
Prior to gradmg, the area was stripped of surface vegetation and debris and disposed of off
site. Removals of unsuitable and potentially compressible soils (including desiccated
previously placed artificial fill soils [associated with the constmction of College
Boulevard], topsoil, colluvium, and weathered formational material) were made to
competent material. The removals of potentially compressible material were performed in
accordance with the recommendations of the project geotechnical report (Appendix A) and
geotechnical recommendations made durmg the course of grading. Specifically, removals of
the potentially compressible material included approximately 2 to 20 feet of desiccated fill
soils, topsoil, colluvium, and weathered formational material.
After the removals were made, the removal bottoms and/or areas flatter than 5:1 (horizontal
to vertical) were scarified a nummum of 12 mches. The steeper natural hillsides were
benched mto competent material as fill was placed. Representative bottom elevations in the
removal areas are shown on the As-Graded Geotechnical Map (Plate 1).
Due to the need to utilize low expansive granular soils as the backfill soils within the
Criblock retaining wall cells, the western portion of the north commercial pad was used as a
borrow site. We understand that some fill soils have been placed in the borrow area;
-4-
Leighton
841363-009
however, the area was left low (i.e. the existmg grades are lower than the proposed pad
grade elevations shown on the grading plans).
2.2 Fill Slope Key
Prior to the placement of the fill slope along tiie north side of the commercial pad, a fill
slope key was constiiicted. The fill slope key was excavated at least 2 feet into competent
formational soil along the toe-of slope and constioicted a minimum of 15 feet wide with the
key bottom angled at least 2 percent into-the-slope.
2.3 Subdrains
Canyon and retaining wall subdrains were placed under the observation of a representative
of Leighton during grading and tiie Criblock retaining wall constiiiction operations. After
the potentially compressible material m the tiibutary canyons were removed to competent
formational material or when compacted fill was placed over competent material to obtain
flow to a suitable outiet location, a subdrain was installed along tiie canyon bottom. The
canyon subdrains consisted of a 6-inch diameter perforated pipe surrounded by a minimum
of 9-cubic feet (per linear foot) of cmshed 3/4-inch gravel wrapped m Mirafi 140N filter
fabric.
A retaining wall subdrain system consisting of two subdrams was installed behind the
Criblock retaining wall. The first subdrain was installed directly behind the lowest-most
Criblock member at the back of the retainmg wall while the second subdrain was placed
along the bottom of the wall backcut which was at least 10 to 15 feet behind the back of the
Criblock wall. The retaining wall subdrains consisted of a 4-inch diameter perforated pipe
surrounded by a minimum of 3-cubic feet (per linear foot) of cmshed 3/4-inch gravel
wrapped in Mirafi MON filter fabric. The location of the subdrains placed during the
grading and retainmg wall constmction operations were surveyed by the project civil
engmeer. The approximate subdrain locations presented on tiie As-Graded Geotechnical
Map (Plate 1).
2.4 Fill Placement and Compaction
As discussed above. Testing Engineers observed and tested tiie compacted fill placed during
tiie rough gradmg operations (TE, 2007). These areas included the large north-facing fill
slope, the area beneath tiie Criblock retaining wall, and the fills associated with tiie
commercial pad. A summary of tiiese observations and testmg services are presented in tiie
Commercial Pad Compaction Testing Report presented in Appendix D.
Subsequent to tiie rough grading operations, Leighton performed observation and testing
services associated witii the Criblock retaining wall subgrade foundation, backfilling of tiie
Leighton
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
841363-009
Criblock retaining wall cells, and placement of the compacted fill behind the Criblock
retaining wall stmcture. In general, the fill was generally spread in 4- to 8-inch loose lifts;
moisture conditioned as needed to attain near-optimum moisture content, and compacted
with either heavy-duty constmction equipment and/or hand operated compaction
equipment. Field density test results performed during the grading operations indicated the
fill soils were compacted to at least 90 or 95 percent of the maximum dry density in
accordance with ASTM Test Method D1557, as required.
As recommended in the project geotechnical documents (Appendix A), the fill soils
comprising the large north-facing fill slope including tiie area beneath the Criblock retaining
wall were compacted to a minimum 95 percent relative compaction (in accordance with
ASTM Test Metiiod D1557) while the fill soils on the pad and the retaining backfill soils
were compacted to a minimum 90 percent relative compaction. Areas of fill in which field
density tests indicated compactions less than the recommended relative compaction or
where the soils exhibited nonuniformity or had field moisture contents less than
approximately 2 to 3 percent below the laboratory optimum moisture content, were
reworked. The reworked areas were recompacted, and re-tested until the recommended
minunum 90 or 95 percent relative compaction and near-optimum moisture content was
achieved.
2.5 Field Densitv Testing
Field density testing was performed using tiie Nuclear-Gauge Metiiod (ASTM Test
Metiiods D2922 and D3017). The approximate test locations are shown on the As-Graded
Geotechnical Map (Plate 1) and Criblock Wall Density Test Location Map (Plates 2 and 3).
The results of the field density tests are summarized in Appendix B. The field density
testmg was performed in general accordance witii the applicable ASTM Standards, the
current standard of care in the industry, and the precision of the testing method itself
Variations in relative compaction should be expected fi-om the results documented herein.
2.6 Laboratory Testing
Laboratory maximum dry density tests of representative on-site soils were performed in
general accordance with ASTM Test Method D1557. Laboratory tests were also performed
to evaluate the fill soil gradation and plastic mdex properties. The laboratory test results are
presented in Appendix C.
Leighton
841363-009
3.0 ENGINEERING GEOLOGIC SUMMARY
3.1 As-Graded Geologic Conditions
The geologic and/or geotechnical conditions encountered during the rough grading and
Criblock retaining wall constmction operations were essentially as anticipated. A
comprehensive summary of tiie geologic conditions (including geologic units, geologic
stmctiire, and faulting) is presented below. The as-graded geologic conditions are presented
on the As-Graded Geotechnical Map (Plate 1).
3.2 Geologic Units
The geologic units encountered during the rough grading of the north commercial pad
consisted of previously placed artificial fill soils, topsoil, colluvium, and the Santiago
Formation. Due to tiie potentially compressible natiire of tiie desiccated fill soils, topsoil,
colluvium, and weathered formational material, these soils were removed to competent
material during the rough grading operations.
The approxunate limits of tiie as-graded geologic units encountered during the grading
operations are presented on tiie As-Graded Geotechnical Map (Plate 1) and discussed
(youngest to oldest) below.
3.2.1 Previously-Placed Artificial Fill ^Unmapped)
Previously-placed artificial fill associated with tiie constiiiction of College
Boulevard was encountered in the soutii eastem portion of the site. The upper 1 to 2
feet of tiie fill was found to be desiccated and was removed prior to the placement of
additional fill.
3.2.2 Topsoil (Unmapped)
A relatively thm veneer of topsoil was removed from the majority of the site. The
topsoil, as encountered, consisted predominately of a brown, damp to moist, loose,
sandy clay and mmor clayey to silty sand. The topsoil was generally massive,
porous, and contained scattered roots and organics. Topsoil removal thicknesses
were on the order 1 to 4 feet thick. During the gradmg operations, tiie topsoil was
observed to have been removed within the limits of grading.
Leighton
841363-009
3.2.3 Colluvium (Unmapped)
Colluvium was encountered during the rough grading in the two tributary canyons
and on the lower portion of the hillside near the bottom of the large north-facing
fill slope. As encountered, the colluvium consisted of dark brown, moist, loose to
stiff, clayey sand, sandy clay, and silty sand. Where encountered, the colluvium
was removed to competent material. Up to approximately 20 feet of colluvium
was removed during the rough grading operations.
3.2.4 Santiago Formation fMap Svmbol-Tsal
The Tertiary-aged Santiago Formation, as encountered during the rough grading
operations, consisted primarily of a massively bedded sandstone with minor
interbedded siftstones. The sandstone generally consisted of orange-brown (iron
oxide staining) to light brown, damp to moist, dense to very dense, silty very fine to
medium grained sandstone. The siltstone interbeds were generally olive-brown,
damp to moist, stiff to hard, and occasionally fractured and moderately sheared.
3.3 Geologic Structure
The general stioicture of tiie formational material appears to be near horizontal. Based on
our geologic mapping during the rough grading operations relative to tiie north commercial
pad, bedding within the Santiago Formation generally exhibited somewhat variable bedding
with strikes ranging from northwest to north and dips typically 2 to 7 degrees (or less) to the
southwest and west.
Jointmg on-site was observed to be very variable, but predomuiantly tiended subparallel to
the existmg slopes. Jointing dips were found to be generally moderately to steeply dipping.
Jointmg was mamly encountered in tiie upper portion of the bedrock becoming less
pronounced with depth.
3.4 Faulting
hiactive normal faults that offset the Santiago Formation were identified during the
project geotechnical investigations (Appendix A). No evidence of any faulting was
encountered during the rough grading of the north commercial pad; however, inactive
faulting was encountered during the grading of the golf course in areas outside the limits
of the commercial pads.
-8-Leighton
841363-009
3.5 Seismicity
Our discussion of tiie seismicity of the site is prefaced witii a discussion of Califomia
legislation and state policies concemmg tiie classification and land-use criteria associated
with fauhs. By definition of tiie Califomia Mining and Geology Board, an active fault is a
fault that has had surface displacement witiiin Holocene time (about tiie last 11,000 years).
The State Geologist has defmed a potentially active fault as any fault considered to have
been active during Quatemary time (last 1,600,000 years) but that has not been proven to be
active or inactive. This defmition is used in delmeating Fault-Ruptiire Hazard Zones as
mandated by tiie Alquist-Priolo Earthquake Fault Zoning Act of 1972 and as most recently
revised in 2007. The intent of this act is to assure that unwise urban development does not
occur across the tiaces of active faults. Based on our review of tiie Fault-Rupture Hazard
Zones, the site is not located within any Fault-Rupttire Hazard Zone as created by the
Alquist-Priolo Act (Bryant and Hart, 2007).
San Diego, like the rest of soutiiem Califomia, is seismically active as a resuh of being
located near tiie active margin between the North American and Pacific tectonic plates. The
principal source of seismic activity is movement along tiie northwest-tiending regional fault
zones such as tiie San Andreas, San Jacinto and Elsinore Faults Zones, as well as along less
active faults such as the Rose Canyon Fault Zone.
The nearest known active fault is tiie Rose Canyon Fault Zone, which is located
approximately 5.7 miles (9.2 kilometers) west of the site, and has a Site Classification of C
based on tiie 2007 Califomia Building Code (CBC). Because of the lack of known active
faults on the site, tiie potential for surface mpttire at tiie site is considered low. Shallow
ground mpttire due to shaking from distant seismic events is not considered a significant
hazard, although it is a possibility at any site.
Liquefaction and dynamic settlement of soils can be caused by strong vibratory motion
due to earthquakes. Both research and historical data indicate that loose, saturated,
granular soils are susceptible to liquefaction and dynamic settlement. Liquefaction is
typified by a loss of shear strength in the affected soil layer, thereby causing the soil to act
as a viscous liquid. This effect may be manifested by excessive settlements and sand boils
at the ground surface. The fill and formational materials underiying the site are not
considered liquefiable due to their fine-grained nature, dense physical characteristics, and
unsaturated condition.
3.6 Ground Water
Ground water was not encountered during the rough grading or retaining wall constinction
operations. Since subdrains were installed in the tiibutaiy canyon bottoms and behind the
retaming wall, ground water conditions should not be a constiaint to fiiture development.
Leighton
841363-009
However, unanticipated seepage conditions may occur and steps to mitigate the seepage
should be made on a case-by-case basis.
3-7 Expansion and Sulfate Content Testing of Representative Finish Grade Soils
Expansion potential and soluble sulfate content tests were not performed on representative
fmish grade soils of the sheet-graded pad. However, we anticipate that the representative
finish grade soils have a very low to possibly medium expansion potential and have a
negligible to moderate soluble sulfate content per the Uniform Building Code criteria.
Additional laboratory testing is recommended to determine the actual expansion potential
and soluble sulfate content of the site.
-10- . ,
Leighton
841363-009
4.0 CONCLUSIONS
The rough gradmg and Criblock retaining wall backfill operations for tiie north commercial pad
were performed in general accordance with tiie project geotechnical reports (Appendix A),
geotechnical recommendations made during gradmg, and tiie City of Carlsbad requirements. The
following is a summary of our conclusions concemmg the grading and constiiiction operations.
• Geotechnical conditions encountered during gradmg were generally as anticipated.
• Site preparation and removals were geotechnically observed.
• The geologic units encountered during the rough grading of the site consisted of
artificial fill, topsoil, colluvium, and the Santiago Formation.
• Desiccated previously placed artificial fill soils and unsuitable topsoil, colluvium, and
weathered formational material were removed to competent material within the limits of
grading.
• Subdrains were placed in the tributary canyons and behind the Criblock retainmg wall.
The fill slope on the north side of tiie north commercial pad was constmcted witii a fill
slope key. The key was constiiicted a mmimum of 15 feet wide, excavated at least 2 feet
into competent material along tiie toe-of-slope and tiie bottom inclmed 2 percent into
the slope.
Fill soils were derived from on-site soils. Fills soils comprising tiie large north-facmg
fill slope including tiie area beneath tiie Criblock retaining wall were compacted to a
minimum 95 percent relative compaction (m accordance with ASTM Test Metiiod
D1557) while tiie fill soils on tiie pad and tiie retainmg backfill soils were compacted to
a muiimum 90 percent relative compaction.
Field density testing indicated tiiat the fill soils were placed and compacted to at least a
90 or 95 percent relative compaction (based on ASTM Test Method D1557) and near-
optimum moistijre contents in accordance witii tiie recommendations of Leighton and
Associates and tiie requirements of the City of Carlsbad. The results of the field density
tests performed by Leighton are summarized m Appendix B while the density tests
performed by Testuig Engineers is included in Appendix D.
The cut/fill ttansition condition present on tiie commercial pad was not mitigated during
tiie gradmg operations. Cut/fill transition conditions present witiiin the limits of any
proposed buildmgs should be mitigated by the overexcavation of the cut portion of tiie
building pad or by special foundation design. Additional subsurface evaluation will be
-11-
Leighton
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
841363-009
necessary to identify tiie location of the cut/fill ti-ansition and to develop design
recommendations for future site improvements or development.
No evidence of faulting was encountered during tiie rough grading operations for the
north commercial pad. However, minor uiactive faults were encountered during the
Carlsbad Golf Course gradmg outside the lunits of the commercial pads.
Ground water was not encountered during the rough grading or retaining wall
constmction operations.
Due to the dense nature of tiie onsite soils, it is our professional opmion tiiat the
liquefaction hazard at the site is considered low.
The expansion potential of representative finish grade soils of the sheet-graded pad was
not tested during site grading. However, very low to possibly medium expansive soils
should be anticipated. Further geotechnical investigation should be performed for tiie
futiire site development, and the representative fmish grade soils should be tested to
determine tiie actiial expansion potential of the soils.
The potential for soluble sulfate attack of the finish grade soils was not tested during site
grading. However, negligible to moderate soluble sulfate contents are anticipated. As
discussed above, further geotechnical mvestigation should be performed for the future
site development, and the representative finish grade soils should be tested to determine
tiie actiial potential for soluble sulfate attack of the soils.
It is our opmion that the slopes of tiie nortii commercial pad possess a static factor of
safety of at least 1.5 to resist deep-seated failure (under normal irrigation/precipitation
pattems), provided the recommendations in the project geotechnical reports are
mcorporated into the post-grading, constiiiction, and post-constiaiction phases of site
development.
Because the Criblock retaining wall was not designed to support additional loads (i.e.
loads other than the assumed level backfill zone behmd the retaining wall), a stmctural
setback is recommended and will limit the buildable area of the commercial pad. The
setback limit was determined by projecting a 1:1 (or 45-degree angle) from the bottom
back portion of the Criblock cell up to tiie proposed finish grade surface on the pad. The
setback limits are presented on the As-Graded Geotechnical Map (Plate 1).
-12- , . ,
Leighton
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
841363-009
5.0 RECOMMENDATIONS
5.1 Additional Geotechnical Investigation
We anticipate tiiat future development of tiie site will consist of site preparation, remedial
grading for tiie mitigation of cut/fill ttansitions, fme grading, utility trench excavation and
backfill, retaming wall backfill, and driveway and parking area pavement section
preparation and compaction. Based on the current as-graded condition of tiie site, we
recommend that a site specific geotechnical investigation be performed for any proposed
future development.
It should be noted that a stiaicttiral setback lunit is recommended for fiittire development of
tiie north commercial pad. The stmcttiral setback limit, rangmg from approximately 10 to 60
feet from top of slope (i.e. top of Criblock retaining wall) was determined by projecting a
1:1 (or 45-degree angle) from the bottom back portion of the Criblock retaining wall cells
up to the proposed fmish grade surface on tiie pad. Factors that determmed this setback was
the type of retaining wall, the location of Criblock wall foundation, tiie slope height, and tiie
type of soil used as backfill. It should be noted tiiat tiie setback zone may be revised by tiie
geotechnical consultant on a case-by-case basis if tiie geotechnical conditions are different
tiian anticipated. For planning purposes any improvement or additional load (such as
additional fill, placement of buildings, vehicle loading, etc.) on tiie retaining wall will need
to be evaluated and either kept out of the setback zone or founded below tiie 1:1 projection
Ime.
5.2 Excavations
Excavations of tiie on-site materials may generally be accomplished witii conventional
heavy-duty earthwork equipment. It is not anticipated tiiat blasting will be required or tiiat
significant quantities of oversized rock (i.e. rock with maximum dimensions greater tiian 8
inches) will be generated during fiitiire gradmg. However, localized cemented zones witiim
tiie cut areas may be encountered on tiie site tiiat may require heavy ripping and/or removal.
If oversized rock is encountered, it should be placed m accordance witii tiie
recommendations presented in Appendix E, hauled offsite, or placed in non-stiiicttiral or
landscape areas.
5.3 Fill Placement and Compaction
The on-site soils are generally suitable for use as compacted fill provided they are free or
organic material, debris, and rock fragments larger tiian 8 inches in maximum dimension.
We do not recommend tiiat high or very high expansive soils be utilized as fill for the
building pads or as retaining wall backfill.
-13-
Leighton
I
i
I
I
I
I
I
I
I
1
I
841363-009
All fill soils should be brought to 2-percent over the optunum moisture content and
compacted in uniform lifts to at least a 90 percent relative compaction based on the
laboratory maximum dry density (ASTM Test Metiiod D1557). The optimum lift tiiickness
required to produce a uniformly compacted fill will depend on the type and size of
compaction equipment used, hi general, fill should be placed in lifts not exceedmg 8 inches
in compacted thickness. Placement and compaction of fill should be performed in general
accordance with Appendix E, the current City of Carlsbad grading ordinances, sound
constmction practices, and the geotechnical recommendations presented herein.
5.4 Subdrain Outlet Maintenance
The approximate location of the subdrains and subdrain outlets constmcted during tiie
rough grading operations are identified on the As-Graded Geotechnical Map (Plate 1). All
subdrain outiets should be periodically cleared of soil cover or otiier potential blockage that
may have occurred smce initial subdrain constmction. In open space areas, it is
recommended that the Property Owner or Management Company further maintain these
outiets, as well as retaining wall drainage outiets to prevent further blockage.
5.5 Slope Maintenance Guidelines
ft is the responsibility of the owner to maintain the slopes, including adequate planting,
proper irrigation and maintenance, and repair of faulty irrigation systems. To reduce the
potential for erosion and slumping of graded slopes, all slopes should be planted with
ground cover, shmbs, and plants that develop dense, deep root stmctures and require
minimal irrigation. Slope planting should be carried out as soon as practical upon
completion of grading. Surface-water runoff and standing water at the top-of slopes
should be avoided.
Oversteepening of slopes should be avoided during constmction activities and
landscaping. Maintenance of proper lot drainage, undertaking of property improvements
in accordance with sound engineering practices, and proper maintenance of vegetation,
including regular slope irrigation, should be performed. Slope irrigation sprinklers should
be adjusted to provide maximum uniform coverage with minimal of water usage and
overlap. Overwatering and consequent runoff and ground sattiration should be avoided. If
automatic sprinklers systems are installed, their use must be adjusted to account for
rainfall conditions.
Trenches excavated on a slope face for any purpose should be property backfilled and
compacted in order to obtain a minimum of 90 percent relative compaction, in accordance
with ASTM Test Method D1557. Observation/testing and acceptance by the geotechnical
consuftant during trench backfill is recommended. A rodent-control program should be
-14-
Leighton
I
I
I
I
I
I
I
841363-009
established and maintained. Prior to planting, recentiy graded slopes should be
temporarily protected against erosion resulting from rainfall, by the implementing slope
protection measures such as polymer covering, jute mesh, etc.
5.6 Construction Observation and Testing
Constiiiction observation and testing should be performed by the geotechnical consultant
during futtire gradmg operations or excavations and foundation or retaining wall
constiiiction. Additionally, footmg excavations should be observed and moisttire
determination tests of subgrade soils should be performed by tiie geotechnical consultant
prior to tiie pouring of concrete. Fme grade and foundation plans should also be reviewed by
the geotechnical consultant prior to site development.
-15-
Leighton
I
841363-009
6.0 LIMFTATIONS
The presence of our field representative at the site was intended to provide tiie owner with
professional advice, opinions, and recommendations based on observations of tiie contractor's
work. Altiiough the observations did not reveal obvious deficiencies or deviations from project
specifications, we do not guarantee the contractor's work, nor do our services relieve the contractor
or his subcontiactor's work, nor do our services relieve tiie contractor or his subcontiactors of their
responsibility if defects are subsequentiy discovered in their work. Our responsibilities did not
include any supervision or direction of the actual work procedures of tiie confractor, his personnel,
or subcontractors. The conclusions in this report are based on test resufts and observations of the
grading and earthwork procedures used and represent our engineering opinion as to the compliance
of the results with the project specifications.
-16-
Leighton
841363-009
APPENDIX A
References
Bryant, W.A., and Hart E.W., 2007, Special Publication 42, Fauft Rupttire Hazard Zones in
Califomia, Alquist-Priolo Earthquake Fautt Zoning Act witii hidex to Earthquake Fault
Zone Maps, Interim Revision 2007.
Califomia Building Standards Commission (CBSC), 2007 Califomia Building Code, Based on
2006 Intemational Building Code.
Califomia Geological Survey (CGS) formally Califomia Division of Mines and Geology
(CDMG), 1996a, Geologic Maps of the Northwestem Part of San Diego County,
Califomia, CDMG Open-File Report 96-02, Plate 1, Geologic Map of the Oceanside, San
Luis Rey, and San Marcos 7.5' Quadrangles, San Diego County, Califomia, Scale
1:24,000.
, 1998, Maps of Knovra Active Fault Near-Source Zones in Califomia and Adjacent
Portions of Nevada, to be used with the 1997 Uniform Building Code, Intemational
Conference of Building Officials, dated Febmary 1998.
Dudek, 2005, Grading Plans for Special Exhibit Drawing, Carlsbad Municipal Golf Course Phase
2, Carlsbad, Califomia, Drawing No. 381-4A, Sheet 18 of 46, dated October 6, 2005.
Leighton and Associates, hic, 1998, Geotechnical Investigation for the Proposed Carlsbad
Municipal Golf Course, Carlsbad, Califomia, Project No. 841363-006, dated Febmaiy 16
1998.
, 2005a, Geotechnical Review of Criblock Retaining Wall Plan and Calculations,
Carlsbad Municipal Golf Course, Carlsbad, Califomia, Project No. 841363-009, dated
November 18, 2005, revised November 29,2005.
, 2005b, Summary of Geotechnical Conditions Related to Criblock Retaining Wall of
the Commercial Pad and North Facing Fill Slope North of College Boulevard, Carlsbad
Municipal Golf Course, Carlsbad, Califomia, Project No. 841363-009, dated December 14
2005.
—, 2005c, Second Geotechnical Review of Criblock Retammg Wall Plan and
Calculations, Carlsbad Municipal Golf Course, Carlsbad, Califomia, Project No. 841363-
009, dated December 28,2005.
A-i
841363-009
APPENDIX A (Continued)
, 2006a, Thkd Geotechnical Review of Criblock Retaining Wall Plan and Calculations,
Carlsbad, Municipal Golf Course, Califomia, Project No. 841363-009, dated January 5'
2006.
2006b, Addendum Remedial Grading Recommendations Concerning the Backfill
Behind the Western Portion of the Criblock Retaining Wall Project Memorandum, Carlsbad
Municipal Golf Course, Carlsbad, Califomia, Project No. 841363-009, dated May 5, 2006.
, Undated, Unpublished In-House Geotechnical Data.
P&D Consultants, 2005, Grading Plans for Carlsbad Municipal Golf Course Phase 2, Carlsbad,
Califomia, Drawing No. 381-4A, 99 Sheets, dated April 15, 2005.
Retaining Walls Company North, 2005, Cribwall Plans, Carlsbad Municipal Golf Course,
Carlsbad, Califomia, Job No. 05-03-07, dated December 5, 2005.
Tan, S.S., and Kennedy, M.P., 1996, Geologic Maps of the Northwestem Part of San Diego
County, Califomia: Califomia Division of Mines and Geology, DMG Open-File Report 96-
02, 2 Plates.
Tan, S.S., and Giffen, D.G., 1995, Landslide Hazards in the Nortiiem Part of tiie San Diego
Mefropolitan Area, San Diego County, California, Landslide Hazard Identification Map No.
35, Division of Mines and Geology, Open-File Report No. 95-04.
Testing Engineers San Diego, hic. (TE), 2007, Supplemental Compaction Testing Report, Carlsbad
Municipal Golf Course, Carlsbad, Califomia, Contract No. 108078, dated March 19
2007.
A-2
841363-009
APPENDIX B
Explanation of Summary of Field Densitv Tests
Test No. Test of
Prefix Test of Abbreviations
(none) GRADING
Natural Ground NG
Original Ground OG
Existing Fill EF
Compacted Fill CF
Slope Face SF
Finish Grade EG
(S) SEWER
(SO) STORM DRAIN
(AD) AREA DRAIN
(W) DOMESTIC WATER
(RC) RECLAIMED WATER
(SB) SUBDRAIN
(G) GAS
(E) •ELECTRICAL
(T) TELEPHONE
(J) JOINT UTILITY
(I) IRRIGATION
Bedding Material B
Shading Sand S
Main M
Lateral L
Crossmg X
Manhole MH
Hydrant Lateral HL
Catch Basin CB
Riser R
Inlet I
(RW) RETAINING WALL
(CW) CRIB WALL
(LW) LOFFELL WALL
(SF) STRUCT FOOTING
Footing Bottom F
Backfill B
-
Wall Cell C
Test No.
Prefix
(SG)
(AB)
(CB)
(PB)
(AC).
Test of
SUBGRADE
AGGREGATE BASE
CEMENT TREATED BASE
PROCESSED BASE
ASPHALT CONCRETE
Curb
Gutter
Curb and Gutter
Cross Gutter
Street
Sidewalk
Driveway
Driveway Approach
Parking Lot
Electric Box Pad
Test of
Abbreviations
(P)
(IT)
C
G
CG
XG
ST
SW
D
DA
PL
EB
PRESATURATION
Moisture Content
INTERIOR TRENCH
Plumbing Backfill
Electrical Backfill
M
N
S
15A
15B
"0"
represents nuclear gauge tests that were perforated in general accordance with most recent version of ASTM Test
Methods D2922 and D3 017.
represents sand cone tests that were performed in general accordance with most recent version of ASTM Test Method Dl 556
represents first retest of Test No. 15
represents second retest of Test No. 15
in Test Elevation Column represents test was taken at the ground surface (e.g. fmish grade or subgrade)
in Test Elevation Column represents test was taken one foot below the ground surface
B-1
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location Test Soil
Lot # Elev (ft) Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
27 6/7/06 CF N. Commercial Pad West Side
28 6/7/06 CF N. Commercial Pad West Side
29 6/7/06 CF . N. Commercial Pad West Side
30 6/7/06 CF N. Commercial Pad West Side
31 6/7/06 CF N. Commercial Pad West Side
32 6/7/06 CF N. Commercial Pad West Side
33 6/8/06 CF N. Commercial Pad West Side
34 6/8/06 CF N. Commercial Pad West Side
254.0 5 114.7 119.0 18.6 . 13.0 96
249.0 5 110.2 119.0 15.1 13,0 93
251.0 5 112,3 119.0 14,4 , 13.0 94
254.0 5 113.1 119.0 13.9 13.0 , 95
254.0 5 • 107.2 119.0 .14.9 13.0 90
255.0 5 111.7 119.0. 15:7 13.0 94
252.0 5 in.7 119.0 13.8 13.0 • 94
253.0 3 • ' 103.2 114.5 17.2 12.5 90
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0 Page 2 of2
3/9/2007 1 •:>9-17PM
Test
No.
SUMMARY OF FIELD DENSITY TESTS
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
CW 1 1/20/06 C Crib Wall #1 Cell #5 Station 9+70
CW • 2 1/20/06 C Crib Wall#l Cell #5 Station 10+10
CW 3 1/20/06 C Crib Wall #1 Cell #4 Station 9+65
CW 4 1/20/06 C Crib Wall #r Cell #4 Station 10+00
CW 5 1/20/06 C Crib Wall#l Cell #3 Station 9+79
CW 6 1/20/06 C Crib Wall #1 Cell #3 Station 10+17
CW 7 1/20/06 c Crib Wall #1 Cell #2 Station 9+75
CW 8 1/20/06 c Crib Wall #1 Cell #2 Station 9+92
CW 9 1/20/06 c Crib Wall#l Cell#l Station 9+72
CW 10 1/20/06 c Crib Wall#l Cell#l Station 10+10
CW 11 1/23/06 c Crib Wall#l Cell #5 Station 11+08
CW 12 1/23/06 c Crib Wall#l Cell #4 Station 11+23
CW 13 1/23/06 c Crib Wall #1 Cell #5 Station 11+40
CW 14 1/23/06 c Crib Wall #1 Cell #4 Station 11+60
CW 15 1/23/06 c Crib Wall #1 Cell #3 Station 11+30
CW 16 1/23/06 c Crib Wall #1 Cell #2 Station 11+20
CW 17 1/23/06 c Crib Wall#l Cell #3 Station 11+50
CW 18 1/23/06 c Crib Wall #1 Cell #2 Station 11+65
CW 19 1/23/06 c Crib Wall #1 Cell#l Station 11+15
CW 20 1/23/06 c Crib Wall#l Cell#l Station 11+50
CW 21 1/24/06 c Crib Wall #1 Cell #5 Station 9+60
CW 22 1/24/06 c Crib Wall #1 Cell #4 Station 9+85
CW 23 1/24/06 c Crib Wall #1 Cell #3 Station 9+75
CW 24 1/24/06 c Crib Wall#l Cell #2 Station 9+65
CW 25 1/24/06 c Crib Wall # I Cell#l Station 9+90
CW 26 1/24/06 c Crib Wall #1 Cell #4 Station 10+38
CW 27 1/24/06 c Crib Wall #1 Cell #3 Station 10+62
CW 28 1/24/06 c Crib Wall#l Cell #5 Station 10+85
CW 29 1/24/06 c Crib Wall #1 Cell #2 Station 10+50
CW 30 1/24/06 c Crib Wall#l Cell #1 Station 11+00
CW 31 1/24/06 c Crib Wall #1 Cell #3 Station 11 + 10
CW 32 1/24/06 c Crib Wall#l Cell #4 Station 11+43
Dry Density
Field Max
Moisture (%) Relative (%)
Field Opt. Compaction Remarks
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0 Page 1 of39
218.0 3 103.1 114,5 16.3 12,5 90
219.0 1 112.6 120,0 13,6 12,0 94
219.0 3 102.8 114,5 18,7 .12.5 90
220.0 1 112.1 120.0 14,4 12,0 93
219.0 3 102.9 114.5 21,1 12.5 90
220.0 1 111.4 120.0 12.2 12.0 93
220.0 3 103.1 1.14.5 18.9 12.5 90
221.0 1 112.0 .120,0 15.1 12,0 93
222.0 3 103,9 114,5 18.6 12,5 91
223.0 1 109.0 120,0 15,3 12,0 91
217.0 1 107,6 120.0 15.1 12,0 90
218.0 1 107.6 120.0 16,7 12,0 90
217.0 1 108,4 120,0 16.9 12,0 90
218.0 1 109.4 120.0 14,3 12,0 91
219.0 4 107.9 !I6,0 16,0 13,0 93
221.0 4 106.4 116.0 17,7 13,0 92
221.0 4. 107.1 • 116.0 16,9 13,0 92
222.0 1 108.5 120.0 14,6 12,0 90
222.0 4 107.5 116.0 16,4 13,0 93
221.0 1 108.4 120.0 13,9 12.0 90
218.0 4 108.0 116.0 15,8 13.0 93
219.0 3 102,6 114,5 14,8 12,5 90
220.0 3 103.4 114,5 14.4 12.5 . 90
221.0 3 102.7 114,5 14,0 12.5 90
222.0 3 103.3 114.5 15,7 12.5 90
220.0 3 104.0 114,5 13,5 12.5 91
221.0 3 104.4 114,5 15.9 12,5 91
219.0 3 105,4 114,5 14.7 12,5 92
222.0 3 104.1 114.5 13.6 . 12.5 91 223.0 3 104,2 114.5 12,9 12.5 91 221.0 4 105.1 , 116.0 13,9 13,0 91 220.0 4 105.3 116,0 13,6 13.0 91
3/9/2007 1 -^snoPN/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 33
CW 34
CW 35
CW 36
CW 37
CW 38
CW 39
CW 40
CW 41
CW 42
CW 43
CW 44
CW 45
CW 46
CW 47
CW 48
CW 49
CW 50
CW 51
CW 52
CW 53
CW 54
CW 55
CW 56
CW 57
CW 58
CW 59
CW 60
CW 61
CW 62
CW 63
CW 64
Test
Date
Test
Of
Location
Lot#
C
C
C
C
C
C
C
C
C
C
c
1/24/06
1/24/06
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06 C
1/25/06 C
1/25/06
1/25/06
1/25/06
1/25/06
1/25/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
1/26/06
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
Project Number:
Project Name:
Project Location:
Client:
Crib Wall #1 Cell #5
Crib Wall #1 Cell #2
Crib Wall#l Cell #4
Crib Wall#l Cell #5
Crib Wall #1 Cell #3
Crib Wair#l Cell #2
Crib Wall #1 Cell #3
Crib Wall#l Cell#l
Crib Wall #1 Cell #5
Crib Wall#l Cell #4
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall #1 Cell #1
Crib Wall#l Cell #4
Crib Wall#l Cell#l
Crib Wall #1 Cell #5
Crib Wall#l Cell #5
Crib Wall#l Cell #5
Crib Wall#l Cell #4
Crib Wall#l Cell #3
Crib Wall#l Cell #4 .
Crib Wall #1 Cell #4
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell #3,
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall #1 Cell #5
Crib Wall #1 Cell #4
841363-009
Carisbad Golf Course
0
d
Station 11+62
Station 11+55
Station 9+60
Station 9+95
Station 10+32
Station 10+55
Station 10+85
Station 10+18
Station 11+20
Station 11+35
Station 11+00
. Station 10+90
Station 10+60
Station 11+55 .
Station 11+60
Station 9+78
Station 10+67
Station 11+45
Station 11+25
Station 11+00
Station 10+75
Station 9+75
Station 10+50
Station 11+55
Station 11+12
Station 10+80
Station 9+55
Station 9+85
Station 10+40
Station 9+90
Station 10+22
Station 10+05
Test
Elev (ft)
219.0
222.0
222.0
221.0
223.0
224.0
223.0
223.0
221.0
222.0
223.0
224.0
225.0
222.0
225.0
222.0
222.0
222.0
223.0
224.0
223.0
223.0
224.0
225.0
226.0
225,0
224.0
225.0
226.0
226.0
223.0
224.0
Soil
Type
4
4
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
105,4
104,9
104.2
102.8
103.8
107.0
103.1
103.0
104,0
106.5
104,4
102,5
103,5
104,5
103,2
103.9
103.5
104.1
103.7
104.2
105.4
103.1
105,1
104.0
102,6
103.2
102.8
103.5
102,8
103.0
102.9
102.6
116.0
116,0
114,5
114.5
114,5
114.5
114.5
114.5
114,5
114,5
114,5
114,5
114,5
114.5
114.5
114.5
114,5
114.5
114.5
114.5
114.5
114.5
114,5
114.5
114.5
114,5
114,5
114,5
114.5
114.5
114,5
114,5
13,9
12,7
16,8
17,0
16,4
15,6
15,3
16,2
17,3
17.7
15,6
17.7
17.2
15,9
16,4
16.4
17.4
17.0
17.2
18.0
17.5
17.2
16.9
16.3
16.7
18,0
17.4
16.4
17.5
15.7
17.6
18.0
13,0
13,0
12,5
12,5
12,5
12,5
12.5
12,5
12,5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12,5
12.5
12,5
12,5
12.5
12,5
12,5
12,5
12,5
12.5
12.5
12,5
12,5
12,5
12,5
12,5
91
90
91
90
91
93
90
90
91
93
91
90
90
91
90
91
90
91
91
91
92
90
92
91
90
90 •
90
90
90
90
90
90
Page 2 of39
3/9/2007
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
CW 65 1/26/06 C Crib Wall#l Cell #3
CW 66 1/27/06, C Crib Wall #1 Cell #5
CW 67 1/27/06 C Crib Wall#l Cell #4
CW 68 1/27/06 C Crib Wall #1 Cell #3
CW 69 1/27/06 C Crib Wall#l Cell #5
CW 70 . 1/27/06 C Crib Wall#l Cell #2
CW 71 1/27/06 C Crib'Wall #1 CeH#l
CW 72 1/27/06 C Crib Wall#l Cell #2
CW 73 1/27/06 C Crib Wall#l Cell#l
CW 74 1/27/06 c Crib Wall # I Cell #5
CW 75 1/27/06 c Crib Wall#l Cell #4
CW 76 1/27/06 c Crib Wall #1 Cell #3
CW 77 1/27/06 c Crib Wall#l Cell #2
CW 78 1/27/06 c Crib Wall#l Cell#l
CW 79 1/30/06 c Crib Wall#l Cell#l
jew 80 1/30/06 c Crib Wall#i Cell #2
CW 81 1/30/06 c Crib Wall #1 Cell #5
CW 82 1/30/06 c Crib Wall#l Cell #5
CW 83 1/30/06 c Crib Wall#l Cell #5
CW 84 1/30/06 c Crib Wall#l Cell #4
CW 85 1/30/06 c Crib Wall#l Cell #4
CW 86 1/30/06 c Crib Wall#l Cell #4
CW 87 1/30/06 c Crib Wall#l Cell #3
CW 88 1/30/06 c Crib Wall #1 Cell #3
CW 89 1/30/06 c Crib Wall #1 Cell #3
CW 90 1/30/06 c Crib Wall#l Cell #3
lew 91 1/30/06 c, . Crib Wall #1 Cell #2
CW 92 1/30/06 c Crib Wall#l Cell #2
CW 93 1/30/06 c Crib Wall#l Cell#l
CW 94 1/30/06 c Crib Wall#l Cell#l
CW 95 1/30/06 c Crib Wall#l Cell#l
CW 96 1/30/06 c Crib Wall#l Cell #5
Station 9+70
Station 10+55
Station 10+27
Station 10+10
Station 11+00
Station 10+00
Station 10+22
Station 10+46
Station 10+95
Station 11+35
Station 11+50
Station 11+30
Station 11+20
Station 10+35
Station 9+35
Station 9+45
Station 9+83
Station 10+43
Station 11+08
Station 9+80
Station 10+60
Station 11+42
Station 9+65
Station 10+72
Station 11 + 17
Station 9+95
. Station 10+80
Station 11+50
Station 9+80
Station 10+40
Station 11+25
Station 9+55
225.0
223.0
224.0
225.0
223.0
226.0
227.0
226.0
227.0
223.0
224.0
225.0
226.0
227.0
219.0
221,0
224.0
224.0
224.0
225.0
225.0
225.0
226.0'
226.0
226.0
227,0
227.0
227.0
228.0
228.0
228.0
220.0
3
4
4
4
• 4
3
3
3
4
4
4
4
4
4
3
3
3
3
3
3
3
3
4
3
3
4
1
1
3
3
3
3
103.4
104.1
106,4
106,8
105.4
103,1
103,5
102,8
107,3
106,2
107.0
106.4
105,6
104,3
103.5
102,6 .
103,8
103,1
103,5
104,1
103,0
103,0
105,6
103,5
102.8
105.5
107,6
107,8
103.2
102,9
105,3
104,3
114,5
116.0
116,0
116,0
116,0
114,5
114,5
114,5
116,0
116,0
116.0
116,0
116,0-
116,0
114,5
114,5
114,5
114,5
114.5
114.5
114.5
114.5
116.0
114,5
114.5
116.0
120.0
120.0
114,5
114,5
114.5
114.5
16.4
13.3
16.0
15,4
13,5
16,1
15,0
18,2
15,4
14,5
13,4
14,0
14,6
14.3
13,4
17,0
15,7
14,6
14,0
15.6
16,4
14.8
15.2
13.5
15.3
15.8
13.9
13.2
15.0
14.1
13.2 •
17.4
12.5
.13.0
13,0
13,0
13,0
12,5
12,5
12,5
13.0
13,0
13.0
13.0
13,0
13.0
12.5
12,5
12.5
12.5
12,5
12,5
12,5
12,5
13,0 -
12,5
12,5
13,0
12,0
12,0
12.5
12,5
12,5
12,5
90
90
92
92
91
90
90
90
93
92
92
92
91
90
90
90
91
90
90
91
90
90
91
90
90
91
90
90
90
90
92
91
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0 Page 3 of 39
1 -T^-mDA/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
CW 97 1/30/06 C Crib WaII#l Cell #3
CW 98 1/30/06 C Crib Wall#l Cell#l
CW 99 1/31/06 c Crib Wall #1 Cell #4
CW 100 1/31/06 c •Crib Wall #1 Cell #2
CW 101 1/31/06 c Crib Wall #1 Cell #5
CW 102 1/31/06 c Crib Wall#l Cell #5
CW 103 1/31/06 c Crib Wall #1 Cell #5
CW 104 1/31/06 c Crib Wall #1 Cell #4
CW 105 1/31/06 c Crib Wall#l Cell #4
CW 106 1/31/06 c Crib Wall #1 Cell #4
CW 106A 1/31/06 c Crib Wall#l Cell #4
CW 107 1/31/06 c Crib Wall#l Cell #3
CW 108 1/31/06 c Crib Wall#l Cell #3
CW 109 1/31/06 c Crib Wall#l Cell #3
CW 110 1/31/06 c Crib Wall #1 Cell #2
CW 111 1/31/06 c Crib Wall #1 Cell #2
CW 112 1/31/06 c Crib Wall #1 Cell #2
CW 113 1/31/06 c Crib Wall#l Cell #1
CW 114 1/31/06 c Crib Wall#l Cell #1
CW 115 1/31/06 c Crib Wall#l Cell#l
CW 116 1/31/06 c Crib Wall#l Cell #5
CW 117 1/31/06 c Crib Wall #1 Cell #3
CW 118 1/31/06 c Crib Wall#l Cell#l
CW 119 2/1/06 c Crib Wall#l Cell #5
CW 120 2/1/06 c Crib Wall#l Cell #4
CW 121 2/1/06 c Crib Wall #1 Cell #3
CW 122 2/1/06 c Crib Wall#l Cell #2
CW 123 2/1/06 c Crib Wall#l Cell#l
CW 124 2/2/06 c Crib Wall#l Cell #4
CW 125 2/2/06 c Crib Wall#l Cell #4
CW 126 2/2/06 c Crib Wall#l Cell #4
CW 127 2/2/06 c Crib Wall #1 Cell #3
Project Number:
Project Name:
Project Location:
Station 9+40
Station 9+27
Station 9+45
Station 9+25
Station 11+26
Station 10+70
Station 10+00
Station 11+45
Station 10+85
Station 9+75
Station 9+75
Station 11+10
Station 10+50
Station 9+60
Station 11+20
Station 10+80
Station 10+05
Station 11+50
Station 10+55
Station 9+90
Station 9+50
Station 9+35
Station 9+42
Station 9+57
Station 9+50
Station 9+38
Station 9+65
Station 9+45
Station 11+25
Station 10+75
Station 10+15
Station 11+00
Lot#
Test
Elev (ft)
222.0
224.0
222.0
224.0
225.0
225.0
225^0
226.0
226.0
226.0
226.0
227.0
. 227.0
227.0
228.0
228.0
228.0
229.0
229.0
229.0
221.0'
223.0-
225.0
222.0
223.0
224.0
225.0
226.0
228.0
228.0
228.0
229.0
Soil
Type
3
3
3
3
3
3
3
3
4
3
3
4
3
3
3
3
3
3
3
3
3
3
3
4
3
4
4
4
1
1
1
1
Dry Density
Field Max
105.0
103.6
104.7
103.8
103.9
102.7
102.9
103.2
106.3
97.4
105.5
106.0
102.6
108.6
103.6
102.9
103.2
103.8
104.1
103.7
104.1
102.9
103.9
103.9
103.6
104.0
104.9
104.8
108.2
112.4
108.6
108.3
114.5
114.5
114.5
114.5
114.5
114.5
114.5
11'4.5
116.0
114.5
114,5
116,0
114,5
114,5
114,5
114,5
114,5
114.5
114.5
114,5
114,5
114.5
114.5
116.0
114.5
116.0
116.0
116,0
120.0
120.0
120.0
120.0
Moisture (%)
Field Opt.
Relative r%)
Compaction
16.6
18.2
17.2
18,1
14.1 ,
, 14,7'
17,2
17.2
13.6
15.5
14.6
15,4
16,5
15':i
17,8
18.6
.17.1
16.3
16.1
15.0
17.4
16.7
17.7
16.3
17.0
15.3
15.1
15.0
11.5
13.9
13.4
13.4
Remarks
12.5
12,5
12,5
12,5
12,5
,1-2.5
12.5
•; 12.5
13.0
12.5
12.5
13,0
12,5
12,5
12,5 ,
12,5
• 12,5
12,5
12,5
12.5
12.5
12.5
12.5
13.0
12.5
13.0
13.0
13,0
12,0
12,0
12,0
12,0
92
90
91
91
91
90
90
90
•" 92
85
92
91
90
95
• 90
90
90
91
91
91
91
90
91
90
90
90
90
90
90
94.
90
90
Retest on 106A
Retest of 106
^/Q/9nn7
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
CW 128 2/2/06 C Crib Wall#l Cell #3 Station 10+60
CW 129 2/3/06 C Crib Wall#l Cell #3 Station 10+18
CW 130 2/3/06 c Crib Wall#l Cell #5 Station 9+87
CW 131 2/3/06 c Crib Wall#l Cell #2 Station 9+85
CW 132 2/3/06 c Crib Wall #1 Cell #2 Station 10+45
CW 133 2/3/06 c Crib Wall #1 Cell #2 Station 11+10
CW 134 2/3/06 c Crib Wall #1 Cell #1 Station 10+10
CW 135 2/6/06 c Crib Wall#l Cell#l Station 11+35
CW 136 2/6/06 c Crib Wall#l Cell#l Station 9+50
CW 137 2/6/06 c Crib Wall #1 Cell #5 Station 9+40
CW 138 2/6/06 c Crib Wall#l Cell #4 Station 9+20
CW 139 . 2/7/06 c Crib Wall#l Cell #4 Station 11+40
CW 140 2/7/06 c Crib Wall#l Cell #4 Station 10+95
CW 140A 2/7/06 c Crib Wall #1 Cell #4 . Station 10+95
CW 141 2/7/06. c Crib Wall#l Cell #4 Station 10+00
CW 142 2/7/06 c Crib Wall#l Cell #3 Station 11+15
CW 142 A 2/7/06 c Crib Wall#l Cell #3 Station 11+15
CW 143 2/7/06 c Crib Wall#l Cell #3 Station 10+70
CW 144 2/7/06 c Crib Wall #1 Cell #3 Station 10+22
CW 145 2/7/06 c Crib Wall #1 Cell #2 Station 11+29
CW 145A 2/7/06 c Crib Wall #1 Cell #2 Station 11+29
CW 146 2/7/06 c Crib Wall#l Cell #2 Station 10+70
CW 147 2/7/06 c Crib Wall#l Cell #2 Station 9+90
CW 148 2/7/06 c Crib Wall#l Cell#l Station 11+30
CW MSA 2/7/06 c Crib Wall#l Cell#r Station 11+30
CW 149 2/7/06 c Crib Wall #1 Cell #1 Station 10+80
CW 150 -2/7/06 c Crib Wall #1 Cell#l Station 10+15
CW 151 2/7/06 c Crib Wall #1 Cell #5 Station 9+52
CW 152 2/7/06 c Crib Wall #1 Cell #4 Station 9+40
CW 153 2/7/06 c Crib Wall#l Cell #3 Station 9+70
CW 154 2/7/06 c Crib Wall #1 Cell #2 Station 9+60
CW 155 2/8/06 c. Crib Wall#l Cell #3 Station 9+00
Project Number-
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
229.0 1 108.1 120,0 14,0 12,0 90
• 229.0 1 109.1 120,0 13,3 12.0 . 91
227.0 1 107.7 120,0 14,8 12.0 90
230.0 1 108.6 120,0 14,9 12.0 90
230.0 1 108.6 120,0 12,1 12.0 ' 90
230.0 1 109.3 120.0 11.3 .. 12.0 91
231.0 4 -104.6 116.0 15.7 13.0 90
231.0 4 104.6 116.0 13.7 13.0 90
229.0 3 104,7 114.5 15.2 12.5 91
227.0 3 103,9 114.5 18,0 12.5 91
228.0 3 103.2 114,5 15,0 12.5 . 90
229.0 4 105.1 116,0 16,1 13.0 91
229.0 3 98.2 114,5 17,0 12.5 86
229.0 3 104.8 114,5 13,3 12,5- ' 92
229.0 1 109.4 120.0 13,0 12,0 91
230.0 3 98.3 114.5 14,7 12.5 86
230.0 1 107.4 120.0 11,6 12.0 90
230.0 1 109,8 120.0 12,3 12.0 92
230.0 4 106,6 116.0 12.5 13,0 92
231.0 3 98.3 114.5 14.6 12.5 86
231.0 3 103.8 114,5 13.2 12.5 91
231.0 3 104.8 114.5 12.4 12,5 92
231.0 3 104.6 114.5 14.3 12,5 91
232.0. 3 99.0 114,5 14.0 • 12,5 86
232.0 3 104.6 114.5 13.3 12,5 91
232.0 3 103.7 114.5 13.1 12,5 91
232.0 3 104.7 114.5 11,0 12,5 91
227.0 3 104.1 114.5 13,0 12,5 91
228.0 3 103.6 114.5 13.5 12.5 90
229.0 3 104.9 114.5 14.3 . 12,5 92 230.0 3 103,7 114.5 16.2 12,5 91
226.0 1 111.8 120.0 14.3 12.0 93
Retest on 140A
Retest of 140
Retest on 142A
Retest of 142
Retest on 145A
Retest of 145
Retest on MSA
Retest of 148
Page 5 of39
1:35:02PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Rerfiarks
CW.156 2/8/06 C Crib Wall #1 Cell #1 Station 9+10
CW 157 .2/8/06 c Crib Wall#l Cell #4 Station 9+18
CW 158 2/8/06 c Crib Wall #1 Cell #2 Station 8+95
CW 159 2/8/06 c Crib Wall#l Cell #5 Station 9+25
CW 160 2/8/06 c Crib Wall#l Cell #4 Station 9+12
CW 161 . 2/8/06 C' Crib Wall #1 Cell #3 Station 9+17
CW 162 2/8/06 c Crib Wall#l Cell #2 Station 9+27
CW 163 2/8/06 c Crib Wall#l Cell#l Station 9+5
CW 164 2/9/06 c Crib Wall#l Cell #5 Station 9+80
CW 165 2/9/06 c Crib Wall #1 Cell #5 Station 9+45
CW 166 2/9/06 c Crib Wall #1 Cell #4 Station 9+55
CW 167 2/9/06 c Crib Wall#l Cell #4 Station 9+16
CW 168 2/9/06 c Crib Wall#l Cell #4 Station 8+85
CW 168A 2/9/06 c Crib Wall #1 Cell #4 Station 8+85
CW 169 2/9/06 c Crib Wall#l Cell #3 Station 9+14
CW 170 2/9/06 c Crib Wall#l Cell #1 Station 9+08
CW 171 2/9/06 c Crib Wall #1 Cell #2 Station 9+35
CW 172 2/9/06 c Crib Wall#l Cell#l Station 9+30
CW 173 2/9/06 c Crib Wall#l Cell #4 Station 8+85
CW 174 2/9/06 c Crib Wall#l Cell #4 Station 9+28
CW 175 2/9/06 c Crib Wall #1 Cell #3 Station 9+75
CW 176 2/9/06 c Crib Wall #1 Cell #3 Station 9+00
CW 177 2/9/06 c Crib Wall #1 Cell #2 Station 8+87
CW 178 2/9/06 c Crib Wall #1 Cell #2 Station 9+45
CW 179 2/9/06 c Crib Wall #1 Cell #1 Station 9+20
CW 180 2/9/06 c Crib Wall#l Cell #1 Station 8+85
CW 181 2/10/06 c Crib Wall,#1 Cell #4 Station 10+00
CW 182 . 2/10/06 c Crib Wall #1 Cell #3 Station 10+45
CW 183 2/10/06 c Crib Wall #1 Cell #2 Station 10+73
CW 184 2/10/06 c Crib Wall#l Cell #2 Station 11+10
CW 185 2/10/06 c Crib Wall #1 Cell #4 Station 11+35
CW 186 2/10/06 c Crib Wall #I Cell #3 Station 11+00
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
228.0 1 109.2 120,0 14.0 12.0 91
226.0 1 112.3 120.0 14.3 12.0 94
228.0 1 108.6 120,0 14.0 12,0 90
226.0 4 104.7 116,0 16.4 13,0 90
227.0 4 105.6 116,0 16.9 13,0 91
228.0 1 110.0 120,0 13.8 12,0 92
229.0 4 104,6 116,0 17.0 13,0 90
230.0 4 105,1 116,0 16,1 13.0 91
228.0 4 104,2 116,0 15,2 .13.0 90
228.0 4 105,7 116,0 12,5 13,0 91
229.0 4 104.8 .116,0 16,3 13,0 90
228.0 4 104,1 116,0 14,2 13.0 90
228.0 4 100,6 .116.0 14,0 13,0 87
228.0 4 106,3 116.0 14,1 13.0 92
227.0 . 4 . 103,9 116.0 . 14,2 13,0 •. 90'
230.0 4 105,3 116.0 • .12,3 , 13,0 91
229.0 4 106.2 116.0 13,3 13,0 92
.230.0 4 104.3 116.0 13.5 13,0 90
230.0 4 104.9 116.0 11.2 13,0 90
229.0 1 • 108.4 120.0 12.4 12,0 • 90
229.0 1 107.6 120.0 12,6 12,0 -90
229.0 1 108.5 1-20.0 11,6 , 1:2.0 • 90
230.0 4 104.4 116.0. 12,8 •. 13.0 90
230.0 1 112,4 120.0 M.O 12,0 94
231.0 1 109.3 120.0 12,0 • 12.0 91
231.0 1 108.6 120.0 12.6 12.0 . 90
230.0 1 116.7 120.0 12,7 12.0 97
231.0 1 108.4 120.0 12,7 12,0 90
232.0 4 105.0 116.0 13.6 13,0 91
233.0 1 109.7 120.0 14.1 12,0 91 230.0 1 108,7 120.0 13.0 12,0 91 231.0 1 108.6 120.0 14.4 12.0 90
Retest on 168A
Retest of 168
Page 6 of39
1 •'!•^.n')D^/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
CW 187 2/10/06 C Crib Wall#l Cell #2 Station 10+55
CW 188 2/10/06 C Crib Wall #l Cell#l Station 9+95
CW 189 2/10/06 C Crib Wall #1 Cell #4 Station 9+70
CW 190 2/10/06 c Crib Wall#l Cell #3 Station 9+85
CW 193 2/13/06 c Crib Wall #1 Cell #4 Station 10+65
CW 194 2/13/06 c Crib Wall#l Cell #3 Station 10+80
CW 195 2/13/06 c Crib Wall #1 Cell #2 Station 11+15
CW 196 2/13/06 c Crib Wall #1 Cell#l Station 11+35
CW 197 2/13/06 c Crib Wall#l Gell#l Station 10+50
CW 198 2/13/06 c Crib Wall#l Cell #2 Station 10+22
CW 199 2/14/06 c Crib Wall#l Cell #3 Station 9+90
CW 200 2/14/06 c Crib Wall #1 Cell #4 Station 9+75
CW 201 2/14/06 c Crib Wall # I Cell#l Station 9+55
CW 202 2/14/06 c Crib Wall #1 Cell #2 Station 9+40
CW 203, 2/14/06 c Crib Wall #1 Cell #3 Station 9+25
CW 204 2/14/06 c Crib Wall #1 Cell #4 Station 9+10
CW 205 2/14/06 c Crib Wall #1 Cell#l Station 8+88
CW 206 2/14/06 c Crib Wall #1 Cell #2 Station 8+80
CW 207 2/14/06 c Crib Wall#l Cell #3 Station 8+75
CW 208 2/14/06 c Crib Wall#l Cell #4 Station 8+63
CW 209 . 2/14/06 c Crib Wall#r Cell #4 Station 11+05
CW 210 2/14/06 c Crib Wall#l Cell #3 Station 11+30
CW 211 2/14/06 c Crib Wall#l Cell #2 Station 10+90
CW 212 2/14/06. c Crib Wall#l Cell#l Station 10+60
CW 213 2/15/06 c Crib Wall #1 Cell #4 Station 10+50
CW 214 2/15/06 • c Crib Wall#l Cell #3 Station 10+95
CW 215 2/15/06 c Crib Wall#l Cell #2 Station 9+60
CW 216 2/15/06 c Crib Wall #1 Cell#l Station 10+00
CW 217 2/15/06 c Crib Wall#l Cell #4 Station 9+90
CW 218 2/15/06 c Crib Wall#l Cell #3 Station 9+50
CW 219 2/15/06 c Crib Wall#l Cell #2 Station 9+27
CW 220 2/15/06 c Crib Wall#l Cell #2 Station 9+37
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
232.0 4 104.8 116,0 14,0 13.0 90
233.0 4 106.3 116.0 13.7 13.0 92
230.0 4 104.4 116,0 14.6 13.0 90
231.0 4 104.2 116,0 14,5 13,0 90
231.0 1 108,3 120,0 12,2 12,0 90
232.0 1 109,4 120.0 15,0 12,0 91
233.0 1 110,3 120.0 12.5 12.0 92
234.0 1 109.1 120.0 13,6 12.0 ,91
234.0 1 108.0 120,0 12.9 12,0 90
233.0 1 108,0 120,0 11,7 12.0 90
232.0 1 108.2 120.0 16,4 12,0 90
231.0 1 112,2 120,0 14,2 12,0 94
234.0 1 108.9 120.0 17,1 12,0 91
233.0 1 107.6 120.0-1 1,0 12,0 90
232.0 1 109.1 120,0 12.0 12,0 91
231.0 1 112.3 120,0 11.1 12,0 94
234.0 1 108.3 120,0 13.1 12.0 90
233.0 4 104,5 116,0 16.7 13.0 90
232.0 1 108,4 1.20.0 13.1 12.0 90
231.0 1 108,0 120.0 13.0 ,12.0 90
232.0 4 104.S 116.0 17.0 13.0 90
233.0 1 107.6 120.0 12.6 ; 12.0 90
234.0 1 .107.6 120.0 16.7 • 12.0 90
235.0 1 108.9 120.0 14.2 • 12,0 91
232.0 1 -108.2 120.0 13:8 ' 12,0 90
233.0 1 108.5 120.0 12.6 12,0 90
234.0 1 108.0 120.0 16.9 12,0 90
235.0 1 108.6 120.0 15.4 12,0 90
232.0 4 104.2 116.0 17.5 13,0 90
233.0 4 104.5 116.0 13.5 13,0 90
234.0 4 104.3 116.0 16.4 13,0 90 235,0 4 104.9 116.0 15.2 13,0 90
Page 7 of 39
3/9/2007 I :^5-n7PM
SUMMARY OF FIELD DENSITY TESTS
Test Test T(
No. Date OI
CW 221 2/15/06 e
CW 222 2/15/06 c CW 223 2/15/06 c CW 224 2/15/06 c CW 225 2/15/06 c CW 226 2/15/06 c
CW 227 2/15/06 c
CW 228 2/15/06 c
CW 228A 2/15/06 c CW 229 2/15/06 c CW 230 2/15/06 c CW 231 2/15/06 c CW 232 2/15/06 c CW 233 2/15/06 c CW 234 2/15/06 c CW 235 2/16/06 c CW 236 2/16/06 c CW 237 2/16/06 c CW 238 2/16/06 c CW 239 2/16/06 c CW 240 2/16/06 c CW 241. 2/16/06 c CW 242 2/16/06 c CW 243 2/16/06 c CW 244 2/16/06 c CW 245 2/16/06 c 'cW 246 2/16/06 c CW 247 2/16/06 c CW 248 2/17/06 c CW 249 2/17/06 c CW 250 2/17/06 c CW 251 2/17/06 c
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative C/o)
Compaction Remarks
Project Number:
Project Name:
Project Location:
Client-
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall #1
Crib Wall#l
Cell #4
Cell #3
Cell #2
Cell#l
Cell #4
Cell #3
Cell #4
Cell #3
Cell #3
Cell #2
Cell #2
Cell#l
Cell#l
Cell #2
Cell#l
Cell #4
Cell #4
Cell #3
Cell #3
Cell #2
Cell #2
Cell#l
Cell#l
Cell#l
Cell #4
Cell #3
Cell #2
Cell#l
Cell #4
Cell #4
Cell #4
Cell #3
841363-009
Carlsbad Golf Course
0
0
Station 8+85
Station 8+62
Station 8+75
Station 8+65
Station 11+00
Station 11+20
Station 10+70
Station 10+40
Station 10+40
Station 10+25
Station 10+65
Station 10+35
Station 10+80
Station 10+36
Station 11+10
Station 9+40
Station 8+62
Station 9+65
Station 8+95
Station 8+68
Station 9+13
Station 9+30
Station 9+00
Station 8+55
Station 10+78
Station 11 + 10
Station 11+20
Station 10+97
Station 10+40
Station 10+15
Station 9+70
Station 10+60
232.0 4 104.3 116.0 14,4 13.0 90
233.0 1 108,2 120.0 18,0 12,0 90
234.0 1 108,9 120,0 14,2 12,0 91
235.0 4 104,6 116.0 15.0 13,0 90
233.0 1 111,3 120,0 18,8 12,0 93
234.0 1 109,6 120.0 17,1 12,0 91
233.0 1 108,2 120,0 15,6 , 12,0 90
- 234.0 1 104,7 120.0 12,6 12,0 87
234.0 1 108.9 120,0 13,1 12,0 91
235.0 1 108.0 120,0 14,2 12,0 90
235.0 1 107,5 120,0 18,3 12,0 90
236.0 1 110.9 120,0 12,6 12,0 92
236.0 1 108.6 120.0 14,4 " 12,0 90
235.0 1 108.5 120.0 14,5 12.0 90
236.0 1 109,3 120.0 14,0 12.0 91
233.0 1 109,4 120.0 12,8 12,0 91
233.0 1 109,0 120.0 12,9 12,0 91
234.0 1 108.3 120.0 15.1 12.0 90
234.0 1 108.8 120.0 .16,8 12.0 91
235.0 1 110.5 120.0 14,3 12.0 92
235.0 1 109.2 120.0 14.8 12.0 91
236.0 1 108.7 120.0 14.5 12.0 91
236.0 1 109.7 120.0 14.2 12,0 • 91
236.0 1 108.4 120.0 14.5 12,0 90
234.0 1 108.2 120.0 12.2 12,0 90 235.0 1 110.4 120.0 13.4 12,0 92 236.0 1 107.8 120.0 12.8 12,0 90
237.0 1 108.8 120,0 12.4 12.0 91
234.0 1 108.3 120,0 10.7 12,0 90
234.0 1 111.3 120,0 11.1 12.0 93
234.0 3 104.6 114,5 13.6 12.5 91
235,0 1 110.2 120,0 13.5 12.0 92
Retest on 228A
Retest of 22 8
Page 8 of39
3/9/2007 :35-n2PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 252
CW 253
CW 254
CW 255
CW 256
CW 257
CW 258
CW 259
CW 260
CW 261
CW 262
CW 263
CW 264
CW 265
CW 266
CW 267
CW 268
CW 269
CW 270
CW 271
CW 272
CW 273
CW 274
CW 275
CW 276
CW 277
CW 278
CW 279
CW 280
CW 281
CW 282
CW 283
Test
Date
Test
Of
Project Number:
Project Name:
Project Location:
Client:
C
C
c
c
2/17/06
2/17/06
2/17/06
2/17/06
2/17/06
2/17/06 C
2/17/06 C
2/17/06
2/17/06
2/17/06
2/17/06
2/17/06 C
2/17/06 C
2/17/06
2/17/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/22/06
2/23/06
2/23/06
2/23/06
C
C
c
c
c c
c
c
c
c
c
c
c c c
c
c
c c
Location
Crib Wall#l Cell #3
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell #2
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #4
Crib Wall#l Cell #3
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #3
Crib Wall#l Cell #4
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell #3
Crib Wall#l Cell #4
Crib Wall#l Cell#l
Crib Wall #1 Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #3
Crib Wall #1 Cell #2
Crib Wall #1 Cel[#l
Crib Wall#l Cell #2
Crib Wall#l Cell #3
841363-009
Carlsbad Golf Course
0
0
Station 10+25
, Station 9+85
Station 10+55
Station 10+10
Station 9+79
Station 10+67.-
Station 10+20
Station 9+35
Station 9+95
Station 8+87
Station 9+60
Station 8+65
Station 8+50
Station 8+42
Station S+80
Station 11+00
Station 10+65
Station 10+00
Station 9+80
Station 9+50
Station 9+00
Station 8+55
Station 9+25
Station 11+17
Station 10+92
Station 10+57
Station 10+50
Station 10+25
Station 10+70
Station 9+85
Station 9+75
Station 9+55
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
235.0 1 108,2 120.0 11,4 12.0 90
235.0 1 110,7 120,0 1 1.6 12,0 92
236.0 1 107,9 120,0 13.6 12.0 90
236.0 1 107,7 120,0 11.6 12.0 90
236.0 1 108,4 120,0 12.2 12.0 90
237.0 1 108,8 120.0 I 1.1 12,0 91
237.0 1 108,7 120.0 10,1 12.0 91
236.0 1 108.5 120,0 1 1,0 12.0 90
237.0 1 107,7 120,0 11,3 12,0 90
236.0 1 109,1 120.0 11,9 12.0 91
237.0 3 104,6 114.5 13,0 12,5 91
234.0 1 108.0 120,0 11,7 12,0 90
235.0 1 109.1 120.0 12,6 12,0 91
'236.0 1 108.6 120,0 12,3 12,0 90
237.0 1 109.4 120.0 13.2 12.0 91
237.0 1 108.1 120,0 13.6 12,0 90
238.0 1 110.7 120.0 13.1 12,0 92
236.0 1 107.7 120.0 12.2 12,0 90 235.0 1 110.7 120.0 11.3 12,0 92
238.0 1 108.9 120,0 10.3 12,0 91
237.0 1 108.5 120,0 .11.4 12.0 90
236.0 1 107.6 120,0 13.5 12,0 90
235.0 1 109.1 120,0 13.2 12,0 91
239.0 1 108.2 120.0 12.0 12,0 90
237.0 1 111.7 120.0 10.3 12,0 93
238.0 1 109.6 120,0 13.6 12,0 91
239.0 1 110.7 120,0 13.9 12,0 92
237.0 1 107.8 120.0 12.0 12,0 90
238.0 1 108.0 120,0 13.7 12,0 90-239.0 1 112.5 120,0 12.2 12,0 94 238.0 1 108.8 120,0 16.5 12,0 91 237,0 1 107.4 120,0 16.1 12,0 90
Page 9 of 39
3/9/2007 1 •'?5n9PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density Moisture (%) Relative (%)
Field Max Field Opt. Compaction Remarks
CW 284 2/23/06 C Crib Wall#l Cell #4 Station 9+15
CW 285 2/23/06 C Crib Wall#l Cell#l Station 8+90
CW 286 2/23/06 C Crib Wall #1 Cell #2 Station 8+70
CW 287 2/23/06 c , Crib Wall #1 Cell #3 Station 8+50
CW 288 2/23/06 c Crib Wall #1 Cell #2 Station 8+40
CW 289 2/23/06 c Crib Wall#l Cell #l Station 8+30
CW 290 2/23/06 c Crib Wall#l Cell #3 Station 11+00
CW 291 2/23/06 c Crib Wall#l Cell #3 Station 10+50
CW 292 2/23/06 c Crib Wall#l Cell #3 Station 10+00
CW 293 2/23/06 c Crib Wall#l Cell #3 Station 9+50
CW 294 2/23/06 c Crib Wall #1 Cell #3 Station 9+00
CW 295 2/23/06 c Crib Wall#l Cell #3 Station 8+42
CW 296 2/23/06 c Crib Wall #1 Cell #2 Station 11+08
CW 297 2/23/06 c Crib Wall #1 Cell#l Station 10+82
CW 298 2/23/06 c Crib Wall #1 Cell #2 Station 10+42
CW 299 2/23/06 c Crib Wall#l Cell#l Station 10+20
CW 300 2/23/06 c Crib Wall#l Cell #2 Station 9+95
CW 301 2/23/06 c Crib Wall#l Cell#l Station 9+67
C W 302 2/23/06 c Crib Wall #1 Cell #2 Station 9+55
CW 303 2/23/06 c Crib Wall #1 Cell#l Station 9+35
C W 304 2/23/06 c Crib Wall #1 Cell #2 Station 9+12
CW 305 2/24/06 c Crib Wall#l Cell #2 Station 8+85
CW 306 2/24/06 c Crib Wall#l Cell#l Station 8+57
CW 307 2/24/06 c Crib Wall#l Cell#l Station 10+95
CW 308 2/24/06 c Crib Wall #1 Cell #2 Station 10+70
CW 309 2/24/06 c Crib Wall#l Cell #3 Station 10+45
'cW 310 2/24/06 c Crib Wall#l Cell#l Station 10+25
CW 311 2/24/06 c Crib Wall#l Cell #2 Station 10+00
CW 312 2/24/06 c Crib Wall#l Cell #3 Station 9+75
CW 313 2/24/06 c Crib Wall#l Cell#l Station 9+50
CW 314 2/24/06 c Crib Wall#l Cell #2 Station 9+25
CW 315 2/24/06 c Crib Wall #1 Cell #3 Station 9+15
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
236.0 1 110,4 120,0 13.9 12.0 92
239.0 1 108,1 120,0 13.1 12.0 , 90
238.0 1 108,4 120,0 14.0 12,0 ' 90
237.0 1 108,7 120,0 12.0 12,0 91
238.0 1 109,7 120,0 13.0 12,0 91
239.0 1 108.2 120,0 !3.8 ,12,0 90
238.0 1 107.6 120,0 . 14,8 12.0 90
238.0 1 . • 110,7 120,0 14.2 12,0 92
238.0 1 109,1 120,0 16.9 12.0 91
238.0 1 109,7 120,0 13.2 12,0 91
238.0 1 111,8 120.0 12.8 12,0 93
238.0 1 111,3 120.0 14.7 12,0 93
239.0 1 108,0 120.0 13,4 12,0 90
240.0 1 107.6 120.0 16.4 12,0 90
239.0 1 108,6 120.0 16.1 " 12,0 , 90
240.0 1 109,3 120.0 15.1 12,0 91
239.0 1 108.3 120.0 13.8 12,0 90
240.0 1 108.6 120.0 14.6 12,0 90
239.0 1 108.7 120,0 15.0 12,0 91
240.0 1 110.5 120,0 14.4 12,0 92
239.0 1 107.8 120.0 15.5 12,0 90
239.0 1 110.6 120.0 14.3 12,0 92
240,0 1 111.2 120.0 16.3 12,0 93
241.0 1 111.1 120.0 12.8 12,0 93
240.0 1 113.2 120.0 13.7 12.0 94
239.0 1 111.5 120,0 13.2 12,0 93
241.0 1 109.5 120,0 13.7 12.0 91
240.0 1 108.6 120,0 14.6 12.0 90
239.0 1 108.2 120,0 13.0 12.0 90
241.0 1 109.4 120,0 13.6 12,0 91
240.0 1 108.3 120,0 15.2 12.0 90
229,0 1 109.6 120.0 13.7 12,0 91
Page 10 of 39
3/9/2007 1 -T^nOPA/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 316
CW 317
CW 318
CW 319
CW 320
CW 321
CW 322
CW 323
CW 324
CW 325
CW 326
CW 327
CW 328
CW 329
CW 330
CW 331
CW 332
CW 333
CW 334
CW 335
CW 336
CW 337
CW 338
CW 339
CW 340
CW 341
CW 342
CW 343
CW 344
CW 345
CW 346
CW 347
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
2/24/06
2/24/06
2/24/06
2/24/06
2/25/06
C
c
c
c
c
2/25/06 C
Project Number:
Project Name:
Project Location:
Client:
C
C
C
c c
c.
c
c c
c
c
c
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
2/27/06
2/27/06
2/27/06 C
2/27/06 C
2/27/06 C
2/27/06 C
2/27/06 C
2/27/06 C
2/27/06
2/27/06
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
C
C
c c
c
c
c c
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall # I
Crib Wall#l
Crib Wair#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Cell #3
Cell #2
Cell#l
Cell #3
Cell #3
Cell #2
Cell#l
Cell #3
Cell #2
Cell#l
Cell #3
Cell #2
Cell#l
Cell #3
Cell #2
Cell #1
Cell #2
Cell #1
Cell #3
Cell #2
Cell#l
Cell#l
Cell #2
Cell #3
Cell#l
Cell #2
Cell #3
Cell #2
Cell #1
Cell #3
Cell #2
Cell#l
841363-009
Carlsbad Golf Course
0
0
Station 8+75
Station 8+50
Station 8+25
Station 8+18
Station 10+60
Station 10+80
Station 11+00
Station 9+60
Station 9+80
Station 10+12
Station 9+55
Station 9+20
Station 9+07
Station 8+62
Station 8+32
Station 8+19
Station S+40
Station 9+15
Station 9+43
Station 9+90
Station 10+45
Station 10+90
Station 10+65
Station 10+40
Station 10+35
Station 10+15
Station 9+85
Station 9+65
Station 9+40
Station 9+00
Station 8+90
Station 8+70
239,0
240.0
241.0
239.0
240.0
241.0
242.0
240.0
241.0
242.0
240.0
241.0
242.0
240.0
241.0
242.0
242.0
243.0
241.0
242.0
243.0
244.0
243.0 •
242.0
244.0
243.0
242.0
243.0
244,0
241.0
242.0
243.0
Soil
Type
Dry Density
Field Max
Moisture (%) Relative (%)
Field Opt. Compaction Remarks
110.1 120.0 14,1 12.0 92
108.5 120.0 14,0 12.0 • 90
108,3 120.0 13,9 12,0' 90
110.9 120.0 12,0 12,0 92
109.9 120.0 12,4 12,0 .92
108,7 120.0 13,8 12,0 91
110.3 120.0 14,3 12,0 92
U0.9 120.0 12,7 12,0 92
108,4 120,0 14,6 12.0 90
110,8 120,0 13,8 12.0 92
109.1 120,0 14,4 12.0 91
112.1 120,0 13,2 12,0 93
109,6 120.0 13,4 12,0 91
107,8 120.0 14,6 12,0 90
108,1 120,0 12,0 12,0 90
107,9 120.0 13,0 12,0 90
108,0 120,0 13,0 ' 12,0 90
107,6 120.0 8,9 , 12,0 90
108,5 120,0 9,3 1-2,0 90
107.8 120,0 12,8 12.0 90
10S.4 120,0 8,2 12.0 90
108.0 120,0 12.2 12.0 90
108.7 120,0 12.2 12,0 91
110.3 120,0 11.8 12,0 92
109.1 120,0 12:9 12,0 91
108.3 120.0 11.8 12,0 90
108.7 120.0 11.2 12,0 91
107.9 120.0 15.0 12,0 90
107.7 120,0 18.0 12,0 90
111.0 120.0 14.2 12,0 93
108.6 120,0 14.2 12,0 90
107.8 120,0 12.8 12,0 90
Page 11 of39
1 -^s-noPM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative ("A)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
CW 348
CW 349
CW 349A
CW 350
CW 351'
CW 352
CW 353
CW 354
CW 355
CW 356
CW 357
CW 358
CW 359
CW 360
lew 361
CW 362
CW 363 ,
CW 364
CW 365
CW 366
CW 367
CW 368
CW 369
CW 370
lew 371
CW 372
CW 373
CW 374
CW 375
CW 376
lew 377
CW 378
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
3/2/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/3/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06 .
3/6/06
3/6/06
3/6/06
C e
c
c
c c
c
c
. c c e
c
e c e
c
c c e
c
c
e c
c
e
c e
c
e
c e
c
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell #2
Crib Wall#l eell#l
Crib Wall #1 Cell #3
Crib Wall#l Cell #2
• Crib Wall #1 eeH'#l
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall #1 Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #2
Crib Wall#l Cell #3
Crib Wall #1 Cell #1
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #3
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall #1 Cell #2
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #2
Station 8+50
Station 8+30
Station 8+30
Station 8+20
Station 7+80
Station 7+60
- Station 7+40
Station 7+20
Station 7+10
Station 8+60
Station 8+40
Station 8+03
Station 7+70
Station 7+38
Station 7+50
Station 10+60
Station 10+22
Station 10+00
Station 9+80
Station 9+50
Station 9+40
Station 8+85
Station 8+50
Station 8+15
Station 8+00
Station 7+84
Station 7+45
Station 7+25
Station 7+28
Station 7+19
Station 7+10
Station 10+77
241.0
242.0
242.0
243.0
241.0
242.0
243.0
241.0
.242.0
242.0
243.0
244.0
243.0
242.0
245.0
243.0
244.0
245.0
243.0
244.0
245.0
243.0
244.0
245.0
244.0
245.0
244.0
244.0
242.0
243.0
243.0
245.0
108.7
102.4
107.8
109.3
107.8
108,0
108.5
109.3
107.9
111.9
107.7
108.7
107,6
108,4
109,4
108,0
111,3
107,6
109.3
108.3
109,1
108.6
109.0
108.0
108.4
102.9
106.2
110.4
108.0
108.4
108.6
108.0
120,0
120.0
120,0
120,0
120,0
120,0
120.0
120.0
120,0
120.0
120.0
120.0
120,0
120.0
120.0
120.0
120.0
120.0
120.0
120.0
120.0
120.0
120.0
120.0
120.0,
114.5
114.5
120.0
120.0
120.0
120.0
120.0
13.9
12.5
13,3
14,6
15,8-
11,7
14,0
11.7
14.1
10.1
10.5
11.6
13.2
11.6
1 1.8
15,9
11,3
15.2
12.5
15,1
9,7
10,7
12,1
10,5
12,9
11,5
12,6
12.1
11.2
12.3
13.1
..12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.5
12.5
12,0
12.0
12.0
12.0
12,0
91
85
90
91
90
90
90
91
90
93
90
91
90
90
91
90
93
90
91
90
91
90
91
90
90
90
93
92
90
90
90
90
Project Number:
Project Name:
Project Location
Client:
841363-009
Carlsbad Golf Course
0
0
Retest on 349A
Retest of 349
Page 12 of 39
3/9/2007 1 •^5-n9PA/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 379
CW 380
CW 381
CW 382
CW 383
CW 384
CW 385
CW 386
CW 387
CW 388
CW 389
CW 390
CW 391
CW 392
CW 393
CW 394
CW 395
CW 396
CW 397
CW 398
CW 399
CW 400
CW 401
CW 402
CW 403
CW 404
jew 405
jcw 406
CW 407
CW 408 ,
Jew 409
CW 410
Test
Date
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/6/06
3/7/06
3/7/06
3/7/06
3/7/06
3/7/06.
3/7/06
3/7/06
3/7/06
3/7/06
3/7/06
3/7/06
3/7/06
3/7/06
3/7/06
3/8/06
3/8/06
3/8/06
3/8/06
3/8/06
3/8/06
3/S/06
3/8/06
3/8/06
Test
Of
Location
Lot#
Project Number:
Project Name:
Project Location:
Client:
C Crib Wall #1 Cell #1
C • Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #3
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #3
C , , Crib Wall #1 Cell#l
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell#l
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
e Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
841363-009
Carlsbad Golf Course
0
0
Station 10+55
Station 10+30
Station 10+00
Station 9+72
Station 9+48
Station 9+10
Station 9+00
Station 8+67
Station 8+30
Station 7+93
Station 7+75
Station 7+48
Station 10+60
Station 10+20
Station 9+90
Station 9+40
Station 9+15
Station 8+80
Station 8+52
Station 8+10:
Station 7+90
Station 7+60
Station 7+41
Station 10+80
Station 10+50
Station 10+28
Station 10+05
Station 9+77
Station 9+55
Station 9+32
Station 9+10
Station 8+75
Test
Elev (ft)
246.0
245.0
246.0
244.0
245.0
244.0
246.0
245.0
246.0
346.0
345.0
346.0
347.0
346.0
347.0
346.0
347.0
346.0
347.0
246.0
247.0
246,0
247.0
248.0
247.0
248.0
247.0
248.0
247.0
248.0
247.0
248.0
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
108.6
108.3
108.4
109.5
108.1
• 109.6
109.5
108,0
108,4
108.2
109.9
108,3
108,4
108,3 .
109,4
109,6
108,0
108,2
108.1
109.3
108.6
109.1
108.0
109.3
107.7
106.4
105.9
106.2
106.4
106.2
107.0
106,4
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120,0
120.0
120.0
120.0
120,0
120.0
120,0
120.0
118.0
118.0
118.0
118,0
118,0
118,0
118,0
118,0
118,0
12,2
12,3
11.8
13,4
13,5
14.3
13,6
12,2
12,6
12,8 .
13.4
13.6
16.0
13,0
13,0
13,7
13.4
12.6
14.2 •'
13.4
15.0
13.5
14.6
10.2
10.2
11.6
10.9
11.5
11.0
13.5
12.5
13.5
12.0
12,0
12,0
12,0
12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
- 12.0
12,0
12,0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0 .
12.0
12.0
12.0
12,0
90
90
90
91
90
91
91
90
90
90
92
90
90
90
91
91
90
90
90
91
90
91
90
93
91
90
90
90
90
90 •
91
90
Page 13 of39
3/9/2007 1 f^-nnviti/i
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
CW 411 3/8/06 C Crib Wall#l Cell #2 Station 8+45
CW 412 3/8/06 C Crib Wall#l Cell#l Station 8+20
CW 413 3/8/06 C Crib Wall#l Cell #2 Station 7+97
CW 414 3/8/06 C Crib Wall#l Cell#l Station 7+76
CW 415 3/8/06 C Crib Wall#l Cell #2 Station 7+55
CW 416 3/8/06 C Crib Wall #1 Cell #1 Station 7+37
CW 417 3/8/06 C Crib Wall#l Cell #3 Station 7+20
CW 418 3/8/06 C Crib Wall #1 Cell #2 Station 7+05
CW 419 3/8/06 C Crib Wall #1 Cell#l Station 6+89
CW 420 3/8/06 C Crib Wall#l Cell #3 Station 6+25
CW 421 3/8/06 C Crib Wall#l Cell #2 Station 6+50
CW 422 3/8/06 C Crib Wall#l Cell #1 Station 6+28
CW 423 3/8/06 C Crib Wall#l Cell #2 . Station 6+15
CW 424 3/9/06 C Crib Wall #1 Cell# l Station 10+50
CW 425 3/9/06 C Crib Wall#l Cell #2 Station 10+00
CW 426 3/9/06 C Crib Wall#l Cell #1 Station 9+50
CW 427 3/9/06 C Crib Wall#l Cell #2 Station 9+00
CW 428 3/9/06 C Crib Wall#l Cell #1 Station 8+50
CW 429 3/9/06 C Crib Wall #1 Cell #2 Station 8+00
CW 430 3/9/06 c Crib Wall#l Cell#l Station 7+50
CW 431 3/9/06 c Crib Wall #1 Cell #3 Station 7+00
CW 432 3/9/06 c Crib Wall#l Cell #2 Station 6+75
CW 433 3/9/06 c Crib Wall#l Cell#l Station 6+50
CW 434 3/9/06 . c Crib Wall#l Cell #2 Station 6+10
CW 435 3/10/06 c Crib Wall #1 Cell #1 Station 7+23
CW 436 3/10/06 c Crib Wall#l Cell #2 Station 7+00
CW 437 3/10/06 c Crib Wall#l Cell #3 Station 6+65
CW 438 3/10/06 c Crib Wall#l Cell#l Station 6+70
CW 439 3/10/06 c Crib Wall#l Cell #2 Station 6+50
CW 440 3/14/06 c Crib Wall#l Cell#l Station 10+65
CW 441 3/14/06 c Crib Wall#l Cell #2 Station 10+30
CW 442 3/14/06 c Crib Wall#l Cell#l Station 9+80
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
247.0
248.0
247.0
248.0
247.0
248.0
240.0
241.0
242.0
240.0
241.0
242.0
241.0
249.0
248.0
249.0
248.0
249.0
248.0
249.0
243.0
. 244.0
245.0
244.0
246,0
245,0
244.0
246.0
245.0
250.0
249.0
250.0
7
7
7
7
7
7
7
7
1
7
7
7
7
1
1
7
7
7
7
1
7
7
7
107,0
107,6
109,6
108.8
109.3
108.6
106,5
107,2
107,6
106.1
106.9
106.4
107,4
109.3
108.5
106.8
107,5
106,1
107.8
109.5
107.2
107.8
106.4
109.3
116.6
109.4
108.0
108.0
107.7
106.3
106.2
106.1
118.0
118.0
118.0
118.0
118,0
118,0
118.0
118.0
120.0
118,0
118,0
118,0
118,0
120,0
120.0
118.0
118.0
118.0
118.0
120,0
118,0
118,0
118.0
120.0
120.0
120.0
120.0
120.0
120,0
118,0
118,0
118,0
14.2
13.1
13.6
14.8
14,0
13,9
11.6
12.7
12.2
15.0
12.9
12.2
13.4
14.0
13.8
12.0
1 1.6
13.5
14.2
12.7
13.9
13.1
13.6
14.4
8.9
15.4
15.3
15.8
14.7
13.7
16.5
14.4
12,0
12,0
12,0
12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12,0
12.0
12,0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
91
91
93
92
93
92
90
91
90
90
91
90
91
91
90
91
91
90
91
91
91
91,
90
91
97
91
90 •
90
90
90
90
90
Page 14 of 39
3/9/2007 1 •^5n9PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
CW 443 3/14/06 C Crib Wall#l Cell #2 Station 9+40
CW 444 3/14/06 C Crib Wall #1 Cell #1 Station 9+20
CW 445 3/14/06 c Crib Wall #1 Cell #2 Station 9+90
CW 446 3/14/06 c Crib Wall #1 Cell#l Station 8+70
CW 447 3/14/06 c Crib Wall#l Cell #2 Station 8+40
CW 448 3/14/06 c Crib Wall #1 Cell #1 Station 8+10
CW 449 3/14/06 c Crib Wall#l Cell #2 Station 7+80
CW 450 3/14/06 c Crib Wall#l Cell #1 Station 7+65
CW 451 3/14/06 c Crib Wall#l Cell #2 Station 7+48
CW 452 3/14/06 c Crib Wall#l Cell#l Station 7+25
CW 453 3/14/06 c Crib Wall#l Cell #2 Station 6+95
CW 454 3/14/06 c Crib Wall#l Cell # I Station 6+75
CW 455 3/14/06 c Crib Wall #1 Cell #2 Station 6+50
CW 456 3/15/06 c Crib Wall#l Cell #3 Station 5+55
CW 457 3/15/06 c Crib Wall#l Cell #2 Station 5+40
CW 458 3/15/06 c Crib Wall#l Cell#l Station 5+25
CW 459 3/15/06 c Crib Wall#l Cell #3 Station 5+00
CW 460 3/15/06 c Crib Wall#l Cell #2 Station 4+75
CW 461 3/15/06 c Crib Wall#l Cell#l Station 4+50
CW 462 3/15/06 c Crib Wall#l Cell #4 Station 4+60
CW 463 3/16/06 c Crib Wall #1 Cell #1 Station 5+90
CW 464 3/16/06 c Crib Wall#l Cell #2 Station 5+70
CW 465 3/16/06 c Crib Wall#l Cell #3 Station 5+40
CW 466"^ 3/16/06 c Crib Wall #1 Cell #1 Station 5+10
CW 467 3/16/06 c Crib Wall #1 Cell #2 Station 4+80
CW 468 3/16/06 c Crib Wall#l Cell #3 Station 4+55
CW 469 3/16/06 c Crib Wall#l Cell #4 Station 4+35
CW 470 3/16/06 c Crib Wall#l Cell #3 Station 4+10
CW 471 3/16/06 c Crib Wall #1 Cell #2 Station 3+80
CW 472 3/16/06 c Crib Wall#l Cell#l Station 3+50
CW 473 3/16/06 c Crib Wall#l Cell #4 Station 3+30
CW 474 3/17/06 c Crib Wall #1 Cell #3 Station 5+97
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
249,0 1 110.7 120.0 14,0 12,0 92
250,0 1 112,6 120,0 12,2 12,0 94
249.0 1 108,6 120,0 16,0 12,0 90
250.0 1 107,7 120.0 14,2 12,0 90
249.0 1 108.5 120.0 14,2 12,0 90
250.0 7 . 106,1 118.0 15,0 12,0 90
249.0 7-106.7 118.0 13,5 12,0 90
250.0 7 106,5 118.0 13,5 ' 12,0 90
249.0 7 106,6 118.0 14,9 12,0 90
246.0 7 106,4 118.0 13,5 12,0 90
245.0 7 105,7 118,0 10,7 12,0 90
246.0 7 - 106,5 118,0 11,6 12.0 90
245.0 7 107,3 118.0 11,8 12.0 91
241.0 7 106,7 118.0 13,9 12.0 90
242,0 1 109,2 120.0 15,9 12.0-91
243,0 1 112,8 120.0 13,7 12.0 94
241.0 1 113,3 120.0 12,6 12.0 94
242.0 1 109,0 120.0 11,7 12.0 91
243.0 1 107.8 120.0 12.9 12.0 90
240.0 1 110.2 120.0 12,8 12.0 92
244.0 1 107.7 120.0 . 11,3 12.0 90
243.0 1 107.4 120.0 11,6 12.0 90
242.0 1 108.0 120,0 12,4 • 12,0 90
244.0 1 107,7 120,0 12,5 12,0 90 243.0 7 106,0 118,0 12,0 12,0 90
242.0 7 107,9 118,0 12,1 12,0 91 341.0 1 107.4 120,0 13,0 12,0 90 342.0 1 108.3 120,0 11.9 12,0 90 343.0 1 110.7 120,0 11.2 12,0 92
344.0 1 108,0 120,0 12.2 12,0 90
341.0 1 108.4 120,0 12.6 12,0 90
243.0 1 10S.4 120,0 10.7 12,0 90
Page 15 of 39
3/9/2007 1 •'! "i.mDA/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 475
CW 476
CW 477
CW 478
CW 479
CW 480
CW 481
CW 482
CW 483
CW 484
CW 485
CW 486
CW 487
Jew 488
CW 489
CW 490
CW 491
CW 492
CW 493
CW 494
CW 495
CW 496
CW 497
CW 498
Jew 499
CW 500
CW 501
CW 502
CW 503
CW 504
CW 505
CW 506
Test
Date
Test
Of
Location
Lot#
3/17/06
3/17/06
3/17/06
3/17/06
3/17/06
3/17/06
3/17/06
3/17/06
'- 3/17/06
3/17/06
3/17/06
3/17/06
3/17/06 C
3/17/06 C
3/17/06 C
3/17/06 C
3/20/06 C
3/20/06 C
3/20/06 C
3/20/06 C
3/20/06
3/20/06
3/20/06
3/20/06
3/20/06
3/20/06
3/20/06
3/20/06
3/20/06
3/22/06
Project Number:
Project Name:
Project Location:
Client:
C
C
c
c
c c
c
c
c c
c
c
c
c c
c
3/20/06 C
C
C
C
C
C
C
3/22/06 C
Crib Wall#l Cell #2
Crib Wall #1 eeir#l
Crib Wall#l Cell #2
Crib Wal!.#l Cell #3
Crib Wall#l Cell #1
Crib Wall #1 Cell #2'
Crib Wall #1 Cell #3
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #3
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #4
Crib Wall #l Cell #3
Crib Wall #1 Cell #2
Crib Wall #1 Cell #4
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall #1 Cell #1
Crib Wall#l Cell #2
Crib Wall #1 Cell #2 .
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #1
Crib Wall#l Cell #2
Crib Wall #1 Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l CeH #l
Crib Wall#l Cell #2
841363-009
Carlsbad Golf Course
0
0
Station 5+65
Station 5+52
Station 5+30
Station 5+00
Station 4+70
Station 4+45
Station 4+30
Station 4+20
Station 4+00
Station 3+80
Station 3+60
Station 3+40
Station 3+20
Station 3+00
Station 2+80
Station 2+90
Station 10+00
Station 9+70
Station 9+40
Station 9+10
Station 10+20
Station 10+40
Station 10.+60
Station 10+75
Station 8+90
Station 8+60
Station 8+20
Station 7+90
Station 7+60
Station 7+48
Station 3+85
Station 3+55
Test
Elev (ft)
244.0
245.0
244.0
243.0
245.0
244.0
243.0
244.0
245.0
243.0
244.0
245.0
242.0
243.0
244.0
242.0
251.0
250.0
251.0
250.0
250.0
251.0
250.0
251.0
251.0
250.0
251:0
250.0
251.0
250.0
245.0
244.0
Soil
Type
I
1
. 1
,1.
7
7
7
7
7
7
7
7
7
7
7 •
7
"7
7
7
1
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
108.1
107.8
110.0
107,6
106,4
107,5
109,1
105,9
105,7
107.3
106.3
106.0
106,8
106,2
108,2
107,4
106,5
106,5
106,9
107.0
108,6
109.5
108.1
109.1
107.8
109,4
106,9
108,6
108,3
106,6
106,3
106.4
120,0
120,0
120,0
120.0
118.0
118.0
118,0
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118,0 .
118.0
118,0
118.0
118.0
118.0
120.0
120.0
120.0
120.0
120,0
120,0
118,0
120,0
120,0
118.0
118.0
118,0
11.9
10.3
10,8
1 1,5
12,7
11,4
9,0
14,4
14,0
12.4
13,0
14.0
14.8
10.9
13.6
13.5
10.3
15.8
15,7
12,6
14,8
11,8
13,2
14,7
12.0
12.3
10.3
9.4
9.6
11.6
10.2
12,0
12,0
12,0
12,0
12.0
12,0
12,0,
12.0
12.0
12.0
12.0
12,0
12,0
12,0
12.0
12,0
,12,0
.12,0
12,0
12,0
12.0
12.0
12,0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12.0
12.0
90
90
92
90 .
90
91
92
90
90 •
91
90
90
91
90
92
91
90
90
91
91
90
91
90 -
91
90
91
91
90
90
90
90
90
Page 16 of 39
3/9/2007 1 •'!5•^^D^/r
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
CW 507 3/22/06 C Crib Wall #1 Cell #3 Station 3+30
CW 508 3/22/06 C Crib Wall #1 Cell #1 Station 3+05
CW 509 3/22/06 c . Crib Wall #1 Cell #4 Station 3+10
CW 510 3/22/06 c Crib Wall#l Cell #3 Station 2+95
CW 511 3/22/06 c Crib Wall #1 Cell #2 Station 2+77
CW 512 3/22/06 c Crib Wall#l Cell#l Station 2+50
CW 513 3/22/06 c Crib Wall #1 Cell #3 Station 5+90
CW 514 3/22/06 c Crib Wall #1 Cell #2 Station 5+65
CW 515 3/22/06 c Crib Wall#l Cell#l Station 5+35
CW 516 3/22/06 c Crib Wall#l Cell #3 Station 4+98
CW 517 3/22/06 c Crib Wall#l Cell#l Station 4+77
CW 518 3/22/06 c Crib Wall#l Cell #2 Station 4+57
CW 519 3/23/06 c Crib Wall #1 Cell #3 Station 4+25
CW 520 3/23/06 c Crib Wall#l Cell#l Station 3+90
CW 521 3/23/06 c Crib Wall #1 Cell #2 Station 3+65
CW 522 3/23/06 c Crib Wall#l Cell #3 Station 3+10
CW 523 3/23/06, c Crib Wall#l Cell#l • Station 2+85
CW 524 3/23/06 c Crib Wall#l Cell #2 Station 2+65
CW 525 3/23/06 c Crib Wall #1 Cell #3 Station 2+35
CW 526 3/23/06 c Crib Wall #1 Cell#l Station 2+10
CW 527 3/23/06 c Crib Wall#l Cell #2 Station 1+90
CW 558 3/24/06 c Crib Wall#l Cell #3 Station 4+00
CW 559 3/24/06 c Crib Wall#l Cell #2 Station 3+50
CW .560 3/24/06 . c Crib Wall#l Cell #1 Station 3+00
CW 561 3/24/06 c Crib Wall #1 Cell #3 Station 2+50
CW 562 3/24/06 c Crib Wall#l Cell #2 Station 2+00
CW 563 3/24/06 c Crib Wall#l Cell#l Station 1+50
CW 564 3/24/06 c Crib Wall #1 Cell #2 Station 1+00
CW 565 3/24/06 c Crib Wall #1 Cell#l Station 5+76
CW 566 3/24/06 c Crib Wal[#l Cell #2 Station 5+25
CW 567 3/24/06 c Crib Wall #1 Cell #3 Station 4+75
CW 568 3/24/06 c Crib Wall#l Cell#l Station 4+25
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
243.0 7 107,2 118,0 1 1,5 12,0 91
245.0 7 107,0 118,0 12,6 12,0 91
242.0 7 106,0 118,0 13,0 12,0 90
243.0 7 107.4 118,0 11,6 12.0 91
243.0 7 -106,8 118,0 14,3 12,0 91
245.0 7 • 107,4 118,0 14,1 12,0 91
244.0 7 108.0 118,0 11,1 12.0 92
245.0 7 108,8 118,0 11,7 12.0 92
246.0 ' 7 106,3 118,0 11,2 12,0 90
244.0 - 7 107,8 118,0 13,3 12,0 91
246.0 7 106,1 118,0 11,6 12,0 90
245.0 7 106,8 118,0 12,2 12,0 91
244.0 7 106,5 118,0 .11,4 12,0 90
246.0 7 106,0 118,0 18,0 12,0 90
245.0 7 106,2 1 IS.O 12,7 12,0 90
244.0 7 106.3 118.0 12,2 12,0 90
246.0 7 106.5 118,0 10,3 12,0 90
245.0 7 106.5 118.0 12,4 12,0 90
244.0 1 110.3 120.0 11,0 12,0 92
246.0 1 108.2 120.0 14,9 12.0 90
245.0 1 108.0 120,0 -13,3 12,0 90
245.0 1 108.8 120.0 10,8 12,0 91
246.0 i 108.1 120.0 13,5 12,0 90
247.0 1 108.0 120.0 14,3 . 12,0 90
245.0 7 106.4 118.0 11,0 12,0 90
246.0 1 113,1 120.0 12.8 12,0 94
247.0 1 109,3 120,0 12.5 12.0 91
246,0 1 108.4 120,0 13.4 12.0 90
248,0 1 108.6 120,0 1 1.5 12.0 90
247.0 7 105,8 118,0 11.3 12.0 90
246.0 3' -104.4 114.5 13.7 12.5 91
248.0 7 107,1 118,0 12.6 12.0 91
Page 17 of 39
3/9/2007 1 ••^S-07PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
CW 569 3/24/06 C Crib Wall#l Cell #2 Station 3+75
CW 570 3/27/06 c Crib Wall#l Cell #3 Station 3+25
CW 571 3/27/06 c Crib Wall#l Cell#l Station 2+75
CW 572 3/27/06 c Crib Wall #1 Cell #2 Staton 2+25
CW 573 3/27/06 c Crib Wall#l Cell #3 Station 2+08
CW 574 . '3/27/06' c. Crib Wall#l Cell#l Station 1+87
CW 575 3/27/06 c Crib Wall#l Cell #2 Station 1+50
CW 576 3/27/06 c Crib Wall#l Cell#l Station 1+00
CW 577 3/27/06 c Crib Wall#l Cell #2 Station 0+50
CW 578 3/30/06 c Crib Wall#l Cell #2 Station 7+25
CW 579 3/30/06 c Crib Wall#l Cell#l Station 7+00
CW 580 3/30/06 c Crib Wall#l Cell #2 Station 6+75
CW 581 3/30/06 c Crib Wall#l Cell #1 Station 6+50
CW 582 3/30/06 c Crib Wall#l Cell #2 Station 6+25
CW 583 3/30/06 c Crib Wall#l Cell#l Station 6+00
CW 584 3/30/06 c Crib Wall#l Cell #2 Station 5+75
CW 585 3/30/06 c Crib Wall#l Cell#l Station 5+50
CW 586 3/30/06 c Crib Wall#l Cell #2 Station 5+20
CW 587 3/30/06 c Crib Wall #1 Cell #1 Station 3+00
CW 588 3/30/06 c Crib Wall#l Cell #3 Station 4+75
CW 589 3/30/06 c Crib Wall #1 Cell #2 Station 4+50
CW. 590 3/30/06 c Crib Wall#l Cell#l Station 4+70
CW 591 3/30/06 c Crib Wall#l Cell #3 Station 4+00
CW 592 3/30/06 c Crib Wall#l Cell #2 Station 3+75
CW 593 ' 3/30/06 c Crib Wall#l Cell #1 Station 3+50
CW 594 3/30/06 c Crib Wall #l Cell #3 Station 3+25
CW 595 3/30/06 c Crib Wall#l Cell #2 Station 3+00
CW 596 3/30/06 c Crib Wall #1 Cell #1 Station 2+65
CW 597 3/30/06 c Crib Wall #1 Cell #3 Station 2+42
CW 598 3/30/06 c Crib Wall#l Cell #2 Station 2+20
CW 599 3/30/06 c Crib Wall #1 Cell#l Station 1+95
CW 600 3/30/06 c Crib Wall#l Cell #2 Station 1+75
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
247.0
246.0
248.0
247.0
246.0
248.0
247.0
248.0
247.0
248.0
249.0
248.0
249.0
248.0
249.0
248.0
249.0
248.0
249.0
247.0
248.0
249.0
247.0
248.0
249.0
247.0
248.0
249.0
247.0
248.0
249.0
248.0
Soil
Type
7
7
7
7
7
7
- 7
7
1
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
Dry Density
Field Max
107,0
106.9
106.6
106,4
- 108,7
105,8
' 107.1
108,0
115,0
109,9
109,9
108,1
107,7
108,7
110.9
109.6
106,1
106.0
106.4
107.7
108.0
106.1
105.9
108.0
107.1
107,0
108,3
106,9
108,5
107.2
110.6
109.7
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
120.0
120.0
120,0
120.0
120,0
120.0
120.0
120.0
118,0
118.0
118.0
118.0
118.0
118.0
118.0
118.0 •
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118,0
Moisture (%) Relative (%)
Field Opt. Compaction Remarks
13,2
12.7
10.8
10.6
14.4
13.5
13.7
15,8
1 1,6
17,0
14,5
13,3
17,8
16,4
14,4
15,1
13,1
14,3
12,7
12,4
12,8 ,
12,0 ,
12,8
13,1
12,0
17,9
15,1
12,2
12,0
15,4
14,6
12.0
12.0
12.0
12.0
12.0
12,0
12.0
12.0
12,0
12,0
12.0
• 12.0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0 .
12,0
12,0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
91
91
90
90
92
90
91
92
96
92
92
90
90
91
92
91
90
90
90
91
92
90
90
92
91
91
92
91
92
91
94
93
Page 18 of 39
1 •15-n9PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 601
CW 602
CW 603
CW 604
CW 605
CW 606 .
CW 607
CW 607A
CW 608
CW 608A
CW 609
CW 610
CW 611
CW 612
CW 613
CW 614
CW 615
CW 616
CW 617
CW 618
CW 619
CW 620
CW 621
CW 622
CW 623
CW 624
CW 625
CW 626
CW 627
CW 628
CW 629
CW 630
Test
Date
Test
Of
Location
Lot#
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/3/06
4/4/06
4/4/06
4/4/06
3/30/06
3/30/06
3/30/06
3/31/06
3/31/06
3/31/06
3/31/06 C
, 4/3/06 • C
3/31/06 C
3/31/06 C
3/31/06 C
3/31/06 C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
Project Number:
Project Name:
Project Location:
Client:
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wan #l Cell #2 •
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell #T
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#r Cell #3
Crib Wall#l Cell #2
Crib Wall #1 Cell#l
Crib Wall#l Cell #3
Crib Wall#l Cell #2
Crib Wall #l Cell#l
Crib Wall #1 Cell #3'
Crib Wall #1 Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
841363-009
Carlsbad Golf Course
0
0
Station 1+50
Station 1+25
Station 1 + 10
Station 0+90
Station 0+70
Station 0+57
Station 7+35
Station 7+35
Station 7+15
Station 7+15
Station 6+90
Station 6+65
Station 6+45
Station 6+25
Station 6+05
Station 5+85
Station 5+55
Station 5+00
Station 4+70
Station 4+50
Station 4+25
Station 4+05
. Station 3+80
Station 3+55
Station 3+30
Station 3+00
Station 2+60
Station 2+20
Station 1+95
Station 1+75
Station 1+50
Station 1+25
Test
Elev (ft)
249,0
248.0
248.0
249.0
248.0
249.0
250.0
250.0
249.0
249,0
250.0
249.0
250.0
249.0
250.0
249.0
250.0
249.0
250.0
249.0
248.0
249.0
250.0
248.0
249.0
250.0
248.0
249.0
250.0
249.0
250.0
249.0
Soil
Type
7
7
7
7
7
7
7
7
•7
7
7
7
7
"7
7
7
7
7
7
7
7
7
7
,7
7
7
7
7
7
7
7
7
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
106.7
107.4
106.1
109.2
106.8
110.2
104.2
106.7
106.6
106.5
106.5
108.2
106.0
106.2
106.0
107.4
106.2
105.8
106.4
107.6
108.1
106.3
106.0
105.7
107,3 .
106.7
108.6
107.4
106,0
107.3
107J
108,1
118,0
118,0
118,0
118.0
118,0
, 118,0
118,0
118,0
118.0
118,0
118.0
118,0
118,0
118,0
118.0,
118,0
118,0
118,0
118,0
118,0
118.0
118.0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
16,1
14,4
14,1
13,0
12,5
12,1
^9,0
tl,2
10,2
13,3
13,9
12,0
13,1
12.6
11,1
13,3
11,3
14,7
11,5
16,0
12,1
.11,8
11,2
12,7
13,6
13,1
14,6
14,0
12,0
13,6
12,1
12.0
12,0
12,0
12,0
-12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
90
91
90
93
91
93
88
90
90
90
90
92
90
90
90
91
90
90
90
91
92
90
90
90
91
90
92,
91
90
91
91
92
Retest on 607A
Retest of 607 •
Retest on 608A
Retest of 608
Page 19 of 39
3/9/2007 I •'^5•n9P^.f
Test
No.
SUMMARY OF FIELD DENSITY TESTS
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
CW 631 4/4/06 C Crib Wall #1 Cell#l Station 1+00
CW 632 4/4/06 C Crib Wall#l Cell #2 Station 0+75
CW 633 4/4/06 C Crib Wall#l Cell#l Station 0+50
CW 634 4/4/06 C Crib Wall #1 Cell #1 Station 0+35
CW 635 4/4/06 C Crib Wall#l Cell #2 Station 0+88
CW 636 4/4/06 C Crib Wall#l Cell#l Station 1+40
CW 637 4/4/06 C Crib Wall#l Cell #2 Station 1+85
CW 638 4/4/06 C Crib Wall#l Cell#l Station 2+37
CW 639 4/4/06 C Crib Wall#l Cell #2 Station 2+80
CW 640 4/4/06 C Crib Wall#l Cell#l Station 6+29
CW 641 4/4/06 c Crib Wall#l Cell #2 Station 6+50
CW 642 4/4/06 c Crib Wall#l Cell#l Station 6+75
CW 643 4/4/06 c . Crib Wall #1 Cell #2 Station 7+00
CW 644 4/4/06 c Crib Wall#l Cell#l Station 7+25
CW 645 4/4/06 c Crib Wall#l Cell #2 Station 7+40
CW 646 4/4/06 c Crib Wall#l Cell#l Station 6+00
CW 647 4/4/06 c Crib Wall#l Cell #2 Station 5+75
CW 648 4/4/06 c Crib Wall#l Cell#l Station 5+50
CW 649 4/4/06 c Crib Wall#l Cell #3 Station 3+10
CW 650 4/4/06 c Crib Wall#l Cell #2 Station 3+60
CW 651 4/4/06 c Crib Wall#l Cell#l Station 4+10
CW 652 4/7/06 c Crib Wall#l Cell#l Station 10+73
CW 653 4/7/06 c Crib Wall#l Cell #2 Station 10+53
CW 654 4/7/06 c Crib Wall#l Cell#l Station 10+33
CW 655 4/7/06 c Crib WaH #l Cell #2 Station 10+13
CW 656 4/7/06 c Crib Wall#l Cell#l Station 9+83
CW 657 4/7/06 c Crib Wall #1 Cell #2 Station 9+63
CW 658 4/7/06 c Crib Wall#l Cell#l Station 9+43
CW 659 4/7/06 c Crib Wall#l Cell #2 Station 9+23
CW 660 4/7/06 c Crib Wall#l Cell #1 Station 9+03
CW 661 4/7/06 c Crib Wall#l Cell #2 Station 8+73
CW 662 4/7/06 c Crib Wall#l Cell#l Station 8+53
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
250.0 7 108.8 118,0 15.2 12,0 92
249.0 .7 108.5 118,0 13,0 12,0 92
250.0 7 107.3 118,0 15,7 12,0 91
251.0 7 106.7 118,0 16,0 12,0 90
250.0 7 107.8 118,0 16,7 12,0 91
251.0 7 106.9 118,0 15,1 12.0 91
250.0 7 106.6 118,0 17,1 12.0 90
251.0 7 106.8 118.0 16,6 12.0 91
250.0 7 108.8 118,0 13,6 12,0 92
251.0 7 106.0 118,0 12,0 12,0 90
250.0 7 106.7 118,0 12,5 12,0 90
251.0 7 108.6 118,0 12,0 12,0 , 92
250.0 7 107.7 118,0 14,4 12,0 91
251.0 7 105.7 118.0 11,0 12,0 90
250.0 7 106.3 118.0 12.6 12,0 90
251.0 7 106.4 118.0 12.7 12,0 90
250.0 7 108.9 118.0 12.0 12,0 92
251.0 7 108.7 118,0 15.2 12,0 92
249.0 7 106.4 118.0 12.9 12,0 90
250.0 7 106.1 118.0 17.3 12,0 90
251.0 7 108.5 118.0 12.9 12,0 92
253.0 7 106.9 118.0 16.7 12.0 91
252.0 7 107.1 118.0 13.1 12.0 91
253.0 7 107,6 118,0 12.1 12.0 91
252.0 7 110,1 118,0 12,8 12.0 93
253.0 1 110.5 120.0 11,8 12,0 92
252.0 1 108.3 120.0 17,1 12,0 90
253.0 1 107.8 120,0 13.5 12.0 90
252.0 1 108.0 120.0 13.9 12,0 90
253.0 1 108,0 120,0 13.3 12.0 90
252.0 1 108,4 120.0 17.3 12,0 90
253.0 1 107,5 120.0 12.1 12,0 90
Page 20 of 3 9
^/Q/9007 1 -K-niUT^A
SUMMARY OF FIELD DENSITY TESTS
Test
No,
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
CW 663
CW 664
CW 665
CW 666
CW 667
CW 668
CW 669
CW 670
CW 671
CW 672
CW 673
CW 674
CW 675
CW 676
Jew 677
CW 678
CW 679
CW 680
CW 681
CW 682
CW 683
CW 683A
CW 684
CW 684A
CW 685
CW 686
CW 687
CW 688
CW 689
CW 690
CW 691
CW 692
4/7/06
4/7/06
4/7/06
4/7/06
4/7/06
4/7/06
, 4/7/06
4/7/06
4/7/06
4/8/06
4/8/06
4/8/06
4/8/06 | C
4/8/06
4/8/06
4/8/06
4/8/06
4/8/06
4/8/06
4/8/06
4/8/06
4/8/06
4/8/05
4/9/05
4/8/05
4/8/05
4/8/05
4/8/05
4/8/05
4/8/05
4/8/05
4/8/05
Project Number:
Project Name:
Project Location:
Client:
C - Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell tfl
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
-C Crib Wall #1 Cell #1
Crib Wall#l Cell #2
C Crib Wall #1 Cell#l
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #3
C Crib Wall #1 Cell #3
C Crib Wall #1 Cell #1
C Crib Wall #i Cell#l
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #2
C Crib Wall#l Cell#l
C Crib Wall #1 Cell #2
C Crib Wall #1 Cell #1
841363-009
Carlsbad Golf Course
0
0
Station 8+33
Station 8+10
Station 7+80
Station 7+60
Station 7+40
Station 7+20
Station 7+00
Station 6+75
Station 6+50
Station 6+02
Station 5+75
Station 5+50
Station 5+25
Station 5+00
Station 4+75
Station 4+50
Station 4+25
Station 4+00
Station 3+75
Station 3+50
Station 3+25
Station 3+25
Station 3+00
Station 3+00
Station 2+70
Station 2+45
Station 2+15
Station 2+00
Station 1+75
Station 1+50
Station 1+00
Station 0+50
252.0
253.0
252.0
253.0
252.0
253.0
252.0
253.0
262.0
253.0
252.0
253.0
252.0
253.0
252.0
253.0
252.0
253.0
252.0
253.0
251.0
251.0
253.0
253.0
252.0
253.0
252.0
253.0
252.0
253.0
252.0 -
233.0
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
109.1
108.9
108.1
110.1
107,9
108.3
107.8
109.6
108,4
108,0
107,3
106,6
105,7
105,9
107,0
106,4
105,9
106,2
106.9
107.0
102.2
106.5
105.8
106.9
107.1
108,6
107.5
106.8
107.3
107.2
108.3
107,9
120,0
120,0
120,0
120,0
120,0
120.0
120.0
120,0
120,0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118,0
118,0
14,0
17,4
17,6
13.1
12,5
13,6
13,6
13,0
13,9
14,1
13,1
12,1
11,9
11,5
12.1
14.7
12.9
11.9
12.3
12.0
9.6
12.0
10:2
13.2
12.2
13.1
12.2
14.4
11.7
12.3
12.0
11.7
12,0
12,0
12,0
• 12,0
12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12,0
12,0
91
91
90
92
90
- 90
90
91
90
92
91
90
90
90
91
90
90
90
91
91
87
90
90
91
91
92
91
91
91
91
92
91
Retest on 683A
Retest of 683
Retest on 684A
Retest of 684
Page 21 of 39
3/9/2007 1 •^5-n9PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
CW 693 4/10/05 C Crib Wall #1 Cell #2 Station 0+65
CW 694 4/10/05 c Crib Wall#l eell#l Station 10+45
CW 695 4/10/05 e Crib Wall #1 Cell #2 Station 10+25
CW 696 4/10/05 c Crib Wall #1 Cell # I Station 10+00
CW 697 4/10/05 c Crib Wall #1 Cell #2 Station 9+75
CW 698 4/10/05 c Crib Wall #1 Cell #2 Station 9+50
CW 699 4/10/05 c Crib Wall#l Cell #2 Station 9+25
CW 700 4/10/05 c Crib Wall #1 Cell#l Station 9+00
CW 701 4/10/05 c Crib Wall#l Cell #2 Station 8+80
CW 702 4/10/05 c Crib Wall #1 Cell#l Station 8+50
CW 703 4/10/05 c Crib Wall#l eell#l Station 8+25
CW 704 4/10/05 c Crib Wall#l Cell#l Station 8+00
CW 705 4/10/05 c Crib Wall#l Cell#l Station 7+80
CW 706 4/10/05 e Crib Wall#l Cell #2 Station 7+50
jew 707 4/10/05 c Crib Wall#l Cell#l Station 7+10
CW 708 4/11/06 c Crib Wall #1 Cell #2 Station 6+90
CW 709 4/11/06 c Crib Wall #1 Cell#l Station 6+65
CW 710 4/11/06 c Crib Wall#l Cell #2 Station 6+35
CW 711 4/11/06 c Crib Wall#l Cell#l Station 5+90
CW 712 4/11/06 c Crib Wall #1 Cell #2 Station 5+65
CW 713 4/11/06 c Crib Wall #1 Cell #1 Station 5+40
CW 714 4/11/06 e Crib Wall#l Cell #2 Station 5+10
CW 715 4/11/06 c Crib Wall#l Cell#l. Station 4+90
CW 716 4/11/06 c Crib Wall #1 Cell #2 Station 4+65
CW 717 4/11/06 c Crib Wall #1 Cell#l Station 4+40
CW 7.18 4/11/06 c Crib Wall #1 Cell #2 Station 4+15
CW 719 4/11/06 c Crib Wall #1 Cell#l Station 3+90
lew 720 4/11/06 e Crib Wall #1 Cell #2 Station 3+65
CW 721 . 4/11/06-c Crib Wall #1 Cell#l Station 3+40
CW 722 4/11/06 c Crib Wall #1 Cell #2 Station 3+20
CW 723 4/11/06 c Crib Wall#l Cell#l Station 2+90
CW 724 4/11/06 c Crib Wall #1 Cell #2 Station 2+60
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
253.0 1 110.9 120.0 12.3 12.0 92
254.0 1 108,9 120.0 12.0 12.0 91
253.0 1 109,3 120.0 12.5 • 12,0 , 91
'254.0 7 108,6 118.0 15.3 12,0 92
253.0 7 ',..107.6 118.0 12.7 12:0 91
254.0 7 106.1 118.0 13.4 ', - " 12.0 90
253.0 7 106.5 118,0 12.3 - 12.0 90
254.0 : 7 106,8 118.0 14,7 12,0 91
253.0 7 107,0 118.0 16,1 12,0 91
254.0 7 107,5 118.0 12,0 12,0 91
254.0 7 107,0 118.0 13,1 12,0 91
254.0 7 108,0 118.0 12,3 •12.0 92
254.0 7 106.1. 118,0 13,0 12,0 90
253.0 7 106.8 118,0 17,6 • 12,0 91
254.0 7 106.9 118,0 16.1 12,0 91
253.0 . 7 -107.0 118,0 15.5 12,0 91
254.0 1 110.6 120.0 13:7 12,0 , 92
253.0 1 108.1 120,0 1 1.6 12,0 90
254.0 7 106.9 118,0 13,4 12,0 91
253.0 7 106.0 118,0 11,0 12.0 ,90
254.0 7 106.3 118.0 12,0 12.0 90
253.0 7 107.0 118.0 14,7 ' 12.0 91 254.0 7 -107.8 118.0 12,0 12,0 91
253.0 7 : 107,6 118,0 13,1 12,0 91
254.0 7 107.0 .118,0 11.8 12,0 91
253.0 7 106.9 118,0 11.4 12,0 91 254.0 7 110.5 118.0 12.3 12,0 94 253.0 -7 110.5 118.0 12.7 12,0 94 254,0 7 108.7 118.0 14.4 12,0 92
253.0 7 108.3 118.0 11,9 12,0 92
254.0 7 107.1 118.0 11,8 12,0 91 253,0 7 106.8 118.0 11.0 12.0 91
Page 22 of 39
1 •t'^-nnm^
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
CW 725 4/11/06 C Crib Wall#l Cell#l
CW 726 4/11/06 C Crib Wall#l Cell #2
CW 727, 4/11/06 c Crib Wall#l Cell#l
CW 728 4/11/06 c Crib Wall #1 Cell #2
CW 729 4/11/06 c Crib Wall#l Cell #1
CW 730 4/11/06 c. . Crib Wall #1 Cell #2
CW 731 4/11/06 c Crib Wall #1 Cell#l
CW 732 4/11/06 c Crib Wall #1 Cell #1
CW 733 4/11/06 c Crib Wall#l Cell#l
CW 734 4/11/06 c Crib Wall#l Cell#l
CW 735 4/11/06 c Crib Wall#l Cell#l
CW 736 4/11/06 c Crib Wall#l Cell #2
CW 737 4/11/06 c Crib Wall#l Cell#l
CW 738 4/11/06 c Crib Wall #1 Cell #2
CW 739 4/11/06 c Crib Wall#l Cell#l
CW 740 4/11/06 c Crib Wall#l Cell #2
CW 741 4/11/06 c Crib Wall#l Cell#l
CW 742 4/12/06 c Crib Wall#l Cell#l
CW 743 4/12/06 c Crib Wall#l Cell #2
CW 744 4/12/06 c Crib Wall#l Cell#l
CW 745 4/12/06 c Crib Wall#l Cell#l
CW 746 4/12/06 c Crib Wall #l Cell#l
CW 747 4/12/06 c Crib Wall #1 Cell#l
CW 748 4/12/06 c Crib Wall#l Cell#l
CW 749 4/12/06 c Crib Wall #1 Cell #1
CW 750 4/12/06 c Crib Wall#l Cell#r
CW 751 4/12/06 c Crib Wall#l Cell#l
CW 752 4/12/06 c Crib Wall #1 Cell#l
CW 753 -4/12/06 c Crib Wall #1 Cell#l
CW 754 4/12/06 c Crib Wall#l Cell#l
CW 755 4/12/06 c Crib Wall#l Cell#l
CW 756 4/12/06 c Crib Wall #1 Cell #1
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Station 2+30
Station 2+05
Station 1+88
Station 1+62
Station 1+40
Station 1+15
Station 0+85
Station 0+60
Station 0+40
Station 0+20
Station 10+50
Station 10+00
Station 9+50
Station 9+00
Station 8+50
Station 8+00
Station 7+50
Station 7+00
Station 6+50
Station 6+00
Station 10+37
Station 10+12
Station 9+89
Station 9+57
Station 9+32
Station 8+90
Station 8+65
Station 8+30
Station 7+92
Station 7+65
Station 7+35
Station 7+07
Test
Elev (ft)
254.0
253.0
254.0
- 253.0
253.0
253.0
254.0
254.0
254.0
254.0
255.0
254.0
255.0
254.0
255.0
254.0
255.0
255.0
254.0
255.0
257.0
257.0
257.0
257.0
257.0
257.0
257.0
257.0
257.0
257.0
257.0
257.0
Soil
Type
7
7
7
7
7
7
1-
1
7
7
7
. 7
7
7 •
7
7
7
7
7
7
7
7
7
7
7:
7
7
7
7
7
7
7
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
107.4
106.2
106.8
108.5
106.2
106.4
108.5
106.7
106.8
107.0
106.2
105.8
- 105.9
106,2
108,5
106.4
107,7
106,3
107,4
107.0
110.5
106.4,
107,0
106,6
105,8
106,0
107.3
107.5
109.9
107.2
106.6
106.7
118.0
118.0
118.0
118,0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118.0
118.0
118.0
118,0
118.0
118.0
118.0
118,0
118.0
118.0
118.0
118,0
118,0
118,0
13.6
12,9
12.2
16,8
14,4
16.2'
16,0
16,2
1 1.5
13.3
14,0
12,8
15,5
13,9
15,3
14,3
15,1
15.4
13.6
14.4
15.8
17.5
12,6
16,3
14,5
15,0
14,6
12,0
13,9
14,9
15,0
14,5
12,0
12.0
12.0
12.0
12.0
12.0
12,0
12,0
12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0 '
12,0
12,0
12,0 .
12,0
12.0
12,0
12,0
12,0
12,0
12.0
12,0
12,0
91
90
91
92
90
90
92
90
91
91
90
90
90
90
92
90
91
90
91
91
94
90
91
90
90
90
91
91
93
91
90
90
Page 23 of 39
3/9/2007 l-^5-09PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
CW 757 4/12/06 C Crib Wall#l Cell #1 Station 6+82
CW 758 4/12/06 C Crib Wall#l Cell #1 Station 6+60
CW 759 4/12/06 c Crib Wall #1 Cell #1 Station 6+33
CW 760 4/12/06 c Crib Wall #1 Cell#l Station 6+12
CW 761 4/12/06 c Crib Wall #1 Cell #2 Station 5+50
CW 762 4/12/06 c Crib Wall#l Cell#l Station 5+00
CW 763 4/12/06 c Crib Wall#l Cell #2 Station 4+50
CW 764 4/12/06 c Crib Wall#rCell#l Station 4+00
CW 765 4/12/06 c Crib Wall #1 Cell #2 Station 3+50
CW 766 4/12/06 c Crib Wall#l Cell#l Station 3+00
CW 767 4/12/06 c Crib Wall#l Cell #2 Station 2+50
CW, 768 4/13/06 c Crib Wall#l Cell#l Station 2+00
CW 769 4/13/06 c Crib Wall#l Cell#l Station 1+50
Jew 770 4/13/06 c Crib Wall#l Cell #1 Station 1+00
CW 771 4/13/06 c Crib Wall#l Cell#l Station 0+50
CW 772 4/13/06 c Crib Wall#l Cell #2 Station 5+85
CW 773 4/13/06 c Crib Wall#l Cell#l Station 5+60
CW 774 4/13/06 c Crib Wall#l Cell #2 Station 5+35
CW 775 4/13/06 c Crib Wall#l Cell #1 Station 5+05
CW 776 4/13/06 c Crib Wall#l Cell #2 Station 4+85
CW 777 4/13/06 c Crib Wall #1 Cell #1 Station 4+60
CW 778 4/13/06 c Crib Wall#l Cell #2 Station 4+35
CW 779 4/13/06 c Crib Wall#l Cell #1 Station 4+10
CW 780 4/13/06 c Crib Wall#l Cell #2 Station 3+84
CW 781 4/13/06 c Crib Wall #1 Cell #1 Station 3+60
'cW 782 4/13/06 c Crib Wair#l Cell #2 Station 3+33
CW 783 4/13/06 c Crib Wall#rCell#l Station 3+13
CW 784 4/13/06 c Crib Wall#l Cell #2 Station 2+83
CW 785 4/13/06 c Crib Wall #1 Cell#l , Station 2+62
CW 786 4/13/06 c Crib Wall#l Cell #2 Station 2+36
CW 787 4/13/06 G Crib Wall#l Cell#l Station 2+09
CW 788 4/13/06 c Crib Wall #1 Cell #2 Station 1+83
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
257.0 7 106.3 118.0 13,1 12.0 90
257.0 7 106.0 118,0 14,1 . 12.0 90
257.0 7 105.9 118,0 12,5 12,0 90
257.0 7 106.3 118,0 13,6 • 12,0 90
255.0 7 105.7 118,0 14,7 12,0 90
256.0 7 106.6 118,0 12.2 . 12,0 90
255.0 7 109,7 118,0 14,1 ' 12,0 93
256.0 7 107,2 - 118,0 15.7 12,0 91
255.0 7 107,8 118,0 14,0 12,0 91
256.0 7 106,4 118,0 15,1 12,0 90
255.0 7 . 106,9 118.0 13,6 12,0 91
256.0 7 107,3 118,0 14,2 12,0 91
256.0 7 • 107,0 118,0 14,0 12,0 91
256.0 7 108,1 118,0 13,4 12,0 92
256.0 7 . 107,6 118,0 15,1 . 12,0 91
256.0 7 • 106,3 118,0 16,0 12,0 90
257,0-7 109,6 118,0 12,0 12.0 93
256.0 7 105,9 118,0 11,9 12,0 • 90
257.0 7 106.9 118,0 12,0 12.0 91. 256.0 7 106,1 118,0 15,0 12.0 90
257.0
!•
• 106,6 118,0 12,8 12.0 90
256.0 1: ,105,9 118.0 17.0 12.0 90
257.0 7 109,5 118.0 13.3 12.0 93
256.0 7 106.8 118.0 17.0 12.0 91
257.0 7 ' 106.5 118.0 12.0 12,0 90
256.0 7 107.8 118.0 12.3 12,0 91
257.0 7 108.8 118.0 . 12.5 12,0 , 92
256.0 7 107.3 118.0 13.3 12,0 91
257.0 7 106.6 118.0 • 13.1 12,0 90
256.0 7 110.5 118.0 13.0 12,0 94
257.0 7 106.4 118,0 13.2 12.0 90
256.0 7 107.1 118,0 14.1 12.0 91
Page 24 of 3 9
3/9/2007 1:35:09PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
CW 789 4/13/06 C Crib Wall #1 Cell #1 Station 1+57
CW 790 4/13/06 c Crib Wall #1 Cell #1 Station 1+30
CW 791 4/13/06 c Crib Wall#l Cell#l Station 1+09
CW 792 , 4/14/06 c Crib Wall #1 Cell #1 Station 10+60
CW 793 4/14/06 c Crib Wall #1 Cell #1 Station 10+10
CW 794 4/14/06 c Crib Wall#l Cell#l Station 9+70
CW 795 4/14/06 c Crib Wall#l Cell#l Station 9+13
CW 796 4/14/06 c Crib Wall#l Cell#l Station 8+62
CW 797 4/14/06 c Crib Wall#l Cell #I Station 8+12
CW 798 4/14/06 c Crib Wall #1 Cell#l Station 7+58
CW 799 4/14/06 c Crib Wall#l Cell#l Station 7+20
CW 800 4/14/06 c Crib Wall#l Cell#l Station 6+73
CW 801 4/14/06 c Crib Wall #1 Cell #1 Station 6+25
CW 802 4/14/06 c Crib Wall#l Cell#l Station 5+95
CW 803 4/14/06 c Crib Wall#l Cell#l Station 5+45
CW 804 4/14/06 c Crib Wall #1 Cell #2 Station 4+95
CW 805 4/17/06 c Crib Wall#l Cell#l Station 4+45
CW 806 4/17/06 c Crib Wall#l Cell #2 Station 3+95
CW 807 4/17/06 c Crib Wall#l Cell#l Station 3+45
CW 808 4/17/06 c Crib Wall #1 Cell #2 Station 2+95
CW 809 4/17/06 c Crib Wall#l Cell#l Station 2+45
CW 810 4/17/06 c Crib Wall #1 Cell #2 Station 1+95
CW 811 4/17/06 c Crib Wall#l Cell#l Station 1+45
CW 812 4/17/06 c Crib Wall#rCell#l Station 0+95
CW 813 4/17/06 c Crib Wall#l Cell#l Station 0+45
CW . 814 4/17/06 c Crib Wall#l Cell #1 StatioriO+10
'cw 315 4/17/06 c Crib Wall#l Cell#l Station 10+22
CW i ?16 4/17/06 c Crib Wall #1 Cell #1 Station 9+98
cw I 517 4/17/06 c . Crib Wall#l Cell#l Station 9+72
cw { !18 4/17/06 c Crib Wall#l Cell#l Station 9+48
CW f 19 4/17/06 c Crib Wall#l Cell#l Station 9+25
cw 820 4/17/06 c Crib Wall#l Cell#l Station 8+97
Project Number-
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
257.0 7 106.9 118,0 13.6 12.0 91
257.0 7 107.7 118,0 14.3 12.0 91
257.0 7 108.3 118,0 15.1 12.0 92
258.0 7 108.2 118,0 12.5 12.0 ,. 92
258.0 7 106.6 118.0 11.5 • 12.0 90
258.0 7 107.6 118.0 12.2 12.0 . 91
258.0 7 106,3 118,0 13:0 12,0 90
258.0 7 106.1 118.0 12.0 12,0 90
258.0 7 107,1 118.0 12.3 12,0 91
258.0 7 106.9 118.0 13.1 12,0 91
258.0 7 105.9 118.0 13.7 12,0 90
258.0 7 107.4 118.0 13.6 12,0 91
258.0 7 106.3 118.0 14.5 - 12,0 90
258.0 7 107.7 118.0 11.9 12.0 91
258.0 7 106.6 118.0 13.2 12.0 90
257.0 7 106,9 118.0 15.1 . 12.0 91
258.0 7 110,2 118.0 12.8 12.0 93
257.0 7 107.2 118.0 14.2 12.0 91
258.0 7 • 107.7 118.0 12.3 12.0 91
257.0 7 106.8 118,0 13.4 • 12.0 91
258.0 7 106.4 118.0 12.2 12.0 , • 90
257.0 7 106.6 118.0 12.0 12.0 90
258.0 7 106.2 118.0 13.7 12.0 90
258.0 7 111.1 118.0 12.2 . 12.0 94
258.0 7 106.7 118.0 11.6 12.0 90
258.0 7 106.2 118.0 12.4 12.0 90
258.0 7 108.5 118.0 11.1 12.0 92
258.0 7 106.7 118.0 13,8 12.0 90
258.0 7 105.8 118'.0 12.9 12.0 90
258.0 7 107.0 -118.0 15.2 12,0 91 258.0 7 108,1 118.0 11.9 12,0 92
259.0 I 110,4 120.0 14.5 12,0 92
Page 25 of 39
3/9/2007 1 •'?5-n9PA/f
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Project Number:
Project Name:
Project Location:
Client:
Test
Of
Location
CW 821 4/17/06 C
CW 822 4/17/06 C
CW 823 4/17/06 c CW 824 4/1-7/06 c CW 825 4/18/06 c CW 826 4/18/06 c CW 827 4/18/06 c CW 828 4/18/06 c CW 829 4/18/06 c CW 830 4/18/06 c CW 831 4/18/06 c CW 832 4/18/06 c CW 833 4/18/06 c CW 834 4/18/06 c
CW 835 4/18/06 c CW 836 4/18/06 c CW 837 4/18/06 c CW 838 4/18/06 c CW 839 4/18/06 c CW 840 4/18/06 c CW 841 4/18/06 c CW 842 4/18/06 c CW 843 • 4/18/06 c CW 844 4/18/06 c CW 845 4/18/06 c CW 846 4/18/06 c CW 847 4/18/06 c CW 848 4/18/06 c CW 849 4/18/06 c CW 850 4/18/06 c CW 851 4/18/06 c CW 852 4/18/06 c
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Cell#l
Cell#l
Cell#l'
Ceil #1
Cell#l
Cell#l
Cell#l
Cell #1
Cell #1
Cell#l
Cell#l
Cell #1
Cell#l
Cell #1
Cell #1
Cell #2
Cell#l
Cell #2
Cell#l
Cell #2
Cell#l
Cell #2
Cell#l
Cell #2
Cell #1
Cell #2
Cell#l
Cell#l
Cell #1
Cell#l
Cell #1
Cell#l
841363-009
Carlsbad Golf Course
0
0
• Station 8+75
Station 8+50
Station 8+23
Station 8+00
Station 7+75
Station 7+50
Station 7+25
Station 7+00
Station 6+75
Station 6+50
Station 6+25
Station 6+00
Station 5+75
Station 5+50
Station 5+25
Station 5+00
Station 4+75
Station 4+50
Station 4+25
Station 4+00
Station 3+75
Station 3+50
Station 3+25
Station 3+00
Station 2+75
Station 2+50
Station 2+25
Station 2+00
Station 1+75
Station 1+50
Station 1+25
Station 1+00
Lot#
Test
Elev (ft)
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
258.0
258.0
258.0
258.0
257.0
258.0
257.0
258.0
257.0
258.0
257.0
258.0
257.0
258.0
257.0
258.0
258.0
258.0
258.0
258.0
258.0
Soil
Type
1
1
7
7
7
7
7
7
7
7
7
7.
7
7 •
7
7
7 -
7
7
Dry Density
Field Max
109,0
108,1
108,6
109.8
109,3
108,6
110.4
110,6
110,7
108,9
107.8
109.0
107.6
108.6
108,6
107,0
107,7
106,9
105,9
108,3
107.1
109.1
110,9
109,6
106,0
106.4
106.3
106.3
106.8
106.4
106.1
106.0
120,0
120,0
120,0
120,0
120,0
120.0
120,0
120,0
120,0
120,0
120,0
120,0
120.0
120,0
120,0
118,0
118,0
118,0
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
Moisture (%)
Field Opt.
Relative (Vo)
Compaction
12,8
13,5
15,3
13,6
14,2
13,6
14,7
• 13,2
12,0
14,8
13,6
11,4
13,9
12,0
15,6
15,0
12,0
11,9
13,3
12,4
13,8
12,9
11.9
13.4
12.6
12.0
12.5
11.1
11.6
12.2
12.0
12.7
Remarks
12.0
12.0
-12.0
12.0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12.0
12.0
12,0
12,0
91
90
90
92
91
90
92
92
92
91
90
91
90
90
90
91
91
91
90
92
91
92
94
93
90
90
90
90
91
90
90
90
Page 26 of 3 9
1 •'?5-n9PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 853
CW 854
CW 855
CW 856
CW 857
CW 858
CW. 859
CW 860
CW 861
CW 862
CW 863
CW 864
CW 865
CW 866
CW 867
CW 868
CW 869
CW 870
CW 871
CW 872
CW 873
CW 874
CW 875
jcw 876
CW 877
CW 878
CW 879
CW 880
CW 881
CW 882
CW 883
CW 884
Test
Date
Test
Of
Location
Lot#
4/18/06 C
4/18/06 C
4/18/06 C
4/18/06 C
4/19/06 C
4/19/06
4/19/06
C
C
4/19/06 C
4/19/06
4/19/06
4/19/06
4/19/06
4/19/06
4/19/06
4/19/06
4/19/06
4/19/06
4/19/06 C
4/19/06 C
4/19/06
4/19/06
4/19/06
4/20/06
4/20/06
4/20/06
4/20/06
4/20/06
4/20/06
4/21/06
4/21/06
4/21/06 C
4/21/06 C
C
C
C
C
C
C
C
C
C
C
C
C
C
c
c
c c
c
c
c
Project Number:
Project Name:
Project Location:
Client:
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell # I
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell #2
Crib Wall #1 Cell #1
Crib Wall#l Cell #2
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall #1 Cell#l
Crib Wall #1 Cell #1
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell #1
Crib Wall#l Celltfl
Crib Wall#l Cell#l
Crib Wall #1 Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#r
841363-009
Carlsbad Golf Course
0
0
Station 0+75
Station 0+50
Station 0+25
Station 0+05
Station 6+10
Station 5+65
Station 5+40
Station 5+15
Station 4+90
Station 4+65
Station 4+35
Station 4+05
Station 3+85
Station 3+60
Station3+35
Station 3+10
Station 2+85
Station 2+60
Station 2+35
Station 2+10
Station 1+85
Station 1+60
Station 1+35
Station 1+10
Station 0+75
Station 0+40
Station 0+15
Station 0+02
Station 8+55
Station 8+05
Station 7+55
Station 7+05
Test
Elev (ft)
258.0
258.0
258.0.
258.0
259.0
259.0
259.0
259.0
258.0
259.0
258.0
259.0
258.0
259.0
258.0
259.0
258.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
259.0
260.0
260.0
260.0
261,0
Soil
Type
1
1
7
7
7
7
7
3
3
3
3
7
7
7
7
7
7
3
7
7
I
1
1
1
1
1
7
7
7
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
106.7
110,5
108,4
108,6.
106,4
106,4
106,0
105,9
106,3
103,4
103,3
105,5
104,6
107.5
106.5
107.1
106,7
105,7
106,0
103,2
107,9
106.6
109,9
108,3
110,2
109.1
107.6
108.0
106,9
107,4
106,3
111.8
118,0
120.0
120.0
120.0
118,0
118,0
118.0
118,0
118,0
114,5
114,5
114,5
114,5
118,0
118.0
118,0
118.0
118,0
118,0
114,5
118.0
118.0
120,0
120.0
120.0
120.0
120.0
120.0
118,0
118,0
118,0
120,0
.11,6
12,8
12,3
13.1
13,8
17,8
14,3
13,7
12.9
12.4
15.6
12.8
14,1
12,8
12,0
13,7
12.2
13.3
14.1
17.5
13.8
11.6
13.4
15.9
14.7
15.2
14.6
12.2
13.9
13.8
12.2
13.5
12.0
12,0
12.0
12,0
12.0
12.0
12.0
12,0
12,0
12,5
12,5'
12,5
12,5
12.0
12,0
12.0
12.0
12,0
12,0
12,5
12.0
12,0
12,0 .
12,0 '
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
90
92
90
90
90
90
90
90
90
90
90
92
91
91
90
91
90
90
90
90
91
90
92 •
90
92
91
90
90
91
91
90
93
Page 27 of 3 9
1 /Q/onm
SUMMARY OF FIELD DENSITY TESTS
Test
No.
CW 885
CW 886
CW 887
CW 888
CW 889
CW 890
CW 891
CW 892
CW 893
CW 894
CW 895
Jew 896
CW 897
CW 898
CW 899
CW 900
CW 901
CW 902
CW 903
CW 904
CW 905
CW 906
CW 907
CW 908
CW 909
CW 910
CW 911
Jew 912
CW 913
CW 914
CW 915
CW 916
Test
bate
Test
Of
Location
Lot#
C
C
C
C
C
C
C
C
C
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06 C
4/21/06 C
4/21/06
4/21/06
4/21/06
. 4/21/06
4/21/06
4/21/06
4/21/06
4/21/06
4/21/06 C
4/25/06 C
>. 4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
4/25/06
Project Number:
Project Name:
Project Location:
Client:
C
C
c
c
e
c
e
c
c
c
e
c
c
e
e
c
c
c
e
Crib Wall#l eell#l
Crib Wall#l Cell #1
Crib Wall#l Cell#l
Crib Wall #1 Cell #1
Crib Wall#l Cell#l
Crib Wall#l Cell #1
Crib Wall#l Cell #2
Crib Wall#i Cell#l
Crib Wall#l Cell#l
Crib Wall #1 Cell #1
Crib Wall#l Cell#l
Crib Wali#l Cell#l
Crib Wall#l Cell#l
Crib Wall #1 Cell #1
Crib Wall #1 Cell#l
Crib Wall#l Ceir#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell #1
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall#l Cell#l
Crib Wall #1 Cell #1
Crib Wall#l Cell#l
Crib Wall #1 Cell #1
Crib Wall#l Cell#l
Crib Wall #1 Cell#l
Crib Wall #1 Cell#l
841363-009
Carlsbad Golf Course
0
0
Station 6+60
Station 6+05
Station 5+55
Station 5+05
Station 4+55
Station 4+17
Station 3+55
Station 3+05
Station 2+55
Station 2+05
Station 2+15
Station 2+70
Station 3+17
Station 3+72
Station 4+25
Station 4+75
Station 5+25
Station 5+75 •
Station 6+25
Station 6+70
Station 6+55
Station 6+00
Station 5+50
Station 5+00
Station 4+60
Station 4+12
Station 3+65
Station 3+10
Station 3+40
Station 2+90
Station 2+40
Station 1+90
Test
Elev (ft)
260.0
260.0
260.0
260.0
260.0
260.0
259.0
260.0
260.0
260.0
261.0
261.0
261.0
261,0
261.0
261.0
261,0
261.0
261,0
261.0
262.0
262.0
262.0
262.0
262.0
262.0
262.0
262.0
262.0
262.0
262.0
262.0
Soil
Type
7
7
7
7
7
7
7-
7
7
7
7
7
.7
:7
7
7
7
7
7
7
3
3
3
3
7
1
1
3
3
3
3
3
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
106.4
107.9
110.4
107,7
106,5
106,9
108.3
105,9
106.8
107.4
108.1
108,3
107.2
106.0
106,1
108,6
109.0
109.4
108,2
107,4
102,5
104.3
106.4
104.3
108.4
108.9
108.1
103.8
105.5
104.3
104,4
103.7
1:
;ij
8,0
8,0
8,0
8,0
8,0
,0
118.0
118,0
118,0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118,0
118,0
114,5 •
114,5
114,5 •
114,5
118.0
120.0
120.0
114.5
114.5
114.5
114.5
114.5
12.0
12.6
12,0
12.9
16.4
15.9
13.0
17.3
15.2
14.6
14.0
15.0
16.5
1 1.6
, 1 1.9
16.1
13.4
12.1
15.0
14.3
13.5
12.5 -
14.3
14.6^
14.6
'13.5
14.5
16.2
15.7
14.6
15.1
14.2
12.0
12.0
12.0
12.0
1.2.0
12.0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,5
12,5
12,5
12,5
12.0
12.0
12.0
12.5
12.5
12.5
12.5
12.5
90
91
94
91
90
, 91
92
90
91
91
92
92
91
90
90
92
92
93
92
91
90
91
93
91
92
91
90
91
92
91
91
91
Page 28 of 39
3/9/2007 1 -T^-mDA^^
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (%)
Compaction Remarks
CW 917 4/25/06 C Crib Wall#l Cell#l Station 1+50
CW 918 4/25/06 C . Crib Wall#l Cell#l Station 1+70
CW 919 4/25/06 c, Crib Wall#l Cell#l Station 2+20
CW 920 4/25/06 c Crib Wall#l Cell#l Station 2+70
CW 921 4/25/06 c Crib Wall #1 Cell #1, Station 3+20
CW 922 4/25/06 c Crib Wall #1 Cell#l Station 3+70
CW 923 4/25/06 c Crib Wall #1 Cell#l Station 4+20
CW 924 4/25/06 c Crib Wall#l Cell#l Station 4+70
CW 925 4/25/06 c Crib Wall#l Cell#l Station 5+20
CW 926 4/25/06 c Crib Wall#l Cell#l Station 5+70
CW 927 4/25/06 c Crib Wall #1 Cell#l Station 6+20
CW 928 4/26/06 c Crib Wall #1 Cell#l Station 5+40
CW 929 4/26/06 c Crib Wall#l Cell#l Station 5+15
CW 930 4/26/06 c Crib Wall #l Cell#l Station 4+90
Jew 931 4/26/06 c Crib Wall#l Cell#l Station 4+65
CW 932 4/26/06 c Crib Wall#l Cell #1 Station 4+35
CW 933 4/26/06 c Crib Wall#l Cell#l Station 4+10
CW 934 4/26/06 c Crib Wall#l Cell#l Station 3+85
CW 935 4/26/06 c Crib Wall#l Cell#l Station 3+50
CW 936 ,4/26/06 c Crib Wall#l Cell #1 Station 3+25
CW 937 4/26/06 c Crib Wall #1 Cell #1 Station 3+00
CW 938 4/26/06 c Crib Wall#l Cell#l Station 2+75
CW 939 4/26/06 c Crib Wall#l Cell#l Station 2+50
CW 940 4/26/06 c Crib Wall #1 Cell #1 Station 2+10
CW 941 4/26/06 c Crib Wall#l Cell#l Station 2+35
CW 942 4/26/06 c Crib Wall #1 Cell #1 ' Station 2+85
CW 943 4/26/06 c Crib Wall#l Cell#l Station 3+35
CW 944 4/26/06 c Crib Wall#l Cell#l Station 3+70
CW 945 4/26/06 c Crib Wall #1 Cell #1 Station 4+20
CW 946 4/26/06 c Crib Wall#l Cell#l Station 4+70
CW 947 4/26/06 c Crib Wall#l Cell #1 Station 5+20
CW 948 4/27/06 c Crib Wall#l Cell #1 Station 4+00
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
262.0 3 104,2 114,5 13.4 12,5 91
263.0 7 107,7 11 8.0 13.3 12,0 91
263.0 7 107,2 11 8.0 11.0 12,0 91
263.0 7 107.4 11 8,0 1 1.0 12.0 91
263.0 7 106,3 11 8.0 13.7 12.0 90
263.0 7 105.9 11 8.0 16.2 12.0 90
263.0 7 107.8 11 8.0 15.0 12,0 91
263.0 7 107,9 11 8.0 15.3 12,0 91
263.0 1 111,7 120,0 14.6 12,0 93
263.0 1 108.9 120,0 12.6 12,0 91
263.0 1 108,0 120.0 16.1 12,0 90
264.0 7 106,5 11 8.0 13.7 12,0 90
264.0 7 106,3 11 8.0 15.5 12,0 90
264.0 7 107,0 11 S.O 14.4 12.0 91
264.0 7 106,0 11 5.0 15.3 12,0 90
264.0 7 105,9 Hi i.O 13,0 12,0 90
264.0 7 106,1 in 5.0 17,3 12,0 90
264.0 7 107,1 ii{ 5.0 13,9 12,0 91
264.0 7 105.8 115 5.0 16.4 12,0 90
264.0 7 106.0 lis .0 15.5 12.0 90
264.0 7 107.5 lis .0 15.2 12.0 91
264.0 7 107.2 118 ,0-14.3 • 12.0 91
264.0 7 105.9 118 .0 17.4 12.0 -. 90
264.0 7 107.3 118 .0 14.3 12,0 91
265.0 7 109.6 118 .0 14.2 12,0 93
265.0 7 106,8 118 .0 16.4 12,0 91
265.0 7 109.6 118 ,0 12.5 12,0 93
265.0 7 108.5 118 ,0 14.4 12,0 92 265.0 7 107.3 118 0 15.2 12,0 91
265,0 7 106.9 118 0 14,3 12,0 91
265,0 7 107.5 118 0 15,4 12,0 91
266,0 7 109.3 118 0 12,0 12,0 93
Page 29 of 3 9
3/9/2007 1:35-09PM
Test
No.
SUMMARY OF FIELD DENSITY TESTS
Test
Date
Test
Of
Location
CW 949 4/27/06 C Crib Wall#l Cell#l Station 3+60
CW 950 4/27/06 C Crib Wall #1 Cell #1 Station 3+00
CW 951 4/27/06 c Crib Wall #l Cell#l Station 2+60
CW 952 4/27/06 c. Crib Wall#l Cell #1 Station 3+89
CW 953 4/27/06 c Crib Wall#l Cell#l Station 3+27
CW 954 4/27/06 c Crib Wall#l Ceir#l Station 2+88
CW 955 4/27/06 B Crib Wall#l Cell#l Station 9+50
CW 956 4/27/06 B Crib Wall #1 Cell#l Station 9+00
CW 957 4/27/06 B Crib Wall #1 Cell #1 Station 8+70
CW 958 4/27/06 B Crib Wall #1 Cell#l Station 0+20
CW 959 4/27/06 B Crib Wall #1 Cell #1 Station 0+65
CW 960 4/27/06 B Crib Wall #1 Cell #1 Station 0+90
CW 961 4/27/06 B Crib Wall #1 Cell #1 Station 1+15
CW 962 4/27/06 B Crib Wall #1 Cell #1 Station 8+40
CW 963 4/27/06 B Crib Wal|#l Cell#l Station 8+15
CW 964 4/27/06 B Crib Wall#l Cell#l Station 7+85
CW 965 4/27/06 C Crib Wall#l Cell#l Station 7+60
CW 966 4/27/06 C Crib Wall#l Cell#l Station 7+10
CW 967 4/27/06 C Crib Wall#l Cell#l Station 6+60
CW 968 4/28/06 C Crib Wall #1 Cell #1 Station 6+10
CW 969 4/28/06 C Crib Wall #1 Cell #1 Station 5+88
CW 970 4/28/06 C Crib Wall#l Cell#l Station 5+60
CW 971 4/28/06 C Crib Wall#l Cell#l Station 4+84
CW 972 4/28/06 C Crib Wall#l Cell#l Station 4+42
CW '973 4/28/06 C Crib Wall#l Cell#l Station 4+15
CW 974 4/28/06 C Crib Wall #1 Cell#l Station 3+80
CW 975 4/28/06 C Crib Wall#l Cell#l Station 3+44
CW 976 4/28/06 C Crib Wall #l Cell#l Station 3+15
CW 977 4/28/06 C Crib Wall#l Cell #1 Station 2+95
CW 978 4/28/06 C Crib Wall #1 Cell#l Station 2+67
CW 979 4/28/06 c Crib Wall #1 Cell#l Station 2+27
CW 980 4/28/06 c Crib Wall#l Cell#l Station 2+03
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
266.0 7 107.4 118,0 12.7 12.0 • 91
266.0 7 106.9 118,0 14.7 12,0 91
266.0 7 107.3 118,0 15.7 12,0 91
267.0 7 107.3 118,0 14.0 12,0 91
267.0 7 106.5 118,0 12.1 12,0 90
267.0 7 109.8 118,0 13,1 12.0 . 93
259.0 1 ' 110.8 120,0 13,1 12,0 92
260.0 1 109.3 120,0 15,0 • 12,0 91
260.0 1 107.5 120,0 14,8 12,0 90
260.0 1 110.1 120,0 13,1 12,0 92
261.0 1 108.2 120,0 14,8 12,0 90
261.0 1 108.0 . 120,0 13,0 12,0 90
262.0 1 108.6 120.0 15,1 12,0 90
261.0 1 107.4 120.0 14,6 12,0 90
261.0 7 105.7 118.0 11,7 12,0 90
261.0 7 108.8 118.0 12,8 12,0 92
262.0 7 105.9 118,0 15,2 12,0 90
262.0 7 107.1 118,0 15,4 12,0 91
263.0 7 105.9 118,0 14,1 12,0 90
264.0 1 107.8 120,0 12.8 12,0 90
264.0 1 111.4 120.0 13,3 12,0 93
264.0 1 114.2 120.0 13,5. . 12,0 95
266.0 1 . 110.9 120,0 13,4 12,0 92
266.0 1 108.2 120,0 12,5 "l2,0 90
267.0 1 109.1 120,0 13,6 12,0 91
268.0 7 106.4 118.0 16,4 12,0 90
268.0 1 109.2 120.0 13,7 12,0 • 91
269.0 1 108.1 120,0 12.0 12.0 90
268.0 1 108.1 120.0 14.0 12.0 90
267.0 1 112.6 120,0 13,6 12.0 94
266.0 7 105.9 118,0 16,9 12.0 90
265.0 7 106.3 118,0 14.6 12.0 90
Page 30 of 39
^/o/9nm
SUMMARY OF FIELD DENSITY TESTS
Test Test Test — L No. Date Of
CW 981 4/28/06 C Crib Wall #1 Ceim
CW 982 5/2/06 C Crib Wall#l Cell#l
CW 983 5/2/06 c Crib Wall #1 Cell#l
CW 984 5/2/06 c Crib Wall#l Cell #1
CW 985 5/2/06 c Crib Wall#l Cell#l
CW 986 5/2/06 c Crib Wall#l Cell#l
CW 987 5/2/06 c Crib Wall #1 Cell #1
CW 988 5/2/06 c Crib Wall#l Cell#l
CW 989 5/2/06 c Crib Wall#l Cell#l
CW 990 5/2/06 c Crib Wall#l Cell#l
CW 991 5/2/06 c Crib Wall#l Cell#l
CW 992 5/2/06 c Crib Wall#l Cell#l
CW 993 5/2/06 c Crib Wall #1 Cell#l
CW 994 5/2/06 c Crib Wall#l Cell#l
CW 995 5/2/06 c Crib Wall#l Cell #1
CW 996 5/2/06 c Crib Wall#l Cell #1
CW 997 5/2/06 c Crib Wall#l Cell #1
CW 998 5/2/06 c Crib Wall#l Cell#l
CW 999 5/2/06 c Crib Wall#l Cell#l
CWIOOO 5/2/06 c Crib Wall#l Cell#l
CWlOOl 5/2/06 c Crib Wall#l Cell#l
CW1002 5/2/06 c Crib Wall#l Cell#l
CW1003 5/3/06 c Crib Wall#l Cell#l
CW1004. 5/3/06 c Crib Wall#l Cell#l
CW1005 5/3/06 c Crib Wall #1 Cell#l
CW1006 5/3/06 c Crib Wall #l Cell#l
CW1007 5/3/06 c Crib Wall#l Cell #1
CW1008 5/3/06 c Crib Wall#l Cell #1
CW1009 5/3/06 c Crib Wall #1 Cell#l
CWlOlO 5/3/06 c Crib Wall#l Cell#l
CWlOll 5/3/06 c Crib Wall#l Cell#l
CW1012 5/3/06 c Crib Wall #1 Cell#l
Location
Lot#
Project Number
Project Name:
Project Location:
Client:
Station 1+82
Station 9+40
Station 9+08
Station 8+65
Station 8+00
Station 7+70
Station 7+30
Station 6+87
Station 6+40
Station 6+05
Station 5+60
Station 5+10
Station 4+60
Station 4+10
Station 3+55
Station 3+08
Station 2+55
Station 2+10
Station 1+60
Station 1+10
Station 0+60
Station 0+02
Station 9+80
Station 9+30
Station 8+80
Station 8+30
Station 7+80
Station 7+20
Station 6+80
Station 6+30
Station 5+80
Station 5+30
Test
Elev (ft)
264.0
260.0
261.0
262.0
262.0
262.0
263.0
263.0
264.0
265.0
265.0
266.0
267.0
268.0
269.0
270.0
269.0
266.0
264.0
263.0
262.0
261.0
262.0
263.0
263.0
263.0
263.0
264,0
265,0
265.0
266.0
267.0
Soil
Type
7
7
,7
7
7
7
7
7
7
7
7
, 7
,7
7
7
7
7
7
7
1
7
1
1
1
1
1
1
1
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
105,9
106,6
,108,9
106,0
106,8
107.2
107.7
108,0
109,9
107,8
106.3
108,2
107.2
106,5
107.6
106.4
106.0
106,1
106,7
106,0
107,8
108.2
107,1
109,5
108,3
107,8
110,6
108,0
108,1
107,8
107.7
108.8
118,0
118,0
118,0
118,0
118,0
118,0
118,0
118,0
120,0
120,0
118,0
118,0
118,0
118.0
118.0
118.0
118,0
118,0
118.0
118,0
118.0
120.0
118.0
120.0
120.0
120.0
120,0
120,0
120,0
120,0
120,0
120,0
12,0
13.4
12.2
16.0
12.6
13.0
13.5
15.5
13.5
15.0
14.0
13.1
12.7
,13,5
14,7
16,0
14,0
14,5
15,8
13,7.
15,2
12,9
13,9
12,0
15,4
14,7
15,4
15,1
14,3
14,5
13.5
14.8
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12.0
12,0
12,0
12.0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12.0
12.0 .
90
90
92
90
91
91
91
92
92
90
90
92
91
90
91
90
90
90
90
90
91
90
91
91
90
90
92
90
90
90
90
91
841363-009
Carlsbad Golf Course
0
0 Page 31 of 39
3/9/2007 1:35-09PM
SUMMARY OF FIELD DENSITY TESTS
j Test Test Test
No. Date Of
CW1013 5/3/06 C Crib Wall#l Cell#l Station 4+80
CW1014 5/3/06 c • Crib Wall#l Cell#l Station 4+30
CW1015 5/3/06 c Crib Wall#l Cell#l Station 3+70
CW1016 5/3/06 c Crib Wall#l Cell #1 Station 3+30
CW1017 5/3/06 c Crib Wall#l Cell#l Station 2+80
CW1018 5/3/06 c Crib Wall #1 Cell #1 Station 2+30.
CW1019 5/3/06 c Crib Wall#l Cell #1 Station 1+80
CW1020 5/3/06 c Crib Wall#l Cell#l Station 1+30
CW1021 5/3/06 c Crib Wall#l Cell#l Station 0+80
CW1022 5/3/06 c Crib Wall#l Cell#l Station 0+30
CW1023 5/3/06 c Crib Wall#l Cell#l Station 0+35
CW1024 5/3/06 c Crib Wall#l Cell#l Station 1+35
jcW1025 5/3/06 c Crib Wall#l Cell #1 Station 2+35
CW1026 5/3/06 c Crib Wall#l Cell#l Station 3+50
CW1027 5/3/06 c Crib Wall#l Cell#l Station 4+50
CW1028 5/4/06 c Crib Wall#l Cell #1 Station 5+50
CW1029 5/4/06 c Crib Wall#l CeH#l Station 6+50
CW1030 5/4/06 c Crib Wall#l Cell#l Station 7+50
CW1031 5/4/06 c Crib Wall#l Cell #1 Station 8+50
CW1032 5/4/06 c Crib Wall#l Cell#l Station 9+50
CW1033 5/9/06 c Crib Wall#l Cell#l Station 11+75
CW1034 5/9/06 c Crib Wall#l Cell#l Station 11+90
CW1035 5/9/06 c Crib Wall #1 Cell#l Station 12+05
CW1036 5/9/06 c Crib Wall#l Cell#l Station 12+20
'CW1037 5/9/06 c Crib WaH#l Cell#l Station 12+35
CW1038 5/9/06 c Crib Wall#l Cell #5 Station 12+30
ICW1039 5/9/06 c Crib Wall#l Cell #4 Station 12+12
CW1040 5/9/06 c Crib Wall #1 Cell #3 Station 11+98
CW1041 5/9/06 c Crib Wall #1 Cell #2 Station 11+83
CW1042 5/9/06 c Crib Wall#l Cell#l Station 12+40
CW1043 5/10/06 c Crib Wall # I Cell #5 Station 11+75
CW1044 5/10/06 c Crib Wall#l Cell #4 Station 11+85
Lot#
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
267.0 7 106.6 118,0 16,9 12,0 90
268.0 7 106,3 118,0 12.5 12,0 90
270.0 7 106.0 118.0 16.2 12.0 90
270.0 7 106.5 118,0 13.6 12,0 90
269.0 7 106,6 118.0 15.1 12,0 90
268.0 1 109,3 120.0 12.2 .12,0 91
266.0 1 108.1 120.0 12.9 12,0 90
264.0 1 108.2 120,0 12.5 12.0 90
263.0 1 107,8 120,0 12.0 12,0 90
262.0 1 109,1 120,0 14.2 12.0 91
0.0 1 113,7 120.0 1 1.0 12,0 95
0.0 1 107,6 120,0 15.1 12.0 90
0.0 1 108,0 120.0 13.4 12.0 90
0.0 1 110,2 120.0 1 1.2 12,0 92
0.0 1 109,5 120.0 10.9 12,0 91 0.0 1 107,8 120.0 10.7 12.0 90
0.0 1 108,7 120.0 10.5 12,0 91
0.0 1 110.3 120.0 11.5 12,0 92
0.0 1 109.6 120,0 12.3 12,0 91
0.0 1 110.6 120.0 12.5 12,0 92
217.0 7 106.8 118.0 12.1 12,0 91
218.0 7 106.6 118,0 11.6 .' 12,0 90
219.0 7 106.2 118.0 11.7 12.0 90
220.0 7 106.1 118.0,. 12.7 12,0 90
221.0 7 107.0 118.0 12.3 12.0 91 217.0 7 106.6 118,0 13.9 12,0 90
219.0 7 107.3 118,0 14.2 12,0 91 220.0 7 106,9 118,0 13.7 12,0 91
221.0 7 107,1 118,0 13.0 12,0 91
222.0 7 106,8 118,0 12.8 12,0 91
219.0 7 107.4 118,0 13.9 12,0 91 220.0 7 106.4 118,0 14.4 12,0 90
Page 32 of 39
1/9/9007 1 •T^.n9DA/t
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
CW1045 5/10/06 C Crib Wall #1 Cell #3 Station 12+05 221.0 7
CW1046 ' 5/10/06 C Crib Wall#l Cell #2 Station 12+20 222.0 7
CW1047 5/10/06 C Crib Wall#l Cell #1 Station 12+35 223.0 7
CW1048 5/10/06 C Crib Wall#l Cell #5 Station 11+80 220.0 7
CW1049 5/10/06 C Crib Wall #1 Cell #4 Station 11+90 221.0 7
CW1050 5/10/06 C Crib Wall#l Cell #3 Station 12+00 222.0 7 CW1051 5/10/06 C Crib Wall#l Cell #2 Station 12+15 223.0 7
CW1052 5/10/06 C Crib Wall#l Cell#l Station 12+30 224.0 7
CW1053 5/11/06 C Crib Wall #1 Cell #5 Station 11+73 221.0 7
CW1054 5/11/06 c Crib Wall#l Cell #4 Station 11+83 222.0 7
CW1055 5/11/06 c Crib Wall #1 Cell #3 Station 12+03 223.0 7
CW1056 5/11/06 c Crib Wall#l Cell #2 Station 12+18 224.0 7 CW1057 5/11/06 c Crib Wall#l Cell#l Station 12+33 225.0 7
CW1058 5/11/06 c Crib Wall #1 Cell #5 Station 11+80 222.0 7
CW1059 5/11/06 c Crib Wall#l Cell #4 Station 11+90 223.0 7
CW1060 5/11/06 c Crib Wall#l Cell #3 Station 12+10 224.0 7
CW1061 5/11/06 c Crib Wall#l Cell #2 Station 12+22 225.0 7
CW1062 5/11/06 c Crib Wall#l Cell#l Station 12+32 226.0 7
CW1063 5/12/06 c Crib Wall#l Cell #5 Station 11+75 223.0 7
CW1064 5/12/06 c Crib Wall#l Cell #4 Station 11+85 224.0 7
CW1065 5/12/06 c Crib Wall #1 Cell #3 Station 11+95 225.0 7 CW1066 5/12/0,6 c Crib Wall #1 Cell #2 Station 12+10 226.0 7
CW1067 5/12/06 c Crib Wall#l Cell #1 Station 12+20 227.0 7 CW1068 5/12/06 c Crib Wall #1 Cell #5 Station 11+70 224.0 7 •
CW1069 5/12/06 c Crib Wall#l Cell #4 Station 11+80 225.0 7
CW1070 5/12/06 c Crib Wall#l Cell #4 Station 11+90 226.0 7
CW1071 5/12/06 c Crib Wall #1 Cell #2 Station 12+15 227.0 7
CW1072 5/12/06 c Crib Wall#l Cell#l Station 12+30 228.0 7 CW1073 5/15/06 c Crib Wall#l Cell #4 Station 11+85 226.0 7 CW1074 5/15/06 c Crib Wall#l Cell #3 Station 11+95 227.0 7
CW1075 5/15/06 c Crib Wall#l Cell #2 Station 12+10 228.0 7
CW1076 5/15/06 c Crib Wall#l Cell #1 Station 12+25 229.0 7
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
107.1
106.5
106.6
106.9
106.4
107.3
106,8
107,5
106.4
106.7
107,}
106,6
106,5
107,2
107,4
107,2
106,9
106,5
107,1
107,3
106,6
106,5
107.5
107.2
106,3
106.5
107.4
106.5
106.5
106,4
106.3
106,6
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118,0
118,0
118,0
118,0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
118.0
13.7
14.2
15,1
15,8
13,4
14,2
13.8
12,2
13,2
13,0
12,1
12,0
1 1,7
12,2
12.1
13,2
13,3
1 1,5
15,3
14,1
14,5
15,3
15,5
14,6
13,8
13,5
15,2
15,0
15,2
15,5
16,3
15,1
12.0
12.0
12,0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12,0
12,0
12.0
12.0
12.0
12.0
12.0
12,0
12,0
12,0
12,0
12,0
12.0
12.0
12.0
12.0
12.0
12.0
12.0
12,0
91
90
90
91
90
91
91
91
90
90
91
90
90
91
91
91
91
90
91
91
90
90
91
91
90
90
91
90
90
90
90
90
Page 33 of 39
1 •T509PM
Test
No.
SUMMARY OF FIELD DENSITY TESTS
Test
Date
Test"
Of
Location
CW1077 5/15/06 C Crib Wall #1 Cell #4 Station 11+80
CW1078 5/15/06 C Crib Wall#l Cell #3 Station 11+95
CW1079 5/15/06 C Crib Wall#rCell #2 Station 12+05
CW1080 5/15/06 C Crib Wall #1 Cell #1 Station 12+20
CW1081 5/16/06 C Crib Wall #1 Cell #4 Station 11+75
CW1082 5/16/06 C Crib Wall#l Cell #3 Station 11+95
CW1083 5/16/06 C Crib Wall#l Cell #2 Station 12+15
CW1084 5/16/06 C Crib Wall#l Cell#l Station 12+33
CW1085 5/16/06 C Crib Wall#l Cell #4 Station 11+80
CW1086 5/16/06 C Crib Wall#l Cell #3 Station 11+90
CW1087 5/16/06 C Crib Wall#l Cell #2 Station 12+05
CW1088 5/16/06 C Crib Wall#l Cell#l Station 12+20
CW1089 5/17/06 C Crib Wall#l Cell #4 Station 11+74
CW1090 5/17/06 C Crib Wall#l Cell #3 Station 11+95
CW1091 5/17/06 c Crib Wall #1 Cell #2 Station 12+14
CW1092 5/17/06 c Crib Wall#l Cell#l Station 12+32
CW1093 5/17/06 c Crib Wall#l Cell #4 Station 11+75
CW1094 5/17/06 c Crib Wall#l Cell #3 Station 11+95
CW1095 5/17/06 c Crib Wall#l Cell #2 Station 12+15
CW1096 5/17/06 c Crib Wall#l Cell#l Station 12+33
CW1097 5/18/06 c Crib Wall#l Cell #4 Station 12+35
CW1098 5/18/06 c Crib Wall#l Cell #3 Station 12+00
CW1099 5/18/06 c Crib Wall#l Cell #2 Station 11+85
CWllOO 5/18/06 c Crib Wall#l Cell#l Station 11+65
CWllOl 5/18/06 c Crib Wall#l Cell #4 Station 12+47
CW1102 5/18/06 c Crib Wall#l Cell #3 Station 12+55
CW1103 5/18/06 c Crib Wall#l Cell #2 Station 12+60
CW1104 5/19/06 c Crib Wall#l Cell #4 Station 11+40
CW1105 5/19/06 c Crib Wall#l Cell #3 Station 11+55
CW1106 5/19/06 c Crib Wall#l Cell #2 Station 11+75
CW1107 5/19/06 c Crib Wall#l Cell#l Station 11+45
CW1108 5/19/06 c Crib Wall #1 Cell #4 Station 11+80
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
Soil
Type
Page 34 of 39
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
227.0 7 107,3 118.0 14,8 12,0 91
228.0 7 106,3 118.0 15,0 12,0 90
229.0 7 106,1 118.0 14.4 12,0 90
230.0 7 106,5 118.0 15,3 12,0 90
227.0 ,7 107,3 118.0 13.7 12,0 91
228.0 7 107,0 118.0 15.9 12,0 91
229.0 7 106,5 118.0 16.1 12,0 90
230.0 7 107,5 118.0 15.1 12.0 91
228.0 7 106,3 118.0 14.4 12,0 90
229.0 7 106,6 118.0 15.3 12,0 90
230.0 7 107,2 118.0 14.9 12.0 91
231.0 7 107,7 118.0 16.3 12.0 91
228.0 7 107,8 118.0 13.9 12,0 91
229.0 7 108,3 118.0 17.0 12,0 92
230.0 7 107,5 118.0 14.0 12,0 91
231.0 7 108,7 118.0 15.1 12,0 92
229.0 7 107,6 118.0 15.0 12,0 91
230.0 7 110,5 118.0 16.5 12.0 94
231.0 7 108,1 118.0 15.8 12,0 92
232.0 7 109.8 118.0 14.1 12,0 93
230.0 7 107.1 118.0 15.6 12,0 91
231.0 7 108,0 118.0 14.0 12,0 92
232.0 7 111,1 118.0 14.5 12,0 94
233.0 7 111,3 118.0 14,8 ,12.0 94
230.0 7 113.3 118.0 15,7 12,0 96
231.0 7 109.4 118,0 15,5 12,0 93
232.0 7 109,2 118,0 15,1 12.0 93
232.0 1 112.5 120,0 12.1 12.0 94
233.0 1 111.7 120.0 13,9 12,0 93
234.0 1 111.0 120,0 13.9 12,0 93
235.0 1 108.7 120,0 14.6 12,0 91
232.0 1 115.2 120,0 12.7 12,0 96
35:02PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
CW1109 5/19/06 C Crib Wall#l Cell #3 Station 12+18
CWlllO 5/19/06 C Crib Wall#l Cell #2 Station 12+55
CWllll 5/19/06 c Crib Wall#l Cell#l Station 12+00
CW1112 5/19/06 c Crib Wall#l Cell#l Station 11+60
CW1113 5/19/06 c Crib Wall#l Cell #2 Station 11+90
CW1114 5/19/06 c Crib Wall #1 Cell #3 Station 12+30
CW1115 5/19/06 c Crib Wall #1 Cell #3 Station 11+40
CW1116 5/19/06 c Crib Wall#l Cell #2 Station 12+00
CW1117 5/19/06 c Crib Wall #1 Cell #1 Station 12+25
CW1118 5/23/06 c Crib Wall #1 Cell#l Station 12+15
CW1119 5/23/06 c Crib Wall#l Cell#r Station 12+70
CW1120 5/23/06 c Crib Wall#l Cell #2 Station 12+43
CW1121 5/23/06 c Crib Wall#l Cell #2 Station 12+30
CW1122 5/23/06 c Crib Wall #1 Cell #3 Station 12+62
CW1123 5/23/06 c Crib Wall#l Cell #3 Station 12+50
CW1124 5/23/06 c Crib Wall#l Cell #3 Station 11+20
CW1125 5/23/06 c Crib Wall #1 Cell #2 Station 11+50
CW1126 5/23/06 c Crib Wall#l Cell #3 Station 11+85
CW1127 5/23/06 c Crib Wall#l Cell #2 Station 12+05
CW1128 5/23/06 c Crib Wall#l Cell#l Station 11 + 18
CW1129 5/23/06 c Crib Wall #1 Cell #1 Station 11+45
CW1130 5/23/06 c Crib Wall#l Cell#l Station 11+70
CW1131 5/23/06 c Crib Wall#l Cell#l Station 12+10
CW1132. 5/23/06 c Crib Wall #1 Cell #3 Station 12+40
CW1133 5/23/06 c Crib Wall#l Cell #2 Station 12+58
CW1134 5/23/06 c Crib Wall #1 Cell #1 Station 12+75
CW1135 5/23/06 c Crib Wall #1 Cell #3 Station 11+58
CW1136 5/23/06 c Crib Wall#l Cell #3 Station 11+95
CW1137 5/23/06 c Crib Wall#l Cell #3 Station 12+60
CW1138 5/23/06 c Crib Wall#l Cell #2 Station 11+35
CWM39 5/23/06 c Crib Wall #1 Cell #2 Station 11+79
CW1140 5/23/06 c Crib Wall#l Cell #2 Station 12+50
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
233.0
234.0
235.0
237.0
236.0
235.0
235.0
236.0
237.0
238.0
238.0
237.0
237.0
236.0
236.0
237.0
238.0
237.0
238.0
239.0
239.0
239.0
239.0
237.0
238.0
239.0
238.0
238,0
238.0
239.0
239.0
239,0
113.0 120.0 12,4 12.0 94
109.6 120.0 14.3 12.0 91
109,6 120.0 13,2 12.0 91
108,6 120.0 13,3 12.0 90
108.1 120.0 12,5 12.0 90
109.6 • 120,0 12,6 12.0 91
111.6 120.0 12,9 12.0 93
110.6 120.0 13,8 12.0 92
110.4 120.0 15,6 12:0 92
113.7 120.0 12,0 12.0 95
110.4 120.0 12,4 12.0 92
112.4 120.0 13,4 12.0 94
111.4 120.0 13.6 12.0 93
113.3 120.0 13.4 12.0 94
112.0 120,0 13.6 12.0 93
114.9 120,0 14.0 12.0 96
112.6 120,0 13.8 12.0 94
110.5 120,0 14.6 12.0 92
109.6 120,0 14.8 12.0 91
107.9 120,0 16.2 12,0 90
112,1 120,0 15.7 12,0 93
111,6 120,0 15.0 12,0 93
110,4 120,0 15.5 12.0 - 92
108,2 120,0 17.4 12.0 90
107,6 120,0 16.8 12.0 90
107,7 120,0 16.2 12.0 90
110,0 120,0 16,3 12.0 92
115,3 120,0 13,2 12.0 96
114,0 120,0 14,6 12.0 95
111.4 120,0 16,4 12.0 93
112.0 120,0 16.0 12.0 93
112.6 120,0 16.3 12.0 94
Page 35 of 39
T/Q/9007 1 .-3 •^.mD^,^
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
CW1141 5/23/06 C Crib Wall #1 Cell #1 Station 11+30
CW1142 5/23/06 C Crib Wall#l Cell#l Station 11+90
CW1143 5/23/06 C Crib Wall#l Cell#l Station 12+42
CW1144 5/24/06 C . Crib Wall #1 Cell #3 Station 11+27
CW1145 5/24/06 C Crib Wall#l Cell #3 Station 11+67
CW1146 5/24/06 C Crib Wall#l Cell #3 Station 12+08
CW1147 5/24/06 C Crib Wall #1 Cell #3 Station 12+47
CW1148 5/24/06 c Crib Wall#l Cell #2 Station 11+20
CW1149 5/24/06 c Crib Wall#l Cell #2 Station 11+62
CW1150 5/24/06 c Crib Wall#l Cell #2 Station 11+93
CW1151 5/24/06 c Crib Wall#l Cell #2 Station 12+67
CW1152 5/24/06 c Crib Wall#l Cell#l Station 11+41
CW1153 5/24/06 c Crib Wall#l Cell#l Station 11+82
CW1154 5/24/06 c Crib Wall#l Cell #1 Station 12+25
CW1155 5/24/06 c Crib Wall#l Cell #1 Station 12+58
CW1156 5/25/06 c Crib Wall#l Cell #1 Station 11+75
CW1157 5/25/06 c Crib Wall#l Cell #1 Station 12+00
CW1158 5/25/06 c Crib Wall#l Cell #2 Station 11+47
CW1159 5/25/06 c Crib Wall#l Cell #2 Station 12+35
CW1160 5/25/06 c Crib Wall#l Cell #3 Station 12+52
CW1161 5/25/06 c Crib Wall#l Cell #3 Station 11+55
CW1162 5/25/06 c Crib Wall #1 Cell #3 Station 11+25
CW1163 5/25/06 c Crib Wall#l Cell #2 Station 11+00
CW1164 . 5/25/06 c Crib Wall #1 Cell #2 Station 11+50
CW1165 5/25/06 c Crib Wall#l Cell #3 Station 11+75
CW1166 5/25/06 c Crib Wall #1 Cell #2 Station 12+00
CW1167 5/25/06 c Crib Wall#l Cell #3 Station 12+10
CW1168 5/25/06 c Crib Wall#l Cell #2 Station 12+50
CW1169 5/25/06 c Crib Wall#l Cell #1 Station 11+15
CW1170 5/25/06 c Crib Wall #1 Cell#l Station 11+67
CW1171 5/25/06 c Crib Wall#l Cell#l Station 12+25
CW1172 5/25/06 c Crib Wall#l Cell #1 Station 12+72
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%) Relative (Vo)
Field Opt. Compaction Remarks
240.0 1 110.4 120,0 15,5 12,0 92
240.0 1 110.9 120,0 16,0 12,0 92
240.0 1 113.1 120.0 16,9 12,0 94
239.0 1 114.7 120.0 14,7 12,0 96
239.0 1 112.1 120,0 14.0 12,0 93
239.0 1 107.8 120,0 13,4 12,0 90
239.0 1 108.6 120.0 13.0 12.0 90
240.0 1 110,8 120.0 14,2 12,0 92
240.0 1 109,2 120.0 14,8 12,0 91
240.0 1 109,8 120.0 14,0 12,0 92
240.0 1 110,0 120.0 13,6 12,0 92
241.0 1 111.2 120.0 13,2 12,0 93
241.0 1 109.6 120.0 14,5 12,0 91
241.0 1 108.9 120.0, • 13,0 12.0 91
241.0 1 111.7 120,0 15,3 12.0 . 93
242.0 1 110,4 120,0 14,6 12,0 92
242.0 1 110,0 120.0 16,1 12.0 92
241.0 1 109,6 120.0 15,8 12,0 91
241.0 1 111.3 120.0 15,0 12,0 93
240.0 1 110,7 120.0 14,3 12.0 92
240.0 1 108,4 120.0 14,0 12,0 90
242.0 1 111.1 120.0 12,5 12,0 93
243,0 1 109.8 120.0 13,0 12,0 92
243.0 1 110.2 120.0 15,3 12,0 92
242.0 1 112,6 120,0 14,0 12,0 94
245.0 1 108,2 120,0 14.7 12,0 90
242.0 1 109.0 120,0 14,0 12,0 91
245.0 1 111,6 120,0 15,0 12,0 93
244.0 1 109,7 120,0 15,8 12,0 91
244.0 1 114,4 120.0 14,3 12,0 95
244.0 1 109,3 120.0 18,7 12,0 91
244.0 1 107,9 120.0 15,8 12,0 90
Page 36 of 39
3/9/2007 1:35:02PM
SUMMARY OF FIELD DENSITY TESTS
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%) Relative (Vo)
Field Opt. Compaction Remarks
CW1173 5/25/06 C Crib Wall#l Cell #2 Station 12+62
CW1174 5/26/06 C Crib Wall#l Cell #2 Station 10+98
CW1175 5/26/06 c Crib Wall#l Cell#l Station 11+23
CW1176 5/26/06 c Crib Wall #1 Cell #2 Station 11+47
CW1177 5/26/06 c Crib Wall#l Cell#l Station 11+73
CW1178 5/26/06 c Crib Wall #1 Cell #2 Station 11+97
CW1179 5/26/06 c Crib Wall#l Gell#l Station 12+23
CW1180 5/26/06 c Crib Wall #l Cell #2 Station 12+45
CW1181 5/26/06 c Crib Wall#l Cell #1 Station 12+70
CW1182 5/26/06 c Crib Wall #1 Cell #2 Station 12+90
CW1183 5/27/06 c Crib Wall#l Cell #2 Station 11+05
CW1184 5/27/06 c Crib Wall #1 Cell #2 Station 11+30
CW1185 5/27/06 c Crib Wall#l Cell #1 Station 11+55
CW1186 5/27/06 c Crib Wall#l Cell #2 Station 11+80
CW1187 5/27/06 c Crib Wall#l Cell#l Station 12+05
CW1188 5/27/06 c Crib Wall #1 Cell #2 Station 12+30
CW1189 5/27/06 c Crib Wall#l Cell #1 Station 12+55
CW1190 5/27/06 c Crib Wall#l Cell #2 Station 12+80
CW1191 5/27/06 c Crib Wall#l Cell #2 Station 10+95
CW1192 5/27/06 c Crib Wall#l Gell#l Station 11+20
CW1193 5/27/06 G Crib Wall#l Cell #2 Station 11+45
CW1194 5/27/06 G Crib Wall#l Gell#l Station 11+70
CW1195 5/27/06 c Crib Wall #1 Cell #2 Station 11+95
CW1196 5/27/06 G Crib Wall#l Cell#l Station 12+20
CW1197 5/27/06 C Crib Wall#l Cell #2 Station 12+45
CW1198 5/27/06 C Crib Wall#l Cell#l Station 12+70
CW1199 5/27/06 G Crib Wall#l Cell#l Station 12+95
CW1200 5/30/06 G Crib Wall#l Cell#l Station 10+85
CW1201 5/30/06 G Crib Wall#l Cell #2 Station 11 + 10
CW1202 5/30/06 C Crib Wall#l Cell#l Station 11+35
CW1203 5/30/06 G Crib Wall#l Cell #2 Station 11+60
CW1204 5/30/06 C Crib Wall#l Cell#l Station 11+85
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
243.0 1 108.4 120.0 15,0 12,0 90
245.0 1 111.5 120.0 14,9 12.0 • 93
246.0 1 110.0 120.0 15,5 12.0 92
245.0 1 109.9 120.0 13,9 .. 12,0 92
246.0 1 112.7 120.0 14,4 12.0 94
245.0 1 109.4 120.0 14,6 12,0 91
246.0 1 113.7 120,0 15,5 12,0 95
245.0 1 113.0 120,0 13,9 12.0 94
246.0 1 109,6 120,0 15,0 12.0 91
245.0 1 110,3 120,0 14,6 12.0 92
248.0 1 107,9 120,0 11,5 12.0 90
247.0 1 108,0 120.0 11,7 12.0 90
248.0 1 107,6 120.0 11,4 12,0 90
247.0 1 109,1 120.0 12,1 12,0 91
248.0 1 108,4 120,0 13,1 12,0 90
247.0 1 107.7 120,0 13,0 12,0 90
248.0 1 108.6 120.0 15,2 12.0 90
247.0 1 109.2 120.0 15.6 . 12.0 91
249.0 1 108.7 120.0 16.9 12,0 91
250.0 1 107.6 120.0 15.6 12,0 90
249.0 1 107.8 120.0 11,5 12,0 90
250.0 1 107.6 120.0 12,5 12,0 90
249.0 1 108.4 120,0 13,9 12,0 90
250.0 1 108.0 120,0 14,2 12.0 90
249.0 1 107.9 120,0 13,7 12,0 90
250.0 1 109.7 120.0 15,8 12,0 91
250.0 1 109.9 120,0 13,6 12,0 92
252.0 1 107.4 120,0 12,6 12,0 90
251.0 1 108.3 120.0 14,1 12,0 90
252,0 1 109.5 120,0 14,0 12,0 91
251,0 1 108.5 120,0 13.4 12,0 90
252.0 1 • 110.5 120,0 15.2 12,0 92
Page 37 of 39
1 :'!5-09PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
CW1205
GW1206
CW1207
GW1208
CW1209
CW1210
CW1211
CW1212-
CW1213
CW1214
GW1215
CW1216
CW1217
CW1218
CW1219
CW1220
GW1221
CW1222
CW1223
CW1224
GW1225
CW1226
CW1227
CW1228
GW1229
CW1230
CW1231
CW1232
CW1233
GW1234
GW1235
CW1236
5/30/06
5/31/06
5/31/06
5/31/06
5/31/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/1/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
6/2/06
Project Number
Project Name:
Project Location:
Client:
G Crib Wall #1 Cell #2
G Crib Wall #1 Cell #1
G Crib Wall #1 Cell #2
G Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
G Crib Wall#l Gell#l
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall # I Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
C Crib Wall #1 Cell#l
C Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
G Crib Wall #1 Cell #1
841363-009
Carlsbad Golf Course
0
0
Station 12+10 251.0 1 107.9 120.0 12,0 12.0 90 Station 12+35 252.0 1 108.4 120.0 13,6 12^0 90 Station 12+60 251.0 1 108,9 120,0 14,1 12.0 91
Station 12+85 252.0 1 109,0 120.0 13,0 12.0 91
Station 13+05 252.0 1 108,6 120.0 13,2 12.0 90
Station 11+00 253.0 1 107,4 120.0 13,9 12.0 90
Station 11+50 253.0 1 108.9 120.0 17,6 12.0 91
Station 12+00 253.0 1 107.9 120.0 14,0 12.0 90
Station 12+50 253.0 1 108.6 120.0 13,6 12.0 90
Station 13+00 253.0 1 109.3 120.0 15,5 12.0 91
Station 13+10 254.0 1 108.1 120,0 11,8 12.0 90
Station 12+72 254.0 1 110.3 120.0 14,3 12,0 92
Station 12+37 254.0 1 107.6 120.0 12.3 12.0 90
Station 12+18 254.0 1 108.7 120.0 16,4 12.0 91
Station 11+70 254.0 1 109.1 120.0 14.7 12.0 91
Station 11+23 254.0 1 108.4 120.0 14.0 12.0 90 Station 10+92 254.0 1 109.2 120.0 14.2 12,0 91 Station 10+78 256.0 1 108.0 120,0 16,5 12,0 90 Station 11+02 256.0 1 109.3 120,0 13,6 12.0 91 Station 11+28 256.0 1 107.9 120,0 12,5 12,0 90 Station 11+52 256.0 1 109.8 120.0 14,4 12,0 92 Station 11+77 256.0 1 112.4 1.20.0 11,4 12.0 94 Station 12+02 256.0 1 108.6 120.0 17,6 12.0 90 Station 12+28 256.0 1 111.1 120.0 12,1 12.0 ,93 Station 12+50 256.0 1 107.9 120.0 18,5 12.0 90 Station 12+75 256,0 1 112.3 120.0 14,1 12,0 94 Station 13+00 256,0 1 110.0 120,0 16,3 12,0 92
Station 13+20 256,0 1 109.4 120,0 15,4 12,0 91
Station 13+18 258,0 1 109.2 120,0 12.4 12,0 91
Station 12+82 258,0 1 109.9 120,0 12.0 12,0 92 Station 12+57 258,0 3 104.3 114,5 17.2 12,5 91 Station 12+33 258.0 3 107.5 114,5 17.5 12,5 94
Page 38 of 39
1/0/9007
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
GW1237 6/2/06 C Crib Wall#l Gell#l Station 12+08
GW1238 6/2/06 G Crib Wall #1 Cell#l Station 11+87
CW1239 6/2/06 G Crib Wall#l Cell #1 Station 11+68
GWI240 6/2/06 C - Crib Wall #1 Cell #1 Station 11+42
GW1241 6/2/06 C Crib Wall #1 Cell #1 Station 11 + 18
GW1242 6/2/06 G Crib Wall#l Cell#l Station 10+93
CW1243 6/2/06 G Crib Wall#l Cell#l Station 10+67
CW1244 6/5/06 C Crib Wall#l Cell#l Station 10+50
CW1245 6/5/06 C Crib Wall#l Cell#l Station 11+00
CW1246 6/5/06 C Crib Wall#l Cell#l Station 11+50
CW1247 6/5/06 C Crib Wall#l Cell#l Station 12+00
CW1248 6/5/06 C Crib Wall#l Cell#l Station 12+50
GW1249 6/5/06 C . Crib Wall #1 Cell #1 Station 13+00
GW1250 6/5/06 C Crib Wall#l Gell#l Station 13+15
GW1251 6/5/06 C Crib Wall #1 Gell#l Station 12+70
GW1252 6/6/06 C Crib Wall#l Cell #1 Station 10+49
IGW1253 6/6/06 G Crib Wall #1 Gell#l Station 10+70
CW1254 6/6/06 G Crib Wall#l Gell#l Station 11+21
GW1255 6/6/06 G Crib Wall#l Gell#l Station 11+72
CW1256 6/6/06 G Crib Wall#l Cell#l Station 12+22
CW1257 6/6/06 C Crib Wall#l Cell#l Station 12+42
GW1258 6/6/06 G Crib Wall#l Cell#l Station 10+88
CW1259 6/6/06 C Crib Wall#l Gell#l Station 12+62
258.0 1 111.3 120.0 11.9 12.0 93
258.0 1 107.7 120,0 16.3 12,0 90
258.0 1 109.2 120,0 12,4 12.0 91
258.0 1 108.3 120.0 14,3 12.0 90
258.0 1 108.7 120.0 14,0 12.0 91
258.0 1 107.9 120,0 15,1 12,0 90
258.0 1 109.6 120,0 12,6 12,0 91
259.0 1 109.2 120,0 16.0 12,0 91
259.0 1 108.3 120,0 16.4 12,0 90
259.0 1 108.7 120,0 16.6 12,0 91
259.0 1 - 110.5 120,0 13.8 12,0 92
259.0 1 109.2 120.0 14.4 12,0 91
259.0 1 112.5 120.0 14,1 12,0 94
259.5 1 108.5 120.0 16,1 12,0 90
259.5 1 112,1 120.0 13,9 -12,0 93
261.4 1 '.110.4 120.0 13.1 12,0 92
261.4 1 108.3 120.0 16,0 12,0 90
260.4 1 108.0 120.0 12.3 12,0 90
260.4 1 110.3 120.0 12.1 12,0 92
260.4 1 108.9 120.0 12.8 12,0 91
260.4 1 111.4 120.0 12.8 12.0 93
260.4 1 112.3 120.0 13.3 12,0 94
260.4 1 109.6 120.0 14.0 12,0 •',91
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0 Page 39 of 39
3/9/2007 1:35:02PM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Dalte
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (%)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
SB 1 1/14/06 L Crib Wall#l Station 9+67 216.0 3
SB 2 1/14/06 L Crib Wall#l Station 9+67 • 217.0 3
SB 3 1/14/06 L Crib Wall#l Station 9+67 219.0 2
SB 4 1/14/06 L •Crib Wall #I Station 9+67 221.0 3
SB 5 1/14/06 L Crib Wall#l Station 9+67 223.0 3
SB 6 1/14/06 L Crib Wall #1 Station 9+67 220.0 3
SB 7 1/14/06 L Crib Wall#l Station 9+69 225.0 2
SB 8 1/24/06 L Crib Wall#l Station 0+50 237.0 3
SB 9 1/24/06 L Crib Wall#l Station 0+50 239.0 3
SB 10 1/24/06 L Crib Wall#l Station 0+50 241.0 3
SB 11 1/24/06 L Crib Wall#l Station 0+50 243.0 3
SB 12 1/24/06 L Crib Wall#l Station 0+50 241.0 3
SB 13 1/24/06 L Crib Wall#l Station 0+50 245.0 3
SB 14 1/25/06 L Crib Wall#l Station 4+00 237.0 3
SB 15 1/25/06 L Crib Wall #1 Station 4+00 339.0 3
SB 16 1/25/06 L Crib Wall#l Station 4+00 241.0 3
SB 17 1/25/06 L Crib Wall #1 Station 4+00 ' 243.0 3
SB 18 2/22/06 L Crib Wall#l Station 12+35 216.0 1
SB 19 2/22/06 L Crib Wall#l Station 12+35 220.0 3
SB 20 2/22/06 L Crib Wall#l Station 12+35 214.0 3
SB 21 2/22/06 L Crib Wall#l Station 12+35 218.0. 3
SB 22 . 2/22/06 L Crib Wall#l Station 12+35 222,0 3
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
109.1
108.7
106.3
108.8
109.1
108.5
106.1
110,9
110,5
110,2
109,4
109,1
111,6
108,8
109,2
110.7
109.1
115,7
110,5
111,6
109.4
109,7
114,5
114,5
111,0
114,5
114,5
114,5
111,0
114,5
114.5
114,5
114.5
114.5
114,5
114,5
114,5
114.5
114.5
120,0
114,5
114,5
114.5
114.5
17.1
16.3
19,8
17,6
16,4
16,6
19,6
15,7
14,6
15,1
14,6
15,1
16,2
15,2
16,2
14,3
11.9
10,7
13.1
13.6
11.1
12,0
12,5
12,5
14,0
12,5
12,5
12,5
14,0
12,5
12.5
12.5
12,5
12,5
12,5
12,5
12,5
12.5
12,5
12,0
12,5
12,5
12.5
12.5
95
95
96
95
95
95
96
97
97
96
96
95
97
95
95
97
95
96
97
97
96
96
Page 1 of 1
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
2
3
4
5
6
7
RW
RW
RW
RW
RW
RW
RW
RW 8
RW 9
RW 10
RW 11
RW 12
RW 13
RW 14
RW 15
RW 16
RW 17
RW 18
RW 19
RW 20
RW 21
RW 22
RW 23
RW 24
RW 25
RW 26
RW 27
RW 28
RW 29
RW 30
RW 31
RW 32
1/25/06 B
1/25/06 B
1/25/06
2/3/06
2/3/06
2/3/06
2/3/06
2/3/06
2/3/06
2/3/06
2/7/05
2/7/05
2/7/05
2/10/06 B
2/10/06 B
2/10/06 B
2/17/06
2/17/06
2/17/06 B
2/23/05 B
2/23/06
2/23/06
2/25/06 B
2/25/06, B
2/25/06
2/25/06
2/25/06
2/25/06
2/25/06
3/3/06
3/3/06
3/3/06
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
Project Number:
Project Name:
Project Location:
Client:
Crib Wall #1
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall #1
Crib Wall#l
Crib Wall#l
Crib Wall#l
841363-009
Carlsbad Golf Course
0
0
Station 10+15
Station 10+75
Station 11+50
Station 11+25
Station 9+55
Station 11+15
Station 9+25
Station 10+80
Station 9+85
Station 9+25
Station 11+30
Station 9+40
Station 10+65
Station 11+70
Station 9+75
Station 10+45
Station 11+00
Station 10+00
Station 9+00
Station 8+90
Station 9+90
Station 10+70
Station 9+30
Station 9+90
Station 10+30
Station 9+16
Station 10+00
Station 10+30
Station 10+75
Station 9+40
Station 10+50
Station 8+50
218.6
220.0
220.0
222.0
222,0
224,0
224,0
226,0
226,0
225,0
228.0
228.0
230.0
230.0
231.0
231.0
233.0
233.0
233.0 ,
235.0
234.0
234.0
237.0
237.0
236.0
239.0
238.0
240,0
239,0
240,0
240,0
242,0
3
3
3
4
4
3
3
4
4
4
4
4
1
1
4
4
3
4
4
4
4
4
4
4
4
4
4
3
3
5
5
5
109,4
105,3
107,5
109,8
104,3
102,7
104,6
107.3
106,5
105,8
106,4
106,6
113,2
110,4
105,4
104,7
103,0
105,1
105,6
104,6
104,2
104,5
104.5
105.2
105,4
106,9
108,2
102.6 '
103,5
109,1 '
108,6
111,3
114,5
114,5
114,5
116,0
116,0
114,5
114,5
116,0
116,0
116,0
116,0
116,0
120.0
120,0
116,0
116,0
114,5
116,0
116,0
116,0
116,0
116.0
116,0
116,0
116,0
116,0
116,0
114,5
114.5
119.0
119,0
119,0
15,6
15,6
16,4
12,6
12,8
12,7
16,3
14,2
14,2
14,1
13,5
14,2
11,6
12,3
14,1
13,1
9,9
10,8
9,1
18,0
19,3
18,9
14,3
12,6,
13,4
13,6
11,0
12.8
13.8
13.6
14.6
15.3
12.5
12.5
12.5
13.0
13.0
12.5
12.5
13.0
13.0
13,0
13,0
13,0
12,0.
12.0
13.0
13.0
12.5
13.0
13.0 ,
13.0
13.0
13.0
13.0
13.0
13.0 '
13.0
13.0
12.5
12.5
13.0
13.0
13.0
96
92
94
95
90
90
91
93
92
91
92
92
94
92
91
90
90
91
91
90
90
90
90
91
91
92
93
90
90
92
91
94
Page 1 of 7
3/11/2007
SUMMARY OF FIELD DENSITY TESTS
Test Test Test
No. Date Of
JLiUCdiiun ——
RW 33 3/7/06 B Crib Wall#l Station 10+30
RW 34 3/7/06 B Crib Wall#l Station 9+45
RW 35 3/7/06 B Crib Wall #1 Station 8+10
RW 36 3/8/06 B Crib Wall #1 Station 9+95
RW 37 3/8/06 B Crib Wall#l Station 8+60
RW 38 3/8/06 B Crib Wall#l Station 8+00
RW 39 3/8/06 B Crib Wall#l Station 7+50
RW 40 3/14/06 B Crib Wall#l Station 6+70
RW '41 3/14/06 B Crib Wall#l Station 7+90
RW 42 3/14/06 B Crib Wall#l Station 9+40
RW 43 3/14/06 B Crib Wall#l Station 10+10
RW 44 3/16/06 B Crib Wall #1 Station 6+50
RW 45 3/16/06 B Crib Wall#l Station 7+05
RW 46 3/16/06 B Crib Wall#l Station 7+75
RW 47 3/20/06 B Crib Wall#l Station 6+00
RW 48 3/20/06 B Crib Wall#l Station 5+10
RW 49 3/20/06 B Crib Wall#l Station 3+90
RW 50 3/22/06 B Crib Wall#l Station 9+70
RW 51 3/22/06 B Crib Wall#l Station 8+70
RW 52 3/22/06 B Crib Wall#l Station 7+50
RW 53 ' 3/24/06 B Crib Wall#l Station 6+80
RW 54 3/24/06 B Crib Wall#l Station 6+15
RW 54A 3/24/06 B Crib Wall#l Station 6+15
RW 55 3/24/06 B Crib Wall#l Station 4+98
RW 56 3/24/06 B Crib Wall#l Station 4+00
RW 57 3/27/06 B Crib Wall #1 Station 0+87
RW 58 3/27/06 B Crib Wall#l Station 2+08
RW 59 3/27/06 B Crib Wall#l Station 3+30
RW 60 3/27/06 B Crib Wall#l Station 4+25
RW 61 4/3/06 B Crib Wall#l Station 6+65
RW 62 4/3/06 B Crib Wall#l Station 5+50
RW 63 4/3/06 B Crib Wall #1 Station 4+50
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Page 2 of 7
Relative (Vo)
Compaction Remarks
241.0 5 110,3 119.0 16.3 13.0 • 93
242.0 5 114,4 119,0 14.1 13.0 . 96
242.0 1 114,2 . 120,0 11.1 12.0 95
245.0 2 102.5 111,0 15.2 14.0 • 92
244.0 2 104,9 111,0 12.1 14.0 95
244.0 . 5 107,3 119,0 12.3 13.0 90
243.0 5 109,6 1,19,0-14.3 13.0-92
241.0 5 107,9 119.0 11.0 13.0 91
245.0 5 106,9 119.0 13.0 13.0 90
244.0 5 110,1 119,0 12.4 13.0 93
244.0 2 103,6 111,0 14.0 14.0 93
244.0 1 112,0 120,0 11.1 12.0 93
246.0 4 105,2 116,0 12.2 13.0 91
247.0 , 5 113,9 119,0 11.2 13,0 96
242.0 4 106,3 116,0 13.9 13,0 92
240.0 4 107,6 116,0 16.4 13,0 93
239.0 4 106,6 116,0 17.3 13,0 92
247.0 4 106,8 116.0 11.8 13,0 92
248.0 5 110,0 119.0 16.0 13,0 92
248.0 4 106,4 116.0 13.8 13,0 92
245.0 5 110,4 119.0 11.0 13,0 93
245.0 5 103,4 119.0 13.0-13,0 87
245.0 5 107.6 119:0 13.3 13,0 90
241.0 5 108.3 119.0 12.2 13,0 91
241.0 1 M5.6 120.0 9.2 12.0 96
245.0 5 110.8 119.0 13.5 13,0 93
244.0 5 107.6 119.0 14.6 13,0 90 245.0 3 103.2 114.5 13.6 12,5 90 243.0 5 108.7 119.0 14.1 13,0 91
247.0 5 110,9 119.0 15.0 13,0 93
246.0 5 107,8 119.0 17.7 13,0 91
246.0 5 109,6 119.0 15.2 13,0 92
Retest on 54A
Retest of 54
3/11/2007 9T1:16AM
SUMMARY OF FIELD DENSITY TESTS
Test Test Test Location Test No. Date Of Lot # Elev (ft)
RW 64 4/3/06 B Crib Wall#l Station 3+50 246.0
RW 65 4/8/06 B Crib Wall#l Station 2+00 246.0
RW 65A 4/8/06 B Crib Wall#l Station 2+00 246.0
RW 66 4/8/06 B Crib Wall#l Station 1+00 245.0
RW 67 4/8/06 B Crib Wall#l Station 0+50 246.0
RW 68 4/8/06 B Crib Wall #1 Station 2+50 249.0
RW 69 4/8/06 B Crib Wall #1 Station 1+50 248.0
RW 70 . 4/8/06 B Crib Wall #1 Station 0+60 248.0
RW 71 4/10/06 B Crib Wall#l Station 10+25 248.0
RW 72 4/10/06 B Crib Wall #1 Station 9+00 249.0
RW 73 4/10/06 B Crib Wall#l Station 8+20 249.0
RW 74 4/10/06 B Crib Wall#l Station 7+80 249.0
RW 75 4/11/06 B Crib Wall#l Station 6+50 249.0
RW 76 4/11/06 B Crib Wall#l Station 5+50 249.0
RW 77 4/11/06 B Crib Wall #1 Station 4+50 249.0
RW 78 4/11/06 B Crib Wall #1 Station 3+50 248.0
RW 79 4/11/06 B Crib Wall#l Station 2+50 249.0
RW 80 4/11/06 B Crib Wall #1 Station 1+50 249,0
RW 81 4/12/06 B Crib Wall#l Station 10+00 251,0
RW 82 4/12/06 B Crib Wall#l Station 8+50 253.0
RW 83 4/12/06 B Crib Wall#l Station 7+50 253.0
RW 84 4/12/06 B Crib Wall #1 Station 5+75 253.0
RW 85 4/13/06 B Crib Wall #1 Station 4+65 252.0
RW 86 4/13/06 B Crib Wall #1 Station 3+25 252.0
RW 87 4/13/06 B Crib Wall#l Station 2+25 251.0
RW 88 4/13/06 B Crib Wall#l Station 9+95 255.0
RW 89 4/13/06 B Crib Wall #1 Station 8+85 254.0
RW 90 4/13/06 B Crib Wall #1 Station 7+50 254.0
RW 91 4/13/06 B Crib Wall #1 Station 6+35 254,0
RW 92 4/13/06 B Crib Wall #1 Station 0+70 252,0
RW 93 4/13/06 B Crib Wall #1 Station 0+50 254,0 RW 94 4/14/06 B Crib Wall#l Station 9+30 254,0
Soil
Type
Dry Density
Field Max
Moisture (%) Relative (%)
Field Opt. Compaction Remarks
Project Number:
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
3
3
5
5
5
5
5
5
5
5
5
5
5
5
5
5
108,7
103,1
108,6
107,4
108,0
108,6
109,4.
107,4'
107,6
111,6
110.4
109,4
112,5
111.4
108.6
107,3
104,5
106.5
111.6
112,3
109,4
108.6
109.9
109.6
107.6
112.6
107.6
108.2
114.0
109.5
107.3
107,0
119,0
119,0
119,0
119,0
119.0
119.0
119,0
119,0
119,0
119.0
119,0
119,0
119,0
119.0
119.0
119,0
114,5
114,5
119,0
119,0
119,0
119,0
119.0
119,0
119.0
119,0
119,0
119,0
119,0
119,0
119,0
119,0
15,7
16,7
16,0
17,6
16,8
12,3
14,1
15,0
13,5
16,1
14,2
14,0
14,0
13,6
15,1
12,6
14,3
16,6
12,5
12,2
11,6
13,6
14,7 •
15,2
16,3
14,1
12,4
14,4
15,2
15.6
16.7
12.0
13.0
13.0
13.0
13.0
13,0
13,0
13,0
13,0
13,0
13,0
13,0
13,0
13,0
13,0
13,0
13,0
12,5
12,5
13,0
13,0
13,0
13,0
13,0
13,0
13.0
13.0
13,0
13,0
13,0
13,0
13,0
13,0
91
87
91
90
91
91
92
90
90
94
93
92
95
94
91
90
91
93
94
94
92
91
92
92
90
95
90
91
96
92
90
90
Retest on 65A
Retest of 65
Page 3 of 7
9:31:16AM
SUMMARY OF FIELD DENSITY TESTS
Test Test Test
No. Date Of i-rOcation
RW 95 4/14/06 B Crib Wall #1 Station 7+60
RW 96 4/14/06 B Crib Wall#l Station 5+90
RW 97 4/17/06 B Crib Wall #1 Station 5+25
RW 98 4/17/06 B Crib Wall #1 Station 4+25
RW 99 4/17/06 B Crib Wall #1 Station 3+10
RW 100 4/17/06 B Crib Wall#l Station 1+50
RW 101 4/17/06 B Crib Wall#l Station 0+50
RW 102 4/19/06 B Crib Wall#l Station 1+50
RW 102A 4/19/06 B Crib Wall#l Station 1+50
RW 103 4/19/06 B Crib Wall #1 Station 2+50
RW 104 4/19/06 B Crib Wall#l Station 4+50
RW 105 4/19/06 B Crib Wall#l Station 5+80
RW 106 4/19/06 B Crib Wall #1 Station 7+00
RW 107 4/20/06 B Crib Wall #1 Station 9+30
RW 108 4/20/06 B Crib Wall#l Station 8+50
RW 109 4/20/06 B Crib Wall #1 Station 7+50
RW 110 4/20/06 B Crib Wall #1 Station 6+50
RW 111 4/20/06 B Crib Wall#l Station 5+50
RW 112 4/20/06 B Crib Wall#l Station 4+50
RW 113 4/20/06 B Crib Wall #1 Station 2+00
RW 114 4/20/06 B Crib Wall #1 Station 3+00
RW 115 4/20/06 B Crib Wall #1 Station 0+50
RW 116 4/25/06 B Crib Wall#l Station 7+85
RW 116A 4/25/06 B Crib Wall #1 Station 7+85
RW 117 4/25/06 B Crib Wall#l Station 5+25
IRW 117A 4/25/06 B Crib Wall #1 Station 5+25
RW 118 4/25/06 B Crib Wall #1 Station 4+00
RW 119 4/25/06 B Crib Wall#r Station 2+00
RW 120 4/25/06 B Crib Wall#l Station 0+25
RW 121 4/26/06 B Crib Wall#l Station 6+20
RW 122 4/26/06 B Crib Wall#l Station 5+20
RW 123 4/26/06 B Crib Wall #1 Station 3+40
Lot#
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Test
Elev (ft)
254.0
254.0
254.0
253.0
254.0
253,0
255.0
255.0
255.0
254.0
254.0
254.0
255.0
256.0
257.0
257.0
256.0
257.0
257.0
257.0
257.0
256.0
259.0
259.0
260.0
260.0
260.0
260.0
258.0
262.0
262,0
262,0
Soil
Type
5
5
5
5
5
5
5
2
5
2
5
5
5
5
5
5
5
4
5
5
1
5
7
7
5
5
5
5
1
4
4
5
Dry Density
Field Max
108,2
111,7
111,8
109,0
106,7
107,5
111,8
97.1
108.4
103.2
108.7
109,3
108,3
106,9
110,7
108,6
109,9
104,1
108.0
rii.i
111.3
108.4
105.2
107.9
105.1
108,0
107.6
108,2
113.3
107,5
104,8 ,
110,0
Moisture (%)
Field Opt.
Relative (Vo)
Compaction Remarks
119,0 14,0 13.0 91
119,0 16,5 13.0 94
119,0 15,7 13.0 94
119,0 18,1 13.0 92
119,0 17,3 13,0 90
119,0 14,2 13,0 90
119.0 13,8 13,0 94
111,0 12,2 14.0 87
119,0 14,6 13.0 91
111.0 14,0 14.0 93
119.0 12,5 13.0 91
119.0 14,2 13.0 92
119.0 13,1 13.0 91
119.0 12.5 13.0 90
119.0 10.1 13.0 93
119.0 1 1.9 13.0 91
119,0 12.5 13.0 92
116,0 14.0 13.0 90
119,0 14.1 13.0 91
119,0 12.0 13.0 93
120,0 11.0 12.0 93
119,0 14.6 13.0 91
118,0 8.7 12,0 89
118,0 13,9 12,0 91
119,0 11,0 13,0 88'
119,0 12,7 13,0 91
119,0 13,6 13.0 90
119,0 16,3 13.0 91
120,0 11,7 12.0 94
116,0 14,9 13.0 93
116,0 13.6 13.0 90
119,0 14.6 13.0 92
Retest on 102A
Retest of 102
Retest on 116A
Retest of 116
Retest on 117A
Retest of 117
Page 4 of 7
3/11/2007 9:31:16AM
SUMMARY OF FIELD DENSITY TESTS
Test Test Test
No. Date Of
LfUL-diion ———
RW 124 4/26/06 B Crib Wall#l Station 1+60
RW 125 4/26/06 B Crib Wall#l Station 2+35
RW 126 4/26/06 B Crib Wall #1 Station 5+10
RW 127 4/26/06 B Crib Wall#l Station 4+00
RW 128 4/26/06 B Crib Wall#l Station 2+50
RW 129 4/27/06 B Crib Wall#l Station 0+55
RW 129A 4/27/06 B Crib Wair#l Station 0+55
RW 130 4/27/06 B Crib Wall#l Station 2+10
RW 131 4/27/06 B Crib Wall#l Station 4+00
RW 132 4/27/06 B Crib Wall #1 Station 6+00
RW 133 4/28/06 B Crib Wall#l Station 3+50
RW 134 4/28/06 B Crib Wall#l Station 1+50
RW 135 4/28/06 B Crib Wall#l Station 5+45
RW 136 4/28/06 B Crib Wall #1 Station 1+50
RW 137 4/28/06 B Crib Wall#l Station 3+00
RW 138 4/28/06 B CribWalltfl Station 5+00
RW 139 4/28/06 B Crib Wall#l Station 6+50
RW 140 4/28/06 B Crib Wall#l Station 8+50
RW 141 5/1/06 B Crib Wall#l Station 2+00
RW 142 5/1/06 B Crib Wall#l Station 4+00
RW 143 5/1/06 B Crib Wall #1 Station 6+00
RW 144 5/1/06 B Crib Wall#l Station 8+00
RW 145 5/1/06 B Crib Wall#l Station 9+25
RW 146 5/2/06 B Crib Wall #1 Station 7+10
RW 147 5/2/06 B Crib Wall#l Station 3+40
RW 148 5/11/06 B Crib Wall#l Station 11+62
RW 149 5/11/06 B Crib Wall#l Station 11+22
RW 150 5/15/06 B Crib Wall#l Station 10+85
RW 151 5/15/06 B Crib Wall#l Station 11+55
RW 152 5/16/06 B Crib Wail #1 Station 10+80
RW 53 5/16/06 B Crib Wall#l Station 11+65
RW 54 5/17/06 B Crib Wall#l Station 11+60
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Moisture (%)
Field Opt.
Page 5 of 7
Relative (Vo)
Compaction Remarks
262.0 5 108.4 119,0 13.6 13,0 91
258.0 4 105.2 116.0 13.4 13,0 91
259.0 5 107.8 119,0 14.9 13,0 91
259.0 5 111.0 119,0 13.7 13,0 93
260.0 5 110.1 119,0 12.3 13,0 93
262.0 5 103.2 119,0 15.3 13,0 • 87
262.0 5 108.3 119,0 15.9 13,0 91
262.0 3 105.4 114,5 15.7 12,5 92
262.0 3 106.7 114,5 13.3 12,5 93
262.0 5 112.3 119.0 12.9 13,0 94
264.0 5 108.5 119.0 13.2 13,0 91
263.0 3 105.5 114,5 16.2 12.5 92
260.0 5 108.5 119,0 12.5 13,0 91
264.0 5 110.1 119,0 12.7 13,0 93
263.0 5 107.9 119,0 12,3 13,0. 91
262.0 5 107,8 119,0 13,8 13,0 91
260.0 2 103,8 111,0 17,4 14,0 94
256.0 5 113,9 119,0 14,2 13.0 96
264.0 5 110,8 119,0 14,8 13.0 93
264.0 5 109,7 119,0 15,0 13.0 92
263.0 5 • 107,6 119,0 14,8 13.0 90
259.0 5 109,1 119,0 12,7 13,0 92
257.0 5 ' 108,4 119.0 11.2 13,0 91
261.0 5 108,7 119,0 12.2 13,0 • 91
265.0 5 110,9 119.0 12.3 13,0 93
224.0 5 108,1 119.0 13.0 13,0 91 224.0 5 107,8 119.0 12.8 13,0 91
226.0 5 108,2 119.0 14.2 13,0 91
226.0 5 108,1 119.0 13.6 13,0 91
228.0 5 108.3 119.0 13.0 13,0 91
228.0 5 109,1 119.0 12.5 13,0 92
229,0 5 108,2 119.0 13.0 13,0 91
Retest on 129A
Retest of 129
3/11/2007
SUMMARY OF FIELD DENSITY TESTS
Test Test Test
No. Date Of
RW 155 5/17/06 B Crib Wall#l Station 12+20
RW 156 5/19/06 B Crib Wall#l Station 12+00
RW 157 5/19/06 B Crib Wall#l Station 11+35
RW 158 5/19/06 B Crib Wall#l Station 12+15
RW 158A 5/20/06 ' B Crib Wall#l Station 12+15
RW 159 5/19/06 B Crib Wall #1 Station 11 + 19
RW 159A 5/20/06 B Crib Wall # I Station 11+19
RW 160 5/20/06 B Crib Wall#l Station 11+95
RW 161 5/20/06 B Crib Wall#l Station 11+15
RW 162 5/23/06 B Crib Wall#l Station 12+00
RW 163 5/23/06 B Crib Wall #1 Station 12+75
RW 164 5/23/06 B Crib Wall#l Station 12+90
RW 165 5/23/06 B Crib Wall #1 Station 13+00
RW 166 5/24/06 B Crib Wall#l Station 13+00
RW 167 5/24/06 B ' Crib Wall #1 Station 11+80
RW 168 5/24/06 B Crib Wall#l Station 11+40
RW 169 5/24/06 B Crib Wall#l Station 11+00
RW 170 5/24/06 B Crib Wall#l Station 11+90
RW 171 5/24/06 B Crib Wall#l Station 12+90
RW 172 5/25/06 B Crib Wall#l Station 11+40
RW 173 5/25/06 B Crib Wall#l Station 12+10
RW 174 5/26/06 B Crib Wall#l Station 13+10
RW 175 5/26/06 B Crib Wall #1 Station 11+75
RW 176 5/26/06 B Crib Wall#r Station 13+20
RW 177 5/26/06 B Crib Wall #1 . Station 13+00
RW 178 5/27/06 B Crib Wall #1 Station 11+25
RW 179 5/27/06 B Crib Wall #1 Station 12+20
'RW 180 5/30/06 B Crib Wall#l Station 10+80
RW 81 5/30/06 B Crib Wall #1 Station 11+98
RW 82 5/30/06 B Crib Wall#l Station 13+15
RW 82A 5/30/06 B Crib Wall#l Station 13+15
RW 1 83 6/1/06 B Crib Wall #1 Station 11+30
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
Lot#
Test
Elev (ft)
Soil
Type
Dry Density
Field Max
Page 6 of 7
Moisture (%)
Field Opt.
Relative (Vo)
Compaction
229.0 5 108.3 119.0 13,2 13.0 91
232.0 5 - 108.4 119,0 12,7 13.0 91
232.0 5 112.0 119,0 12,1 13.0 94
233.0 1 104.9 120,0 9,3 12,0 87
233.0 1 110.0 - 120,0 12,8 12,0 ' 92
232.0 1 105.8 , 120.0 11,2 12,0 88
232.0 1 109,6 , 120.0 13,2 12.0 91 235.0 1 113,9 120,0 13,1 12.0 95
235.0 5 111,2 119,0 13,6 13,0 93 229.0 5 112,2 119,0 14,1 13,0 94
231.0 1 113,0 120,0 12,9 12,0 94
234.0 5 108,7 1 19,0 15,0 13,0 91 234.0 5 108,0 119.0 15,9 13,0 91 236.0 3 106,0 114.5 I 1,5 12,5 93
236.0 3 107,6 114.5 12,2 12,5 94
237.0 5 1:10,4 119.0 13,6 13,0 93 239.0 5 107,5 119,0 13,3 13,0 90
238.0 5 107.2 119,0 14,2 13,0 90
238.0 5 108,1 119,0 14,0 13,0 91
241.0 1 113.3 120,0 13,1 12,0 94
240.0 1 109,6 120,0 13.3 12,0 91
240.0 1 109.6 120,0 13.6 12,0 91
243.0 1 111.6 120,0 14.1 12,0 93
243.0 1 112.3 120,0 12.8 12,0 94
243.0 i 110.6 120,0 15.1 12,0 92 245.0 5 109.3 119,0 16.4 13,0 92
245.0 5 108.6 119,0 -16.0 13,0 91
247.0 1 118.0 120,0 9.9 12,0 98
247.0 1 113.2 120,0 12.6 12,0 94
247.0 1 102.7 120.0 10.6 12,0 . 86 247.0 1 108.0 120,0 13.6 12.0 90 -250.0 1-104.9 120,0 7.2 12.0 87
Remarks
Retest on 158A
Retest of 158
Retest on 159A
Retest of 159
Retest on 182 A
Retest of 182
Retest on 183 A
3/11/2007 9:31:1fiAM
SUMMARY OF FIELD DENSITY TESTS
Test
No.
Test
Date
Test
Of
Location
Lot#
Test Soil Dry Density Moisture (%) Relative (Vo)
Elev (ft) Type Field Max Field Opt. Compaction Remarks
RW 183 A 6/1/06 B Crib Wall #1 Station 11+30 250,0 1
RW 184 6/1/06 B Crib Wall#l Station 12+50 250.0 1
RW 185 6/1/06 B Crib Wall#l Station 13+00 252.0 •"4
RW 186 6/1/06 B Crib Wall #1 Station 12+00 252.0 4
RW 187 6/1/06 B Crib Wall#l Station 11+00 252.0 4
RW 188 . 6/2/06 . B Crib Wall #1 Station 11+40 254.0 ' 1
RW 189 6/2/06 B Crib Wall #1 Station 12+40 254.0 4
RW 190 6/5/06 -B Crib Wair#l Station 10+60 256.0 1
RW 191 , 6/5/06 B Crib Wall #1 Station 11+55 256.0 1
RW 192 6/5/06 B Crib Wall#l Station 12+10 256.0 1
RW 193 7/11/06 B Crib Wall#l Station 12+70 215.0 5
RW 194 7/11/06 B Crib Wall#l Station 11+60 220.0 5
RW 195 7/11/06 B Crib Wall#l Station 10+65 220.0 5
RW 196 7/11/06 B Crib Wall#l Station 9+70 230.0 5
RW 197 7/11/06 B Crib Wall#l Station 8+65 230.0 5 RW 198 7/1*1/06 B Crib Wall#l Station 7+60 235.0 5 RW 199 7/11/06 B Crib Wall#l Station 6+55 240.0 5
RW 200 7/11/06 B Crib Wall #1 Station 5+65 245.0 5
RW 201 7/lil/06 B Crib Wall #1 Station 5+65 245.0 5
Project Number
Project Name:
Project Location:
Client:
841363-009
Carlsbad Golf Course
0
0
111.0
110,1
105,2
106,6
107.3
110.6
105,6
110,3
114,2
112,1
110,7
110,9
108,8
111,7
111,7
110,5
110,0
109,6
110.4
120.0
120,0
116,0
116,0
116,0
120,0
116,0
120,0
120,0
120,0
119,0
119,0
119,0
119,0
119.0
119.0
119.0
119.0
119,0
13,6
13,4
16,3
12,6
14,6
14,3
13,3
17,0
12,9
1 1,2
13,6
13,4
13,2
12,8
12,7
13.9
14,1
13,5
13.0
12,0
12.0
13.0
13.0
13.0
12.0
13.0
12.0
12.0
12.0
13.0
13,0
13,0
13,0
13,0
13,0
13,0
13.0
13,0
93
92
91
92
93
92
91
92
95
93
93
93
91
94
94
93
92
92
93
Retest of 183
Page 7 of7
9:31:16AM
841363-009
APPENDIX C
Laboratory Testing Procedures and Test Results
Maximum Densitv Tests: The maximum dry density and optimum moisture content of typical soils
were determined m accordance with ASTM Test Method D1557. Tlie results of these tests are
presented in the table below:
Sample
Number Sample Description Maximum Dry
Derisity (pcf)
Optimum Moisture
Content (%)
1 Yellowish-brown silty clayey SAND 120.0 12.0
2 Olive-brown clayey SAND 111.0 14.0
3 Brovwi silty SAND 114.5 12.5
4 Gray-green silty SAND 116.0 13.0
5 Yellow-brown silty SAND 119.0 13.0
6 Yellow-brown silty SAND 121.0 11.5
7 Gray silty SAND 118.0 12.0
8 Brown silty SAND 122.5 11.0
9 Dark gray silty SAND 119.5 12.5
^^^1 o^? Atterberg Limits were determmed in accordance with ASTM Test Method
D4318 for engineenng classification of the fine-grained materials and presented in the table below:
Sample
Number
Liquid Limit
- (%)
Plastic Limit
(%)
Plastic Index
(%)
USCS
Soil Classification
1 — — NP SP-SM
2 45 17 28 SC
3 — NP SM
C-l
841363-009
APPENDIX C (Continued)
^Tcx^^^ffl^^L^"" ^"'"""^ ^^''^S Sieve analysis was performed according to AS 1M Dl 140. The percent fine particles from these analyses are summarized below.
Sample Number Percent Passing No. 200 Sieve
3 22
5 42
6 29
7 13
8 32
9 47
Classification or Grain Size Tests: Typical materials were subjected to mechanical grain-size
analysis by sievmg from U.S. Standard brass screens (ASTM Test Methods D4318 D422) The
data was evaluated in determining the classification of the materials. The grain-size distribution for
gravel, sand, fines and the Unified Soil Classification (USCS) are presented below
Sample Number % Gravel % Sand % Fines USCS Soil
Classification
1 0 88 12 SC-SM
2 0 66 34 SC
I
I C-2
mmmm VERITAS
I
I
I
I
I
H
n
D
I
I
I we„ed by TKD from Nove„,ber 28. 2«35 .„ J™™^7S K sh^M L „„"
report refers lo testing performed on two commercial pad areas located on the west end of th
stte, north and sooth of College Boulevard. The p^ose of this report is to lupplement
I "n""' Number 2) that i^cl„ded^ough gradtag fTte " ™n™ercial pads as well as other areas of the golf course. 8 aumg tor these
n tuK'T'^'"" °' "1' "T'^" ""Sh 8"<lins and placement of on-site and import fill soils
n wt hin the comn^rcal pads. AU fill areas were tested in accordance wid, the prt,ject"pSflc.ta
udess odterwtse directed by the Geotechnical Engineer of Recotd (i.e. Leighton aaj AssSt)
U The approMinate site location and features are presented on Figures 1 and 2 resnectivel.
Locattons of field density testing are presented on Figure 3. Sum4ries of laLL^Md field
I compactton test, results are provided in Appendix A, Tables 1 and 2, respectively OnTte and
mport matenal was used as fiU for the new development. Fill was placed, compacted and tested
ZtS^""" ™"™ • ''^ "^-d on AITM DTSSV as
It should be noted that the precision of the field and laboratoiy maximum dry density test results
are subject to vanation inherent with testing procedures and heterogen^L mSeri
IH charactenstics. Quantitative values of testing precision have been documented by the Ame Lan
Society of Testmg and Materials. For example, results indicate the accuracy of the ASTM D
Testing Engineers San Diego, Inc.
A Bureau Veritas Company
700, r- c . ' Main: (858) 715-5800 7895 l.x>nvoy Court, Suite 18
_ ^ ^, Fa^ (858715-5810 San Diego, CA 92111
www.us.bureauveritas.com
City of Carlsbad u .
5950 El Camino Real P t TT''
Carlsbad, CA 92009 - Contract No.: 108078
Attention: Mr. Skip Hammann
Subject: Supplemental Compaction Testing Report
Project: Commercial Sites
Carisbad - Municipal Golf Course
Palomar Airport Road/ Palomar Oaks Way
Carlsbad, CA
Reference: 1. "Contract Documents and Supplemental Provisions" far Carlsbad
Municipal Golf Course Project. Project No. 39721-1 dated June 13, 2005.
2. "Compaction Testing Report, Carlsbad Municipal Golf Course"
prepared by Testing Engineers - San Diego, dated July 18, 2006.
Dear Mr. Hammann:
I
I
n
»
I
I
I
I
n
fl
D
D
D
I
I
I
I
D
n
«
«
City of Carlsbad
Municipal Golf Course Contract No.: 108078
1557 test to be plus or minus 2 percent of the mean density. Based on this information relative
Survey lines and elevations relative to grMe modifications, final design grades, locations of
various elements, etc., were established by others. iucauons or
Field Monitoring services provided by this office, consisting of visual observation of compaction
operations aiid random m-place density testmg, are intended as assistance to the owner/cHent nd
Geotechnical Engineer of Record (i.e. Leighton and Associates) in monitorinfaplem
reasonable compliance with the project earthwork specifications. The presence of our fidd
epresentative during the work progress did not involve any direcf supervision "f
contractor/subcontractor,, nor any recommendations in a geotechnical capacity. Technical adv ce
and suggestions were provided upon request based upon the results of the test's and ob ervatt s
hi any case, no waixanty or responsibility for the contractor's performance is intended or implied
LTsiS'atS) 7?5-T8^^^^^^ ^'^^ ~ P'-- - - die
Sincerely,
Testing Engineers - San Diego, Inc.
A Bureau Veritas Company
Nick Tracy, EIT
Staff Engineer Van W. Olin, G.E.
Principal Geotechnical Engi
NTA^O:mm
Attachments:
Distribution:
Figure 1; Site Location Map
Figure 2: Overall Exhibit Drawing
Figure 3: Plot Plan
Appendix A: Table 1 and Table 2
.*(4) Addressee
* Includes copies for building department submitted
As graded
H
I
I
I
I
n
D
0
I
I
I
I
0
0
fl
I
I
1
I
I
I
1
I
1
1
1
I
I
I
1
1
1
1
1
I
i
1
I
1
I
I
I
I
1
1
1
1
1
1
I
1
I
I
1
I
I
1
City of Carlsbad
Municipal Golf Course Contract No.: 108078
TABLE 1
RESULTS OF MAXIMUM DENSITY TESTS
(ASTM-D-1557)
e , ^ ^ . Maximum Dry Optimum Moisture
Sample # Descnption Density (PCF) Content (%)
1. On-site: Grayish Silty Sand 127,5 9.5
2. Import: Mixed Gray Silty Sand 123.5 11.0
3. On-site: Red Brown Clayey Sand 124.0 12.0
4. On-site: Yellowish Brown Silty Sand 114,5 14.5
5. On-site: Greenish Brown Silty Sand 124,5 11.0
6. On-site: Mbced Brown Silty Sand 123.0 10.5
7. On-site: Dark Green & Brown 126.0 10.0
Clayey Sand
8. On-site: Brown Silty Sand 128.5 9.5
9. On-site: Tan Clayey Sand 119.0 13.5
10. On-site: Brown Clayey Sand 121.5 10.5
11. On-site: Brown Sandy Clay 124.5 10.5
12. On-site: Yellow Silty Sand I17.0 13.0
Print Date:
Project Number:
Project Name:
Location:
Table 2
March 12. 2007 COMPACTION TEST DATA
108078
Carlsbad Municipal Golf Course
Palomar Airport Road and Palomar Oaks Way
Carlsbad, California
Test # Test
Date Test Location
38 9/28/2005 Plate 2 Keyway"
39 9/28/2005 Plate 2 Keyway
40 9/28/2005 Plate 2
41 9/28/2005 Plate 2
42 9/28/2005 Plate 2
73 10/7/2005 Plate 2
74 10/7/2005 Plate 2
75 10/7/2005 Plate 2
108 10/19/2005 Plate 2 Bottom Right on Plate
109 10/19/2005 Bottom Right of Plate 2
166 11/3/2005 Plate 2 Commercial Pad
167 11/3/2005 Plate 2 Commercial Pad
168 11/3/2005 Plate 2 Commercial Pad
187 11/10/2005 Plate 2 Hole 16
188 11/10/2005 Plate 2 Hole 16
189 11/10/2005 Plate 2 Hole 16
190 11/10/2005 Plate 2 Hole 16
191 11/10/2005 Plate 2 Hole 16
192 11/10/2005 Plate 2 Hole 16
193 11/10/2005 Plate 2 Hole 16
281 11/23/2005 Plate 2 Central Fill Slope South
Side
282 11/23/2005 Plate 2 Central Fill Slope North
Side
11/23/2005 Retest of #282
11/23/2005 Plate 2 NE Comer Area of Fill
Scope West of College
11/23/2005 Retest of #284
11/23/2005 Plate 2 Lower Commercial Pad
11/23/2005 Plate 2 Lower Commercial Pad
11/23/2005 Plate 2 Commercial Pad
11/23/2005 Plate 2 Commercial Pad
11/23/2005 Retest of 286, 287 &288
11/28/2005 Plate 2 Commercial Pad West
11/28/2005 Plate 2 Commercial Pad West
11/28/2005 Retest #292
11/28/2005 Plate 2 Commercial Pad West
283
284
285
286
287
288
289
290
291
292
292A
293
I Elev.
Jft)
252.0
256.0
258.0
261.0
260.0
268.0
282.0
280.0
283.0
282.0
284.5
285,0
287.0
132.5
134.0
135.0
138,0
128.0
126,0
138,0
154.0
Moisture
Field f Optimum
13.6% 14.5%
13.6% 14.5%
13.6% 14.5%
13.6% 14.5%
13.6% 11.0%
11-1% 9.5%
12.3% 11.0%
12.3% 11.0%
9.8% 10.5%
9.8% 10;5%
11.1% 10.5%
12.3% 10.5%
11.1% 10.5%
11.1% 10.5%
12.3% 14.5%
12.3% 14.5%
12.3% 10.5%
12.3% 10.5%
12.3% 14.5%
12.3% l4.5o/„
11,1% 14.5%
154.0 16.3% 14,5%
154.0
247.0
247.0
153.0
152.0
247.0
152.0
152.0
155.0
157.0
.137.0
158.0
13.6%
17.0%
16.3%
13.'2%
13.8%
13.9%
13.3%
12.3%
14.5%
13.2%
12.4%
13.6%
14.5%
14.5%
13.5%
11.0%
11.0%
11.0%
11.0%
11.0%
11.0%
11.0%
11.0%
11.0%
Field I Maximum"
110.3 114.5
110.0 114.5
110.0 114.5
110.0 114.5
118.9 124.5
124.5 128.0
120.9 127.0
120.0 124.5
118.0 123.0
119.2 123.0
117.4 123.0
117.1 123.0
119.3 123,0
115.7 123.0
112.6 114.5
112.8 114,5
114.6 123,0
114.7 123.0
117.3 123.0
115.8 123.0
106.6 114.5
100.9
106.7
100.5
105.0
118.3
115.7
115.2
120.9.
120.3
121.3
119.2
121.9
117.6
114.5
114.5
114.5
119.0
127.0
127.0
127.0
127.0
127.0
127.0
127.0
127.0
127.0
Obtained |
96%
96%
96%
96%
96%
97%
95%
96%
96%
97%
95%
95%
97%
94%
98%
99%
93%
93%
95%
94%
93%
88%
93%
88%
88%
93%
91%
91%
95%
95%
96%
94%
96%
93%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
Conform
Non-Confonn
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Non-conform
Conform
Conform
Non-conform 1
Non-conform 1
Conform
Non comform 1
Non-conform
Non-conform
Non-conform
Non comform
Non-conform
Non-conform
Non-conform
Non-conform
Conform
Non comform
Conform
Non-conform
Conform
Non-conform
Print Date:
Project Number:
Project. Name:
Location:
Table 2
March 12,2007 "^^^''^ COMPACTION TEST DATA
108078
Carlsbad Municipal Golf Course
Palomar Airport Road and Palomar Oal<s Way
Carlsbad, Califomia
Test
Date
293A 11/28/2005
294 11/28/2005
295 11/28/2005
299 11/29/2005
300 11/30/2005
301 11/28/2005
302 11/28/2005
Retest #293
Plate 2 Commercial Pad West
Plate 2 Commercial Pad West
Plate 2 Commercial Pad West
Plate 2 Commercial Pad West
Retest of #285
Plate 2 NE Corner Area of Mail Fill
Slope. West Adj. to College Ave.
158.0
160.0
160.0
152.0
154.0
247.0
253.0
12.8%
11.0%
11.5%
10.7%
11.5%
10.1%
12.9%
307 11/29/2005 Plate 2 Commercial Pad West
308 11/29/2005 Plate 2 Commercial Pad West
. 309 11/29/2005 Plate 2 Commercial Pad West
309A 11/29/2005 Retest of #309
310 11/29/2005 Plate 2 Commercial Pad West
311 11/29/2005 Plate 2 Commercial Pad West
311A 11/29/2005 Plate 2 Commercial Pad West
312 11/29/2005 Plate 2 Commercial Pad West
313 11/29/2005 Plate 2 Commercial Pad West
314 11/29/2005 Plate 2 Commercial Pad West
315 11/29/2005 Plate 2 Commercial Pad West
316 11/29/2005 Plate 2 Commercial Pad West
316A 11/29/2005 Retest of #316
317 11/29/2005 Plate 2 Commercial Pad West
318 11/29/2005 Plate 2 Commercial Pad West
319 11/29/2005 Plate 2 Commercial Pad West
330 11/30/2005 Plate 2 East Area Main Slope Fill
331 11/30/2005 Plate 2 East Area Main Slope Fill
331A 11/30/2005 Plate 2 East Area Main Slope Fill
346 12/1/2005 Plate 2 Commercial Pad East
Area
347 12/1/2005 Plate 2 Commercial Pad East
Area
348 12/1/2005 Plate 2 Commercial Pad East
Area
348A 12/1/2005 Retest of #348
156.0
158.0
160.0
160.0
162.0
164.0
164.0
165.0
167.0
168.0
170.0
171.0
171.0
173.0
174.0
176.0
253.0
10.3%
9.5%
10.3%
9.9%
9.1%
8.9%
10.7%
11.1%
11.5%
9.9%
12.4%
12.9%
12.4%
11.5%
11.1%
10.7%
14.9%
11.0%
11.0%
11.0%
9.5%
9.5%
14.5%
13.5%
9.5%
9.5%
9.5%
9.5%
9.5%
9.5%
9.5%
10.0%
10.0%
10.0%
11.0%
11.0% .
11.0%
11.0%
11.0%
11.0%
13.5%
122,3
121.7
123.1
121.9
121.8
109.3
110.5
124.7
123.2
119.8
124.0
124.4
115.6
122.1
121.2
122.1
120.1
122.3
119.2
121.8
123.2
123.2
122.7
108.0
255.0 15.4% 13.5% 104,5
255.0 13.2% 13.5% 110,5
258.0 11.7% 11.0% 113.4
259.0 13.8% 11.0% 114.2
260.0 13.0% 11.0% 111.3
260.0 11.8% 11.0% 114,5
127.0
127.0
127.5
127,5
114.5
119.0
127,5
127.5
127.5
127.5
127.5
127,5
127.5
126.0
126.0
126.0
127.0
127.0
• 127.0
127.0
127.0
127.0
119,0
119,0
96%
96%
97%
96%
96%
95%
93%
98%
97%
94%
97%
98%
91%
96%
, 96%
97%
• 95%
96%
94%
96%
97%
97%
97%
91%
88%
93%
91%
92%
88%
90%
95%
95%
95%
95%
95%
95%
90%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
90%
90%
90%
90%
90%
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Non-conform
Conform
Conform
Non-conform
Conform
Conform
Conform
Conform
Conform
Non-conform
Conform
Conform
Conform
Conform
Conform
Non-conform
Conform
Conform
Conform
90% Non comform
90% Conform
Print Date:
Project Number-
Project Name:
Location:
March 12, 2007
108078
Carlsbad Municipal Golf Course
Palomar Airport Road and Palomar Oaks Way
Carlsbad, California
Table 2
REPORT OF COMPACTION TEST DATA
Tests Test
Date
349 12/1/2005
350 12/1/2005
351 12/1/2005
352 12/1/2005
358 12/2/2005
359 12/2/2005
360 12/2/2005
,361 12/2/2005
362 12/2/2005
Test Location Elev. Moisture Dry Density (pcf) I Relative Compactlnn
Area
Plate 2 Commercial Pad East
Area
Plate 2 Commercial Pad East
Area
Plate 2 Commercial Pad East
Area
Plate 2 Commercial Pad East
Area
363 12/2/2005 Plate 2 Commercial Pad East
Area
364 12/2/2005 Plate 2 Commercial Pad East
Area
365 12/5/2005 Plate 2 Hole 16 Commercial Pad
366 12/5/2005 Plate 2 Hole 16 Commercial Pad
365A 12/5/2005 Retest of #365
366A 12/5/2005 Retest of #366
367 12/5/2005 Plate 2 Hole 16 Commercial Pad
368 12/5/2005 Plate 2 Hole 16 Commercial Pad
367A 12/6/2005 Retest of #367
368A 12/6/2005 Retest of #368
369 12/5/2005 Plate 2 East Area Commercial
Pad
370 12/5/2005 Plate 2 East Area Commercial
Pad
373 12/6/2005 Plate 2 Hole 16 Commercial Pad
374 12/6/2005 Plate 2 Hole 16 Commercial Pad
373A 12/6/2005 Retest of #373
180.0 10.3%
182.0 11.1%
184.0 12.4%
250.0 12.5%
11.0%
11.0%
11.0%
11.0%
11.0%
119.5
121.6
122.5
122.6
115.5
124.5
127.0
127,0
127.0
124.5
96%
96%
96%
97%
93%
95%
95%
95%
95%
90%
Conform
Non-Conform |
Conform
Conform
Conform
Conform
Conform
252.0 13.0% 11,0% 116.1 124.5 93% 90% Conform
254.0 11.6% 11.0% 115,3 124.5 93% 90% Conform
256.0 11.3% 11.0% 121.4 127.0 96% 90% Conform
258.0 12.2% 11.0% 119.3 127.0 94% 90% Conform
260.0 13.0% 11.0% 114.6 124.5 92% 90% Conform
262.0 10.9% 11.0% 115,3 124.5 93% 90% Conform
196.0 17.3% 14.5% 103.5 114,5 90% 95% Non-conform
197.0 17.1% 14.5% 104.5 114.5 91% 95% Non-conform
196.0 17.0%
197.0 17.2%
198.0 14.8%
14,5%
14.5%
14.5%
109.9
111.1
104.8
114,5
114.5
114,5
96%
97%
92%
95%
95%
95%
Conform
Conform
Non-conform
198.0 17.6% 14.5% 103.1 114,5 90% 95% Non-conform
198.0 14.9%
198.0 15.8%
263.0 13.9%
14.5%
14.5%
10.0%
109.9
108.8
114.0
114.5
114.5
124.5
96%
95%
92%
95%
95%
90%
Conform
Conform
Conform'
258.0 16.0% 14.5% 104.8 114.5 92% 90% Conform
198.0 16.4% 13.5% 105.8 119.0 89% 95% Non comform
198.0 14.7%
198.0 15.1%
13.5%
13.5%
107.8
115.4
119.0
119.0
91%
97%
95%
95%
Non-conform
Conform
Print Date:
Project Number:
Project Name:
Location:
Table 2
March 12, 2007 °' COMPACTION TEST DATA
108078
Carlsbad Municipal Golf Course
Palomar Airport Road and Palomar Oaks Way
Carlsbad, California
374A
375
376
377
380
380A
381
382
383
384
385
388
389
390
391
392
393
394
395
396
404
Test
Date
12/6/2005
12/6/2005
12/6/2005
12/6/2005
12/7/2005
12/7/2005
12/7/2005
12/7/2005
12/7/2005
12/7/2005
12/7/2005
12/7/2005
12/7/2005
12/8/2005
12/8/2005
12/8/2005
12/8/2005
12/8/2005
12/8/2005
12/9/2005
12/9/2005
Test Location
Retest of #374
404A
405
405A
406
406A
407
408
409
12/9/2005
12/9/2005
12/9/2005
12/9/2005
12/9/2005
12/9/2005
12/9/2005
12/9/2005
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Retest of #380
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
Plate 2 Hole 16 Commercial Pad
South Side
Retest of #404
Plate 2 Hole 16 Commercial Pad
South Side
Retest of #405
Plate 2 Hole 16 Commercial Pad
North Side
Retest of #406
Plate 2 Hole 16 Commercial Pad
North Side
Plate 2 Hole 16 Commercial Pad
South Side
Plate 2 Hole 16 Commercial Pad
North Side
Elev.
jft)
198.0
202.0
202.0
204.0
200.0
200.0
200.0
204.0
204.0
206.0
206.0
207.0
208.0
211.0
211.0
211.0
211,0
213.0
213.0
212.0
216.0
14.0%
14.5%
15.1%
15.3%
13.0%
12.8%
10.7%
9.7%
10.2%
7.2%
7.9%
11.5%
8.9%
11.2%
13.9%
14.1%
12.9%
18.7%
19.1%
18.0%
14.6%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
14.5%
13.5%
14.5%
13.5%
13.5%
13.5%
13.5%
Field
114.2
115.4
115.4
107.1
110.7
113.1
117.1
114.2
115.4
114.7
113.1
113,1
116.2
113.1
108.8
114,2
108.8
105.9
98.7
96.0
103.0
Maximum
119.0
119.0
119.0
119.0
119,0
119.0
119.0
119.0
119.0
119.0
119.0
119.0
119.0
119,0
114.5
119.0
114.5
119.0
119.0
119.0
119.0
Relative
I Obtained
96%
97%
97%
90%
93%
95%
98%
96%
97%
96%
95%
95%
98%
95%
95%
96%
95%
89%
83%
81%
87%
Compaction I Conform
Required |^Non-Confonn |
Conform 95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
Conform
Conform
Non-conform
Non-conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Non conform
Non-conform
Non-conform 2
Non-conform 2
216.0
216.0
13.6%
16.8%
13.5%
14.5%
113.5
101.5
119.0
114.5
95%
89%
95%
95%
Conform
Non-conform
216.0
216.0
15.4%
12.9%
14.5%
14.5%
109.9
102.7
114.5
114.5
96%
90%
95%
95%
Conform
Non-conform
216.0
217.0
15.7%
12.3%
14.5%
13.5%
108.8
114.2
114.5
119.0
95%
96%
95%
95%
Conform
Conform
219,0 11.3% 13.5% 106.3 119.0 89% 95% Non-conform
219.0 11.7% 13.5% 108.3 119.0 91% 95% Non-conform
Print Date:
Project Number-
Project Name:
Location:
Table 2
March 12, 2007 "^''^''^ COMPACTION TEST DATA
108078
Carlsbad Municipal Golf Course
Palomar Airport Road and Palomar Oaks Way
Carlsbad, Califomia
Test# Test
Date
408A 12/10/2005
409A 12/10/2005
41 OA 12/10/2005
411A 12/10/2005
412 12/10/2005
412A 12/10/2005
413 12/10/2005
413A
412B
412C
414
413B
415
414A
416
417
418
431
12/10/2005
12/10/2005
12/12/2005
12/10/2005
12/12/2005
12/13/2005
12/12/2005
12/13/2005
12/13/2005
12/13/2005
12/13/2005
432 12/13/2005
433 12/14/2005
434 12/14/2005
435 12/14/2005
436 12/14/2005
437 12/14/2005
438 12/14/2005
439 12/15/2005
440 12/15/2005
441 12/15/2005
442 12/15/2005
Plate 2 Hole 16 Commercial Pad
North Side
Plate 2 Hole 16 Commercial Pad
South Side
Retest of #408
Retest of #409
Retest of #410
Retest of #411
Plate 2 Hole 16 Commercial Pad
Center & West Edge
Retest of #412
Plate 2 Hole 16 Commercial Pad
South Side
Retest of #413
Retest of #412A
Retest of #412B
Plate 2 Commercial Pad Center
Retest of #413A
Plate 2 Commercial Pad
Retest of #414
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Commercial Pad 90% Area Plate
2
Commercial Pad 90% Area Plate 4
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Plate 2 Commercial Pad
Commercial Pad Plate 2
Commercial Pad Plate 2
Commercial Pad Plate 2
Retest of #439
219.0 14.6%
219.0 11.0%
13.5%
219.0
219.0
219.0
219.0
221.0
221.0
221.0
221.0
221.0
221.0
221.0
221.0
226.0
221.0
226.0
226.0
226:0
237.0
13.9%
14.1%
12.9%
11.3%
12.6%
17.3%
18.1%
15,6%
12,1%
11.1%
15.1%
14.1%
14.0%
14.8%
14.3%
14.0%
14.4%
14.2%
240,0 13.8%
235.0
240.0
244.0
257.0
253.0
258.0
260.0
258.0
261.0
260.0
14.6%
15.1%
13.4%
15.1%
14.7%
15.2%
13.4%
12.7%
12.0%
12.7%
13.5% 105,9 119.0 89%
13.5% 113,1 119.0 95%
13.5% 113.1 119.0 95%
13.5% 114.2 119.0 96%
13.5% 113.1 119.0 95%
13.5% 105.1 119.0 88%
13.5% 101.9 119.0 86%
13,5% 102.4 119.0 86%
13.5% 104.1 119.0 87%
13.5% 105.8 119.0 89%
13.5% 108.3 119.0 91%
13.5% 102.9 119.0 86%
13.5% 107.1 119,0 90%
13.5% 109.5 119.0 92%
13.5% 108,3 119.0 91%
13.5% 110.7 119.0 93% 13.5% 109,5 119,0 92%
13.5% 109,5 119.0 92%
13,5% 109,8 119.0 92%
13,5% 109.1 119.0 92%
13.5%
13.5%
13.5%
13.5%
13.5%
13.5%
11.0%
11.0%
11.0%
11.0%
108.6
110.8
109.8
110.8
107.5
109,6
106,3
109,1
107,2
111.9
119.0
119,0
119,0
'119.0
119.0
119.0
123.5
123.5
123.5
123.5
91%
93%
92%
93%
90%
92%
86%
88%
87%
91%
95%
95%
95%
95%
95%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
90%
Non-conform
Non-conform
Conform
Conform
Conform
Conform
Non-conform
Non-conform
Non-conform
Non-conform
Non-conform
Conform
Non-conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
Conform •
Conform
Conform
Conform
Conform
Conform
Non-conform
Non-conform
Non-conform
Conform
Print Date:
Project Number:
Project Name:
Location:
Table 2
March 12, 2007 REPORT OF COMPACTION TEST DATA
108078
Carlsbad Municipal Golf Course
Palomar Airport Road and Palomar Oaks Way
Carlsbad, Califomia
Test # Test Location Moisture
443
444
445
446
447
525
526
527
528
529
530
531
532
533
534
535
12/15/2005
12/15/2005
12/15/2005
12/15/2005
12/15/2005
1/5/2006
1/5/2006
1/5/2006
1/5/2006
1/5/2006
1/5/2006
1/5/2006
1/6/2006
1/6/2006
1/6/2006
1/6/2006
Retest of #440
Retest of #441
Commercial Pad Plate 2
Commercial Pad Plate 2
Commercial Pad Plate 2
Plate 2 Fainway 5 Repair Slope
Retest of #525
Plate 2 Fairway 5 Repair Slope
Plate 2 Fairway 5 Repair Slope
Retest of #528
Plate 2 Fairway 5 Repair Slope
Plate 2 Fairway 5 Repair Slope
Plate 2 Fainvay 5 Repair Slope
Plate 2 Fainvay 5 Repair Slope
Plate 2 Fain/vay 5 Repair Slope
Plate 2 Fairway 5 Repair Slope
I Elev.
(ft) I Field I Optimum
258.0 12.4% 11.0%
261.0 11.8% 11.0%
262.0 12.6% 13.5%
264.0 14.2%' 13.5%
263.0 14.6% 13.5%
276.0 12.2% 13.0%
276.0 12.0% 13.0%
277.0 13.2% 13.0%
279.0 13.4% 13.0%
279.0 12.6% 13.0%
280.0 12.8% 13.0%
282.0 13.3% 13.0%
284.0 12.6% 13.0%
284.0 12.1% 13.0%
285.0 13.0% 13.0%
285.0 12.6% 13.0%
Field I Maximum
113.7 123.5
111.6 123.5
109.0 119.0
109.8 119,0
109.8 119.0
111.0 119.0
113.6 119,0
114.6 119.0
109.5 119,0
113.5 119,0
115.7 119.0
114.6 119.0
114.7 119,0
113.2 119.0
114.6 119.0
114.5 119.0
1 Areas reworked and non-confonning density tests are waived
2 Density tests approved by Randy Wagner of Leighton and Associates
3 Relative compaction requirement reduced from 95% to 90% by Leighton and Associates
Obtained |
92%
90%
92%
92%
92%
93%
95%
96%
92%
95%
97%
96%
96%
95%
96%
96%
Required
90%
90%
90%
90%
90%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
Conform
Non-Conform
Conform
Conform
Conform
Conform
Conform
Non-conform
Conform
Conform
Non comform
Conform
Conform
Conform
Conform
Conform
Conform
Conform
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Leighton and Associates, Inc.
GENERAL EARTHWORK AND GRADING SPEaPICATIGNS
Page 1 of 6
LEIGHTON AND ASSOCIATES, INC.
GENERAL EARTHWORK AND GRADING SPECIFICATIONS FOR ROUGH GRADING
1.0 General
1.1 Intent: These General Earthwork and Grading Specifications are for the grading and
earthwork shown on the approved grading plan(s) and/or indicated in the geotecimical
report(s). These Specifications are a part of the recommendations contained in the
geotechnical report(s). In case of conflict, the specific recommendations in the
geotechnical report shall supersede these more general Specifications. Observations of the
earthwork by the project Geotechnical Consultant during the course of grading may result
in new or revised recommendations that could supersede these specifications or the
recommendations in the geotechnical report(s).
1-2 The Geotechnical Consultant of Record: Prior to commencement of work, the owner shall
employ the Geotechnical Consultant of Record (Geotechnical Consultant). The
Geotechnical Consultants shall be responsible for reviewing the approved geotechnical
report(s) and accepting the adequacy of the preliminary geotechnical findings, conclusions,
and recommendations prior to the commencement of the grading.
Prior to commencement of grading, the Geotechnical Consultant shall review the "work
plan" prepared by the Earthwork Contractor (Contractor) and schedule sufficient personnel
to perform the appropriate level of observation, mapping, and compaction testing.
During the grading and earthwork operations, the Geotechnical Consultant shall observe,
map, and document the subsurface exposures to verily the geotechnical design
assumptions. If the observed conditions are found to be significantly different than the
interpreted assumptions during the design phase, the Geotechnical Consultant shall inform
the owner, recommend appropriate chan ges in design to accommodate the observed
conditions, and notify the review agency where required. Subsurface areas to be
geotechnically observed, mapped, elevations recorded, and/or tested include natural ground
after it has been cleared for receiving fill but before fill is placed, bottoms of all "remedial
removal" areas, all key bottoms, and benches made on sloping ground to receive fill.
The Geotechnical Consultant shall observe the moisture-conditioning and processing of the
subgrade and fill materials and perform relative compaction testing of fill to determine the
attained level of compaction. The Geotechnical Consultant shall provide the test results to
the owner and the Contractor on a routine and frequent basis.
3030.1094
I Leighton and Associates, Inc.
GENERAL EARTHWORK AND GRADING SPECIFIG\TIONS
Page 2 of 6
1-3 The Earthwork Contractor: The Earthwork Contractor (Contractor) shall be qualified,
experienced, and knowledgeable in earthwork logistics, preparation and processing of
ground to receive fill, moisttire-conditioning and processing of fill, and compacting fill.
The Contractor shall review and accept the plans, geotechnical report(s), and these
Specifications prior to commencement of grading. The Contractor shall be solely
responsible for performing the grading in accordance with the plans and specifications.
The Contractor shall prepare and submit to the owner and the Geotechnical Consultant a
work plan that indicates the sequence of earthwork grading, the number of "spreads" of
work and the estimated quantities of daily earthwork contemplated for the site prior to
commencement of grading. The Contractor shall inform the owner and the Geotechnical
Consultant of changes in work schedules and updates to the work plan at least 24 hours in
advance of such changes so that appropriate observations and tests can be planned and
accomplished. The Contractor shall not assume that the Geotechnical Consultant is aware
of all grading operations.
The Contractor shall have the sole responsibility to provide adequate equipment and
methods to accomplish the earthwork in accordance with the applicable grading codes and
agency ordinances, these Specifications, and the recommendations in the approved
geotechnical report(s) and grading plan(s). If, in the opinion of the Geotechnical
Consultant, unsatisfactory condifions, such as unsuitable soil, improper moisttire condition,
inadequate compaction, insufficient buttress key size, adverse weather, etc., are resulting in
a quality of work less than required in these specifications, the Geotechnical Consultant
shall reject the work and may recommend to the owner that construction be stopped until
the conditions are rectified.
2.0 Preparation of Areas to be Filled
21 Clearing and Grubbing: Vegetation, such as brush, grass, roots, and other deleterious
material shall be sufficiently removed and properly disposed of in a method acceptable to
the owner, governing agencies, and the Geotechnical Consultant.
The Geotechnical Consultant shall evaluate the extent of these removals depending on
specific site conditions. Earth fill material shall not contain more than 1 percent of organic
materials (by volume). No fill lift shall contain more than 5 percent of organic matter.
Nesting of the organic materials shall not be allowed.
If potentially hazardous materials are encountered, the Contractor shall stop work in the
affected area, and a hazardous material specialist shall be informed immediately for proper
evaluation and handling of these materials prior to continuing to work in that area.
As presently defined by the State of Califomia, most refined petroleum products (gasoline,
diesel fiiel, motor oil, grease, coolant, etc.) have chemical constittients that are considered
to be hazardous waste. As such, the indiscriminate dumping or spillage of these fluids
onto the ground may constittite a misdemeanor, punishable by fines and/or imprisonment,
and shall not be allowed.
I
I
3030.1094
I
I
Leighton and Associates, Inc.
GENERAL EARTHWORK AND GRADING SPEaPICATIONS
Page 3 of 6
2.2 Processing: Existing ground that has been declared satisfactory for support of fill by the
Geotechnical Consultant shall be scarified to a minimum depth of 6 inches. Existing
ground that is not satisfactory shall be overexcavated as specified in the following section.
Scarification shall continue until soils are broken down and free of large clay lumps or
clods and the working surface is reasonably uniform, flat, and free of uneven features that
would inhibit uniform compaction.
2-3 Overexcavation: In addition to removals and overexcavations recommended in the
approved geotechnical report(s) and the grading plan, soft, loose, dry, saturated, spongy,
organic-rich, highly fractured or otherwise unsuitable ground shall be overexcavated to
competent ground as evaluated by the Geotechnical Consultant during grading.
2.4 Benching: Where fills are to be placed on ground with slopes steeper than 5:1 (horizontal
to vertical units), the ground shall be stepped or benched. Please see the Standard Details
for a graphic illustrafion. The lowest bench or key shall be a minimum of 15 feet wide and
at least 2 feet deep, into competent material as evaluated by the Geotechnical Consultant.
Other benches shall be excavated a minimum height of 4 feet into competent material or as
otherwise recommended by the Geotechnical Consultant. Fill placed on ground sloping
flatter than 5:1 shall also be benched or otherwise overexcavated to provide a flat subgrade
for the fill.
2-5 Evaluation/Acceptance of Fill Areas: All areas to receive fill, including removal and
processed areas, key bottoms, and benches, shall be observed, mapped, elevations recorded,
and/or tested prior to being accepted by the Geotechnical Consultant as suitable to receive
fill. The Contractor shall obtain a written acceptance from the Geotechnical Consultant
prior to fill placement. A licensed surveyor shall provide the survey control for
determining elevations of processed areas, keys, and benches.
3.0 Fill Material
3.1 General: Material to be used as fill shall be essentially free of organic matter and other
deleterious substances evaluated and accepted by the Geotechnical Consultant prior to
placement. Soils of poor quality, such as those with unacceptable gradation, high
expansion potential, or low strength shall be placed in areas acceptable to the Geotechnical
Consultant or mixed with other soils to achieve satisfactory fill material.
3.2 Oversize: Oversize material defined as rock, or other irreducible material with a maximum
dimension greater than 8 inches, shall not be buried or placed in fill unless location,
materials, and placement methods are specifically accepted by the Geotechnical Consultant!
Placement operations shall be such that nesting of oversized material does not occur and
such that oversize material is completely surrounded by compacted or densified fill.
Oversize material shall not be placed within 10 vertical feet of finish grade or within 2 feet
of future utilities or underground construction.
3030,1094
I
I
I
I
I
I
I
I
I
I
I
I
Leigiiton and Associates, Inc.
GENERAL EARTHWORK AND GRADING SPEaRCATlONS
Page 4 of 6
3.3 Import: If importing of fill material is required for grading, proposed import material shall
meet the requirements of Section 3.1. The potential import source shall be given to the
Geotechnical Consultant at least 48 hours (2 working days) before importing begins so that
its suitability can be determined and appropriate tests performed.
4.0 Fill Placement and Compaction
4.1 Fill Layers: Approved fill material shall be placed in areas prepared to receive fill (per
Section 3.0) in near-horizontal layers not exceeding 8 inches in loose thickness. The
Geotechnical Consultant may accept thicker layers if testing indicates the grading
procedures can adequately compact the thicker layers. Each layer shall be spread evenly
and mixed thoroughly to attain relative uniformity of material and moisture throughout.
4-2 Fill Moisture Conditioning: Fill soils shall be watered, dried back, blended, and/or mixed,
as necessary to attain a relatively uniform moisture content at or slightly over optimum.
Maximum density and optimum soil moisture content tests shall be performed in
accordance with the American Society of Testing and Materials (ASTM Test Method
D1557-07).
4-3 Compacfion of Fiji: After each layer has been moisture-conditioned, mixed, and evenly
spread, it shall be uniformly compacted to not less than 90 percent of maximum dry density
(ASTM Test Method Dl557-07). Compaction equipment shall be adequately sized and be
either specifically designed for soil compaction or of proven reliability to efficiently
achieve the specified level of compaction with uniformity.
4-4 Compaction of Fill Slopes: In addition to normal compaction procedures specified above,
compaction of slopes shall be accomplished by backrolling of slopes with sheepsfoot
rollers at increments of 3 to 4 feet in fill elevation, or by other methods producing
satisfactory results acceptable to the Geotechnical Consultant. Upon completion of
grading, relative compaction of the fill, out to the slope face, shall be at least 90 percent of
maximum density per ASTM Test Method D1557-07.
4-5 Compaction Testing: Field tests for moisttire content and relative compaction of the fill
soils shall be performed by the Geotechnical Consultant. Location and frequency of tests
shall be at the Consultant's discretion based on field conditions encountered. Compaction
test locations will not necessarily be selected on a random basis. Test locations shall be
selected to verify adequacy of compaction levels in areas that are judged to be prone to
inadequate compaction (such as close to slope faces and at the fill/bedrock benches).
4-6 Frequency of Compaction Testing: Tests shall be taken at intervals not exceeding 2 feet in
vertical rise and/or 1,000 cubic yards of compacted fill soils embankment. In addition, as a
guideline, at least one test shall be taken on slope faces for each 5,000 square feet of slope
face and/or each 10 feet of vertical height of slope. The Contractor shall assure that fill
construction is such that the testing schedule can be accomplished by the Geotechnical
Consultant. The Contractor shall stop or slow down the earthwork construction if these
minimum standards are not met.
3030.1094
I
I
Leighton and Associates, Inc.
GENERAL EARTHWORK AND GRADING SPECIFICATIONS
Page 5 of 6.
4-7 Compaction Test Locations: The Geotechnical Consultant shall document the approximate
elevation and horizontal coordinates of each test location. The Contractor shall coordinate
with the project surveyor to assure that sufficient grade stakes are established so that the
Geotechnical Consultant can determine the test locations with sufficient accuracy. At a
minimum, two grade stakes within a horizontal distance of 100 feet and vertically less than
5 feet apart from potential test locations shall be provided.
5.0 Subdrain Installafion
Subdrain systems shall be installed in accordance with the approved geotechnical report(s), the
grading plan, and the Standard Details. The Geotechnical Consultant may recommend additional
subdrains and/or changes in subdrain extent, location, grade, or material depending on conditions
encountered during grading. All subdrains shall be surveyed by a land surveyor/civil engineer for
line and grade after installation and prior to burial. Sufficient fime should be allowed by the
Contractor for these surveys.
6.0 Excavation
Excavations, as well as over-excavation for remedial purposes, shall be evaluated by the
Geotechnical Consultant during grading. Remedial removal depths shown on geotechnical plans
are estimates only. The actual extent of removal shall be determined by the Geotechnical
Consultant based on the field evaluation of exposed conditions during grading. Where fill-over-cut
slopes are to be graded, the cut portion of the slope shall be made, evaluated, and accepted by the
Geotechnical Consultant prior to placement of materials for construction of the fill portion of the
slope, unless otherwise recommended by the Geotechnical Consultant.
3030.1094
I
I
Leighton and /Associates, Inc.
GENERAL EARTHWORK AND GRADING SPECIFICATIONS
Page 6 of 6
7.0 Trench Backfills
7.1 The Contractor shall follow all OHSA and Cal/OSFTV requirements for safety of trench
excavations.
7.2 All bedding and backfill of utility trenches shall be done in accordance with the applicable
provisions of Standard Specifications of Public Works Construction. Bedding material
shall have a Sand Equivalent greater than 30 (SE>30). The bedding shall be placed to 1
foot over the top of the conduit and densified by jetting. Backfill shall be placed and
densified to a minimum of 90 percent of maximum from 1 foot above the top of the conduit
to the surface.
7.3 The jetting of the bedding around the conduits shall be observed by the Geotechnical
Consultant.
7.4 The Geotechnical Consultant shall test the trench backfill for relafive compaction. At least
one test should be made for every 300 feet of trench and 2 feet of fill.
7:5 Lift thickness of trench backfill shall not exceed those allowed in the Standard
Specifications of Public Works Construction unless the Contractor can demonstrate to the
Geotechnical Consultant that the fill lift can be compacted to the minimum relative
compaction by his alternative equipment and method.
3030.1094
FILL SLOPE
PROJECTED PLANE
1 TO 1 MAXIMUM FROM
TOE OF SLOPE TO
APPROVED GROUND
EXISTING
GROUND SURFACE
BENCH HEIGHT
(4' TYPICAL)
REMOVE
UNSUITABLE
MATERIAL
2 MIN.—I
KEY
DEPTH
LOWEST
BENCH
(KEY)
FILL-OVER-CUT SLOPE
EXISTING
GROUND SURFACE
OMPACTED:
T
l-BENCH HEIGHT
(4' TYPICAL)
REMOVE
UNSUITABLE
MATERIAL
CUT-OVER-FILL SLOPE
-CUT FACE
SHALL BE CONSTRUCTED PRIOR
TO FILL PLACEMENT TO ASSURE
ADEQUATE GEOLOGIC CONDITIONS
EXISTING
GROUND
SURFACE
PROJECTED PLANE
1 TO 1 MAXIMUM
FROM TOE OF SLOPE
TO APPROVED GROUND
2' MIN.-
KEY
DEPTH
CUT FACE SHALL BE
CONSTRUCTED PRIOR
TO FILL PLACEMENT
OVERBUILD AND
TRIM BACK
REMOVE
UNSUITABLE
MATERIAL
BENCH HEIGHT
(4' TYPICAL)
FOR SUBDRAINS SEE
STANDARD DETAIL C
LOWEST
BENCH
(KEY)
BENCHING SHALL BE DONE WHEN SLOPE'S
ANGLE IS EQUAL TO OR GREATER THAN 5-1
MINIMUM BENCH HEIGHT SHALL BE 4 FEET
AND MINIMUM FILL WIDTH SHALL BE 9 FEET
KEYING AND BENCHING GENERAL EARTHWORK AND
GRADING SPECIFICATIONS
STANDARD DETAILS A
FINISH GRADE
SLOPE FACE
* OVERSIZE ROCK IS LARGER THAN
8 INCHES IN LARGEST DIMENSION.
* EXCAVATE A TRENCH IN THE COMPACTED
FILL DEEP ENOUGH TO BURY ALL THE
ROCK.
* BACKFILL WITH GRANULAR SOIL JETTED
OR FLOODED IN PLACE TO FILL ALL THE
VOIDS.
GRANULAR MATERIAL TO BE'
DENSIFIED IN PLACE BY
FLOODING OR JETTING.
DETAIL
• DO NOT BURY ROCK WITHIN 10 FEET OF
FINISH GRADE.
• WINDROW OF BURIED ROCK SHALL BE
PARALLEL TO THE FINISHED SLOPE.
-JETTED OR FLOODED
GRANULAR MATERIAL
TYPICAL PROFILE ALONG WINDROW
OVERSIZE
ROCK DISPOSAL
GENERAL EARTHWORK AND
GRADING SPECIFICATIONS
STANDARD DETAILS B
I
BENCHING
REMOVE
UNSUITABLE
MATERIAL
SUBDRAIN
TRENCH
SEE DETAIL BELOW
CALTRANS CLASS 2 PERMEABLE
OR #2 ROCK (9FT''3/FT) WRAPPED
IN FILTER FABRIC
FILTER FABRIC
(MIRAFI 140N OR APPROVED
EQUIVALENT)'
•^nji^^^-ij^ll 4" MIN. BEDDING
COLLECTOR PIPE SHALL
BE MINIMUM 6" DIAMETER
SCHEDULE 40 PVC PERFORATED
PIPE. SEE STANDARD DETAIL D
FOR PIPE SPECIFICATIONS
SUBDRAIN OFTAii
DESIGN FINISH
GRADE
NONPERFORATED 6"0 MIN
PERFORATED
6" 0MIN. PIPE
FILTER FABRIC
(MIRAFI MON OR APPROVED
EQUIVALENT)
CALTRANS CLASS 2 PERMEABLE
OR #2 ROCK (9FT"3/FT) WRAPPED
IN FILTER FABRIC
DETAIL OF CANYON SUBDRAIN OUT! FT
CANYON SUBDRAINS GENERAL EARTHWORK AND
GRADING SPECIFICATIONS
STANDARD DETAILS C
15' MIN.
OUTLET PIPES
4" 0 NONPERFORATED PIPE
'100' MAX. O.C. HORIZONTALLY,
30' MAX O.C. VERTICALLY
BACK CUT
1:1 OR FLATTER
-±1'\ -1
COMPACTED'RLbX-:
SEE SUBDRAIN TRENCH
DETAIL
LOWEST SUBDRAIN SHOULD
BE SITUATED AS LOW AS
POSSIBLE TO ALLOW
SUITABLE OUTLET
-KEY DEP
(2' MIN.)
:-2% MIN. •:-:vCj
KEY WIDTH
AS NOTED ON GRADING PLANS
TH (15' MIN.) 12" MIN. OVERLAP-
FROM THE TOP HOG
RING TIED EVERY
6 FEET
CALTRANS CLASS
PERMEABLE OR #2
ROCK (3 FT"3/FT)
WRAPPED IN FILTER
FABRIC
r-4" 0
\ NON-PERFORATED
\ OUTLET PIPE
PROVIDE POSITIVE
SEAL AT THE
JOINT
T-CONNECTION
FOR COLLECTOR
PIPE TO OUTLET PIPE
6" MIN,
COVER
4" 0
PERFORATED
PIPE
FILTER FABRIC
ENVELOPE (MIRAFI
140 OR APPROVED
EQUIVALENT)
4" MIN.
BEDDING
SUBDRAIN TRENCH DETAII
SUBDRAIN INSTALLATION - subdrain collector pipe sholl be installed with perforation down or
unless otherwise designated by the geotechnical consultant. Outlet pipes shall be non-perforated
sSl be f/4" ttT/2''" f T^.'r °' ' perforations uniformly's'paced per fooL ZZuo.
least 2% YolarS \il outlet'" °" "^^'^ ° ^^^^^^
"Sn^O^f SDR ^fftK^'r, '"In o^, ''•^™ 23.5 or ASTM D1527. Schedule 40, or AbIM D3034, SDR 23.5. Schedule 40 Polyvinyl Chloride Plastic (PVC) pipe.
All outlet pipe shall be placed in o trench no wide than twice the subdrain pipe. Pipe shall be in
sol backfill ' °' '""^ 5 f^^* «'ich shaS be nafive
BUTTRESS OR
REPLACEMENT FILL
SUBDRAINS
GENERAL EARTHWORK AND
GRADING SPECIFICATIONS
STANDARD DETAILS D
I
I
SOIL BACKFILL. COMPACTED TO
90 PERCENT RELATIVE COMPACTION
BASED ON ASTM 01557
RETAINING WALL
WALL WATERPROOFING
PER ARCHITECT'S
SPECIFICATIONS
WALL FOOTING
FILTER FABRIC ENVELOPE
(MIRAFI HON OR APPROVED
EQUIVALENT)*'
3/4" TO 1-1/2" CLEAN GRAVEL
4" (MIN.) DIAMETER PERFORATED
PVC PIPE (SCHEDULE 40 OR
EQUIVALENT) WITH PERFORATIONS
ORIENTED DOWN AS DEPICTED
MINIMUM 1 PERCENT GRADIENT
TO SUITABLE OUTLET
3" MIN.
COMPETENT BEDROCK OR MATERIAL
AS EVALUATED BY THE GEOTECHNICAL
CONSULTANT
NOTE: UPON REVIEW BY THE GEOTECHNICAL CONSULTANT
COMPOSITE DRAINAGE PRODUCTS SUCH AS MIRADRAIN OR '
J-DRAIN MAY BE USED AS AN ALTERNATIVE TO GRAVEL OR
CLASS 2 PERMEABLE MATERIAL. INSTALLATION SHOULD BE
PERFORMED IN ACCORDANCE WITH MANUFACTURER'S
SPECIFICATIONS.
RETAINING WALL
DRAINAGE DETAIL
I
GENERAL EARTHWORK AND
GRADING SPECIFICATIONS
STANDARD DETAILS E