HomeMy WebLinkAboutCD 2017-0003; Kaiser Carlsbad Parking Lot Expansion; PRELIMINARY SOIL INFILTRATION TESTING AND PAVEMENT STRUCTURAL SECTION REPORT; 2017-05-10I
::,";~~
Y RMAGroup
Every Proj~cl Matten1jwww.rmocompanies.com
May 10, 2017
Hanna Gabriel Wells Architects
1955 Bacon Street
San Diego, Ca 92107
Attention: Randy Hanna, AIA
Principal
RECORD COPY
S)Z1t_ /M.gl
Initial Date
RMA Project No.: 17-0497-01
EC VE
Subject: Preliminary Soil Infiltration Testing and Pavement Structural Section Report , ,Y ! G 2017 Kaiser Permanente Carlsbad Parking Lot Expansion
6860 Avenida Encinas
Carlsbad, CA LAND DL\ E ._opr\ ~NT
-NGI. ~ G
Gentlemen:
In accordance with your request and authorization, we have completed an infiltration testing and pavement investigation
report for the subject site. The report includes the results of four exploratory borings and six soil infiltration tests, along
with infiltration system and pavement section design recommendations. Tbe infiltration tests were performed using a
Double-Ring Infiltrometer (ASTM Test Method D 3385). This report was completed based upon the requirements of
City of Carlsbad BMP Design Manual and Technical Guidelines for Geotechnical Reports.
It is our understanding that the project includes tl1e parking lot expansion and installation of two biofiltration basins.
According to a Preliminary Parking Layout map, two lined biofiltration basins are planned on the west side of the site and
will be connected to an existing storm drain. The basins will range from 1 to 3 feet in depth below design grades. The
location of the proposed basins are shown on Figure 1.
Site Description and Proposed Usage
The site is located at 6860 A venida Encinas in the City of Carlsbad, California. The site is bounded by an auto dealership
to the north, Interstate 5 to tl1e east, a residential development to the south and A venida Encinas to the west.
The proposed parking lot expansion area and biofiltration basins are currently landscaped witl1 small shrubs, palm trees
and a few other trees located west of the existing building.
Subsurface Exploration and Earth Materials
The four °'l'loratory borings and six infiltration test locations are shown on a site map provided by Hanna Gabriel \Veils
Architects and were completed within 50 feet of the proposed BMP's in order to characterize the soil conditions beneath
the site (Figure 1). The exploratory borings were extended to a depth of 16.5 feet The infiltration test locations were
excavated to depths of 1 foot in the proposed parking lot area and 2 to 3 feet witllin the proposed biofiltration basin
locations, corresponding to the depth of the basins in the area of tile tests.
Based upon regional mapping by Kennedy, M.P, et al (2007) the site is underlain by late to middle Pleistocene old paralic
deposits. The paralic deposits consisted of light brown, brown and gray silty sand and gray sand with silt at depths below
13 feet and were generally moist and medium dense to dense.
Logs of the exploratory borings are included in Appendix A. The locations of the borings are shown on Figure 1.
12130 Santa Margarita Court Rancho Cucamonga, CA 91730 IT: 909.989.1751 IF: 909.989.4287 I www.rmacompanies.com
-
..J
\----z
...
• -..
-.. -..
------... --.. -... ..
,.., -.. ---------.. -..
-..
~;~~
y'"ifMAGroup
Every Proj«t Mattera\www.rmocompanks.com
Groundwater Conditions
No areas of ponding or standing water were present at the time of our study. Groundwater was not encountered during
our subsurface exploration.
According to the Geotracker website (http://geotracker.waterboards.ca.gov), groundwater was encountered in a
monitoring well located approximately 1 mile northwest of the site was at a depth of 28 feet in 2005. Based upon
information on the website, the elevation of the monitoring well is 67 feet above sea level, elevation at the site ranges
from 64 to 6 7 feet above sea level.
Infiltratlon Test Procedure
The infiltrometer equipment consisted of two calibrated plastic cylinders, two alwninum rings, constant level float values,
shutoff values, and plastic tubing to connect the cylinders and aluminum rings. Calibrations were marked directly on the
plastic cylinders. The cylinders were connected to special supports to prevent tipping and to maintain proper height. The
aluminum rings were 12 and 24 inches in diameter and 20 inches high. The float valves were used to maintain a constant
water level in the aluminum rings. Infiltration rate of water during the test was determined by monitoring volume changes
in the calibrated cylinders. Testing was continued until a relatively uniform infiltration rate was obtained .
Infiltration Test Results
The testing yielded the following infiltration rates:
Table 1 Measured Infiltration Rates
Location Infiltration Rate Infiltration Rate
(cm/hr) (in/hr)
P-1 (Center of nronosed parking lot) 0 0
P-2/South side of orooosed parkiru, lot) 0 0
P-3 /Center of south basin) 2.55 1.00
P-4/North side of south basin) 2.12 0.84
P-5/Center of north basin) 0.85 0.33
P-6/Northeast comer of north basin) 1.27 0.50
Infiltration of water into the paralic soils consisting of dense silty sand at the depths tested ranged from 0.0 to 2.55 cm/hr
(0.0 to 1.00 in/hr). Infiltration test result sheets are included in Appendix A.
Desiga Considerations
Monitoring of actual facility performance has shown that the full-scale infiltration rate is far lower than the rate
measured by small-scale testing. The infiltration rate will decline between maintenance cycles as the Best Management
Practices (BMP) surface becomes clogged and fine soil particulates accumulate in the basin bottom. Thus an
appropriate factor of safety must be applied to the measured infiltration rate and incorporated into facility design.
The City of Carlsbad BMP Design Manual specifies a procedure for determining safety factors by using a point system
related to the suitability of underlying soils for infiltration and design of infiltration systems.
There are four safety factors considerations related to soil conditions (Factor Category A):
• Soil assessment methods (e.g., number of borings or test pits) and the measurement method used to
determine short-term infiltration rates .
• Predominant soil texture and the percent of fines that can influence the potential for clogging.
Kaiser Pennanente Ca~sbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page2
..
• ----------------------.. -...
----... --..
--
~;~~
Y'RMAGroup
Every Projtcl Mattera! www.rmocompanits.com
• Vertical and horizontal soil variability.
• Depth to seasonal high groundwater and the presence of relatively impervious layers.
Descriptions of each concern are presented in the following table.
Factor Category A
Suitabilirv Assessment Related Considerations for Infiltration Facilirv Safetv Factors
Consideration Hi"h Concern (3) Medium Concern (2) Low Concern (1)
Direct measurement of Direct measurement of 2'.:
Use of soil survey maps 2 20% of the infiltration 50% of infiltration area
with localized
Assessment methods or simple texture analysis area with localized measurement methods or to estimate short-term infiltration measurement use of extensive test pit infiltration rates methods (e.g. infiltration measurement infiltrometer) methods
Texture Class Silty and clayey soils with Loamy soils Granular to slightly
siimificant fines loamv soils
Highly variable soils
indicated from site Soil borings/test pits Multiple soil borings/test
Site soil variability assessment or limited soil indicate moderately pits indicate relatively
borings collected during homogeneous soils homogenous soils.
site assessment
Depth of groundwater or < 5 feet below facility 5-10 feet below facility > 10 feet below facility
imnervious laver bottom bottom bottom
There are three safety factors considerations related to facility design (Factor Category B):
• Level of pretreatment and expected influent sediment loads.
• Redundancy of BMP facilities.
• Intended or unintended compactions of soils during or after construction.
Descriptions of each concern are presented in the following table.
Kaiser Permanente Ca~sbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page3
..
• -.. .. .. .. ---------.. .. .. --.. .. ---------.. -----
~:;~#..
Y'iRMAGroup
Every Proj«t Mattenlwww.rmocompanies.com
Factor Category B
Desi= Related Considerations for Infiltration Facilitv Safet Factors
Consideration Hie:h Concern (3) Medium Concern (2) Low Concern (1)
Pretreatment from gross Good pretreatment with solids removal devices Excellent pretreatment
only such as BMP's that mitigate with BMPs that mitigate coarse sediments such as hydrodynamic vegetated swales AND fine sediments such as
Level of pretreatment or separators, racks and influent sediment loads bioretention or media
screens AND tributary filtration OR expected influent area includes landscaped from the tributary area sedimentation or facility sediment load areas, steep slopes, high are expected to be only treats runoff only
traffic areas, or any other relatively low (e.g. low treats runoff from
areas expected to traffic, mild slopes, relatively clean surfaces,
produce high sediment, disconnected impervious such as rooftops.
trash or debris loads. areas, etc.).
High redundancy,
Medium redundancy, multiple components
other BMPs available in capable of operating
Redundancy of treatment No redundancy in BMP treatment train to independently and in
treatment train. maintain at least 50% of parallel, maintain at least
function of facility in 90% of facility
event of failure . functionality in event of
failure.
Heavy equipment
Construction of facility actively prohibited from
Compaction during on a compacted site or Medium probability of infiltration areas during
construction elevated probability of unintended/indirect construction and low
unintended/indirect compaction. probability of
compaction . unintended/indirect
comoaction .
The City of Carlsbad BMP Design Manual specifies the following procedure to determine a safety factors for
measured infiltration rates:
• A level of concern is determined for each consideration in the Factor Category tables above. A
corresponding Factor Value (v) is determined for each concern. The Factor Values are 3 for high concerns, 2
for medium concerns, and 1 for low concerns.
• Each Factor Value (v) is multiplied by an Assigned Weight (w) to determine a Product Value (p).
• The Product Values (p) within each Factor Category (A and B) are summed to obtain a Safety Factor (SA and
Ss) for each Factor Category.
• The Safety Factors for each Factor Category are multiplied to determine a Combined Safety Factor (S-rm). If
the Combined Safety Factor is less than 2, then 2 shall be used as the Safety Factor.
• The Measured Infiltration Rate (KM) is divided by the Combined Safety Factor (SrnT) to determine the
Design Infiltration Rate (KnESIGN)-
Our selected Factor Values (v), Measured Infiltration Rate (KM) and Calculated Safety Factor (SA) are presented in the
table below .
Kaiser Pennanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page4
.. .. -..
-..
---..
---------.. -------------.. ----
:,-;<#..
Y'RMAGroup
Every ProjtctMatteralwww.rmacompanies.com
Factor of Safety and Des;..., Infiltration Rate and Worksheet
Assigned Factor Product (p)
Factor Category Factor Description Weight (w) Value (v) p=wxv
Soil assessment methods 0.25 2 0.5
Predominant soil texture 0.25 2 0.5
A Suitability Site soil variability 0.25 I 0.25
Assessment Depth to groundwater / impervious layer 0.25 I 0.25
Suitabilitv Assessment Safety Factor, SA = L" 1.5
Level of pretreatment/ expected sediment loads 0.25 I 0.25
B Design Redundancy 0.25 3 0.75
Compaction during construction 0.25 3 0.75
Desi= Safetv Factor, Sa -L" 1.75
Combined Safety Factor, Srm·= SA x S8 2.6
Measured Infiltration Rate, inch/hr, KM (corrected for test-specific bias) See Table 2
Design Infiltration Rate, in/hr, KoF.SIGN = KM/S-rcrr See Table 2
We recommend that the lowest measured infiltration rate from each basin and the proposed parking lot be used to
determine the design infiltration rate for each area by dividing the measured infiltration rate by the safety factor
determined above. The minimum safety factor according to the City of Carlsbad's Design Manual is 2.0. Based upon
the above Factor of Safety and Design Infiltration Rate and Worksheet, the calculated Factor of Safety is 2.6. Table 2
below lists the recommended design infiltration rates for the proposed parking lot and both of the proposed
biofiltration basins. The design engineer may also specify a higher safety factor at his discretion.
T able 2 Recommended Measured and Desian Infiltration Rate
Measured Design
Location Infiltration Rate Infiltration Rate
(in/hr) (in/hr)
Proposed na~ lot 0 0
South Basin 0.84 0.32
North Basin 0.33 0.13
It is also recommended that if a basin is proposed the bottom be tipped once design grade is reached to help mitigate
unintended compaction of soils that might occur during excavation of the basin. A maintenance plan should also be
developed and implemented to restore infiltration properties of soils that may be impacted by sedimentation or other
adverse conditions.
Infiltration Test Conclusions
The City of Carlsbad does not include a minimum infiltration rate in their BMP Design Manual. Some other agencies
(the counties of Los Angeles, San Bernardino and Riverside) in southern California apply a minimum corrected
infiltration rate of 0.3 in/hr.
It is our professional opinion, based upon the infiltration rates obtained in our testing, that the use of permeable pavement
in the proposed parking lot is not recommended due to the very low infiltration rate encounter in the tests within the
proposed parking lot. Additionally, the proposed biofiltration basins had infiltration rates, when the minimum safety
Kaiser Permanente Carlsbad PaI1<ing Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page 5
•
" ..
"' .. .. ..
• ..
• .. .. -.. .. --
"" .. ..
----... .. ---.. .. .. -.. -.. --
factor is applied, of 0.32 and 0.13 in/hr and would be considered infeasible in other jurisdictions. Therefore, it is our
opinion that based upon the onsite soils very low infiltration rates that the site is not suitable for full stormwater
infiltration. Additionally, if permeable pavement is proposed, the City of Carlsbad's BMP Manual indicates that since the
infiltration rate is less than 0.5 in/hr an underdrain is required. Additionally, the permeable pavement's design goal is for
pollutant control only and not for infiltration .
The City of Carlsbad I-8 form is also attached in Appendix B. Based upon the Form 1-8, the site qualifies as a no
infiltration site due to the low infiltration rates (infiltration rates below 0.5 in/hr) and existing underground utilities
(particularly to electrical and telephone utilities) that service the existing Medical Office Building in the area of the proposed
biofiltration basins .
Pavement Structural Section
Laboratory testing of samples obtained from the site by our representative indicates that subgrade soil bas a Resistance (R)
Value of 71. The results of our laboratory tests are attached as Appendix A of this report .
Structural sections were designed using the procedures outlined in Chapter 630 of the California Highway Design Manual
(Caltrans, 2012). Tbis procedure uses the principle that the pavement structural section must be of adequate thickness to
distribute the load from the design traffic index (TI) to the subgrade soils in such a manner that the stresses from the
applied loads do not exceed the strength of the soil (R-value).
Development of the design traffic indexes on the basis of a traffic study is beyond the scope of this report; however, our
experience indicates that traffic indexes of 5 is typical for light auto parking and 7 is typical for fire and delivery truck lanes
for the heavier delivery vehicles and drive lanes. We have provided alternate structural sections for each traffic index.
Selection of the final pavement structural section should be based on economic considerations which are beyond the
scope of this investigation. The recommended structural section is as follows:
Light Auto Parking ffi=S.0 R-Value=71):
3.0 inches of asphaltic concrete over
4.0 inches of crushed aggregate base
or
4.0 inches of asphalt concrete on
12.0 inches of compacted subgrade soils
Fire and deliyezy truck Janes m-1.0 R-Value-71):
4.5 inches of asphalt concrete over
4.5 inches of crushed aggregate base
or
5.0 inches of asphalt concrete on
12.0 inches of compacted subgrade soils
Portland cement concrete (PCC) pavements for areas which are subject to traffic loads may be designed with a minimum
thickness of 6.0 inches of Portland cement concrete on 6.0 inches of crushed aggregate base .
The materials and methods used during construction should conform to the latest edition of the Standard Specifications
for Public Works Construction (SSPWC). The aggregate base course should conform to the SSPWC Section 200-2.2 for
Crushed Aggregate Base.
The asphalt surface course should conform to the SSPWC Section 203-6. If the asphalt concrete section is placed in two
lifts, the cold joint between lifts should not be designed at the center of the asphaltic-concrete section .
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page6
..
• ------------------.. --------
-
• -..
----
Closure
This report is subject to review of the local building official who may request clarification or modifications of the report
prior to approval.
We appreciate this opportunity to be of continued service to you. If you have any questions regarding this report, please
do not hesitate to contact us at your convenience.
Respectfully,
neth owell, PG, CEG
Project Geologist
CEG 2470
.. ~r::-
President
GE2362
Attachments:
Kaiser Pennanente Carisbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 2, 2017
RMA Project No.: 17-0497-01
Page?
-.. ---------------.. .. ---
----
---.. .. .. .. ..
--
~
'V RM.A Group Every Proj«t Matteralwww.rmacomponJes.com
FIGURE
EXISTING TREES TO
REMAIN PROTECTED
--
IN PLACE, TYP.
\~
o
!,-r~.,.._-;:-''1.-------..rlUIIT, -~ <13> c • f« 1/ EXISTING\
,, ,r flii!~--· PARKING
.
,,<; , (6)EXISTINGPARKING ~,. ,,.., / m ,,, ',:,,., p~/->"' (7)NEWPARKING ' STAI.LS "'j O STA/..LS.._/'"°' o , , .., / .., .., ~" .., · ~ .., STAI.LS
'---"-, (7 ACCE E STAL S !!l! \ _j '--> It¼ ~ ACCESS AISLES 2s ~ ,._,,,__----.,~ ~ \
N ~
~CURBRAMP ,, --'I-'-""'~ ' m a "' ~ I DELETEmEXJSTING~ARKING I I FtN. ~ ,..,.=.,Mov .. ,~ ol ~~~: m~I .
--
--
\§ "'1 a---n,L ) , -.. c---L. ~ ~r::=~ ~ ~~l~ , -~ --Y l ~,. J ~~(~~ ~~~ch tJ~ ~-~~ ) f
EXISTING MONUMENT
SIGN
(11)NEWSHADE
TREES ADJACENT
TO NEW PARKING
STALLS
AVENIDA ENCINAS
NEW STORM DRAIN POINT
CONNECTION PER CML
ENGINEER
NEW BIORETENTlON
BASIN PER CML
ENGINEER
EXISTING
PLANTERS,
TYP.
[!STING TREES
REMAIN PROTEC-
IN PLACE, TYP.
LEGEND !t -Indicates Approximate Boring Location
S:N
0 10' 2<1
M-i 40' !;,
~ ~
,/'fAMAlOAJUl"ACOl!U ~-.. --------~-....----! ~ CUCA.\IOf«iA.CA917lO IIT'EMI -1 ·· 10.-.n:I ,_~4:~0~1•~=:::M
PLAN CHANGES
Boring and Infiltration Tesr
Location Map
!t -Jadicates Approximate Infiltration Test Location
P-:'11
BASE MAI' PROVIDED BY: Hanna Gabriel waua Nthl".ects
THIS PLA.'l HAS BF.EN PRE.PAR.FD FOR USE AS
A GE011;0{N1CAL AND GEOL(XjfCAL MAP _,,....,.,,.,.....,,.,,...,,...,.,,..,.,..n,._,
Hanna Gabriel Wells Architects
1955 Bacon Street
San Diego, Ca 92107
NORTH
Ki.iser Pcrmanentt UrlsMd
Parking Lot Expansion
6860 A,.·cnida Encinas
Carlsbad, CA
iR.\lA.IOBNO~
11-0'!1'1-0I ilo' I OF I
1
.. ---.. ---------------.. -.. .. ..
• ..
• .. ..
.. .. .. .. .. ..
...
::,:; ... ~
YilMAGroup
Every ProjectMattenlwww.rmacompanies.com
APPENDIXA
FIELD INVESTIGATION
AND
INFILTRATION TEST RESULTS
..,
...
.., ------------------.. ..
... ..
... .. .. .. .. ..
... .. .. .. ..
•
...
:,";~#.,
YRMAGroup Every Proje<I Matten!www.rmacompanks.com
APPENDIXA
FIELD INVESTIGATION
A-1.00 FIELD EXPWRATION
A-1.01 Number of Borings
Our subsurface investigation consisted of 4 exploratory borings drilled with a Mini Mole solid flight auger drill rig.
A-1.02 Location of Borings
A Boring and Infiltration Test Location Map showing the approximate locations of the borings is presented as Figure 1.
A-1.03 Boring Logging
Logs of borings were prepared by one of our staff and are attached in this appendix. The logs contain factual information
and interpretation of subsurface conditions between samples. The strata indicated on these logs represent the
approximate boundary between earth units and the transition may be gradual. The logs show subsurface conditions at the
dates and locations indicated, and may not be representative of subsurface conditions at other locations and times.
Identification of the soils encountered during the subsurface exploration was made using the field identification procedure
of the Unified Soils Classification System (ASTM D2488). A legend indicating the symbols and definitions used in this
classification system and a legend defining the terms used in describing the relative compaction, consistency or firmness of
the soil are attached in this appendix. Bag samples of the major earth units were obtained for laboratory inspection and
testing, and the in-place density of the various strata encountered in the exploration was determined
A-1.04 Soil Infiltration Testing
Six soil infiltration tests were performed using the dual ring infiltrometer test procedure (ASTM Test Method D 3385)
described in the City of Carlsbad BMP Design Manual (2016). Results of the testing are attached to this appendix.
Locations of the tests are shown on Figure 1 .
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
PageA1
.. .. .. .. .. .. .. .. .. --.. --.. .. .. .. .. .. .. .. ..
• .. ..
-... ..
... .. .. .. ..
• ..
..
_,-;,~
...iRMAGroup Every Proj«tMatteralwww.rmacompanies.com
-" w g
0 •
~ ~ 0 0
I 0
~ 8
-
~ •
:
' "
MAJOR DIVISIONS
COARSE
GRAINED
SOILS
(-tw,5()%ol
.-.illl.AAGER
tt-.,l,b.:100-
liz•)
GRAVELS
(MnthlnOO'lllol --· LARGERhnh
No.4-.....
SANDS
CLEAN
GRAVELS
(lillloormr...)
GRAVELS
WITHFINES -~---,
CLEAN
SANDS
GROUP
SYMBOLS
. . . -. GW
0 < GP
/ol /1 . . . . .
. . .
GM
GC
SP
• • • SM
TYPICAL NAMES
Well i,tldedgrwal, gr......-.l mx1 .......
trttleorno~nes.
(/)
>-
::.
...J
w
N
(/)
w
...J u
•.
jMn11wl50'llool --· SMAI.LER!hanlhe r,1o.,_.,.) SANDS ~•+.•~•~-+-------------< WITH FINES ;;,' ,/4 ,l
>-
et:
<(
0..
0 ~
I
-
~
ra ,
>--
~
~ " 0
>a •
N .
FINE
GRAINED
SOILS
(ll<itahn50%ol --~ t.nNo.:100-_,
~-l (~/.; SC
ML
SILTS AND CLAYS CL (Llql.id lltrit LESS ltGn 50)
OL
MH
SIL TS AND CLAYS
(Llql.idmlGREAlERthan50) ~ CH
-, , , , , , OH , , ,
HIGHLY ORGANIC SOILS Pt
tnorganlcsib inlVf:f'ffino-. rockft<U
eil:yordl!l/fl'lftne.-.:ltorfR/<1i,ib
'Mltl811gl!pla!illdty
1rio.,;ir;ncc:1aysa11owtomed,-,, pla&tidly,
~ ~. &a"laf clayll, .. ~ lean ,.,.
lnorgaricsib, rricacecus ordlatamaoaous
ftnesa-.ct,or!lilly""'ls,elar;licS1ks
Orga,icdayacfmedhmtol-jg,J:(aslldty.
orga,icsills.
BOUNDARY CLASSIFICATIONS: soils po$$8SSing charadllliltica of tv,o !JOUP' ani designated by corminations of goup IS)"IT'bok.
UNIFIED SOIL CLASSIFICATION SYSTEM
Kaiser Permanente Ca~sbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
PageA2
-..
----------------------.. ..
-..
----------
::r-;~~
Y'RMAGroup Every ProjtctMatteralwww.rmocomponfes.com
I. SOIL STRENGTH/DENSITY
BASED ON STANDARD PENETRATION TESTS
Compactness of sand Consistency of clay
Penet.ration Resistance N Compactness Penetration Resistance N Consistency
(blows/Ft) (blows/ft)
0-4 Very Loose <2 Very Soft
4-10 Loose 2-4 Soft
10-30 Medium Dense 4-8 Medium Stiff
30-50 Dense 8-15 Stiff
>50 Very Dense 15-30 Very Stiff
>30 Hard
N = Number of blows of 140 lb. weight falling 30 in. to drive 2-in OD sampler 1 ft.
BASED ON RELATIVE COMPACTION
Compactness of sand
% Compaction
<75
75-83
83-90
>90
II. SOIL MOISTURE
Compactness
Loose
Medium Dense
Dense
Very Dense
Moisture of sands
% Moisture
<5%
5-12%
>12%
Description
Dry
Moist
Very Moist
Consistency of clay
% Compaction
<80
80-85
85-90
>90
Moisture of clays
% Moisture
<12%
12-20%
>20%
Consistency
Soft
Medium Stiff
Stiff
Very Stiff
Description
Dry
Moist
Very Moist, wet
Soil Description Legend
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page A3
------------------.. --------... -------..
-·-
Date Drilled:
Logged By:
4-20-2017
KRD
Exploratory Boring Log
Drilling Equipment:
Boring I Iole Diameter:
Boring No. B-1
Mini Mole
6"
Location: See Boring and Infiltration Test Location Map Drive Weights: 140 lbs.
30"
Samples
.c if ~1= a.e t~ ~-! ~ Q) -U) -~ Q) -"9 E sS-" E » ::;u "'""" ID m
U) ma U)
-
-
-0 23 -
5-0 27 -
-
-0 25
-
10-0 34 -
-
-0 32
-
15-0 29 -
-
-
-
20-
-
-
-
-
25-
-
-
-
-
Sample Types:
{!] -Ring Sample
{!] -Tube Sample
~ ~ 'ii' U) ~:s u a. E o-5 U) ~ >,
2:-::, <9 en
"
SM :
.. '
i ..
,·.
..
' ..
'
Drop:
Material Description
This log contains factual infonnation and interpretation of the subsur1ace conditions between the
samples. The stratum indicated on this log represent the approximate boundary between earth
units and the transition may be gradual. The log show subsurface conditions at the date and
location indicated, and may not be representative of subsurface conditions at other locations and
limes.
Paralic deposits (Qop): Light yellowish-brown silty fine to medium sand, moist,
medium dense to dense, thin silty clay lens (about 1" thick) at 1 foot.
At 2 feet becomes reddish-brown in color
At 7 feet becomes gray in color
At 10 feet becomes reddish-brown in color
Gray brown fine sand with silt, moist, medium dense to dense
r.J -Bulk Sample ~-No Recovery
@) -SPT Sample ~ -End of Boring
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
RMA Project No.: 17-0497-01
PageA-4
..
• .. --------..
-----------
, ..
------------.. ..
·~ ::,-; ... ~
YRMAGroup
Every Project Mattera I www,rmocompanies.com
Exploratory Boring Log Boring No. B-2
Date Drilled:
Logged By:
4-20-2017
KRD
Location: See Boring and Infiltration Test Location Map
Samples ~ <I) -~:g :g_~ l! f -c "' ! 8. ~t ~~* ai 'U &l o. E
<I) -•,e; ~ >-• i~ "SE oo-:::, .2 0 a, ~ ::;o 2, (!)"' co e "' •
-
I -
-0 21 -
5-0 32
SM
..
:
: :
-
-·.
-0 28 •. :
--..
IQ-
0 27 -
-,·,
-0 35 '·' •. ' -
SM-SP 15-0 37 -
-
-
-
20-
-
-
-
-
25-
-
-
-
-
Sample Types:
:
Drilling Equipment:
Boring Hole Diameter:
Drive Weights:
Drop:
Mini Mole
6"
140 lbs.
30"
Material Description
This log contains factual infonnation and interpretation of the subsur1ace conditions between the
samples. The stratum indicated on this log represent the approximate boundary between earth
units and the transition may be gradual. The log show subsurface conditions at the date and
location indicated, and may not be representative of subsurface conditions at other locations and
times .
Pamlic deposits (Qop): Light yellowish-brown silty fine to medium sand, moist,
medium dense to dense, thin silty clay lens (about 1" thick) at 1 foot.
At 2 feet becomes reddish-brown in color
At 7 feet becomes gray in color
At 10 feet becomes reddish-brown in color
Gray brown fine sand with silt, moist, medium dense to dense
[!] -Ring Sample E'] -Bulk Sample ~-No Recovery
I!] -Tube Sample ~ -SPT Sample ~ -End of Boring
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
RMA Project No.: 17-0497-01
PageA-5
.. .. -----------.. -------..
-------.. .. .. .. .. .. -
::r;:~
Y' RMA Group
Every Project Matters I www.rmacompanies.com
Exploratory Boring Log Boring No. B-3
Date Drilled:
Logged By:
4-20-2017
KRD
Location: See Boring and Infiltration Test Location Map
Samples
~ l!g 15.-! 8. " .:!: 0. "s Cl !~ .2! ~ E a, .. co 8-rn
-
-
-0 -
5-0
19
29
I
-
-
-0 38
-
10-0 -41
-
-0 36
-
15-0 47 -
-
-
-
20-
-
-
-
-
25-
-
-
-
-
Sample Types:
~ ~c 0 rn ~ " -cc-(J ~§~ " 0 Cl8 rn :::, ~(.) ~ Cl
SM
SM-SP
~ :8 o. E ~ >-Cl rn
·. :
·.
: :
'·
'·
-..
:
'
:
Drilling Equipment:
Boring Hole Diameter:
Drive Weights:
Drop:
Mini Mole
6"
140 lbs.
30"
Material Description
This log contains factual information and interpretation of the subsurface conditions between the
samples. The stratum Indicated on this log represent the approximate boundary between earth
units and the transition may be gradual. The log show subsurface condi~ons at the date and
location indicated, and may not be representative of subsurface conditions at other locations and
times.
Paralic deposits (Qop): Light yellowish-brown silty fine to medium sand, moist,
medium dense to dense.
At 2 feet becomes reddish-brown in color
----
Gray brown fine sand with silt, moist, medium dense to dense
[!] -Ring Sample [J -Bulk Sample ~-No Recovery
I!] -Tube Sample ~ -SPT Sample .............. -End of Boring
Kaiser Permanente Ca~sbad Par1<ing Lot Expansion
Hanna Gabriel Wells Architects
RMA Project No.: 17-0497-01
PageA-6
.. -.. -.. ..
----... --..
... -----... --... --------------
:r;:~
Y'ilMAGroup
Every Project Matterslwww.rmocomponies.com
Date Drilled:
Logged By:
4-20-2017
KRD
Exploratory Boring Log
Drilling Equipment;
Boring Hole Diameter:
Boring No. B-4
Mini Mole
6"
J..ocation: See Boring and Infiltration Test Location Map Drive Weights: 140 lbs.
30"
Samples
ie if ~ 1:
" ~t :, " -0. 8-u,-* " -0 5-Cl E >-"SE
ffl f-a:ie, "' ffl ~(.) rn rn
-I -
-0 23 -
5-0 26 -
-
-0 31
-
10-0 -44
-
-0 39
-
15-0 42 -
-
-
-
20-
-
-
-
-
25-
-
-
-
-
Sample Types:
~ -Ring Sample
[!] -Tube Sample
,;,
0 cc-
" 0 Cl-!,
2:-Cl
rn .!::!Q
(.) .c .c "-E rn ~>, :,
" rn
SM
·.
: :
~ :
Drop:
Material Description
This log contains factual infonnation and inte,pratation of the subsurface conditions between the
samples. The stratum indicated on this log represent the approximate boundary between earth
units and the transition may be gradual. The log show subsurface conditions at the date and
locatioo indicated, and may not be representative of subsurface conditions at other locations and
times.
Paralic deposits (Qop): Light yellowish-brown silty fine to medium sand, moist,
medium dense to dense.
At 2 feet becomes reddish-brown in color
-~r~~--~--------------sM-sP ](~ Grnybcown fines,nd with silt, moist, medium dense to dense
r.J -Bulk Sample ~-No Recovery
~ -SIYf Sample ............... -End of Boring
Kaiser Pennanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
RMA Project No.: 17-0497-01
PageA-7
..
• .. .. ------.. -----------.. -------.. -.. ..
... --..
-
~
'VRMA.Group
Every Proj«I Mattera\www.rmocompanits.com
INFILTRATION TEST RESULTS
Project ID 17-0497-01 Constants
Test Location P-1 Center of proposed parking lot Inner Ring
Tested By 520DKR Anlr. Space
Date 4/20/17
Flow Readings
s Date Tune Elpd Inner Ring
o, Y, h, Tune Rg Flow
No. E 2014 (min) (min) (cm3) (cnl)
s 4/20 9:00:00 0 50
1 125
E 4120 9:02:00 2 175
s 4/20 9:02:00 5 175 2 25
E 4/20 9:09:00 7 200
s 4/20 9:09:00 5 200 3 50
E 4/20 9:14:00 12 250
s 4/20 9:14:00 5 250
4 0
E 4/20 9:19:00 17 250
s 4/20 9:19:00 5 250
5 0 E 4/20 9:24:00 22 250
s 4/20 9:24:00 10 250
6 0 E 4/20 9:34:00 32 250
s 4/20 9:34:00 10 250
7 0
E 4/20 9:44:00 42 250
s 4/20 9:44:00 10 250 • 0
E 4/20 9:54:00 52 250
s 4/20 9:54:00 10 250 9 0
E 4/20 10:04:00 62 250
Kaiser Permanente Ca~sbad Parking Lot Expansion
Hanna Gabriel Wells Architects
AnlrSpace
R;ng Flow
(cm3) (cm3)
1,600
3,700 2,100
3,700 1,000
4,700
4,700 400
5,100
5,100
300
5,400
5,400
300
5,700
5,700
200 5,900
5,900
200 6,100
6,100 200
6,300
6,300 200
6,500
Area Depth ofLiq
(cm2) (cm)
707 7.6
2106 7.6
Iner Infil
Rate
ln, Ank
(cm'hr) (cm'hr)
5.30 29.91
0.42 5.70
0.85 2.28
0.00 1.71
0.00 1.71
0.00 0.57
0.00 0.57
0.00 0.57
0.00 0.57
Iner Infil
Rate
lm Ank
(in/hr) (in/hr) Remuks
2.09
0.17
0.33
0.00
0.00
0.00
0.00
0.00
0.00
11.78
2.24
0.90
0.67
0.67
0.22
0.22
0.22
0.22
May 10, 2017
RMA Project No,: 17-0497-01
Page AS
..
• .. .. .. .. ------------... ----------------..
-..
:::r-;,~
YilMAGroup Every ProjectMatteralwww.rmocompanies.com
INFILTRATION TEST RESULTS
Project ID 17-0497-01 Constants
Test Location P-2 South side ofproposed parking lot Inner Ring
Tested By 520DKR Anlr. Space
Date 4/20/17
Flow Readings
s Date Tune Elpd Inner Ring
o, Y, h, Tune Rg Flow
No. E 2014 (min) (min) (cm3) (cnl)
s 4/20 10:15:00 0 0
I 25
E 4/20 10:25:00 10 25
s 4/20 10:25:00 10 25
2 25
E 4/20 10:35:00 20 50
s 4/20 10:35:00 10 50
3 10
E 4/20 10:45:00 30 60
s 4/20 10:45:00 10 60
4 0
E 4/20 10:55:00 40 60
s 4/20 10:55:00 10 60
5 0
E 4/20 11:05:00 50 60
s 4/20 11:05:00 10 60
6 0
E 4/20 IUS:00 60 60
Kaiser Pennanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
Anlr Space
rung Flow
(cni:1) (cnl)
0
250
250
250
100 350
350 100
450
450 100
550
550
50
600
600
50
650
Area Depth ofLiq
(cm2) (cm)
707 7.6
2106 7.6
Iner Infil
Rate
'"' An~
(cm'hr) (cm'hr)
0.21 0.71
0.21 0.28
0.08 0.28
0.00 0.28
0.00 0.14
0.00 0.14
lnerlnfil
Rate
'"' (in/hr)
0.08
0.08
O.D3
0.00
0.00
0.00
Anlr
(in/hr) RenmrlG
0,28
0.11
0.11
0.11
0.06
0.06
May 10, 2017
RMA Project No.: 17-0497-01
Page A9
-.. -.. ---------------------...
-...
-.. ---
• ...
...
--
:,-; ... ~
YRMAGroup
Every Proj«t Matteralwww.rmacomponles.com
INFILTRATION TEST RESULTS
Project ID 17-0497-01 Constants
Test Location P-3 Center of south basin Inner Ring
Tested By 520DKR Anlr. Space
Date 4/20/17
Flow Readings
s Date Ton, Elpd Inner Ring AnlrSpace
o, Ye he Ton, Rg
No. E 2014 (min) (min) (cm3)
s 4/20 11:30:00 0 100
I E 4/20 11:40:00 10 750
s 4/20 11,40,00 10 750
2 E 4/20 11:50:00 20 1,175
s 4/20 11:50:00 10 1,175
3
E 4/20 12:00:00 30 1,550
s 4/20 12:00:00 10 1,550
4 E 4/20 12:10:00 40 1,850
s 4/20 12:10:00 10 1,850
5
E 4/20 12:20:00 50 2,150
s 4/20 12:20:00 10 2,150
6
E 4/20 12:30:00 60 2,450
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
Flow Ring Flow
(cm3) (cnl) (cm3)
300
650 2,700 3,000
3,000 425
5,900
2,900
5,900
375 2,200
8,100
8,100
300 2,100
10,200
10,200
300 1,800
12,000
12,000
300 1,800
13,800
Area Depth ofLiq
(cm2) (cm)
707 7.6
2106 7.6
Iner Jnfil
Rate
Im Anlr
(cm'hr) (cm'hr)
5.52 7.69
3.61 8.26
3.18 6.27
2.55 5.98
2.55 5.13
2.55 5.13
Iner Infil
Rate
Im Ank
(in/hr) (in/hr) Remuks
2.17
1.42
1.25
1.00
1.00
1.00
3.03
3.25
2.47
2.36
2.02
2.02
May 10, 2017
RMA Project No.: 17-0497-01
Page A10
.. .. -.. -.. -----------..
---------..
-----.. .. ..
--
Project ID 17-0497-01 Constants
Test Location P-4 North side of south basin Inner Ring
Tested By 520DKR Anlr. Space
Date 4/20/17
Flow Readings
s Date Time Elpd Inner Ring AnlrSpace
o, Y, he Time Rg
No. E 2014 (min) (min) (cm3)
s 4/20 12:45:00 0 0
1
E 4/20 12:55:00 10 800
s 4/20 12:55:00 10 800 2
E 4/20 13:05:00 20 1,250
s 4/20 13:05:00 10 1,250 3
E 4/20 13:15:00 30 1,600
s 4/20
4
13:15:00 10 1,600
E 4/20 13:25:00 40 1,900
s 4/20 13:25:00 10 1,900
5
E 4/20 13:35:00 50 2,150
s 4/20 13:35:00 10 2,150
6
E 4/20 13:45:00 60 2,400
Kaiser Permanente Ca~sbad Parking Lot Expansion
Hanna Gabriel Wells Architects
Flow Rmg Flow
(cm3) (cm3) (cni:1)
100
800
2,800
2,700
2,800 450 1,900
4,700
4,700 350 2,000
6,700
6,700 300 1,800
8,500
8,500
250 1,600
10,100
250
10,100
1,600
11,700
Area Depth ofLiq
(cm2) (cm)
707 7.6
2106 7.6
Inerlnfil
Rate
In, Anh-
(cm'hr) (cm'hr)
6.79 7.69
3.82 5.41
2.97 5.70
2.55 5.13
2.12 4.56
2.12 4.56
Inerlnfil
Rate
In, Anh-
(in/hr) (in/hr) Remarl<s
2.67 3.03
1.50 2.13
1.17 2.24
1.00 2.02
0.84 1.79
0.84 1.79
May 10, 2017
RMA Project No.: 17-0497-01
Page A11
.. .. -.. ---,.
-------.. --.. .. .. .. ..
• -------.. ------
::,::: ... ~
YRMAGroup
Every ProjectMatte,.lwww.rmocompan~s.com
Project ID 17-0497-01 Constants
Test Location P-4 Center of north basin Inner Ring
Tested By 520DKR Anlr. Space
Date 4/20/17
Flow Readings
s Date Tim: Elpd Inner Ring Anlr Space
o, Y, h, Tim: Rg
No. E 2014 (mm) (mm) (cm3)
s 4/20 14:00:00 0 0
1
E 4/20 14:10:00 10 250
s 4/20 14:10:00 10 250
2 E 4/20 14:20:00 20 450
s 4/20 14:20:00 10 450
3 E 4/20 14:30:00 30 650
s 4/20 14:30:00 10 650
4
E 4/20 14:40:00 40 800
s 4/20 14:40:00 10 800
5
E 4/20 14:50:00 50 900
s 4/20 14:50:00 10 900
6
E 4/20 15:00:00 60 1,000
Kaiser Pem,anente Carlsbad Parl<ing Lot Expansion
Hanna Gabriel Wells Architects
Flow Rmg Flow
(cm') (cm3) (cm3)
200
250 3,100
3,300
3,300
200 1,700
5,000
5,000
200 1,700
6,700
6,700
150 1,700
8,400
8,400
100 1,500
9,900
9,900
100 1,400
11,300
Area Depth ofLiq
(cm2) (cm)
707 7.6
2106 7.6
Iner Infil
Rate
In, Anrr
(cm'hr) (cm'hr)
2.12 8.83
l.70 4.84
1.70 4.84
1.27 4.84
0,85 4.27
0.85 3.99
Inerlnfil
Rate
In, Anrr
(in/hr) (in/hr) Remarks
0.84 3.48
0,67 l.91
0.67 1.91
0.50 1.91
0.33 1.68
0.33 1.57
May 10, 2017
RMA Project No.: 17-0497-01
Page A12
..
• .. -------------.. -.. -------------.. ----..
::r-;~~
y'ifMAGroup
Every Project Matteralwww.rmacompanies.com
Project ID 17-0497-01
Test location P-6 Northeast comer of north basin
Tested By 520DKR
Date 4/20/17 -------
Constants
Inner Ring
Anlr. Space
Flow Readings
s Date Tm Elpd Inner Ring
o, Y, h, Tm Rg
No. E 2014 (mm) (mm) (cm3)
s 4/20 15:12:00 0 0
l
E 4/20 15:22:00 10 200
s 4/20 15:22:00 10 200
2
E 4120 15:32:00 20 400
s 4120 15:32:00 10 400
3
E 4120 15:42:00 30 550
s 4/20 15:42:00 10 550
4 E 4/20 15:52:00 40 700
s 4/20 15:52:00 10 700
5
E 4/20 16:02:00 50 850
s 4120 16:02:00 10 850
6
E 4/20 16:12:00 60 1,000
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
Flow
(cm3)
200
200
150
150
150
150
Anlr Space
Ring Flow
(cm3) (cnl)
100
2,900
3,000
3,000
2,000
5,000
5,000
1,400
6,400
6,400
1,400
7,800
7,800
1,300
9,100
9,100
1,300
10,400
Area Depth ofLiq
(cm2) (cm)
707 7.6
2106 7.6
Iner Infil
Rate
In, Anrr
(cm'hr) {cm'hr)
1.70 8.26
1.70 5.70
1.27 3.99
1.27 3.99
1.27 3.70
1.27 3.70
Iner Infil
Rate
In, Anrr
(in/hr) (in/hr) Remarks
0.67 3.25
0.67 2.24
0.50 1.57
0.50 1.57
0.50 1.46
0.50 1.46
May 10, 2017
RMA Project No.: 17-0497-01
Page A13
.. ..
-------..
-----------------------.. ----
:=r;~~
YilMAGroup Every Proj«tMattefl/www.nnacompanies.com
APPENDIXB
LABORATORY TESTS
.. .. .. .. -----------... ..
"' -
--... --
.. ----.. ..
"' ...
, ... -•
:,-;~~
Y'ifMAGroup
Every Project Mattera! www.rmocomponie.s.com
B-1.00 LABORATORY TESTS
B-1.01 Resistance Value (R-Value)
Resistance Value tests were performed on representative samples of the major soil types encountered by the test methods
outlined in California 301.
B-1.02 Test Results
Test results for all laboratory tests performed on the subject project are presented in this appendix.
Kaiser Permanente Cartsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page B1
::,-;:~
Y RMAGroup
Every Project Mattera I www.rmocompanies.com
CTM 301 -Detennination of Resistance "R" Value of Treated and Untreated Bases, Subbases
--~ .... Q)
1ii
E g
..c ro u5
>, ..c
"' "' Q) C: .-"<'.
(.) ~ .... Q) > 0 (..)
and Basement Soils by Stabilometer
Sample No. B-2@ 1-4 feet
Specimen No A
Moisture Content(%) 11.0
Dry Density (pcf) 123.0
Exudation Pressure (psi) 736
Stabilometer R Value 79
Expansion Pressure Dial 0
Use: Traffic Index= 5.0 Gravel Factor= 1.00
Thickness by Expansion (ft)
Thickness by Stabilometer (ft) 0.34
&j uilibrium Thick (ft)
&juilibrium Pressure R Value
Exudation Pressure R Value @300 psi
,,
B
11.9
123.0
253
72
0
0.45
n/a
71
C
11.5
123.0
376
7 1
0
0.46
Use Exudation R Value
Expansion Pressures Exudation Pressures
2.00
1.80
1.60
1.40
1.20
1.00
0.80
0.60
0.40
0.20
0.00 L/
~
~ ...
./ _..,...
./
~ ...,
./ 100
Q) 90
:::, 80 ni > 70 --
a::: 60
Q) 50 1ii 40 E g 30
..c 20 ro u5 10
0 0.00 0.50 1.00 1.50 2.00 0 100 200 300 400 500 600 700 800
Cover Thickness by Expansion Pressure (ft) Exudation Pressure (psi)
Expansion Pressure R-Value is based on the following structural section:
Thickness of AC (ft)= " 0.50 Gi(ac) = 2.50 W(ac) = "
Thickness of Aggregate Base (ft)= " 0.50 Gr(base) = 1.1 0 W(base) ="
G,{avg) = 1.80 W(avg) = "
145
130
138
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page 82
:r;:~
Y'RMAGroup
Every Project Mattera I www.rmocompanies.com
APPENDIXC
CITY OF CARLSBAD 1-8 FORM
Categorization of Infiltration Feasibility Condition Form 1-8
Part 1 -Full Infiltration Feasibility Screening Criteria
Would infiltration of the full design volume be feasible from a physical perspective without any
undesirable consequences that cannot be reasonably mitigated?
Criteria
1
Screening Question
Is the estimated reliable infiltration rate below proposed facility locations greater than
0.5 inches per hour? The response to this Screening Question shall be based on a
comprehensive evaluation of the factors presented in Appendix C.2 and .Appendix D.
Provide basis:
Yes No
X
Measured infiltration rates ranged from 0.0 in/hr to 0.84 in/hr. With application of the minimum factor of safety th<
design infiltration rates would be 0.0 in/hr to 0.32in/hr. This form is included with site infiltration report prepared b,
RMAGroup.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability.
2
Can infiltration greater than 0.5 inches per hour be allowed without increasing risk of
geotechnical hazards (slope stability, groundwater mounding, utilities, or other factors)
that cannot be mitigated to an acceptable level? The response to this Screening
Question shall be based on a comprehensive evaluation of the factors presented in
Appendix C.2.
Provide basis:
X
!Not applicable. Measured infiltration rates ranged from 0.0 in/hr to 0.84 in/hr. With application of the minimum factoi
bf safety the design infiltration rates would be 0.0 in/hr to 0.32in/hr.
Infiltration at the site will not impact slope stability since there are no nearby slopes at the site, the soils onsite are
!medium dense to dense silty sand and sand with silt and are not subject to hydrocollapse or consolidation based upon
ISPT blow counts, are non-expansive and not subject to liquefaction. Groundwater mounding would not be expected
!based on the separation between the bottom of the proposed basins being greater than 10 feet and the slow infiltration
trates obtained in our testing.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability.
hirm 1-8 Page 2 of 4
Criteria Screening Question
3
Can infiltration greater than 0.5 inches per hour be allowed without increasing risk of
groundwater contamination (shallow water table, storm water pollutants or other
factors) that cannot be mitigated to an acceptable level? The response to this Screening
Question shall be based on a comprehensive evaluation of the factors presented in
Appendix C.3.
Provide basis:
Yes N o
X
!Not applicable. Measured infiltration rates ranged from 0.0 in/hr to 0.84 in/hr. With application of the minimum facto1
lof safety the design infiltration rates would be 0.0 in/hr to 0.32in/hr.
!Ground water beneath the site was not encountered in or exploratory borings that extended to a depth of 16.5 feel
!below the existing ground surface.
!According to the Geotracker website (http://geotracker.waterboards.ca.gov), groundwater was encountered in 2
imonitoring well located approximately 1 mile northwest of the site was at a depth of 28 feet in 2005.
!Due to the slow infiltration rate and the separation between the groundwater level and the proposed basin bottom
1Plevation and the proposed use as vehicle parking, an increased risk of groundwater contamination is considered veri
ow.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability.
4
Can infiltration greater than 0.5 inches per hour be allowed without causing potential
water balance issues such as change of seasonality of ephemeral streams or increased
discharge of contaminated groundwater to surface waters? The response to this
Screening Question shall be based on a comprehensive evaluation of the factors
presented in Appendix C.3.
Provide basis:
X
!Not applicable. Measured inftltration rates ranged from 0.0 in/hr to 0.84 in/hr. With application of the minimum facto,
lof safety the design infiltration rates would be 0.0 in/hr to 0.32in/hr.
!Due to the slow infiltration rate and the separation between the groundwater level and the proposed basin bottorr
elevation and the proposed use as vehicle parking, and increase potential water balance issues such as change oJ
seasonality of ephemeral streams or increased discharge of contaminated groundwater to surface waters is considered
very low. No ephemeral streams are located onsite or nearby and the Geotracker website does not indicate a source oJ
known contamination within a mile of the site.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability.
Part 1
Result"
If all answers to rows 1 -4 are "Yes" a full infiltration design is potentially feasible.
The feasibility screening category is Full Infiltration
If any answer from row 1-4 is "No", infiltration may be possible to some extent but would
not generally be feasible or desirable to achieve a "full infiltration" design. Proceed to Part 2
See Part
~
*To be completed usmg gathered site information and best professional judgment considering the definition ofMEP 1n
the MS4 Permit. Additional testing and/ or studies may be required by City Engineer to substantiate findings.
Form I-8 Page 3 of 4
Part 2 -Partial Infiltration vs. No Infilttation Feasibility Screening Criteria
Would infiltration of water in any appreciable amount be physically feasible without any negative
consequences that cannot be reasonably mitigated?
Criteria Screening Question
5
Do soil and geologic conditions allow for infiltration in any appreciable rate or volume?
The response to this Screening Question shall be based on a comprehensive evaluation
of the factors presented in Appendix C.2 and Appendix D.
Provide basis:
Yes No
X
Measured infiltration rates ranged from 0.0 in/hr to 0.84 in/hr. With application of the minimum factor of safety the
design infiltration rates would be 0.0 in/hr to 0.32in/hr. This form is included with site infiltration report prepared by
RMAGroup.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability and why it was not feasible to mitigate low infiltration rates.
6
Can Infiltration in any appreciable quantity be allowed without increasing risk of
geotechnical hazards (slope stability, groundwater mounding, utilities, or other factors)
that cannot be mitigated to an acceptable level? The response to this Screening
Question shall be based on a comprehensive evaluation of the factors presented in
.Appendix C.2.
Provide basis:
X
Infiltration at the site will not impact slope stability since there are no nearby slopes at the site, the soils onsite ar,
medium dense to dense silty sand and sand with silt and are not subject to hydrocollapse or consolidation based upon
~PT blow counts, are non-expansive and not subject to liquefaction. Groundwater mounding would not be expecte<I
~ased on the separation between the bottom of the proposed basins being greater than 10 feet and the slow infiltration
~ates obtained in our testing. Would increase risk to existing underground utilities (particularly to electrical an<I
elephone utilities) servicing the existing Medical Office Building.
~ummarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
kliscussion of study/ data source applicability and why it was not feasible to mitigate low infiltration rates.
Form 1-8 Page 4 of 4
Criteria Screening Question
7
Can Infiltration in any appreciable quantity be allowed without posing significant risk
for groundwater related concerns (shallow water table, storm water pollutants or other
factors)? The response to this Screening Question shall be based on a comprehensive
evaluation of the factors presented in Appendix C.3.
Provide basis:
Yes No
X
Infiltration at the site will not impact slope stability since there are no nearby slopes at the site, the soils onsite are densf
silty sand and sand with silt and are not subject to hydrocollapse or consolidation based upon SPT blow counts, arf
~on-expansive and not subject to liquefaction. Groundwater mounding would not be expected based on the separatior.
between the bottom of the proposed basins being greater than 10 feet and the slow infiltration rates obtained in ou1
testing.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability and why it was not feasible to mitigate low infiltration rates.
8
Can infiltration be allowed without violating downstream water rights? The response to
this Screening Question shall be based on a comprehensive evaluation of the factors
presented in Appendix C.3.
Provide basis:
X
The site is not up gradient from a stream course and is located about ½ mile from the ocean. Also, no known watei
wells are located within a ½ from the site. Evaluation of downstream water rights is outside of the purview of
geotechnical engineering.
Summarize findings of studies; provide reference to studies, calculations, maps, data sources, etc. Provide narrative
discussion of study/ data source applicability and why it was not feasible to mitigate low infiltration rates.
Part2
Result*
If all answers from row 1-4 are yes then partial infiltration design is potentially feasible.
The feasibility screening category is Partial Infiltration.
If any answer from row 5-8 is no, then infiltration of any volume is considered to be
infeasible within the drainage area. The feasibility screening category is No Infiltration.
Infiltration
*To be completed using gathered site information and best professional judgment considering the definition of MEP in
the MS4 Permit. Additional testing and/or studies may be required by City Engineer to substantiate findings.
:r;:~
y7RMAGroup
Every Pro}tel Mattera I www.rmacompanies.com
APPENDIX D
REFERENCES
:r-;:~
Y iRMAGroup
Every Proj~ct Mattera/ www.rmacompanies.com
APPENDIXD
REFERENCES
1. City of Carlsbad BMP Design Manual, date February, 2016.
2. City of Carlsbad Technical Guidelines for Geotechnical Reports, date January, 1993.
3. Kennedy, M.P., Tan, S.S., Bovard, KR., Alvarez, RM., Watson, M.J., and Gutierrez, C.I., 2007, Geologic map of
the Oceanside 30x60-minute quadrangle, California: California Geological Survey, Regional Geologic Map No. 2,
scale 1:100,000.
Kaiser Permanente Carlsbad Parking Lot Expansion
Hanna Gabriel Wells Architects
May 10, 2017
RMA Project No.: 17-0497-01
Page D1