HomeMy WebLinkAbout; May Dept Store Co; Soils Report; 1969-05-26- RECEIVED
- MAY 27 1969
- CITY OF CARLSBAD Building Department
-
-
-
-
-
-
-
-
-
-
-
-
-
-
INSPECTION OF FOUNDATION EXCAVATIONS, AND
INSPECTION AND TESTING OF COMPACTED BACKFILL
PROPOSED DEPARTMENT STORE AND MAINTENANCE BUILDING
PLAZA CAMINO REAL SHOPPING CENTER
CARLSBAD, CALIFORNIA
FOR THE
MAY DEPARTMENT STORES COMPANY
(OUR JOB NO. B-68004-C)
- CcJNSULTlNG FOUNDATlON ENGINEERS m 711 NORTH AL”AR.4W STREET 0 LOS ANGELES, C*LIFORNIA 90026 17 TELEPHONE 386.3920 -~
LEROY CRANDALL - AND ASSOCIATES - May 26, 1969 -
-
-
Plaza Camino Real
The May Department Stores Company
801 South Broadway
Los Angeles, California 90014
Gentlemen:
(Our Job No. B-68004-C)
-
-
-
_-~
-
-
-
-
-
Inspection of Foundation Excavations, and
Inspection and Testing of Compacted Backfill
Proposed Department Store and Maintenance Building
Plaza Camino Real Shopping Center
Carlsbad, California
for the May Department Stores Company
SCOPE
This report confirms our inspection and approval of the excava-
tions fqr spread footings installed to support the proposed Department
Store and Maintenance Building at the subject site; included are the re-
sults of our inspection and testing of the compacted soils placed as back-
fill for the project. The locations of the proposed structures'are shown,
with relation to the project coordinates, on the attached Plot Plan. The
inspection work was performed during the period of March through December,
1968. We previously performed a foundation investigation of the site, and
submitted our recommendations in a report dated August 12, 1966 (our Job
No. A-66035); supplementary reports have been issued from time to time as
additional recommendations have been required. We also performed inspection
L. kRcJY CRANDALL. c. E. RUSSELL c. WEBER. c. E. SEYMOUR s. CH,“. c, Ed FREDRlCK A. BARNES J. Do KIRKGARD. c. E, Pi A. MALJIAN. c. E. LEOPOLD HIRSCHFELDT JAMES M. MCWEE. c. E,
ROBERT CHIERUZZI, c. Ed JAMES L. “AN BEYEREN, 7. F.
Plaza Camino Real
Page 2
May 26, 1969
(Our Job No. B-68004-C)
and testing of the compacted fill placed at the site and presented the
results in a report dated January 12, 1967 (our Job No. B-66165); the
results of our inspection of the grading for Phase II of the project were
presented in a report dated April 29, 1968 (our Job No. B-68004).
INSPECTION OF FOUNDATION EXCAVATIONS _
-
-
-
-
-
-
-
In our foundation investigation report we stated that if the re-
quired fill materials at the site were properly compacted, the proposed
Department Store and Maintenance Building could be supported on conventional
spread footings established in the properly compacted fill.
Accordingly, upon completion of the general site grading, excava-
tions for footings to support the proposed structures were constructed. Our
field representatives checked all excavations to verify that the soils were
properly compacted fill soils capable of supporting at least the design
pressure. All excavations were cleaned of any loose materials prior to
final approval. Based on the results of our inspection, the soil conditions
for the footing excavations were satisfactory. The properly compacted soils
are capable of providing adequate foundation support for the proposed Depart-
ment Store and Maintenance Building.
INSPECTION AND TESTING OF COMPACTED BACKFILL
-
After completion of the foundations and building walls below grade,
- compacted soils were placed as backfill around and over foundations, in utility
-
-
-
-
-
-
.-
-
-
-
Plaza Camino Real
Page 3
May 26, 1969
(Our Job No. B-68004-C)
trenches, against perimeter walls below grade, and around various
appurtenant interior installations. The specifications required that
all backfill materials be placed in loose lifts not exceeding eight
inches in thickness, brought to optimum moisture content, and compacted
to at least 90% of the maximum dry density obtainable by the ASTM
Designation D1557-66T method of compaction, modified to use three layers
instead of five.
During the required filling, mainly the on-site soils, consisting
primarily of silty sand and sand with gravel, were used; crushed rock was
also utilized in some backfill areas. Compaction tests were performed on
the soils used for backfilling, to establish the maximum dry densities.
The tests were performed in accordance with the specified method of compac-
tion which utilizes a l/30-cubic-foot mold in which each of three layers of
soil is.compacted by 25 blows of a ten-pound hammer falling 18 inches. The
results of the compaction tests were utilized in establishing the degree of
compaction achieved during the placing of the backfill.
After the areas to receive backfill were first cleared of any
construction debris and loose soils, the required backfill materials were
placed in loose lifts not exceeding eight inches in thickness, brought to
approximately optimum moisture content, and oompacted. To establish the
degree of compaction achieved, field density tests were taken as the back-
filling progressed. Where a test indicated less than 90% compaction, the
sotls were reworked to the satisfaction of our field representative and
-
-
-
-
-
-
-
-
-
-
-
.-~
Plaza Camino Real May 26, 1969
Page 4 (Our JOB No. ~-68004-C)
approved without further testing. In addition to testing the general
backfilling, our field representative tested the compacted subgrade of
the proposed structures. Wet areas were encountered in the subgrade of
the Department Store; the areas were subsequently overexcavated and re-
placed with crushed rock. The results of all field density tests are
presented in the attached Table of Test Results; the locations of the
tests for the Department Store are shown on the Plot Plan. Tests Nos.
88, 89, and PO, which were taken in the Maintenance Building in the south-
western portion of the site, are not shown on the Plot Plan. Based on
our observations of the methods employed and the test results, the back-
fill soils were placed in accordance with the specifications and to our
satisfaction.
Yours very truly,
LeROY CRANDALL AND ASSOCIATES
Russell C. Weber
RW-Rq/lg
Attachments (22)
(6 copies submitted)
CC: c2) Shuirman, Rogoway & Associates
c22) Carlsbad Dept. of Bldg. & Safety
-
-
-
-
-
-
.-.
?!
Y
>
: -
I-
P
:-
I
-
,
TEST ELEVATION
& (FEET)
MOISTURE DRY MAXIMUM
CONTENT DENSITY DENSITY
(% OF DRS WT.) (LBS./CU.FT.) (LBS./CU.FT.)
PERCENT
COX?ACTION
1 2
2
5
6
7
8
9
10
27
27
27
27
27
27
27
27
27
25%
14.2
6.5
7.0
6.8
6.8
7.6
5.6
5.4
12.7
13.6
111 120 93
113 118 96
111 118 94
113 118 96
109 118 92 111 118 94
113 118 96
112 118 35
114 124 92
115 124 93
11. 26 15.6 112, 124 90 12 24 13.0 112 120 93
13 26 11.2 111 120 93
14 27 8.6 109 120 91
15 27 6.5 113 118 96
16 27 7.6 114 124 92
17 27 8.2 114 124 92
18 27 9.1 112 124 90
19 27 9.8 112 120 93
20 27 6.5 108 118 92
21 27 10.1 118 124 95
22 27 9.5 118 124 95 23 27 11.6 115 124 93
24 26% 7.6 108 120 90
25 26 7.1 120 124 97 26 26 7.0 117 124 94 27 27 6.5 115 124 93
28 27 9.8 112 124 90
.29 27 6.2 111 120 93
30 27 6.5 113 118 96
31 27 7.6 112 118 95 32 27 6.5 116 118 98
33 27 8.0 110 120 92
34 27 7.2 111 120 93 35 23 5.4 106 118 90 36 24 7.6 107 118 91
37 25% 5.6 110 118 93 38 27 5.4 109 118 92 39 23 5.4 110 120 92
40 25 6.2 112 120 93
41 26 5.8 110 120 92
42 25 6.5 111 120 93 43 24 7.6 114 124 92
TABLE ----- OF TEST RESULTS -- -_-- -------
-
-
-
-
-
-
Page 2
TEST
NO.
ELEVATION
(FEET)
MOISTURE DRY
CONTENT DENSITY
MAXIMUM
DENSITY PERCENT
(% OF DRY h!.) (LBS./CU.FT.) (LBS./CU.FT.) COMl'kTION
44 26 a.0 111 124 90
45 23% 7.9 111 124 90
46 25 7.6 112 124 90
47 26% 8.1 111 124 90
48 25 5.4 109 118 92,
49 27 7.6 115 124 93
50 25 6.5 110 120 92
51 26% 6.0 113 120 94
52 27 6.8 114 120 95
53 29% 8.7 119 124 96
54 28 9.0 101 I,18 86"
55 30 8.6 107 118 91
56 31 11.2 112 124 90
57 32 10.6 115 124 93
58 32 11.7 114 124 92
59 30 12.1 114 124 92
60 32 10.4 111 124 90
61 30 9.2 99 118 84*
62 32 10.6 109 118 92
63 34 7.6 114 124 92
64 33% 8.3 114 124 92
65 32 11.7 118 124 95
66, 32% 10.0 123 124 99
67 35 10.6 118 124 95 68 34 12.1 114 124 92
69 34 10.9 119 124 96
70 36 9.8 116 124 94
71 34 6.9 106 118 90
72 35 11.0 109 118 92 73 35 8.9 104 118 88"
74 36 9.0 108 118 92
75 37 7.6 110 118 93
76 365 1.6 107 118 91 77 36 8.0 107 118 91
78 37% 9.2 109 118 92
79 39 8.8 108 118 92 80 38 9.8 114 124 92
81 40 6.5 110 118 93 82 41 7.6 110 118 93 83 40 7.2 106 118 98
84 40% 9.8 119 124 96 85 40 7.6 110 118 93 86 42 8.7 114 124 92 87 43 8.3 115 124 93 '
-
-
_-
-
-
-
-
-
-
Page 3
MOISTURE DRY HAXINUM
TEST ELEVATION CONTENT DENSITY DENSITY PERCENT
& (FEET) (% OF DRY tn.) (LBS./CU.FT.) (LBS./CU.PT) COWACTION
88 43 11.0 112 124 90
89 43 10.1 112 124 90
90 42 11.4 114 124 92
NOTES: Elevations refer to job datum.
* Indicates area reworked and approved without further testing.
-.
-