HomeMy WebLinkAbout3190; RANCHO SANTA FE RD ALIGNMENT; 2009/ 2010 STORM DAMAGE ASSESSMENT AND REPAIR RECOMMENDATIONS; 2010-02-16I DUDE.K . . . . .
. MAIN OFFICE
605 THIRD STREET
I
.ENCINITAS. CALIFORNIA 92024 -
I 760.942S147 I 800.450.1818 F 760.632.0164
1 February 16, 2010 3385-07
John Cahill . . . .
City of Carlsbad
I 1635 Faraday Avenue . .
Carlsbad, California 92008-7314 .. . .
0
I Subject: Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-
Site Wetland. Mitigation Project - 2009/2010 Storm Damage Assessment
I .
and Repair RecommeAdations .
Dear Mr. Cahill: . . . . . . .
As requested by the City of Carlsbad (City), Dudek provides the following analysis of the storm
damage that has occurred to date as a result of the winter 2009/2010 storm events, at the off-site
I wetland mitigation area associated with the Rancho Santa Fe Road Realignment and Bridge
Replacement Project. . . . . .
As you know, the off-site wetland mitigation and revegetation portion of the project, being
implemented along San Marcos Creek, within the University Commons open space area, was
nearing completion of the planting phase of the installation in late November/early December
2009 when several "El Niflo" related storm events hit our area. 'In Dudek' s . opinion, the project
was approximately 95% complete at the time the second large storm in early December hit. All
that remained to be completed, at that time was for the upper canyon area (i.e., secondary
drainage area, east of the quarry) to be hydroseeded and a few areas along the upper and lower
creek margins still needed to be hand seeded.
- The first winter storms started on November 27 and 28 and continued on December 6 and 7. The
1 .
early December storm produced a large rainfall amount in .a short period of time. . In the. San
Marcos area, there was approximately 1.5 inches of rainfall in a 24-hour. period. This was a much
larger than normal rainfall event. Per discussions with U.S. Army Corps of Engineers Staff they
I believe that the December 6 and -7 storm equated to a 10- or 20-year storm event. Additional rain
events have occurred since that time, in mid to, late January and early February as well, resulting
I ,
. in continued higher than normal seasonal rainfall amounts. This has lead to additional erosion
and further damage to the mitigationlrevegetation areas. In addition, the week long storm event
between January 17 and 23 resulted ,in over 5.5 inches of rainfall in the San Marcos area. (Note:
I it should be pointed out. that after the first November storm event, 'Dudek made
recommendations to the City to conduct remedial repair work to correct the erosion problems
WWW.DUDEK.COM
1
Mr. John Cahill
I Subject Rancho Santa Fe Road Realignment and Bridge Replacement Project Off-Site
Wetland Mitigation Project - 2009/2010 Storm Damage Assessment and Repair
I Recommendations
I that resulted from that first storm. See Dudek Site Observation Report #8, dated November30,
2009. Dudek also; provided a more comprehensive damage repair assessment and,
recommendations, per the city's request, in our letter dated, December 29, 2009.)
In Dudek's opinion the project was in substantial compliance with the intended installation
program prior to the onset of the early December rain event, as all of the container plants had
been installed in the lower canyon area, and only minor hand seeding of these areas was still
outstanding. The substantial flood event that occurred on December 6 and 7, which lead to the I .Lake San Marcos dam overtopping, resulted in a significant amount of flood flow passing
through the San. MarcOs Creek canyon and through the mitigation area. As the creek flowed
through the recently graded and planted mitigation area east of the check dam, the flow diverted
I completely from the main creek and flowed almost entirely through the mitigation area, causing
significant head cutting, scouring, and resultant deposition of sediment behind the check dam. ' The check dam also overtopped at that time, which lead to significant flood flow moving through
the lower mitigation area west of the check dam, eroding soil in. that area, washing out plants and
causing deposition of sediment in the lower westerly portion of the site In addition, much of the
flow in the existing creek channel also diverted through the recently graded area below the check
dam. Since that time, continued flow over the top of the check dam has also lead to undercutting
I of the toe of the rip/rap at the downstream side of the check dam. (Note: This undercutting could
potentially compromise the integrity of the check dam. This situation should be evaluated further
by the City, the contractor, and 0-Day Consultants (i.e., project engineer) to determine if any
1 corrective action is needed.) In addition, significant head cutting and erosion has also occurred in
the lower mitigation area below the check dam and sediment deposition has resulted at the west
1
.. end of this: lower area. Approximately 800/o_90% of the container plants installed in the two
lower canyon mitigation areas have either been washed away, or have been buried by sediment.
The majority of the plantings on .the adjacent slope area have survived, with only .minor damage
1 incurred along the toe of this slope. . .
Figure 1 shows the physical layout of the mitigation areas and the locations where the storm
I damage has occurred Figures 2-5 show the mitigation areas prior to and after the major storm
events
I It should be pointed out that 'the physical area (i.e., acreage) originally intended for the wetland
mitigation areas still exists The creek flow through these areas has demonstrated that there is
I adequate hydrology to support the intended wetland plantings in these areas; however, the
problem is that the intended wetland plant 'materials have not had adequate time to become
rooted into the soil and become adequately established to withstand the flood flows As a result
3385-07 DUDEK. 2 . ' . February 2010 I .
H
I. H.
Mr. John Cahill . . .
I
Subject: Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site
Wetland Mitigation Project -' 2009/2010 . Storm Damage Assessment and Repair
Recommendations
I . of the damage, much of the plant material has been lost and there is currently little to no plant
'material remaining in these areas to help stabilize the soil surfaces against erosion
Approximately 800/6-90% of the plant'inateniat in these areas have been lost or have been buried
by sediment Only 100/6_20% of the total installed plant material in this lower canyon area have
survived, primarily along the margins of these areas. Over time this plant material should
I establish and should help to stabilize the edges of these areas, and will also provide a future seed
source for natural native plant recruitment However, until the remaining disturbed areas fill in,
these bare areas will continue to be subject to additional erosion and further disturbance Dudek
I
expects that there will be significant natural native plant recruitment that will likely take place
within the disturbed areas during this coming spring penod, resulting from the natural seeding
I and recruitment process. Natural . seed distribution has likely taken place as part of the soil
deposition process and from the flood flow dispersion of seed throughout the areas. More. seed
dispersal will likely occur as the surrounding native plants go to seed and spread into the area.
I With sufficient soil moisture and adequate growing conditions these areas should experience
significant natural recruitment. . .
I It should be pointed out that the previous University Commons wetland mitigation areas that
were installed in this same creek area, have been in the ground since November 2005
I (approximately 4 years) and are still doing well. These areas have only incurred minor damage
from the recent flood events, since the plant materials were already well established. These areas
are now able to withstand these types of storm events. Photographs of the University Commons
I areas are shown on Figure 6 included herein.
As a result of the redirected creek flow through the east end of the mitigation area (i.e., area east
of the check dam), the brow ditch and slope bordering the access road have become undermined
and the slope area has given way, causing the brow ditch to break-off just east of the outfall point
into the upper basm The spillway and rip/rap at the outfall location have also been undermined
and they are currently in jeopardy of failing Dudek has recommended to the City that this area
be repaired to help stabilize these areas against the continued winter, flood flow. This repair work
has been previously considered by the City in coordination with the contractor Sierra Pacific
West (SPW), but to our knowledge has not yet been authorized.
I Figure 1 included herein, shows the physical configuration of the mitigation areas and indicates
where the flood damage has occurred. Of the total 3.65 acres of intended wetland mitigation
.I acreage within the entire off-site project area (i.e., both wetland creation and. enhancement
areas), both in the lower canyon (i.e., 2.71 acres), as well as within the upper canyon (i.e., 0.94
acre), approximately 1 33 acres of the planted area has been disturbed or severely damaged by
DUDEK
I
3385-07
3 . . February 2010
El
I Mr. John Cahill
Subject: Rancho 'Santa Fe Road Realignment and Bridge Replacemelit Project, Off-Site
Wetland Mitigation Project - 2009/2010 Storm Damage Assessment, and Repair
Recommendations
the flood flows This equates to approximately 35% of the total overall mitigation area having
been impacted The damage occurred primarily in the lower canyon area, with only minor
damage incurred in the upper canyon It should be pointed out that the upper canyon area, east of
the old quarry and waterfall area, incurred only minor damage from the flooding, and the
majority of the plantings in those areas have survived and are doing well Some minor damage
occurred to the enhancement area in the main creek
The storm events that have occurred to date (between November 2009 and February 2010)
during this winter period, occurred on the following dates, with the approximate amount of
rainfall for each storm event noted (Note Data taken from the National Oceanic and
Atmospheric Administration (NOAA), National Weather Service Forecast Office, San Diego,
Ca, hydrologic data records and from Fox 5/The Weather Underground precipitation source
information):
November 27 and 28, 2009, light ram event, with approximately 0.02 inch of
precipitation in the San Marcos area
December 6 and 7, 2009, large rain event, with approximately 1.5 inches of precipitation
in the San Marcos area, over an approximate 24-hour period
December 11, 12, and 13, 2009, moderate rain event, with approximately .0 .43 inch of
precipitation in the San Marcos area.
January 17 through 23, 2010, week-long rain event, with approximately 5 7 inches of
precipitation in the San Marcos area
January 26 and 27,2010, light rain in the p.m. of January 26, with approximately 0.21
inch of precipitation in the San Marcos area
February 5 through 7,-2010, light rain in p m of February 5 and heavy all day the
February 6, with approximately 0 58 inch of precipitation in the San Marcos area
Table 1 shows the original habitats and impacts, the mitigation areas and ratios that were
required, the acreage that has been damaged due to the flooding and the approximate un-
damaged areas that remain I
I
1:
i'DUDEK 4
3385-07
February 2010
H:
Mr. John Cahill
I Subject: Rancho Santa Fe Road Realignment and Bridge Replaceiient Project, Off-Site
'Wetland Mitigation Project - 2009/2010 Storm Damage Assessment and Repair
I .
Reconimendations S .
'table 1. :
Mitigation Summary for Impacts and Damage Due to Flooding
,•.f' i- '.' 'V, 4.
Mitigation Area Planting Area
7 . . Required Mitigation Areas and Ratios . .. . -. Damaged Due to Flooding (Off site) Mitigation
.
fImpactsor On site and Off site Locations (Acres)
Crëatin Enhàncernent ration' Creation .j Resto
damaged
. Enhancement Restoratin Habitat Tye Acres)* (Acres)
- Permanent Impacts
S. (Mit,ationProvidedat Off-siteLdcation)'
Southern willow scrub 0.42: '' 1.26 - ' ' 1.19 '
' 0.07
• .. (3:1)
SWS
Disturbed wetlands ' 0.27 0.27' 0.54 ' 0.14 ' 0.67w :() (2:1)
• . FWM FWM.
Waters Of the U.S. ' 0.24 '. 0.24 ' -. - 0.00 -' 0.247*
' /
•
FWM
Subtotals 0.93 1.77 ' .0.54 ' - . 1.33 : - - 0.98
Temporary Impacts
(Mitigation Provided Partially at the Os-site, as ell as atOff-siteLôcations) '.
Southern willow scrub 0.97 ' 0.54 0.54 -'
On-site mitigation ' ' (1:1)
(at bridge) : at on-site bridge
Southern willow scrub- . ' . ' ' ' area)
Off-site mitigation
(university commons-
site) . ... ' . •• ' ' . '.
5
0.43 0.86 0.00 • 0.00 .
' 1.29
(1:1) (2:1) • - ' _____ __________ ______ ______
Subtotals 0.97 ' 0:43' . 0.86 0.54 .. -. - : 1.83
Grand Totals 1.90 . 2.20 1.40 0.54 1.33
..
J 0.00 0.00 ' 2.81
(rounded)
I Total Mitigation Required On site at Bridge Location: 0.54 acre.
Total Mitigation Required Off site at University Commons: 3.6 acres.
Total Mitigation Required Both On site and Off site: 4.14 acres:
* Permanent impacts resulting from the Rancho Santa Fe filling and grading. . •. . S
Temporary impacts, are being compensated for through on site restoration at a 1:1 ratio at the bridge location, plus additional
creation/enhancement acreage credited at a'2:1 ratio at the off site location.
Mitigation acreage for impact to disturbed wetlands and waters of the U.S. 'are being compensated for through freshwater marsh 'creation
at the off site location. ' : • S S . •
HI
'S S • 33557 DUDEK •. .
. .' 5 • • '5 5 5 February 2010' I I
A /
I 1
I
I
I
I .
I
Mr. John Cahill
Subject: Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site-
Wetland Mitigation Project 2009/2010 Storm Damage Assessment and Repair
Recommendations
OPTIONS FOR RESPONDING TO THE STORM EVENT IMPACTS
Dudek provides the following alternatives/options for addressing the storm damage impacts that
have occurred within the project area. Three options are presented below for consideration by the
City. Each option has its own ramifications related to resource agency compliance that the City
should consider before moving forward.
A Interim Repair Work and Return Areas to Previous intended Design
Configuration in Spring 2010 .
The first option/alternative the city should consider is to conduct some initial interim erosion
control and damage repairs to stabilize the hardest hit locations and then reconfigure and replant
the entire mitigation area to its original intended design configuration in late spring 2010. If this
alternative/option is elected, then Dudek recommends that the following repair work be
conducted immediately in order to help stabilize the areas and to help save what is remaining
from the Original planting effort:
Install gravel bags on the check dam to divert flows towards the main existing creek
channel and away from the graded/plantedareas. .
Create a gravel bag diversion structure on the downstream side of the check dam, in order
to divert low-flow out of the second low-flow pipe from the west, from flowing into the
graded/planted area and instead divert it back into the existing creek area.
The eroded slope below the brow ditch, near the end of the access road, needs to be
repaired and stabilized The easterly section of brow ditch that failed would not need to
be replaced The damaged portion of the concrete brow ditch should be broken-up and
either removed from the site, or used as a base below the new rip/rap to be installed in
this location Reinstallation Of that portion of the brow ditch is probably not necessary, as
it carries little runoff from the road/trail area
Secure any loose/washed-out irrigation pipe and heads, and temporarily re-stake the pipe
into higher upland positions where possible to help save the systems from further creek
damage until future repair efforts can be conducted. Irrigation operation needs to be
restored to any areas where plant material is still present, in order to keep this plant
material alive All lateral line pipe crossings of the creek channel need to be repaired and
should be placed in galvanized pipe sleeves and, securely staked in place, to better protect
them against water flow breakage
I
I
L
/
3385-07
February 2010
1
Mr John Cahill
I .Subject. Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site
Wetland Mitigation Project - 2009/2010 Storm Damage Assessment and Repair
I Recommendations ..-
I 5 The irrigation mainline crossing through the area where the creek breached through\the
site upstream of the check dam should be re-routed out of the creek channel and secured
in another location where it can be better protected against the creek flow. Dudek will
I work with the contractor to determine an appropriate location: An interim solution is to
securely stake the pipe in place until an alternative location-can be worked out.
6 The irrigation mainline feeding the revegetation areas east of the quarry, in the upper
canyon area, needs to be periodically assessed for damage and repaired where necessary
I
to assure operation of the irrigations systems in the upper area. All creek crossings of
pipe and wire should be assessed and repaired and/or secured as necessary.
I .
7 Any plant material that was partially washed out of the ground by the flooding, exposing
the rootballs should be replanted where, necessary and/or have additional soil added
: around the rootballs to help cover the roots and avoid the rotballs from drying out.
8 The upper canyon area should be hydroseeded, as was originally specified
/
9. All hand seeding of the remaining wetland areas should be postponed for now and
I implemented towards the end of the maintenance period, once the threat of additional
flooding has subsided.
I 10. The eroded/damaged soil areas will be left for now, until additional remedial grading and
repair measures can be determined for iter: implementation in spring 2010. Plant
5materials remaining in these areas shall be left and maintained/irrigated to the greatest
I degree possible to save this plant material
11 For plant material that was buried by sediment and can still be detected, the contractor
I should dig out sediment from around the plants in order, to help these plants survive and
grow up through the sediment
I 12 In late spring 2010, (i.e., after April 15) return all areas to their original grade elevations
and replant all areas per the original planting plans The total quantity of plant materials
and species to he installed would be determined by Dudek prior to that time.
B Partial Repair Work in Late Spring 2010
As second alternative/option, the City could postpone doing any initial repair work now and
could wait until after the threat of additional winter flooding has subsided, which in an "El Niflo"
year like this, would be mid April 2010. At that time remedial grading work would take place to
repair the eroded/undermined slope area through installation of additional rip/rap material to
stabilize the slope In addition, a berm would need to be re-established between the main creek
DUDEK 7
3385-07
February 2010
.1
.1
I
I
I
I
I
I
I
I
I
I
I
I
I"
I
I
I
I
Mr: John Cahill
Subject: Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site-
Wetland Mitigation Project 2009/2010 Storm' Damage Assessment and Repair
Recommendations
and the mitigation area A: portion of the deposited sediment from behind the check dam would
need to be removed and used to build the berm and to fill and repair, the worst upstream eroded
areas. The irrigation system would then need to. be repaired and additional planting would need
to be installed per recommendations provided by Dudek, based upon the resultant disturbed areas
needing additional planting
If this alternative/option is elected, then Dudek' s' recommends that the repair work be conducted
in the mid April 2010 and that the work include the following:
Repair the eroded slope area east of *the check dam and install additional rip/rap material.
Dudek recommends basically leaving the newly formed flow channels through the
revegetation mitigation areas, both upstream and downstream of the check dam, however,
they should be partially filled with additional native boulders and cobble to help raise the
elevation up closer to the intended planting elevations and to help reduce additional
erosion and head-cutting that might occur within the channels
3 Dudek recommends removing approximately half of the sediment/sandbar, area (i.e.,
closest to the check dam) that has developed behind the check dam and utilize this
material to help restore the grades of the eroded areas upstream. These' restored areas
would then be replanted and reseeded, per direction by Dudek
4. In addition, Dudek recommends that 'a mound/berm be re-established between the
existing creek and the mitigation area east of the check dam, in order to' repair the breach
where, the creek diverted completely through the mitigation area. Dudek recommends
installing a rip/rap check dam with soil fill over it, with surface erosion control fabric
protection and plantings to re-establish the grade elevations between the adjacent creek
banks and the new mitigation area Low-flow pipes would be installed through the berm
to help provide minor flow through the mitigation planting area, along the newly
established creek channel This would be designed to help restore partial flow to the main
creek channel, while still, providing low flow, through the mitigation area. This will also
allow ,for some ponding to be held behind this location, which will help support the
intended freshwater marsh habitat in that area Dudek also recommends the use of some
type of temporary portable check dam units such as "Environmental Barncade", which
would be incorporated into the top of the new mound/berm to protect the mitigation areas
from future flood breaching until the plant material growth is adequately established to
help stabilize the areas. (Note: These units would need to be left in place for several years
I'
DUDEK
I, ' '
9
Mr. John Cahill
Subject Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site
Wetland Mitigation Project - 2009/2010 Storm Damage Assessment and Repair
Recommendations
I
LI
I
I:
i:
I
I
I
1
I.
I .
I.
I ..
I.
I
I ,.
I
until growth is determined to be sufficient. They can-then be removed later by hand,
without the use of mechanized equipment.) :
5.. Dudek also recommends removing some of the sediment/sandbar area that has developed
at the far southwest end of the project below the check dam and using this material to
help restore the eroded areas in the remaining planting areas below the check dam. These
restored areas would then be replanted and reseeded, per direction by Dudek
6. Dudek recommends that the broken irrigation pipescrossing the eroded area be re-routed
to the restored planting areas to provide adequate irrigation coverage to the remaining
and restored planting areas
7 Dudek recommends that additional wetland trees and shrubs be planted along the new
flow channels in late spring 2010 (i.e., after the grading repair work is complete) The
quantities of plants would be determined at a later date, based upon survival of the
previously planted matenal, amount of natural recruitment of native wetland plants that
has been achieved and the resultant remaining open areas that need to be planted.
C Delayed Repair Work until Spring 2011
As a third alternative/option, the City would postpone conducting the remedial repair work this
year (i.e., 2010), and instead the City would wait and see how much natural- recruitment takes
place over the coming-growing season (i.e., approx. one year period). This approach would be
designed to leave the erodedldisturbed areas basically as they have been redefined by the creek
flooding and would likely not include any future grading. The redefined creek flow and grade
elevations of the disturbed areas, as well as the soil deposition areas, would be left in place as
they exist after the winter rain events of 2010. Natural: native plant recruitment would be allowed
to take place in the disturbed areas. Future plantings would be determined in winter of 2011
based upon the degree of natural recruitment that has been achieved by that time, and additional
plantings would be recommended at that time (i.e., in late spring 2011) to supplement the natural
plant recruitment. It should be pointed out that this approach runs the risk of. being out of
compliance with the resource agency permits and could lead to a delay in the long-term
maintenance and monitoring program This approach also leaves portions of the site open to
additional erosion and damage from subsequent storm events in 2010 and potentially the
following winter, if adequate natural native plant recruitment is not achieved If this approach
were taken, then the monitoring :and maintenance program could also potentially get delayed by
approximately one year, depending upon the degree of natural recruitment that takes place The
3385-07
February 2010
I S
Mr. John Cahill I Subject: Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site
Wetland Mitigation Project -. 2009/2010 Storm Damage Assessment and Repair
Recommendations
I resource agencies could also pose additional mitigation requirements onto the program since
there would likely be a resultant delay in fulfilling the original mitigation obligations
' If this alternative/option is elected, then Dudek recommends that the following items be
completed, with the following clarifications noted
In late spring 2010. (i.e., March/April), repair and secure all loose/washed-out irrigation
pipe and heads, and re-stake the pipe into higher upland positions where possible
I Irrigation operation would need to be restored to all areas where plant material is still
present, in order to keep this plant material alive during the dry periods of the year. In
addition, irrigation coverage would need to be re-established to all disturbed soil areas
I and intended mitigation areas to help promote the growth of volunteer native wetland
species that might recruit into these areas. All.irrigatiori lateral line pipe crossings of the ' creek channel would need to be repaired and would be placed in galvanized pipe sleeves
and securely staked in place, to better protect the systems against future flood flow
damage. . .
In fall/winter of 2010/2011, Dudek or the designated biological monitor at that time,
would assess the extent of the natual recruitment that has been achieved in the
I .designated mitigation areas and determine a quantity of additional container plants and
seed to be applied, to the areas in the spring of 2011. (Note: Plants would need to be
ordered a minimum of 4 months pnor to the intended delivery/installation date, to assure I that the specified plant material will be available.)
The biological monitoring period would likely need to be extended by approximately one
: year to reflect the limited progress of the areas during the 2010 time period.
4. Additional resource agency mitigation requirements, and/or'penalties could possibly
result from the City's delay in taking action to repair the site damage in a timely manner.
RESOURCE AGENCY PERMIT RAMIFICATIONS OF STORM DAMAGE
Dudek recommends that the City be proactive and transparent with the resource agencies about
the storm damage that has occurred and notify them as soon as possible about the status of the
project and the desired course of action. In Dudek's opinion the project was in substantial
conformance with the intended mitigationlrevegetation design at the time of completion of the
plantings in early December 2009, prior to the major storm damage If the project had stayed on-
track without the storm damage and December 1 had been used as the official start date of the
1207day plant establishment maintenance period, then technically the end of the 120-day period
DUDEK S • • ' - 3385-07
10 : '
' February 2010
I
I
I'
I
I
I
I
Mr. John Cahill
Subject: Rancho Santa Fe Road Realignment and Bridge Replacement Project, Off-Site
Wetland Mitigation Project - 2009/2010. Storm Damage Assessment and Repair
Recommendations .. -
I would be April 1. That would be the normal time frame at which Dudek would prepare a letter to
the resource agencies signifying the completion of the initial installation and plant establishment
-
period and would designate the formal start of the five year maintenance and monitoring period.
1 However, since the storm damage has occurred, the normal timeline has been disrupted and there
are obviously delays to the program that have resulted.
In Dudek's opinion, the City should notify the resource agencies as soon as possible regarding
- these problems and propose a remedial workladaptive management strategy for correcting the
I . problems and moving forward. .The agencies could respond by requesting amendments to the
'permits to address the project changes, or they might simply agree to the proposed repair
strategies This may or may not include extending the proposed maintenance and monitoring
I period depending upon the decisions, by the applicable agencies. At this point in time Dudek does
not know how the agencies will respond and if additional mitigation measures might be
I necessary. We do feel however that it would be better for the City to be proactive, rather than
waiting to see if the agencies become aware of the problems and impose additional penalties or
I
other supplemental mitigation requirements.
In conclusion, it is Dudek's opinion that-the project was designed and constructed in accordance
with the requirements of the resource agency permits, and in compliance with the intended
I ' mitigation strategies. The work that was conducted in the field was monitored by Dudek and was
found to be in substantial compliance with the project plans and specifications prior to the onset
I of the winter rains. The rain events that occurred from late November 2009 through January
2010 were larger than normal "El Niño" related storm events, were unusual and unforseen at the
time they occurred and lead to significant flooding of the mitigation areas and subsequent
I . '
damage to the revegetation areas. As has been pointed-out, the plant materials and seeded areas
did not have adequate time to become'rooted and establish prior to the onset of the. storms and
I thus they could not withstand the flood flow. Dudek's opinion is that if the mitigation areas can
be reasonably repaired and the damaged areas revegetated, then the City should still be able to
meet the long-term goal of the mitigation program. The City. needs to evaluate the three
I alternatives/options presented herein and 'decide upon an appropriate course of action. Dudek is
committed to helping the City reach a resolution on how to repair the damaged areas and to
move forward to a successful conclusion to the installation phase of the mitigation program.
338507
I
DUDEK. ' .11 . , ' February 2010
1
lION AREAI
,158 S.F.)
If
I
0E)OI
JNDER
AN
/
/ Planting/Seeding Legend
- SWS Area (Including lower slope)
-MFS Area
- CSS Area - Slope
EM -FWM Area
- Installed Rip-Rap
--rr-, r
'--(7
'.
- -, —
---. - - - - - - -
-MAIN CREEK I - _z -_ -• (- 1-
-. -
--
/
--- / - — -_ --- - - -------- - - - APRROX % 10 REMAINII
- ----:-0F PLANTED ANDY
il --jRRlGATI0N INSTALLAT
-AREAJ3 63Ac (27,484 S
J)j
r6E OFSLOPE -
-O -25.J00 100 •... )\... -- ,-
-- I " \ - -•-'•. " ,' ' I
Rancho Santa Fe Road Bridge Offsite Mitigation Area FIGURE
Winter Impact Assessment - West Project Area (Lower Canyon) 1
r I •Y,)
F
.*_ç.p; .¼ - ii _-
0 * -I . .__, -•
Photo 2: Planting (November 2009)
Photo 5: Planting (November 2009)
-';
4 =
-,
*,i._ -,- • t -
- 1J' -
Photo 1: Planting (November 2009)
Photo 4: Planting (November 2009)
:
-I&-_
-. • :- .. . - h •-
-
- - - - . - - • • .
: --
- - 1.—. çr - - - .- ••
1 J
3
Photo 3: Planting (November 2009)
0
-
I. • -
•• c,
11110
zip
I
.
-411
0
0- .• -
- -I- - -- .- .
0 • IL 0 0 -
-
0
Photo 6: Planting (November 2009)
Rancho Santa Fe Road Bridge Offsite Mitigation Area FIGURE
Site Photographs - Plantings (November 2009) 2
Photo 1: Post Major Storm (December)
Photo 4: Post Major Storm (December)
Photo 3: Post Major Storm (December)
Photo 6: Post Major Storm (December)
Photo 2: Post Major Storm (December)
Photo 5: Post Major Storm (December)
Rancho Santa Fe Road Bridge Offsite Mitigation Area FIGURE
Site Photographs - Post Major Storm (December 2009)
,
•- •
,'
4••
4' £,
N :
*
.--.
.:- - - 14• £
....,-'-- -.4-'••:- - • • -
/ ••
I 4
4
• )
- - -
1 '\ t3' -, -C
-C
* =-*
-C
C - - -
-.?_
: - --- -
-
•-
-
• -
C
• - - 1!
-
- - -
- - - • -r--'--- _-. -'• - ---. --p-- - --
-•--• ,4_•_•
- L . ;•-..•-
ills - Storm I-low (January /L Al 11
WPM
-
fk
--------------
A ---
•
-.,_--- .-' --I
* • -.5*
- -
.
— -- -
' -r ..•
a -
~~ -- AN NAZI 6,
-- -
-'
- - - I
:;.
lW
t
a J—,;r tp
.5 'S..'
~M- MW
ii
--
_*_ I •- - --
-
-----
____________________
* '
- - - _5•*_ *5• • • - .5-..- p.-. -,
j 5-:-;4..5 -
5--- -
5.
•
A.
- .— - r. ; - • .. -
If Rj - • - .-
'5'
.
-%.• VS. ._-• .. _______ - -
. - : -
.. •*J .•-. r'.- -
a- -
- - - ;-.- .4
- - c-±3, m - -. • . ._
54-
j—: 7 % &. -.• ..- r - -
1 C!) c\..FL IP••_JI_, -
-- • ;_ 2 - ...
'.5. t4 -;.-- r.(j.*,* I-•••-• -'..• •
'•
-
; .•- --.5-
-.5 4-
,.r II-
/( -
-.1&. •' 'I
5- -
/
Ip AssAssmc
Photo 1: View looking east into main creek, prior to start of Rancho Santa Fe
Road construction.
Photo 2: View looking north along University Commons mitigation area after
November 2009 storm.
Photo 3: View looking north along University Commons mitigation area after
December 2009 storm.
Photo 4: View looking east of University Commons area, left of construction
fence after December 2009 storms.
Photo 5: View looking into University Commons mitigation area after January
2010 storms.
Photo 6: View looking south at north end of University Commons mitigation
area. (January 2010)
Rancho Santa Fe Road Bridge Offsite Mitigation Area FIGURE
Site Photographs - University Commons Pre and Post Damage Assessment 6