HomeMy WebLinkAboutCDP 02-35; HENDRIX SECOND DWELLING UNIT; PRELIMINARY GEOTECHNICAL EVALUATION; 2002-07-29,.·. ·' ~ '
. 1,,
·',•,
l ·:··
. , '·~ ·,, .. -: -~ ,.•,
,• .-,,, 1:'·.
' ...
" ~, :;1~-.:~·
: \
. ·,.:• .
' . ,_,--' ~. __ '
, .;.,
'· ,,,;,
·:,
• 'I--·,•,.!
,-s ~ ,: .. ' ~-f'
', ' ' ' C •
J-t_"'
,./; • ' !"'
. .... ,,
,,, '··:'
,"\·.
. ;, .,, ·,,·
..., .. ,.,
'
: ~ •" ' < '
_,,.,:
. ~ ; , ..
-,,.,
.' .··
·-·: '' '
, ..
. .: ~ ;
'',,:,,':· ·;_
. , ,.,·
··.·)
,_-' ' '~·· :.,
'' ,;_ .. ·
' .· ..
, ~ L, ... ,
•, ';
' -:~
•• , · .. -.·.4
:·, ;•;:
·, : " ' ·,·;·~ . ",_•
' .. '' ,•,I'•
'I ... ,
'• .·
-i •• '
-s.'·: .· ·':'·
·. ~' '·,
': • '·_.. f .~.,,,. -'
"\, ,,.,
.. ,,..,
' .. _. '... .
,':(:;
'I I
':·;·
,...,_ ..
. •,.
-~\. ·: . . ~ • 1 • r
,:,:-! '.f,: ... ·_.· :/_\::'_~ , ,.~ t :-: •• ~ ~ , .
,_. ,, : ,~\· :, ~· ;~-.:,: _:.~~? ~ ~ .. . .... :,, '
• • > '.•, C' ~.· ·, ! ·, '• ~~ ~ : } -.. , ~ ·.-,:,,',_:,.~,.;_•, ·:~ :• . -:' 1·;-, .• ~ ., :. :·. .
•t ..... • '' ,_J.-·, ~ .;-
• ~ > ' I
< , .... ' / -~~ >~' '
-~ ·...-:: ·,. ' . ~.
,; '
Ci· ~.: •.
-.. .' •. ,. ':·· -,,, , .. ','
. ~· \ ,.; ·,t. .. • _..,_ ';
-~ ....
,::·, '.,,. ,<
•••• r.,
,, .... ·,;
: '•.
. -.~ ..
·.";:-:, ·; ., ,• -..
(1. ' ••
', '. .··, .. :,,, .. '.;:.
, \ ~· t· .. ~ .,_ . ;, .\ .,' . )
;-i :-
{ ·. ~ .~
' .. , ' -:,--_
,,._,·:·
i·,,.: ,.. .... ,.:. ' ';
~ < .:. '
:. 1,:: ,·'
·.· { ;·.,., ,.,;
•'' ';1
·,'-:
Ir_,:
~"\ .! •
,, .,,
' : :-~ •' ...... ~
'-1··.:
'.'i,
.-. , :~' .
.. ,·. ,, ,.
<": ._,,,'
_ ..... _.:_
.,•: .,,
I, ~ ,/..__,
. .,.,., ..
' ·~ .J ·,.' ...
·-:.,
• ·,-_ I•: .
...,,...,:•.
;.. .:· ' ,,. ·-·
• ·'<" ~ •
.. · :>
. : .. ,, :: . ~ , ·,· .,·
. ,_, ,
,,' ,1' .·.·,·
I,,,, ·,f
: -..:··-~= : ',, -;,
A,,".•'
: .... , : ._ ... ~
·, I
-·,,,,;'? -, ..... ,
•,,, .·f
1'.' ,' . ,.',,' ,, ' . ,:. '. .} .·-.
·' r'., :,,-
I
I
I
I
I
I
I-
I
I
I
.I
I
I
I
·.,
I
I I
I
·1
Geotechnical • Geologic • Environmental
5741 Palmer Way • Carlsbad, California 92008 • (760) 438-3155 • FAX (760) 931-0915
July 29, 2002
W.0. 3344-A-SC
Mr. Ed Hendrix
470 Chinquapin Avenue
Carlsbad, California 92008
Subject: Preliminary Geotechnical Evaluation, 470 Chinquapin Avenue, Carlsbad,
San Diego County, California
Dear Mr. Hendrix:·
In accordance with your request, GeoSoils, Inc. (GSI) is pleased to present the results of our
preliminary geotechnical evaluation of the subject site. The purpose of our investigation
was to evaluatethe geologic and geotechnical conditions of the site and their effects on the
proposed site development for construction, from a geotechnical standpoint.
EXECUTIVE SUMMARY
Based on our field exploration, geologic and geotechnical engineering analysis, the
·proposed development appears feasible from a geotechnical and geologic viewpoint,
provided that the recommendations presented herein are ·properly incorporated into the
design and construction of the project. The most significant elements of our study are
summarized below:
•
•
Colluvium/topsoil, artificial fill, which are underlain at depth by terrace deposits were
encountered during our investigation. The colluvium/topsoil, artificial fill, and near-
surface weathered terrace deposits are typically porous, loose·, and subject to
settlement. These soils are considered potentially compressible in their existing
state, and have a moderate potential for hydrocollapse or hydrocompression; thus,
colluvium/topsoil, artificial fill; and weathered near-surface terrace deposits onsite
may settle appreciably under additional fill, foundation, or improvement loadings.
Depth of removals are outlined in the conclusions and recommendations section of
this report. In general, removals will be on the order of ±1 to ±2 feet across a
majority of the site.
Groundwater was-not encountered onsite and is generally not anticipated to affect
site development, providing that the recommendations contained in this report are
incorporated into final design and construction, and that prudent surface and
-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,1
I
I
I
•
•
•
•
subsurface drainage practices are incorporated into the construction plans. Perched
groundwater conditions along zones of contrasting permeabilities may not be
precluded from occurring in the future as a result of site irrigation, poor drainage
conditions, or damaged utilities. Should perched groundwater conditions develop,
this office could · assess the affected area(s) and provide the appropriate
recommendations to mitigate the observed groundwater conditions.
Our laboratory test results indicate that soils onsite are generally very low in
expansion potential, per the 1997 UBC. Typical samples of the site materials were
analyzed for corrosion/soluble sulfate potential. The testing included determination
of pH, soluble sulfates, and saturated resistivity. At the time of this report the results
were not available. An addendum to this report will be issued when the testing is
complete.
Field mapping in the site vicinity, noted the presence of numerous paleoliquefaction
(ancient) features_ ("sand blows," liquefaction craters, sand filled fissures and
injection dikes, sand vents, etc.), which may also exist within the site. Potential
liquefaction in such areas (in the future) impacting surface improvements is
considered very low, provided that the recommendations presented in this report are
incorporated into design and construction of this project.
Based on our review, the site is expected to have a low risk to be affected by seismic
hazards. The seisrnicity acceleration values provided herein should be considered
during the design of the proposed development.
The geotechnical design parameters provided herein should be considered during
project planning design and construction by the project structural engineer and/or
architects.
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
W.O. 3344-A-SC
Page Two
GeoSoils, lne.
I.
I The opportunity to be of service is sincerely appreciated. If you should have any questions,
please do not hesitate to contact our office.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Respectfully submitted,
GeoSoils, Inc.
~~E
C-1fry~1-_ E. yoss
Staff Geologist
BV/JPF/DWS/jh
Distribution: (4) Addressee
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
Page Three
1·
I
1·
I
I
I
I
·1
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONTENTS
SCOPE OF SERVICES .................................................... 1
SITE DESCRIPTION AND PROPOSED DEVELOPMENT .......................... 1
FIELD STUDIES ..................................... ~ .................... 3
REGIONAL GEOLOGY .................................................... 3
EARTH MATERIALS ....................................................... 3
. Colluvium/fopsoil (Not Mapped) ....................................... 3
Terrace Deposits (Map Symbol -Qt) .................................... 5
FAULTING AND REGIONAL SEISMICITY ...................................... 5
Faulting ........................................................... 5
Seismicity ......................................................... 7
Seismic Shaking Parameters .......................................... 8
Seismic Hazards .................................................... a
OTHER GEOLOGIC HAZARDS .............................................. 9
GROUNDWATER ......................................................... 9
LIQUEFACTION ......................................................... 1 O
LABORATORY TESTING .................................................. 10
Laboratory Standard ................................................ 1 o
· Expansion Potential ................................................. 11
Shear Testing ..................................................... -11
Corrosion/Sulfate Testing ........... ·, ~--·· ~ . ; ........ , .................. 11
DISCUSSION AND CONCLUSIONS ......................................... 12
General .......................................................... 12
Earth Materials .................................................... 12
Colluvium/f.opsoil ............................................ 12
Artificial fill ............... ~ . , . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... 12
Terrace Deposits ............................................. 12
Expansion/Corrosion Potential ....................................... 13
Subsurface and Surface Water ....................................... 13
Regional Seismic Activity ................................. : .......... 13
EARTHWORK CONSTRUCTION RECOMMENDATIONS ........................ 13
General .............. ; ........................................... 13
Site Preparation ................................................... 14
Removals (Unsuitable Surficial Materials) ............................... 14
Fill Placement ..................................................... 14
Overexcavation .................................................... 14
·, GeoSo~ls, fne.
1·
·I
I
I
I
·1
I
I
I
I
I
I
I
1·
1·
I
I
I
I
RECOMMENDATIONS -FOUNDATIONS ..................................... 15
General ............................................................ 15
Conventional Foundation Design ..................................... 15
Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Expansion Classification -Very Low (E.I. O to 20) ......................... 16
EXTERIOR FLA TWORK ................................................... 17
.
CONVENTIONAL. RETAINING WALLS ....................................... 18
General .......................................................... 18
Restrained Walls ............................. · ...................... 18
Cantilevered Walls ................................................. 18
Wall Backfill and Drainage ........................................... 19
Retaining Wall Footing Transitions .................................... 19
Footing Excavation Observation .... · .................................. 20
DEVELOPMENT CRITERIA ................................................ 20
Landscape Maintenance and Planting ................................. 20
Additional Site Improvements ........................................ 20
Trenching ......................................................... 21
Drainage .......................................................... 21
Utility Trench Backfill ............................................... 21
PLAN REVIEW .......................................................... 22
INVESTIGATION LIMITATIONS ............. ; ............................... 22
FIGURES:
Figure 1 -Site Location Map .......................................... 2
Figure 2 -Geotechnical _Map .......................................... 4
Figure 3 -California Fault Map·.·,:.=: .. :.: ...... ;, .... , ...... ~ ... _. .• ,. ......... :. 6
ATTACHMENTS:
Appendix A -References .................................... Rear of Text
Appendix B -Boring Logs ................................... Rear of Text
Appendix C -Laboratory Data .............................. · .. Rear of Text
Appendix D -General Earthwork and Grading Guidelines .......... Rear of Text
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
Table of Contents
Page ii
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
·1
PRELIMINARY GEOTECHNICAL EVALUATION
470 CHINQUAPIN AVENUE
CARLSBAD, SAN DIEGO C,OUNTY, CALIFORNIA
SCOPE OF SERVICES
The scope of our services has included the following:
· 1. Review of readily available soils and geologic data {Appendix A).
2. Subsurface exploration consisting of the excavation off our exploratory hand auger
borings in the area of proposed improvements, for geotechnical logging and
sampling {Appendix B).
3. Laboratory testing of representative soil samples collected during our subsurface
exploration· program {Appendix C).
4. Appropriate engineering and geologic analysis of data collected and preparation of
this report.
SITE DESCRIPTION AND PROPOSED DEVELOPMENT
The site consists of a roughly rectangular shaped parcel located on the north side of
Chinquapin Avenue in Carlshad, San Diego County, California (see Site Location Map,
Figure 1). There is an existing two-story single family residence at the south end of the
property. The existing site is surrounded by housing developments. Overall, the property
is relatively level with a gently sloping gradient to the southwest. According to a USGS
1968 {photo revised 1975) San Luis Rey Quadrangle. map, the subject site is approximately
±50 feet above Mean Sea l,..evel (MSL).
It is our understanding that the proposed site development will consist of a lot split and
preparing a new pad for the construction of a two-story single-family residence at the north
end of the property. Cut and fill grading techniques would be utilized to create design
grades for the proposed single-family residential structure with slab-on-grade floors and
continuous footings, utilizing wood-frame construction. Building loads are assumed to be
typical for this type of relatively light construction. The need for import soils is unknown.
GeoSoils, Jne.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
l ,.
: l},133",9,5; ...... ~~--.;+...--=-,,----¥.i-~r-
i
--,,. .•
0 2.000 40.00
Scale: Feet
i
\ \
N
w.o.
3'3'44-A-SC
SITE LO-CATION MAP
Figure 1
I
-1
I
I
I
I
I·
-I
I
I
I
I
I
I
I
I
I
I
I
FIELD STUDIES
Field studies conducted by GSI consisted of four exploratory hand auger borings for
evaluation of near-surface soil and geologic conditions. Borings were logged by a
geologist from our firm who collected representative bulk and undisturbed samples for
appropriate laboratory testing. Logs of the borings are presented in Appendix B. The
locations of the borings are presented on Geotechnical Map, Figure 2.
REGIONAL GEOLOGY
The subject property is located within a prominent natural geomorphic province in
southwestern California known as the Peninsular Ranges. It is characterized by steep,
elongated mountain ranges and valleys thattrend northwesterly. The mountain ranges are
underlain by basement rocks consisting of pre-Cretaceous metasedimentary rocks,
Jurassic metavolcanic rocks, and Cretaceous plutonic rocks of the southern California
batholith.
In the San Diego region, deposition occurred during the Cretaceous period and Cenozoic
era in the continental margin of a forearc basin. Sediments, derived from Cretaceous-age
plutonic rocks and Jurassic-age volcanic rocks, were deposited into the narrow, steep,
coastal plain and continental margin of the basin. These rocks have been uplifted, eroded
and deeply incised. During early Pleistocene time, a broad coastal plain was developed
·from the deposition of marine terrace deposits. During mid to late Pleistocene time, this
plain was uplifted, eroded, and incised. Alluvial deposits have since filled the lower valleys,
and young marine sediments are currently being deposited/eroded within coastal and
beach areas.
EARTH MATERIALS
Earth materials encountered on the site consist of colluvium/topsoil, artificial fill, and terrace
deposits. ·
Colluvlum/Topsoll {Not Mapped}
Surficial colluvium/topsoil was encountered in all borings excavated onsite.
Colluvium/topsoil materials consisted of brown, silty sand. The materials generally were
dry and loose with roots and rootlets. The thickness of the colluvium/topsoil is on the order
of ± ½ foot. These surficial soils are considered unsuitable for support of additional fill
and/or settlement sensitive improvements in-their existing state, owing to their potential for
hydrocollapse.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Page3
I
I
I
I
I
I
I
.I
I
·1
-I
I.
I
I
I
I
I
I
I
afu
Qt
~ --· ----------. -. -. ---. -------·'r --------. ·-~
'. ----~ , I : , I l . · t b I ! f afu \ Qt J , i
1 I ,1.--: • ·• ··--·-·, : • • • • • ,, --, -="
,1 ~i , . :-·. " B-4 •, .. ·: . " B-~ ·, I • : .. : • ·. ,:> . : -.:i: • .: . •.' PAOPOS:ED 2 CAA AND i
• 0 ---·~ ~-; •• .. O 2ND FLOOR F-l.o'\T . '?
'1 • • • i · • •• ·• • • •: ~ B 1 . • .. • .. , • " " •, ~ I ,: ~ -~ • I ' " . • .• ~ • • '-A .. !,~ .. _.... • ., .a:, f
!Qt';. > : . : . · · · ' : ... • -. ·: !-~ B-3 1
1
1 •
1 I ti a,• •' • I fi;, • .:,ii ! , .. It .. • 'I ,. • f I .. , ,
• I • ·~ •" ·~~•.,:..·...:.·-"~· .. •--11:---------------l 4 : l 1,_. a. • " .... • .,,,.... I • f •. • . ...... ~ __lL. ;_; •. ,,..
: • • ~ , ~ / /I 6' o·T'"""-------211· a.·~-~--. a• -O'-:?l •. • ,,. // , I
r .• I, I "t / f .. . . '
I 9 •1 \ • /
I I j • :. '° • • f
, I• ., ': • j I ·;· •• ·i L . .l,
-;,·'-T 0--71 17' c.:• ' I , •1 /
C I • ; • .. . i 1-· ------------
'
J. .. _ _.,.
I "' ..... ~ , I 1! • 1, ....
I ' . i ' • ' ' • • I j -~ t >: .. EXISTING .SINGLE
-------.&.6·~---
I ~
~ I f
i~·~ ': •• ···: :·, FAMILY DEWLLING
.. • • • I
•. I
• .... L. ~. ·(
1 :, -.z::. -:j GARAGE I
,. ·.·,; 2CAR ,
; • • • 61 "· '·J .,,.41} ··1 ••• -·~·"' ~ .. •1 ,:· I ••.•• I l II.,, " • , ~ 4, .,. r
I 1 , I I • t •• '• •,
• : .. • I • I Iii • . '.. . . . .. ~ .. ; .. .. • .. ... I
!• ,•. • ,,i "' I ., •• • • " .:• 4 • I
I 'Co, , -~ I . " . "
I( ~ IQ ... • • " Qt ... . -· .. •" ') . . ;
I. '.. •• ; I .. --e:
I I • •: t I "' • •~ ' 41,. • f : ~ ! . . " .. • • I
I I ~ • t i i:a : • ·~ '( " • 0 ~ • • • -" IJ ,. " I ' • "" • ; I I .. • •
I . I . • • . • • • .... I
I ,. I ! ! • • •• • •
t •• "' ""' I i •• a. • I
• : I •• I C • " • .. I ' ! 1 · : .··. ::·: ~ ·J l 1 . .':'. ~-· ~· .\ ._. : -~~ ~ I 1
I I ,, • •" 1 .. • • ! l_ J,_:. __ _:1t_: .. .1-..---·-----' ___ J...---~-:._k.:._.:·..___L. ___ j
LEGEND
Undocumented, artificial fifl
Quaternary Terrace depo~it-
Base map provided by client,
I .
, •
LOS ANGELES CO:
RIVERSIDE CO •
ORANGE CO .
SAN DIEGO CO.
...... --. Approximate location of geologic
contact GEOTECHNICAL MAP
Fi"gure 2: ; Approximate location of expJoratory
boring ' W.O. 3344-A-SC_ DATE 7 /02 SCALE. 1":10'.
I
-I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Artificial Fill (Map Symbol Afi
Artificial fill was encountered in Boring 8-4 excavated onsite. The artificial fill materials
consisted of brown, silty sand. These soils generally were dry and loose with roots and
rootlets. The thickness of the colluvium is on the order of ± 1 foot. This soil is considered
unsuitable for support of additional fill and/or settlement sensitive improvements in their
existing state, owing to their potential for hydrocollapse.
Terrace Deposits (Map Symbol -Qt)
The Quaternary-age terrace deposits underlie the entire site at depth. As encountered, the
terrace deposits generally consist of reddish brown to orange brown, silty sand, and are
medium dense to dense with depth. As a result of the relatively loose and weathered
condition of the upper±½ foot, these weathered sediments should be removed, moisture
·conditioned, and recompacted and/or processed in place, should settlement-sensitive
improvements be proposed.
FAUL TING AND REGIONAL SEISMICITV
Faulting
The site is situated in an area of active as well as potentially-active faults. Our review
indicates that there are no known active faults crossing the site within the areas proposed
for development (Tan and Kennedy, 1996), and the site is not within an Earthquake Fault
Zone.
There are a number offaults in the southern California area that are considered active and
would have an effect on the site in the form of ground shaking, should they be the source
of an earthquake. These include-but are -not limited to-the San Andreas fault, the
San Jacinto fault, the Elsinore fault, the Coronado Bank fault zone, and the
Newport-Inglewood/Rose Canyon fault zone. The location of these and other major faults
relative to the site are indicated on Figure 3. The possibility of ground acceleration or
shaking at the site may be considered as approximately similar to the southern California
region as a whole.
The following table lists the major faults and fault zones in southern California that could
have a significant effect on the site should they experience significant activity.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Pages
I·
I
I
I
I-
I
I
I
I
.I
I
I
·1
·I
I
I
!
I
I
I
\
I
SITE L0CATI0~_(:t
--L;tit~d_e_ -33.1485 N w
Lo.ngitude -117.3397
HENDRIX .
0
CALIFORNIA .FAULT
w .0. 3344-A-SC
50 100
SCALE
(Miles)
Figure 3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-
ABBREVIATED APPROXIMATE DISTANCE ..
FAULTNAME· . MILES (KM)
Coronado Bank-Agua Blanca 21 (33}
Elsinore 25 (40}
La Nacion 24 (39) .
Newport-Inglewood-Offshore 8 (12}
Rose Canyon · 4 (7)
-San Diego Trough-Bahia Sol 30 (48)
. Seismicity
The acceleration-attenuation relations of Joyner and Boore (1982}, Campbell and
Bozorgnia (1994), and Sadigh and others (1989} have been incorporated into EQFAULT
(Blake, 1997). For this study, peak horizontal ground accelerations anticipated at the site
were determined based on the random mean plus 1 -sigma attenuation curves developed
by Joyner and Boore (1982), Campbell and Borzorgnia (1994), and Sadigh and others
(1989}. These acceleration-attenuation relations have been incorporated in EQFAULT, a
computer program by Thomas F. Blake (1997), which performs deterministic seismic
hazard analyses using up to 150 digitized California faults as earthquake sources.
ihe program estimates the closest distance between each fault and a user-specified file.
If a fault is found to be within a user-selected radius, the program estimates peak horizontal
ground acceleration that may occur at the site from the upper bound ("maximum credible")
and 11maximum probable" earthquakes on that fault. Site acceleration (g) is computed by
any of the 14 user-selected acceleration-attenuation relations that are contained ·in
EQFAULT. Based on the abov~. peak horizontal ground accelerations from an upper bound
event may be on the order of 0.65 g to 0.79 g, and a "maximum probable" event may be
on the order of 0.32 g to 0.46 g, assuming an earthquake, on the Rose Canyon fault zone,
located approximately 4.6 miles from the subject site.
Historical site seismicity was evaluated utilizing the computer program EQSEARCH (Blake,
1989}. This program performs a search of historical earthquake records, for magnitude 5.0
to magnitude 9.0 within a specified radius (e.g., 100 miles), between the years 1800 to
2002. Based on the selected acceleration-attenuation relation, a peak horizontal ground
acceleration is estimated, which may have affected the site during the specific seismic
event listed. In addition, site specific probability of exceeding various peak horizontal
ground accelerations and seismic recurrence curves are also estimated/generated from the
historical data. The maximum horizontal peak ground acceleration experienced by the site
during the period of 1800 to June, 2002 was estimated to be about 0.8 g corresponding to
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, Ine.
, ;.· '
W.O. 3344-A-SC
July 29, 2002
Page7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-I
I
I I
an earthquake of about M 6.5 approximately 11 miles away, that occurred on
November 22, 1800.
A probabilistic seismic hazards analysis was also performed using FRISKSP (Blake, 1997),
which models earthquake sources as lines and evaluates the site specific probabilities.
Based on a review of these data and considering the relative seismic activity of the
southern California region, a horizontal peak ground acceleration in the range of 0.28 g to
0.33 g was obtained. These values were considered as they correspond to a 1 O percent
probability of exceedance in 50-years (or a 475 year return period).
Seismic Shaking Parameters
Based on the site conditions, Chapter 16 of the Uniform Building Code (International
Conference of Building Officials, 1997),. the following seismic parameters are provided:
Seismic zone (per Figure 16-2*} 4
Seismic Zone Factor (per Table 16-1*} 0.40
Soil Profile Type (per Table 16-J*) So
Seismic Coefficient c. (per Table 16-Q*) 0.44 Na
Seismic Coefficient Cv (per Table 16-R*) 0.64 NV
Near Source Factor N. (per Table 16-S*) 1.0
Near Source Factor Nv (per Table 16-T*) 1.15
Seismic Source Type (per Table 16-U*) B
Distance to Seismic Source 4.1 mi (6.5 km}
Upper Bound Earthquake Mw6.9
* Figure and table references from Chapter f6 of the Uniform Building Code (1997}.
Seismic Hazards
. The following list includes other seismic related hazards that have been considered during
our evaluation of the site. The hazards listed are considered negligible and/or completely
mitigated as a result of site location, soil characteristics and typical site development
procedures:
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Pages
I
I
I
I
I
1.
I
I
I
I
I
I
I
I
I
I
I
I
I
• Liquefaction
• Dynamic Settlement
• Surface Fault Rupture
• Ground Lurching or Shallow Ground Rupture
• Tsunami
It is important to keep in perspective that in the event of a maximum probable or credible
earthquake occurring on any of the nearby major faults, strong ground shaking would occur
in the subject site's general area. Potential damage to any structure(s} would likely be
greatest from the vibrations and impelling force caused by th~ inertia of a structure's mass,
than from those induced by the hazards considered above. This potential would be no
greater than that for other existing structures and improvements in the immediate vicinity.
OTHER GEOLOGIC HAZARDS
Mass wasting refers to the various processes by which earth materials are moved down
slope in response to the force of gravity. Examples of these processes include slope creep,
surficial failures, and deep-seated landslides. Creep is the slowest form of mass wasting
and generally involves the outer 5 to 1 o feet of a slope surface. During heavy rains, such
as those in 1'969, 1978, 1980, 1989, 1993, and 1998 creep-affected materials may become
saturated, resulting in a more rapid form of downslope movement {i.e., landslides and/or
surficial failures}. The site topography is very flat lying, no such slopes are proposed, and
indications of deep seated landsliding on the site were not observed during our site
reconnaissance. Therefore, the potential for seismically induced landsliding is considered
nil.
GROUNDWATER
Subsurface water was not encountered within the property during field work performed in
preparation of this report. Subsurface water is not anticipated to adversely affect site
development, provided thatthe recommendations contained in this report are incorporated
into final design and construction. These observations reflect site conditions at the time of
our investigation and do not preclude future changes in local groundwater conditions from
excessive irrigation, precipitation, or that were not obvious, at the time of our investigation.
Seeps, springs, or other indications of a high groundwater level were not noted on the
subject property during the time of our field investigation. However, seepage may occur
locally (as a result of heavy precipitation or irrigation} in areas where fill soils overlie terrace
deposits. Depth to the regional water table is anticipated to be greater than 50 feet below
existing grade.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Page9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
LIQUEFACTION
Liquefaction describes a phenomenon in which cyclic stresses, produced by earthquake
induced grou·nd motion, create excess pore pressures in relatively cohesionless soils.
These soils may thereby acquire a high degree of mobility, which can lead to lateral
movement sliding, consolidation and settlement of loose sediments, sand boils, and other
. · damaging deformations. This phenomenon occurs only below the water table, but after
liquefaction has developed, it can propagate upward into overlying, non-saturated soil, as
. excess pore water dissipates.
Liquefaction susceptibility is related to numerous factors and the following conditions must
exist for liquefaction to occur: 1) sediments must be relatively young in age and not have
developed large amount of cementation; 2) sediments must consist mainly of medium to
fine grained relatively c;:ohesionless sands; 3) the sediments must have low relative density;
4) free groundwater must be present in the sediment; and 5) the site must experience
seismic event of a sufficient duration and large enough magnitude, to induce straining of
soil particles. At the subject site, three of the five conditions which are necessary for
liquefaction to occur exist, and the site may or may not experience the other two.
One of the primary factors controlling the potential for liquefaction is depth to groundwater.
Liquefaction susceptibility generally decreases as the groundwater depth increases for two
reasons: 1) the deeper the water table, the greater normal effective stress acting on
saturated sediments at any given depth and liquefaction susceptibility decreases with
increased normal effective stress; and 2) · age, cementation, and relative density of
sediments generally increase with depth. Thus, as the depth to the water table increases,
and as the saturated sediments become older, more cemented, have higher relative
density, and confining normal stresses increase, the less likely they are to liquefy during a
seismic event. Typically, liquefaction has a relatively low potential where groundwater is
greater than 30 feet deep, and virtually unknown below 60 feet. Mitigation of liquefaction
potential is also accomplished by the incorporation of our grading guidelines foundation
. design parameters into project planning design and construction.
LABORATORY TESTING
Laboratory tests were performed on a representative sample of representative site earth
materials in order to evaluate their physical characteristics. Test procedures used and
results obtained are pres~nted below. ·
Laboratory Standard
The maximum density and optimum rn9i§ture content was determined for the major soil
type encountered in the borings. The laboratory standard used was ASTM D-1557. The
moisture-density relationship obtained for this soil is shown in the following table:
Mr. Ed Hendrix ·
470 Chinquapin Avenue, Carlsbad .
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Page 10
I
I
I
I
I
I-
I
I
I
I
I
I
I
I
I
I
I
I
I
MAXIMUM DENSITY OPTIMUM MOISTURE
LOCATION SOIL TYPE (PCF) CONTENT(%)
8-1 @0-4' Silty Sand, Brown 133.5 9.5
Expansion Potential
Expansion testing was performed on representative samples of site soil in accordance with
UBC Standard 18-2 {UBC, 1997). The results of expansion testing are presented in the
following table.
Shear Testing
Shear testing was performed on a representative, "remolded" sample of site soil in general
accordance with ASTM test method D-3080 in a Direct Shear Machine of the strain control
type.· The shear test results are presented as in Plate C-1 in Appendix C, and as follows:
-' : : .... _., ."' ' :.,·:<:::.: i·.-i,<(:.: .. ' .. p~~MA~4..;.': :: :.':_: ' ·.-_:-. '', .·.: ,', :··. RESIDUAL' ~ ::·::_./i ·sAM-~(e:: ·, ; · > · ... -,-.; =-: ... .-:··: :· ·:.-: : .. ,.:1-., ...... ·,· .. ·: · :i. . .-.= .-.-_._.. -·· . . ...
:-_:'.' LOCATiON ·:·, s.;·:·.:c61-fEs'1otf:' . ..: '.:=:.·.FR_ICTIO~: < ·_. .... COH,ESION '-: .. .'_:_·_·. FRICTION '
,:i:'r~:,i·r::_;-\:::::;-.·: __ :_ {.:,:.::/;::· ... }PS,f(\.;::\·_\::·. ·.::Jo:~~~~S)': '. ::_·: '_·.·(PSF)'.-' ,: ·:-::·--.,~:~~~~S).
8-1@0-4'
(remolded) 177
Corrosion/Sulfate Testing
33 165 31
Typical samples of the site materials were analyzed for corrosion/soluble sulfate potential.
The testing included determination of pH, soluble sulfates, and saturated resistivity. At the
time of this report the results were not available. An addendum to this report will be issued
when the testing is complete.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3~44a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Page 11
I·
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
DISCUSSION AND CONCLUSIONS
General
Based on our field exploration, laboratory testing, and geotechnical engineering analysis,
it is our opinion that the subject site i's suitable for the proposed development from a
geotechnical engineering and geologic viewpoint, provided that the recommendations
presented in the following sections are incorporated into the design and construction
phases of site development. The primary geotechnical concerns with respect to the
proposed development and improvements are:
• Earth materials characteristics and depth to competent bearing material.
• Expansion and corrosion potential of site soils.
• Subsurface water and potential for perched water.
• Regional seismic activity .
. The recommendations presented herein consider these as well as other aspects of the site.
In the event that any significant changes are made to proposed site development, the
conclusions and recommendations contained in this report shall not be considered valid
unless the changes are reviewed and the recommendations of this report verified or
modified in writing by this office. Foundation design parameters are considered preliminary
until the foundation design, layout, and structural loads are provided to this office for review.
Earth. Materials
Colluvium/Topsoil
Colluvium/topsoil materials are generally dry and loose, susceptible to hydrocollapse and
do not meet the current industry minimum standard of 90 percent (or greater) relative
compaction. Recommendations for the treatment of colluvium/topsoil are presented in the
earthwork section of this report.
Artificial fill
Artificial fill materials are generally dry and loose, susceptible to hydrocompression and do
not meet the current industry minimum standard of 90 percent (or greater) relative
compaction. Recommendations for the treatment of artificial fill are presented in the
earthwork section of this report.
Terrace Deposits
Terrace deposits will be encountered ~wing site earthwork. The upper±½ foot of the
terrace deposits are weathered and should be removed and recompacted. Below the
-weathered zone, the materials are considered comp~tent to support settlement-sensitive
structures in their existing state.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
Geo.Soils, lne. . .
W.O. 3344-A-SC
July 29, 2002
Page 12
I
I
I
I
I
I
I
-I
I
I
I
I
I
I
I
I
I
I
I
Expansion/Corrosion Potential
Our laboratory test results indicate that soils with a very low expansion potential (expansion
index [E.1.] range Oto 20). This should be considered during project design. Foundation
design and construction recommendations are provided herein for very low expansion
potential classifications.
Subsurface and Surface Water
Subsurface and surface waters, as discussed previously, are not anticipated to affect site
development, provided that the recommendations contained in this report are incorporated
into final design and construction· and that prudent surface and subsurface drainage
practices are. incorporated into the construction plans. Perched groundwater conditions
along fill/formational contacts and along zones of contrasting permeabilities may not be
precluded from occurring in the future during grading, or as a result of site irrigation, poor
drainage conditions, or damaged utilities. Should perched groundwater conditions develop,
this office could assess the affected area(s) and provide the appropriate recommendations
to mitigate the observed groundwater conditions.
The groundwater conditions observed and opinions generated were those at the time of our
investigation. Conditions may change with the introduction of irrigation, rainfall, or other
factors that were not obvious at the time of our investigation.
Regional Seismic Activity
the seismic acceleration values provided herein should be considered during the design
of the proposed development.
EARTHWORK CONSTRUCTION RECOMMENDATIONS
General
All grading should conform to the guidelines presented in Appendix Chapter A33 of the
Uniform Building Code, the requirements of the City of Carlsbad, and the Grading
Guidelines presented in Appendix D, except where specifically superseded in the text of this
report. Prior to grading, a GSI representative should be present at the preconstruction
meeting to provide additional grading guidelines, if needed, and review the earthwork
schedule.
During earthwork construction all site preparation and the general grading procedures of the
contractor should be observed and the fill selectively tested by a representative(s) of GSI.
If unusual or unexpected conditions are ·exposed in the field, they should be reviewed by
this office and if warranted, modified and/or additional recommendations will be offered.
All applicable requirements of local and national construction and general industry safety
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge ·
GeoSoils, Ine.
W.O. 3344-A-SC
July 29, 2002
Page 13
I
·I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
orders; the Occupational Safety and Health Act, and the Construction Safety Act should be
met.
Site Preparation
Debris, vegetation and other deleterious material should be removed from the building area
prior to the start of grading. Sloping areas to receive fill should be properly benched in
accordance with current industry standards of practice and guidelines specified in the
Uniform Building Code.
Removals (Unsuitable Surficial Materials)
As a result of the relatively loose/soft condition of colluvium/topsoil, artificial fill, and
weathered terrace deposits, these materials should be removed and recompacted in areas
proposed for settlement sensitive structures, or areas to receive compacted fill. Atthis time,
removal depths on the order of ± 1 to ±2 feet should be anticipated; however, locally
deeper removals may be necessary. Removals should be completed below a 1 :1
projection down and away from the outside bottom edge of any settlement sensitive
structure and/or limits of proposed fill. Once removals are completed, the exposed bottom
should be reprocessed and compacted.
Fill Placement
Subsequentto-ground preparation, onsite soils may be placed in thin (±6-inch) lifts, cleaned
of vegetation and debris, brought to a least optimum moisture content, and compacted to
achieve a minimum relative compaction of 90 percent. If soil importation is planned, a
sample of the soil import should be evaluated by this office prior to importing, in order to
assure compatibility with the onsite site soils and the recommendations presented in this
report. Import soils (if any) for a fill cap should be very low expansive (E.I. less than 20).
· The use· of subdrains at the bottom of the fill cap may be necessary, and subsequently
recommended based on compatibility with onsite soils.
Overexcavation
In order to provide for the uniform support of the planned structure, a minimum 3-foot thick
fill blanket is recommended for the graded pad. Any cut portion of the pad for the residence
should be overexcavated a minimum 3 feet below finish pad grade. Areas with planned fills
less than 3 feet should be overexcavated in order to provide the minimum fill thickness. Fill
thickness should not exceed a ratio of 3: 1 (maximum to minimum) across the building
areas. This overexcavation should be performed 5 feet outside the building footprint.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils,. Ine.
W.O. 3344-A-SC
July 29, 2002
Page 14
I
I
I
I
I
I
I
I
I
·1
I
I
I
·I
I
I
I
I
I
RECOMMENDATIONS-FOUNDATIONS
General
Recommendations for conventional foundation system are reiterated and/or provided in the
following sections. Conventional foundations may be utilized for soils with Expansion
Indices (E.I.) of less than 20 (E.I. very low classification). The foundation system may be
used to support the proposed structure, provided they are fouAded in competent bearing
material. The proposed foundation systems should be designed and constructed in
accordance with the guidelines contained in the Uniform Builc;ling Code, and in accordance
with the recommendations of the project structural engineer.
Conventional Foundation Design
1.
2.
3.
4.
5.
Conventional spread and continuous footings may be used to support the proposed
residential structure provided they ~re founded entirely in properly compacted fill or
other competent bedrock.
Analyses indicate that an allowable bearing value of 1,500 pounds per square foot
may be used for design of footings which maintain a minimum width of 12 inches
(continuous) and 24 inches square (isolated), and a minimum depth of at least
12 inches into the properly compacted fill or bedrock. The bearing value may be
increased by one--third for seismic or other temporary loads. This value may be
increased by 200 pounds per square foot for each additional 12 inches in depth, to
a maximum of 2,500 pounds per square foot. No increase in bearing value for
footing width is recommended.
For lateral sliding resistance, a 0.35 coefficient of friction may be utilized for a
concrete to soil contact when multiplied by the dead load.
Passive earth pressure may be computed as an equivalent fluid having a density of
250 pounds per cubic foot with a maximum earth pressure of 2,500 pounds per
square foot.
When combining passive pressure and frictional resistance, the passive pressure
component should be reduced by one-third.
6. All footings should maintain a minimum 7-foot horizontal distance between the base
of the footing and any adjacent descending slope, and minimally comply with the
guidelines depicted on Figure No. 18-1-1 of the UBC (1997).
Construction
The following foundation construction recommendations are presented as a minimum
criteria from a soils engineering viewpoint. The onsite soils expansion potentials are
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, Jne.
W.O. 3344-A-SC
July 29, 2002
Page 15
I • I I
I
I
I
1·
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1·
generally in the very low range (Expansion Index [E.1.] Oto 20). Recommendations by the
project's design-structural engineer or architect, which may exceed the soils engineer's
recommendations, should take precedence over the following minimum requirements.
-Expansion Classification -Very Low (E.I. o to 20}
1. -Continuous exterior footings should be founded at minimum depths of 12 and
18 inches below the lowest adjacent ground surface, for one-or two-story floor loads,
respectively, and in accordance with the minimum requirements of the latest edition
of the Uniform Building Code. The project structural engineer should review and
approve these recommendations. Continuous interior footings may be founded at
a minimum depth of 12 inches below the lowest adjacent ground surface. Footings
should be a minimum of 12 inches wide, or as determined by the structural engineer.
2. .All footings should have one No. 4 reinforcing bar placed at the top and one No. 4
reinforcing bar-placed at ttie bottom of the footing. Isolated interior or exterior piers
and columns should be founded at a minimum depth of 18 inches below the lowest
_adjacent ground surface, and in accordance with the structural engineers
recommendations.
3. A grade beam, reinforced as above, and at least 12 inches square, should be
provided across the garage entrances. The base of the reinforced grade beam
should be at the same elevation as the adjoining footings.
4. Concrete slabs in residential and garage areas should be underlain with a vapor
barrier consisting of a minimum of 6-mil, polyvinyl-chloride membrane with all laps
sealed. This membrane should be covered with a minimum of 2 inches of sand to
_ aid in uniform curing of the concrete (2 inches of sand total).
· 5. For pads with very low expansion indices (E.I. Oto 20), concrete slabs, including
garage slabs, should be reinforced with No. 3 reinforcement bars placed on 18-inch
centers, in two horizontally perpendicular directions (i.e., long axis and short axis).
All slab reinforcement should be supported to ensure proper mid-slab height
positioning during placement of the concrete. "Hooking" of reinforcement is not an
acceptable method of positioning.
6. Garage slabs should be poured separately from the residence footings and be
quartered with expansion joints or saw cuts. A positive separation from the footings
should be maintained with expansion joint material to permit relative movement.
7. The residential and garage slabs should have a minimum thickness of 4 inches, and
the slab subgrade should be free of loose and uncompacted material prior to placing .
concrete. The design engineer should determine the actual thickness of concrete
slabs based upon proposed loading and use.
Mr. Ed Hendrix .
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Page 16
I
I
I
I
I
1·
I
I
1·
·I
I
I
I
I
I
I
I
I
I
8. Presaturation is not necessary for these soil conditions; however, the moisture
content of the subgrade soils should be equal to or greater than optimum moisture
to a depth of 12 inches below the adjacent ground grade in the slab areas, and
verified by this office within 72 hours of the vapor barrier placement.
·9. As an· alternative, an engineered post-tension foundation system may be used.
Recommendations for post-tensioned slabs can be provided on request.
10. Soils generated from footing excavations to be used onsite should be compacted to
a minimum relative compaction 90 percent of the laboratory standard, whether it is
to be placed inside the foundation perimeter or in the yard/right-of-way areas. This
material must not alter positive drainage patterns that direct drainage away from the
structural areas and toward the s~reet.
1 t. Design of proposed pools and other appurtenant structures should be reviewed by
GSI.
EXTERIOR FLATWORK
Exterior driveways, walkways, sidewalks, or patios, using concrete slab on grade
construction should be designed and constructed in accordance with the following criteria:
1. Structural and driveway slabs should be a minimum 4 inches in thickness; all other
exterior slabs maybe a nominal 4 inches in thickness. A thickened edge (minimum
of 12 inches) should be constructed for all flatwork adjacent to landscape areas.
2. Slab subgrade (i.e., existing fill materials) should be compacted to a minimum
90 percent relative compaction and moisture conditioned to at or above the soils
optimum moisture content. This should be verified by this office at least 72 hours
prior to pouring concrete. The use of Class 2, Class 3, or decomposed granite (i.e.,
. DG) as a base for the concrete slab in non-vehicle traffic areas is not required.
3. The use of transverse and longitudinal control joints should be considered to help
control slab cracking due to concrete shrinkage or expansion. Two of the best ways
to control this movement is: 1) add a sufficient amount of reinforcing steel, increasing
tensile strength ofthe slab; and/or 2) provide an adequate amount of control and/or
expansion joints to accommodate anticipated concrete shrinkage and expansion.
We would suggest that the maximum control joint spacing be placed on 5-to 8-foot
centers, or the smallest dimension of the slab, whichever is least.
4. No traffic should be allowed upon the newly poured concrete slabs until they have
been properly cured to within 75 percent of design strength.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbac;I
File:e:\wp7\3300\3344a.pge
Ge-,Soils, lne.
W.O. 3344-A-SC
July 29, 2002
Page 17
;J
I
I
I
I
I
I
I-
I
I
I
I
I
I
I
I
I
I
I
I
5. Positive site drainage should be maintained at all times. Water should not be allowed
to pond or seep into the ground. If planters or landscaping are adjacent to paved
areas, measures should be taken to minimize the potential for water to enter the
pavement section. This may be accomplished using thickened PCC pavement edges
and _concrete cut off barriers or deepened curbs, in addition to eliminating granular
base materials (i.e., Class 2, 3, D.G. etc.) underlying the slab.
6. In areas directly adjacent to a continuous source of moisture (i.e., irrigation,
planters, etc.), all joints should be sealed with flexible mastic.
7. Concrete compression strength should be a minimum of 2,500 psi.
CONVENTIONAL RETAINING WALLS
General
The design parameters provided below assume that very low expansive soils (such as Class
2 permeable filter material or Class 3 aggregate base) are used to backfill any retaining
walls. If high to very highly expansive soils are used to backfill the proposed walls,
increased active and at-rest earth pressures will need to be utilized for retaining wall design,
and may be provided upon request. Building walls, below grade, should be water-proofed
or damp-proofed, depending on the degree of moisture protection desired. The foundation
system for the proposed retaining walls should be designed in accordance with the
recommendations presented in the preceding sections of this report, as appropriate.
Footings should be embedded a minimum of 18 inches below adjacent grade (excluding
landscape layer, 6 inches). There should be no increase in bearing for footing width.
Restrained Walls
Any retaining walls that will be restrained prior to placing and compacting backfill material
or that have re-entrant or male corners, should be designed for an at-rest equivalent fluid
pressure (EFP) of 65 pounds per cubic foot (pcf), plus any applicable surcharge loading. For
areas of male or re-entrant corners, the restrained wall design should extend a minimum
distance of twice the height of the wall laterally from the corner.
Cantilevered Walls
The recommendations presented below are for cantilevered retaining walls up to 1 O feet
high. Active earth pressure may be used for retaining wall design, provided the top of the
wall is not restrained from minor deflections. An equivalent fluid pressure approach may be
used to compute the horizontal pressure against the wall. Appropriate fluid unit weights are
given below for specific slope gradient~ qfthe retained material. These do not include other
superimposed loading conditions such as traffic, structures, hydrostatic pressures, seismic
events or adverse geologic conditions. When wall configurations are finalized, the
appropriate loading conditions for superimposed loads can be provided upon request.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad ·
File:e:\wp7\3300\3344a.pge
GeoSoils, l ne.
W.O. 3344-A-SC
July 29, 2002
Page 18
I
I
I·
I
I·
I·
I
I
I
I
I
I
I·
I
I
I
I
I
I
SURFACE SLOPE OF EQUIVALENT SELECT
RETAINED MATERIAL FLUID WEIGHT MATERIAL
HORIZONTAL TO VERTICAL P.C.F. (Native soil) P.C.F.
Level 42 35
2to 1 60 45
The equivalent fluid density should be increased to 65 pounds per cubic foot for level backfill
at the angle point of the wall (corner or male re-entrant) and extended a minimum lateral
-distance of 2H (two times the wall height) on either side of the corner.
Wall Backfili and Drainage
The above criteria assumes that very low· expansive soils are used as backfill, and that
hydrostatic pressures are not allowed to build up behind the wall. Positive drainage must
be provided behind all retaining walls in the form of perforated pipe placed within gravel
wrapped in geofabric and outlets. A backdrain system is considered necessary for retaining
walls that are 2 feet or greater in height. Backdrains should consist of a 4-inch
diameter perforated PVC or ABS pipe encased in either Class 2 permeable filter material or
1/2-to ¾-inch gravel wrapped in approved filter fabric (Mirafi 140 or equivalent). The
filter material should extend a minimum of 1 horizontal foot behind the base of the walls and
upward at least 1 foot. Outlets should consist of a 4-inch diameter solid PVC or ABS pipe
spaced no more greater than ± 100 feet apart. The use of weep holes in walls higher than
· 2 feet should not be considered. The surface of the backfill should be sealed by pavement
or the top 18 inches compacted with relatively impermeable soil. Proper surface drainage
should also be provided. Consideration should be given to applying a water-proof
membrane to all retaining structures. The use of a waterstop should be considered for all
concrete and masonry joints.
Retaining Wall Footing Transitions
Site walls are anticipated to be founded on footings designed in accordance with the
recommendations in this report. Wall footings may transition from competent terrace
deposits to fill. If this condition is present the civil designer may specify either:
a) If transitions from terrace to fill transect the wall footing alignment at an angle of less
than 45 degrees (plan view), then the designer should perform a minimum 2-foot
overexcavation for a distance of two times the height of the wall and increase
overexcavation until such transition is between 45 and 90 degrees to the wall
alignment.
Mr. Ed Hendrix W. 0. 3344-A-SC
July 29, 2002
Page 19
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, Ine.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
b) Increase of the amount of reinforcing steel ·and wall detailing (i.e., expansion joints
or crack control joints) s1,Jch that an angular distortion of 1/360 for a distance of 2H
(where H =wall height in feet) on either side of the transition may be accommodated.
Expansion joints should be sealed with a flexible, non-shrink grout.
c) Embed the footings entirely into a homogeneous fill.
Footing Excavation Observation
All footing excavations for walls and appurtenant structures should be observed by the
geotechnical consultant to evaluate the anticipated near surface conditions prior to the
placement of steel or concrete. Based on the conditions encountered during the
observations of the footing excavation, supplemental recommendations may be offered, as
· appropriate.
DEVELOPMENT CRITERIA
Landscape Maintenance and Planting
Water has been shown to weaken the inherent strength of soil and slope stability is
significantly reduced by overly wet conditions. Positive surface drainage away from graded
slopes should be maintained and onlythe amount of irrigation necessary to sustain plant life
should be provided for planted slopes. Overwatering should be avoided.
Graded slopes constructed within and utilizing onsite materials would be erosive. Eroded
debris may· be minimized and surficial slope stability enhanced by establishing and
maintaining a suitable vegetation cover soon after construction. Plants selected for
landscaping should be light weight, deep rooted types which require little water and are
capable of surviving the prevailing climate. Compaction to the face offill slopes would tend
to minimize short term erosion until vegetation is established. In order to minimize erosion
on a slope face, an erosion control fabric (i.e., jute matting) may be considered.
From a geotechnical standpoint leaching is not recommended for establishing landscaping. ·
If the surface soils area processed for the purpose of adding amendments they should be
recompacted to 90 percent relative compaction.
Additional Site Improvements
Recommendations for additional grading, exterior concrete flatwork design and construction,
including driveways, can be provided upon request. If in the future, any additional
improvements are planned for the site, recommendations concerning the geological or
geotechnical aspects of design and con~truction of said improvements could be provided
upon. request. · " ·
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, Ine.
W.O. 3344-A-SC
July 29, 2002
Page20
I
I
-I
I.
I
I
I
I
I
I
I
I
I
I
I
I
I-
I
I
Trenching
All footing trench excavations for structures and walls should be observed and approved by
a representative of this office prior to placing reinforcement. Footing trench spoil and any
excess soils generated ·from utility trench excavations should be compacted to a minimum
relative compaction of 90 percent if not removed from the site. All excavations should be
observed by one of our representatives and conform to CAL-OSHA and local safety codes.
GSI does not consult in the area of safety engineers.-·
In addition, the potential for encountering hard spots during footing and utility trench
excavations should be anticipated. If these concretions are encountered within the proposed
footing trench, they should be removed, which could produce larger excavated areas within
the footing or utility trenches.
Drainage
Positive site drainage should be maintained at all times. Drainage should not flow
uncontrolled down any descending slope. Water should be directed away from foundations
and not allowed to pond and/or seep into the ground. Pad drainage should be directed
toward the street or other approved· area. Roof gutters and down spouts should be
considered to control roof drainage. Down spouts should outlet a minimum of 5 feet from
the proposed structure or into a subsurface drainage system. We would recommend that
any proposed open bottom planters adjacent to proposed structures be eliminated for a
minimum distance of 1 O feet. As an alternative, closed bottom type planters could be
utilized. An outlet placed in the bottom of the planter, could be installed to direct drainage
·away from structures or any exterior concrete flatwork.
Utility Trench Backfill
1, All utility trench backfill in structural areas, slopes, and beneath hardscape features
should be brought to near optimum-moisture content and then compacted to obtain
a minimum relative compaction of 90 percent of the laboratory standard.
Flooding/jetting is not recommended for the site soil materials. As an alternative,
imported sandy material with a sand equivalence (S.E.) of 30 or greater, may be
flooded/jetted 1n shallow (±12 inches or less) under-slab interior trenches, only.
2, Sand backfill, unless trench excavation material, should not be allowed in exterior
trenches adjacent to and within an area extending below a 1 : 1 plane projected from
the outside bottom edge of the footing.
3. All trench excavations should minimally conform to CAL-OSHA and local safety
codes.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge ·
GeoSoils, Ine.
W.O. 3344-A-SC
July 29, 2002
Page 21
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4. · Soils generated from utility trench excavations to be used onsite should be
compacted to 90 percent minimum relative compaction. This material must not alter
· positive drainage patterns that direct drainage away from the structural area and
towards the street.
PLAN REVIEW
Final project plans should be reviewed by this office prior to construction, so that construction
is in accordance with this report. Based on our review, supplemental recommendations
and/or further geotechnical studies may be warranted. ·
INVESTIGATION LIMITATIONS
Inasmuch as our: study is based upon the site materials observed, selective laboratory
testing and engineering analysis, the conclusion and recommendations are professional
opinions. These opinions have been derived in accordance with current standards of
practice, and no warranty is expressed or implied. Standards of practice are subject to
change with time.
These opinions have been derived in accordance with current standards of practice, and no
warranty is expressed or implied. Standards of practice are subjectto change with time. GSI
assumes no responsibility or liability for work or testing performed by others, for our scope-
of-work was expressly limited to the evaluation of the sediments/soils underlying the
proposed residence. In addition, this report may be subject to review by the controlling
authorities.
Mr. Ed Hendrix
470 Chinquapin Avenue, Carlsbad
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
W.O. 3344-A-SC
July 29, 2002
Page 22
~ --. .,. . ,._,
'', ~-~ :,-
;;,:1· 't. ·,
'' t',.' -·. ' .
.",,,1 .. ,··:'
''. .
1.., ..,, • 1: -~
.. ._ '~· :·: .
,. I ..,. ~'
• -_,, J
.. _ -~. '.--: , ~
. ,:. \,,'. ',,
',,
,,, .-. ,: :,, -
' ~. -,' .. ,: ,; ... ·
~ •,• : I '
'.•',
,, . . ,
,.. ~ ',' . •. .,.,, ..
~-',-t,\ i' ... :·.~/>/: i'' __ ., .... , _'-t
', ,•.,.,,;· ···'·
. ,, ,.,
.. ~· --~~· ', ' ·_ .. ,,
' ~ -~~\,
. ',:
', \·-
-·-, t"
..
/ ' '''
,.
,'1 _. ·,: ., .,,
·. ,,._,
·L
~,'
,t,'
' ... ·. ~ '
.. ·,' .... <:':-·
.-• •, ''· ..
. _; .··,_ ·. ·._;_, : .
._• •• ,4•'
. ::, .. ~-_-', :·' ~ ..
r•':
j ',-:: : ~ . ~ ~ ' ... -· •.. ·: .... ,--:,' ; •'·':,.
' -/ ~ .... '
,\, :.•
'1, ••
".",',
', ,. ':'
··:_ .... -_.
.. ~
' , ' ~' ' -.:.' .· .. , ', .
·-,·. , ' -(' ..
',, >--.
,:,_. ..
,, ' ·-,~ ', ,, ~"~·; .....
;,,. ·'
• ·,i.1.
·;,\ ·-: , ',",
_, .t
:r :
;•'
-~ .. '.,, ..
. . :·
.f,,, i.
' '·
... ~-._· ~ .. : ': : .
:.:-·.-.. ,.:,_' -
• t .. ~ • -' .. _.: -~ .:t, '
' ' "--,--~_:·
,,.: },. ':"' > -; ,·
, •. , ,'•· ,' '1.•,,'. •. ;r ,; .,,
.,_ t '' :, ·,.' ', ,. ,.----•• <.,, ''._·,.· .<_·· \_ :;-' '• • '~l
·., ~-::' /, . ·~-~-
I•\•:.,' : : '·, < .,./
.. _.,:
·' ;_ ,, -~~;;~~t~it /:•,
1 ./.·· '·';: _-,
," 1-,;..,','
_.-.· .
·,. ~ '
' • ~; .p
'_ ', .. ~_ .:. ..
,: J .:,1'
•• .,.1··.'. ·,_
~ ! ' ,, ',
,/ '-. •'I:•
:::_.
,,, '.,' , ' ' ' .. ·<'./\ .., ti
•• _#'--,· -·-
' ........ ' I':
' ',
r,
, ... 1.',,-
·. . ' ' ,, ~
:, .... ,· .. :·
I _, -' ., .. ,_ , '<~ ,• ·, ,
'.,_,·,.,·-_·
·,;.
--:., ... . : '·
. ,. ··-_.,'.· ,.·:·'
_,.,_;.·,,
• ? ._~,.. -;
... , ' ',,
't,
.•!_'
--.-.:· ·, . '' ~ ~'
·' ',; ~,._ . ' .. , ; ,.,_ ...
:-.'
'.-·"
,•., '1:,.
~-,·, .·.-·-'. ; __ .
<:-; ·_
'. ,.~ -
:· .~ •'
• ,f ,. ,-.. --.. ,.
. ,,-
'''
.. ,,··,
.,, ~< :
' . :" .~·
' .... ,.
·, / J
...... ~' ' ·.
~-r' ·., -,;-
'•' ,,
-•1.,
.'. '• ' ' '1 '.. • •• .. -·. ~: . '.·' ,,, ·-·,: ~ .· '
'• . -~-~· ,,
'
. ' , .. ,,
:·._: . , . ~
... , <,• •
., .. · ','
l. ·~ ; .... ._. ~ '
,, '' .,. ~ '.: ,,-:,, ... :1. ~ . '
: :~ \' ~ '
,,,:·,
·"·: : . :.~ ... ~-. J,
:·\~.
. :.:..·.
''•''
,. :,, ..,J '
... . ·,~
',,., ,• ' .. -: :~..-' ,.: f ., •
•, ~' f_
:,:,~' :' 1 '•' < ~\:-.::I ·· ..
:' ··-·.,' ,...:· .. ,.
': i ·~ ,i • t ~.'-;:: ' ~:
. ;,, . .,
',,.' ·'r· :-··,·',"':,,.'
: : '
_..;'
,.'
. ~' ," .'
-,~_,·,'. "t .f, . :._'
·1:,•, ,!•."
!, :.,,!':
-.-..
'.-:,, ., .. ·,. \•
. ··,,· ..
'I ,,
• ·,1
:, ·~ ·-
-, . •' . _;. : ~_ .... ,
·~:, .
'. ~.
< .. .-
, ... ,! ~, ,' . ·.~ '
( -~ . -. : . ' .. . •\
' •. ~·"!, .~ :·
', :., .. :
-•,1 •
, :. : 5. -' -~ \ ,_
•./.
,--' ,., '
._;;. I,
:-',('. . ..~·-. ·~
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
APPENDIX A
REFERENCES
Blake, Thomas F., 1997, EQFAULT computer program and users manual for the
deterministic prediction of horizontal accelerations from digitized California faults.
Campbell, K.W., 1994, Empirical prediction of near-source ground motion from large
earthquakes, in Johnson, J.A., Campbell, K.W., and Blake, eds., T.F., AEG Short
Course, Seismic Hazard Analysis, June 18. ·
Greensfelder, R. W., 1974, Maximum credible rock acceleration from earthquakes in
California: California Division of Mines and Geology, Map Sheet 23.
Hart, E.W. and Bryant, W.A., 1997, Fault-rupture hazard zones in California: California
Department of Conservation, Division of Mines and Geology, Special Publication 42.
Housner, G. W., 1970, Strong ground motion in Earthquake Engineering, Robert Wiegel, ed.,
Prentice-Hall.
International Conference of Building Officials, 1997, Uniform building code: Whittier,
California.
· Jennings, C.W., 1994, Fault activity map of California and adjacent areas: California Division
of Mines and Geology, Map Sheet No. 6, scale 1 :750,000.
Joyner, W.B, and Boore, D.M., 1994 a, Estimation of response-spectral values as functions
of magnitude, distance and site conditions, in Johnson, J.A., Campbell, K.W., and
Blake, eds., T.F., AEG Short Course, Seismic Hazard Analysis, June 18.
__ ,.1994 b, Prediction of earthquake response spectra, in Johnson, J.A., Campbell, K. W.,
and Blake, eds.,T.F., AEG Short Course, Seismic Hazard Analysis, June 18.
Sadigh, K., Egan, J., and Youngs, R., 1989, Predictive ground motion equations reported in
Joyner, W.B., and Boore, D.M., 11Measurement, characterization, and prediction of
strong ground motion11, in Earthquake Engineering and Soil Dynamics II, Recent
Advances in Ground Motion Evaluation, Von Thun, J.L., ed.: American Society of Civil
Engineers Geotechnical Special Publication No. 20, pp. 43-102.
Sowers and Sowers, 1970, Unified soil classification system {After U. S. Waterways
Experiment Station and ASTM 02487-667) in Introductory Soil Mechanics, New York.
Tan, S.S., and Kennedy, Michael P., 1996, Geologic maps of the northwestern part of San
Diego County, California: California Division of Mines and Geology, Open File Report
96-02.
· · GeoSoils; lne.
. i
. ·, ,,1.,,
' -,' . ~
,,,,.·:.· '·•,
',•.
·' ' .. :. ' .. ·'. ':
'I!
' '·,." , ,.
,.. ··\' ,-.
' .,, .,
;, . ~ ..
•'':,.,;
.>---1
. ) ",;
.·•
:~,. '• . -.....
,~ :·. : · ..
' -,-~~
,..._ ,-
1. •,
;.\ ! ;/
'• , -: ,(.: ' '
' • r • • •
! .·'
1-··.,
• • \A' ,,•'
':,:,,
-:,·'
·._ ....... ..
.,· ./ ..
,'\~ '.I-'
-b:, ·-~·-'
. ' : ,. ~
,'', ',,,
'·,
--I' ',~•'
' . . ... ... .. , ..
. ; ·. : ,.: .. ,
,· ,.., ,.' ,-. --·~
-,_,. ,';1 ',
~·-. ', .-
' :·. ' ~ " . ~ i
··•. ',,,}
'•• ..
.· _.,.
' ·-(, : -
. [·. , ,,
l -:-·-:
, .. , '.
'' ,\.J -•.
.•
·,'
,, < •\
... '. -
• j '_,! : .... ~
. . ~~ . : .. '
'·.:.
.~ . .,. :.':
• C , , r •,. ·,' .. ~
·. ', ..
• ..
''; ··.,
'· )' ..
{.·· :,/·.··,
_,,:,
; ;,'• ·;,.•\"'.!'.,
. ~-,,, \ ','
·:.. ...
' .. , ,,
1, •••
I•.' ' ,!',. :,: .. +
;· ~
,•, ~' '-~-:' ·: '
;; :·:-\ ,-
' \./'· \.,:~\~-~--
•• , •t
··.:· . : ,, ..
,,.
~ ... , ..
:~ l, '
··'? ,
.. , !-.. :'·
~ _-, ·'. ',,,,-
' ....
. ' ,•.t.
_., .-1,,,; ...
. ,-......
,-•. ,·
• • f • ~ ; f._ :, • '\ : ··,, ..
';! • ', ,v
. . ' • !.' ~:;,.,. -
-',( ~ ' .. -,, ~ ~ . .·--
.-,_:·:::,
:.. .. , •, \, I";,
'~,/'·;,..
' . ... ,
_, ,.J : ~. · ...
··., '
-. : ·~,
A. ~: ~ ••• • •• f
'·'. { '.' :-·_. ~
. , :
# ··: • .-,',
'-·i' ',,.
-•• ' t
l \..--.
,, .. '
... ~-
.. ,._..,
··,, ,;
1. •
,,,,{ .. :
-~ .... -,,, . . ~ ..
.• : .,-,:•
,: : :'
-•,\)
. ~ --::-~ ~. ' "
,; • _ _l -
· .........
,. ',.-·,;
,, ::.,·
J '.. ·/'
, \ (
' ·,· . ' . ~-~
, , .
,: ,,. _;
·. ~ , :, .
•.' ·:·-·
...... .. ' ',.'' ·-~ . ·-·; ··_.:,,-,:
,::·,.,
'..,_• .. ~ a ' . ,• ~
:···:·,.--.--. . . ,,
£..'
,-·,,,
• ', >. ~.;, ;, .. . ' '• l ,.,_ .' . -~.
•-" ..
·· .. , ·~ '..;·: .. ,, '
~. . . \
'•~-. ...~·' ~ ,::,
-..... t : -
,: '' .,· •'"!1<,... .. ,, -.·, ·-··-;-.· .. , .... ·
', : • ' ~ ,, i
'{,'_,;··: •.• J
·c.' -··,:-·
. ,, ._,,,.
',-'_'
.. _ ..... ,, :: ·: ,,.,.
,-.~} ,'
.,-:
',/" ,• .,
'-''<
.~ ,'
-, '-~ ", ,t_' -·: ..
'·,
, ,. · .. ~. ·:--:.·
,,
• ... :
•,. -.·
,.1 ••
. ..
,-r.r. . :' .~-',c,.,:· . '
~-.--~ ~
, ........
;,' ";-_·'•I
.... ··-_:,. .<l -:: '
.1
I
I
I
I
I:
I
I
I
I
I
I
I
I
I
I
I
11
I
GeoSoils, Inc.
PROJECT: ED HENDRIX
470 Chinquapin Avenue
Sample
-~ "#. --E I Cl.):s :!i e?
i ~~ §-::I -~ UE .!!! a, :5 t5.a en>-~ 0
C Ill Ill ::>en C :::i:
·cu
~M
SM·
5-
-
-
-
-
10-
-
-
-
-
15-
-
~
-
-
20-
-
-
-
-
25-
-
-
-
-
470 Chinquapin Avenue
-~ ~
C .Q e ::I 'tu en
BORING LOG
w.o. 3344-A-SC
BORING 8-1 SHEEIJ_ OF 1 -
DATE EXCAVATED 7-10-02
SAMPLE METHOD: HAND AUGER .
m Standard Penetration Test
~ Undisturbed, Ring Sample A.I Water Seepage into hole
Description of Material
-~-· COLLUVIUMfTOPSOIL: r
. '-!". · ,® 0-½' SIL TY SAND, brown, drv, loose· roots and rootlets . ,o..r-. : WEATHERED TERRACE DEPOSITS: .:..--.
,•:-,:,:,,• : @ ½-1' SIL TY SAND, orange brown, damp to moist, loose to medium :0: : \dense. I .v-. ·~·. TERRACE DEPOSITS: -~--IRi 1-4' SIL TY SAND, reddish brown, moist, medium dense to dense. r
Total Depth= 4'
No Groundwater Encountered
Backfilled 7-10-02
-
GeoSoils, Inc. PLATE B-1
I
I
I
I
I
I
·I
-1
1.
I
I
I
I
I
I
I
I
I
I
GeoSoils, Inc.
PROJECT: ED HENDRIX
470 Chinquapin Avenue
Sample
.......
~C' c ~ E cn:S ~g_ ~
..c ~i ! ::,-.a '5.. .:it!. UE 1/J
:i -c-e ~ ·5 Cl), 6.a Cl) >,
C al al ::> Cl) C :E
~u
~II.A
SM
-
-
5-
-
-
-
-
10-
-
-
-
-·
15-
-
-
-
~
20-
-
-
-
-
25-
-
-
-
-
470 Chinquapin Avenue
....... ..,. -C ~ ::::,
1ii en
BORING LOG
w.o. 3344-A-SC
BORING B-2 SHEEI_1_ OF 1 -
DATE EXCAVATED 7-10-02
SAMPLE METHOD: HAND AUGER . m Standard Penetration Test
-~ Undisturbed, Ring Sample I\# Water Seepage into hole
Description of Material
.-...r-.· COLLUVIUM/TOPSOIL: r . '-!"'.· ""' 0-½' SIL TY SAND, brown, drv, loose· roots and rootlets . ,
,"(9',· WEATHERED TERRACE DEPOSITS: ,:..;.,
':--":'" : \
1
@ ½-1' SIL TY SAND, orange brown, damp to moist, loose to medium . ..,,....
,../"'-, : dense. I
-~-TERRACE DEPOSITS: . ..,,.... · , lfil 1-4' SIL TY SAND reddish brown moist. medium dense to dense. r
Total Depth = 4'
No Groundwater Encountered
Backfilled 7-10-02
-
GeoSoils, Inc. PLATE B-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
BORING LOG
GeoSoils, Inc. w.o .. __ 3344 __ -A_-s_c __
PROJECT: ED HENDRIX BORING B-3 SHEEIJ_ OF_1_
470 Chinquapin Avenue
DATE EXCAVATED ____ 7_-1....;.0_-0_2 ___ _
Sample SAMPLE METHOD,_: _H_A_ND_A_UG_E_R _____________ _
-~ $ E rn:S
~ cs
I °C c:: C.
i ~~ .! ::::,-
~ UE ~ CD "5 1:5::::, rn >-C IX! ,-CD ::::>rn C
m· Standard Penetration Test
~ Undisturbed, Ring Sample ~ Water Seepage into hole
Description of Material
c:u
C:P.A
SM
~---,--l----1---...j;.·.:;..'-('..;..J-,· · COLLUVIUM/TOPSOIL:
· '-('_ · -=--0-½' SIL TY SAND, brown drv, loose: roots and rootlets.
r
: ~:: WEATHERED TERRACE DEPOSITS: -
-
... ·:-r.·. @ ½-1' SIL TY SAND, orange brown, damp to moist, loose to medium :t:: dense. I
· _;....-:..: TERRACE DEPOSITS:
-1---1--1----1---1-----i----1----i-=·..,,,.=· ·-'h· ·, rm 1-4' SIL TY SAND, reddish brown moist medium dense to dense. /"
5-
.
. ·
10-
-
-
.
15-
.
.
-
-
20-
-
-
.
25-
-
-
-
470 Chinquapin Avenue
Total Depth= 4'
No Groundwater Encountered
Backfilled 7-10-02
GeoSoils, Inc. PLATE B-3
I
I
I
I
I
I
I
I
I
I
I
I
·1
I
I
I
I
I
I
GeoSoils, Inc.
PROJECT: ED HENDRIX
470 Chinquapin Avenue
Sample
...... '#. ......
Q) ..... .a .!!! 0 :E
BORING LOG
BORING 8-4
w.o •. __ 33_4_4-_A_-s_c __
SHEE[J_ OF_1_
~~~~~~D~ ___ 7_-_10~-_02 ___ _
SAMPLE METHOD,_: _H_A_ND_A_UG_E_R _____________ _
~ ffl Standard Penetration Test ...... j ~ Undisturbed, Ring Sample
1,-C' ,s 1------------.-.---------------l-
ci.i Description of Material
1\# Water Seepage into hole
SM . '-('. · ARTIFICIAL FILL:
-11--_-_-r_-_--+t-_-_-_--1tc~~l4j"::::::::::::.t::::::j"~::::::..r·....:;""::;;; ...;.+,·:4-:....,_~1mo~-:.!.1 '~S~IL!::..TY!..!...:S~A~Nl!!, D-:!.J,~b~ro~w!!.n!L.'· ~drv!.I.!...!, l~oo~s~e:i..· ~ro~o!!:ts~a!:!.!n~d!..!r~oo~t~le~ts!.:.... ____ --Jr
-
5-
-
-
-
-,
10-
-
-
-
15-
-
-
-
-
20-
-
-
-
-
25-
-
-
-
-
~u ::·: COLLUVIUM/TOPSOIL: ,
SM :.:;,.:. I® 1-1½' SILTY SAND, brown, drv, loose. 'r
· "'· .. WEATHERED TERRACE DEPOSITS:
::;::: \In) 1½-2' SILTY SAND oranoe brown, moist. medium dense .
. · ._. · TERRACE DEPOSITS: !
\
@ 2-4' SIL TY SAND, reddish brown, moist, medium dense to dense with
death.
Total Depth = 4'
No Groundwater Encountered
Backfilled 7-10-02
470 Chinquapin Avenue GeoSoils, Inc. PLATE 8-4
,_',• •'
:~. •,', ' r ', •• '
;)l:i/\ti ' ..
\ ·. .., .·. -.. ·.,. . ~ ~: . ,• ; :'
' ·, ' ·: -~ -
: ~ ,
_,,·;
·,l'· <1_:; ' . '
\. ··,·.· ., .. ,,.,'
;,
•.,,,
. ~. ' '
I ~/ ~ • • I
. ·~, ?, .. ' : ~'
I·~•'
' ,, .....
.··:
.. , •'!I'• ;·,
,·.
·'. '--.'.•
.. '
·.~ ·.
:.~ . ·:"
· ..
• I ,··'
< ·, • .::' -~ 1 •
',·1·
......
,.·:·, .. •', .-·
·,,·_:· .. ,· 1.
.r.-'
... ~ ,'
• ._', I
. ;, : ~ ) . .
~ .J. .... '•
; ;;
·,\,.,
. -.,
',' ,,.•, .... _.
·--··· ·,
._,_ \
,. . ,,~
' .. , ·,.
·,
.·1 ·
,.:•.·
··-,,"' . :. ,
", ,_ .. -/, ; ',•.
·:·, .,
' > ~ ',,.
'·
', .~ t
... ,\
:; : '( .· /' . ';, '· >·:,_-;_ ..
·J ,,.'' '!
•• , t
',, .-,,_.·
'': I
... ;-,.,.f,,
••• 1 •
' ,. 'C •
,·,.
''\'•
,..__,. ...
-,',·
·.·;·
';·\
~--'
·.'·· .. -:../.• .,. ,,. ,· ·:::"-'"' ' ... I .·,. ,· .. \,.,
,, ,, ' ,1 • : ,i. {~
• .. ,/ '· ~.
' : ~--
' -. ,: ~-, .. . -. ,·
•, .,.
': ~:;/ "). l ~ ;,', .·, 'L:.~/ .. •
' ..
. ,,
:·, .. ~-·,~ ', -~l -:
' .,,,
',. ,.
,· .'.
,,::
·-~--... ' --.' ,·,.
~ ;::1 I
• l'' ,. ... , ,.
'. -·, ,I -·:.-...
.-. ;. :'' :;~:'. :~~
_,. ; -,
! 1.; 1,,-•'
·,,, .
.· .. ; \
.,-,,_
't;.
·1.,·
·. : .
·.~'
~ ::. ; •',I
'·-i
,,t, ,,,· " .... ,.
. ,:· .. . ,_, ... ,,
.,,: ... y;, .
. ·~ 1: ·/,. {' --~· , ' .• •,1
. ' _.,.:: ·,
··:
. ~·, l
,::;,1
·1 . . . , ,,:,·'
',-.,
·.::~ ; ·-~ -~~· -~
-r··· .. ··-
~. '. · .. ',,
.,· ...... _,.,,el
,·-t, ·.·.i".' ,,
.... _._. ,,,
·-,. '\1' . : ..
' .. '~ -'\·.
-~ . ' ' '·''";-,.t ;._
...;. •: ' . :-~ ¥ • ~ -,
:. '·1 • ~;-' . •, A•',":·'','•'•
:,-.~ ·,,.
• t , '
' : ,;,,,.._._,.
' ~. ~:-< :"'.·/ /. '_:, •:
<, '/ . '
.'\ .
:'.,\
... ·,,,
t•-;:_
" ) . -~
:,
. ...
I
I
I
I
1·
I
I
I
·I
I
·1
I
I
I
I
I
I
I
I gi
3,000
2,500t-------t------+-,,-------+------t--------l-------l
Cl 0-----..,,,500~----.,..1,o""'o..,.o----~1,.,.,.so::-,o-----2_,_,oo--o-----2-',5-oo----....,3~,ooo
NORMAL PRESSURE, psf
Sample Depth/El. Primary/Residual Shear
• s~1 o.o Primary Shear
8-1 o.o Residual Shear
Note: Sample lnnundated prior to testing
GeoSoils, Inc.
57 41 Palmer Way.
Carlsbad, CA 92008
Telephone: (760) 438-3155
Fax: (760) 931-0915
Sample Type 'Yci MC% c
Remolded 120.1 9.5 177
Remolded 120.1 9.5 165
DIRECT SHEAR TEST
Project: HENDRIX
Number: 3344-A-SC
Date: July 2002 Figure: C-1
33
31
.... ______________________________________ ..
;·• r: ,:..;~·. : "
";'• ~-'1': •
•.• ; , .: .~ •. • r'-.
\ ,.,
. -·-•,'.'
' . ',\.
~ .... _
,,
---·1 '
' ~ '
•-..
,··-· .. _ ... -·
/_',,''.
'•·/,
·' . ;::; . -
I.:._.
'' •,:·-
\ .
,·
',1', ..... :.i ', • .._-,, ,> ,, l,
·; ~· :
•,, :,./.
.,
,._, :,·:·,,
_., •. ~: -,:.:"~ .. •
'• . -~ '
; .. ,
,. ... , ..
·.-.-.·.· '. ' '·
. , .
'·. ;~-, :· ",-,•
.. , .
I , • •
' ' ',• -~
'.· .~ .,· '. ,,_.
.' -~ . , ),,• : .
.: ""· .. ,:',,
•.-
.,,,--;_•
,·I\}'
I ', '','-;,
' -~' . . . . .~ •..
• ~ • I ' : • ·~, f
; •'/• ,·>~ :'.··.:•.'
.-.. _.'::,_ .. ,
... :, .
',:~', -:,:-:' ... ;:{ .. ~-~-. 1·, ."..:
1··:,.,._'': -. '•'
·.:·· ,: ...... ·,< .. '-· ~· '·'
' :·, •'
·, ... ,• ·,
',,',' ··:
·.' ,,' . ·' . ,, ,
',"'. ,',,·: ,·
, •. '" ,~· I
·.,
·~, • I I•'' ·:.::
·.:·:-,:·t\·:{,,:.: ~-! .{, ,:.:'.',
~ ~_..··, : ,·· ·,,;,·.~ '·." -~ .
. '''°-: ..... ·t-·, '_;·· :, ,,
', / :· ~· ' ' ':.~.·: .. , . ..
• • <,
·' 1,
' '··~ '! ' ·,'
•• > • -: L '" ~ T : .,_,_ ... :·
·v,'
. . ' ;
,-. ,.'--~ ..
.,' ~I.::~ ·, ,. ~. ' · ..
. "~ .. .. ,, , ' " '~
'; ~,
', ,,
;-v,
:,·,.-,.:' ~ ., ,-,
::-~.' . ,.
. ~· '. ... ,,:;,·'.
·' i•--:.'_
···:,
; ::·· ·~ : ,· . ·. :··· ,,: . ,
l,'.,::: :. ·. ;. \_ :-:_' ,:.~ '': . ' .
• • .f ', ••
.:.!,_.'·, I .1;
• ,. '• • ~I• , ; ·.' > ' .. -·~
·;· .... ·,',,," -·.
~, -.~ .,._, .. . ... .
;,
. ·.
.,t ..... _ , ,· ,··J l
',,
'.> J, •
'•, --~ ..
. ','•' .•·.·'-
' \ ~. . . /,\
·-,';' -_..,,.,.
l ·: • '11'" ~·
".: ,· t.-.... •.!_
, ~.. I, ·::< :, ~ ,,_,:\·
'--~'
_;, ·-,. :
•;·;· _,,
.' ', •,',,
·-,'. J.
::, .',;
.~ :-· ' -. ; ~ . '
•,,
,'',•
. ' ',•"'".
.. ~-,: , ( .
<':.·,
·' ,,
,:,,,),.-.. _ ... ,; ',.
;: ·_,. ~ _,
,_·;~ .\-,_
.... ·,
r ~ [ ..
i: ·., r ·,,·· • .::
·' •-1; -~
·' :,:·,.,.
' ,,", ,:· J
:, '~ , ~ ,.. • _i : -~ 'l
. 1: ·~ . -
... ~' "
·-~··. _...,.' .. : ,-::...; ,, :,.',_ .... ,.
I
I
-I
I
-I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GENERAL EARTHWORK AND GRADING GUIDELINES
General
These guidelines present general procedures and requirements for earthwork and grading
as shown on the approved grading. plans, including preparation of areas to filled, placement
of fill, installation of subdrains and excavations. The recommendations contained in the
geotechnical report are part of the earthwork and grading guidelines and would supersede
the provisions contained hereafter in the case of conflict. Evaluations performed by the
consultant during the course of grading may result in new recommendations which could
supersede these guidelines or the recommendations contained in the geotechnical report.
The contractor is responsible for the satisfactory completion of all earthwork in accordance
with provisions of the project plans .and specifications. The project soil engineer and
engineering geologist (geotechnical consultant) or their representatives should provide
observation and testing services, and geotechnical consultation during the duration of the
project.·
EARTHWORK OBSERVATIONS AND TESTING
Geotechnlcal Consultant
Prior to the commencement of grading, a qualified geotechnical consultant (soil engineer
and engineering geologist) should be employed for the purpose of observing earthwork
procedures and testing the fills for conformance with the recommendations of the
geotechnical report, the approved grading plans, and applicable grading qodes and
ordinances.
The geotechnical consultant should provide testing and observation so that determination
may be made that the work is being accomplished as specified. It is the responsibility of
the contractor to· assist the consultants and keep them apprised of anticipated work
schedules and changes, so that they may schedule their personnel accordingly.
All clean-outs, prepared ground to receive fill, key excavations, and subdrains should be
observed and documented by the project engineering geologist and/or soil engineer prior
to placing and fill. It is the contractors's responsibility to notify the engineering geologist and
soil engineer when such areas are ready for observation.
Laboratory and Field Tests
Maximum dry density tests to determine the degree of compaction should be performed in
accordance with American Standard Testing Materials test method ASTM designation D-
1557-78. Random field compaction tests should be performed in accordance with test
method ASTM designation 'D-1556-82, D-2937 or D-2922 and D-3017, at intervals of
~pproximately 2 feet of fill height or every 1 oo cubic yards of fill placed. These criteria
would vary depending on the soil conditions-and the size of the project. The location and
frequency of testing would be at the discretion of the geotechnical consultant.
GeoSoils, Ine.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Contractor's Responsibility
All clearing, site preparation, and earthwork performed on the project should be conducted
by the contractor, with observation by geotechnical consultants and staged approval by the
governing agencies, as applicable. It is the contractor's responsibility to prepare the ground
surface to receive the fill, to the satisfaction of the soil engineer, and to place, spread,
moisture condition, mix and compactthe fill in accordance with the recommendations of the
soil engineer. The contractor should also remove all major noR-earth material considered
unsatisfactory by the soil engineer.
It is the sole responsibility of the contractorto provide adequate equipment and methods
to accomplish the earthwork in accordance with applicable grading guidelines, codes or
agency ordinances, and approved grading plans. Sufficient watering apparatus and
compaction equipment should be provided by the contractor with due consideration for the
fill material, rate of placement, and climatic conditions. If, in the opinion of the geotechnical
consultant, unsatisfactory conditions such as questionable weather, excessive oversized
rock, or deleterious material, insufficient support equipment, etc., are resulting in a quality
of work that is not acceptable, the consultant will inform the contractor, and the contractor
is expected to rectify the conditions, and if necessary, stop work until conditions are
satisfactory.
During construction, the contractor shall properly grade all surfaces to maintain good
drainage and prevent ponding of water. The contractor shall take remedial measures to
control surface water and to prevent erosion of graded areas until such time as permanent
drainage and erosion control measures have been installed.
SITE PREPARATION
All major vegetation, including brush, trees, thick grasses, organic debris, and other
deleterious material should be removed and disposed of off-site. These removals must be
concluded prior to placing fill. Existing fill, soil, alluvium, colluvium, or rock materials
determined by the soil engineer or engineering geologist as being unsuitable in-place
should be removed prior to fill placement. Depending upon the soil conditions, these
materials may be reused as compacted fills. Any materials incorporated as part of the
compacted fills should be approved by the soil engineer.
Any underground structures such as cesspools, cisterns, mining shafts, tunnels, septic
· tanks, wells, pipelines, or other structures not located prior to grading are to be removed or
treated in a manner recommended by the soil engineer. Soft, dry, spongy, highly fractured,
or otherwise unsuitable ground extending to such a depth that surface processing cannot
adequately improve the condition shq4ld be overexcavated down to firm ground and
approved by the soil engineer before compaction and filling operations continue.
Overexcavated and processed soils which have been properly mixed and moisture
conditioned should be re-compacted to the minimum relative compaction as specified in
these guidelines.
. Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge GeoSoils, lne.
Appendix D
Page2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I'
I
I
Existing ground which is determined to be satisfactory for support of the fills should be
scarified to a minimum depth of 6 inches or as directed by the soil engineer. After the
scarified ground is brought to optimum moisture content or greater and mixed, the materials
should be compacted as specified herein. If the scarified zone is grater that 6 inches in
depth, it may be necessary to remove the excess and place the material in lifts restricted
to about 6 inches in compacted thickness.
Existing ground which is not satisfactory to support compacted fm should be overexcavated
as required in the geotechnical report or by the on-site soils engineer and/or engineering
geologist. Scarification, disc harrowing, or other acceptable f9rm of mixing should continue
until the soils are broken down arid free of large lumps or clods, until the working surface
is reasonably uniform and free from ruts, hollow, hummocks, or other uneven features
which would inhibit compaction as described previously.
Where fills are to be placed on ground with slopes steeper than 5: 1 (horizontal to vertical),
the ground should be stepped or benched. The lowest bench, which will act as a key,
should be a minimum of 15 feet wide and should be at least 2 feet deep into firm material,
and approved by the soil engineer and/or engineering geologist. In fill over cut slope
conditions, the recommended minimum width of the lowest bench or key is also 15 feet with
the key founded on firm material, as designated by the Geotechnical Consultant. As a
general rule, unless specifically recommended otherwise by the Soil Engineer, the
minimum width of fill keys should be approximately equal to ½ the height of the slope.
Standard benching is generally 4 feet (minimum) vertically, exposing firm, acceptable
material. Benching may be used to remove unsuitable materials, although it is understood
that the vertical height of the bench may exceed 4 feet. Pre-stripping may be considered
for unsuitable materials in excess of 4 feet in thickness.
All areas to receive fill, including processed areas, removal areas, and the toe of fill
benches should be observed and approved by the soil engineer and/or engineering
geologist prior to placement of fill. Fills may then be properly placed and compacted until
design grades (elevations) are attained.
COMPACTED FILLS
Any earth materials imported or excavated on the property may be utilized in the fill
provided that each material has been determined to be suitable by the soil engineer. These
materials should be free of roots, tree branches, other organic matter or other deleterious
materials. All unsuitable materials should be removed from the fill as directed by the soil
engineer. Soils of poor gradation, undesirable expansion potential, or substandard strength
characteristics may be designated by the consultant as unsuitable and may require
blending with other soils to serve as a satisfactory fill material.
Fill materials derived from benching operations should be dispersed throughoutthe fill area
and blended with other bedrock derived material. Benching operations should not result
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
Appendix D
Page3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I I
I
I
in the benched material being placed only within a single equipment width away from the
fill/bedrock .contact.
Oversized materials defined as rock or other irreducible materials with a maximum
dimension greater than 12 inches should not be buried or placed in fills unless the location
of materials and disposal methods are specifically approved by the soil engineer.
Oversized material should be taken off-site or placed in accordance with recommendations
of the soil engineer in areas designated as suitable for rock disposal. Oversized material
should not be placed within 10 feet vertically of finish grade (elevation) or within 20 feet
horizontally of slope faces.
To facilitate future trenching, rock should not be placed within the range of foundation
excavations, future utilities, or underground construction unless specifically approved by the
soil engineer._and/or the developers representative.
If import material is required for grading, representative samples of the materials to be
utilized as compacted fill should be analyzed in the laboratory by the soil engineer to
determine its physical properties. If any material other than that previously tested is
encountered during grading, an appropriate analysis of this material should be conducted
by the soil engineer as soon as possible.
Approved fill material should be placed in areas prepared to receive fill in near horizontal
layers that when compacted should not exceed 6 inches in thickness. The soil engineer
rriay approve thick lifts if testing indicates the grading procedures are such that adequate
compaction is being achfeved with lifts of greater thickness. Each layer should be spread
evenly and blended to attain uniformity of material and moisture suitable for compaction.
Fill layers at a moisture content less than optimum should be watered and mixed, and wet
fill layers should be aerated by scarification or should be blended with drier material.
Moisture condition, blending, and mixing of the fill layer should continue until the fill
materials have a uniform moisture content at or above optimum moisture.
After each layer has been evenly spread, moisture conditioned and mixed, it should be
uniformly compacted to a minimum of 90 percent of maximum density as determined by
ASTM test designation, D-1557-78, or as otherwise recommended by the soil engineer.
Compaction equipment should be adequately sized and should be specifically designed
for soil compaction or of proven reliability to efficiently achieve the specified degree of
compaction.
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
Appendix D
Page4
I
I
I
I
I
I
I
I-
I
I
I
I
I
I
-,I
I
I
1·
I
Where tests indicate that the density of any layer of fill, or portion thereof, is below the
required relative compaction, or improper moisture is in evidence, the particular layer or
portion shall be re-worked until the required density and/or moisture content has been
attained. No additional fill shall be placed in an area until the last placed lift of fill has been
tested and found to meet the density and moisture requirements, and is approved by the
soil engineer. ·
Compaction of slopes should be accomplished by over-buikfing a minimum of 3 feet
horizontally, and subsequently trimming back to the design slope configuration. Testing
shall be performed as the fill i~ elevated to evaluate comp~ction as the fill core is being
developed. Special efforts may be necessary to attain the specified compaction in the fill
slope zone. Final slope shaping should be performed by trimming and removing loose
materials with appropriate equipment. A final determination of fill slope compaction should
be based on observation and/or testing of the finished slope face. Where compacted fill
slopes are designed steeper than 2:1 (horizontal to vertical), specific material types, a
higher minimum relative compaction, and special grading procedures, may be
recommended.
If an alternative to over-building and cutting back the compacted fill slopes is selected, then
special effort should be made to achieve the required compaction in the outer 1 o feet of
each lift of fill by undertaking the following:
1.
2.
3.
4.
5.
An extra piece of equipment consisting of a heavy short shanked sheepsfoot should
be used to roll (horizontal) parallel to the slopes continuously as fill is placed. The
sheepsfoot roller should alsobe used to roll perpendicular to the slopes, and extend
out over the slope to provide adequate compaction to the face of the slope.
· Loose fill should not be spilled out over the face of the slope as each lift is
compacted. Any loose fill spilled over a previously completed slope face should be
trimmed off or be subject to re-rolling.
Field compaction tests will be made in the outer (horizontal) 2 to 8 feet of the slope
at appropriate vertical intervals, subsequent to compaction operations.
After completion of the slope, the slope face should be shaped with a small tractor
and then re-rolled with a sheepsfoot to achieve compaction to near the slope face.
Subsequent to testing to verify compaction, the slopes should be grid-rolled to
achieve compaction to the slope face. Final testing should be used to confirm
compaction after grid rolling.
Where testing indicates less than adequate compaction, the contractor will be
responsible to rip, water, mix ~nd. re-compact the slope material as necessary to
achieve compaction. Additional testing should be performed to verify compaction.
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
Appendix D
Pages
GeoSoils, lne.
I
I
I
I
I·
I
I
I
I
I
I
I
I
I
·1
I
I
I
I
6. Erosion control and drainage devices should be designed by the project civil
engineer in compliance with ordinances of the controlling governmental agencies,
and/or in accordance with the recommendation of the soil engineer or engineering
geologist.
SUBDRAIN INSTALLATION
Subdrains should be installed in approved ground in accordance with the approximate
alignment and details indicated by the geotechnical cons1.:1ltant. Subdrain locations or
materials should not be changed or modified without approval of the geotechnical
consultant. The soil engineer and/or engineering geologist may recommend and direct
changes in subdrain line, grade and drain material in the field, pending exposed conditions.
The location of constructed subdrains should be recorded by the project civil engineer.
EXCAVATIONS
Excavations and cut slopes should be examined during grading by the engineering
geologist. If directed by the engineering geologist, further excavations or overexcavation
and re-filling of cut areas should be performed and/or remedial grading of cut slopes should
be performed. When fill over cut slopes are to be graded, unless otherwise approved, the
cut portion of the slope should be observed by the engineering geologist prior to placement
of materials for construction of the fill portion of the slope.
The engineering geologist should observe all cut slopes and should be notified by the
.contractor when cut slopes are started.
If, during the course of grading, unforeseen adverse or potential adverse geologic
conditions are encountered, the engineering geologist and soil engineer should investigate,
evaluate and make recommendations to treat these problems. The need for cut slope
buttressing or stabilizing should be based on in-grading. evaluation by the engineering
geologist, whether anticipated or not.
Unless . otherwise specified in soil and geological reports, no cut slopes should be
excavated higher or steeper than that allowed by the ordinances of controlling
governmental agencies. Additionally, short-term stability of temporary cut slopes is the
contractors responsibility.
Erosion control and drainage devices should be designed by the project civil engineer and
should be constructed in compliance with the ordinances of the controlling governmental
agencies, and/or in accordance with tt,e recommendations of the soil engineer or
engineering geologist. '
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
GeoSoils, lne.
Appendix D
Page6
I
I
1·
I
I
I
I
I
·1
I
I
I
I
I
I
I
I
I
I
COMPLETION
Observation, testing and consultation by the geotechnical consultant should be conducted
during the grading operations in order to state an opinion that all cut and filled areas are
graded in accordance with the approved project specifications.
After completion of grading and after the soil engineer and engineering geologist have
finished their observations of the work, final reports should be submitted subject to review
by the controlling governmental agencies. No further excavation or filling should be
undertaken without prior notification of the soil engineer anq/or engineering geologist.
All finished cut and fill slopes should be protected from erosion and/or be planted in
accordance with the project specifications and/or as recommended by a landscape
architect. Such protection and/or planning should be undertaken as soon as practical after
completion -of grading.
JOB SAFETY
General
At GeoSoils, Inc. (GSI) getting the job done safely is of primary concern. The following is
the company's safety considerations for use by all employees on multi-employer
construction sites. On ground personnel are at highest risk of injury and possible fatality on
grading and construction projects. GSI recognizes that construction activities will vary on
each site and that site safety is the prime responsibility of the contractor; however, everyone
must be safety conscious and responsible at all times. To achieve our goal of avoiding
accidents, cooperation betwee·n the client, the contractor and GSI personnel must be
maintained.
In an effort to minimize risks associated with geotechnical testing and observation, the
following precautions are to be implementE;!.d for the safety of field personnel on grading and
construction projects:
Safety Meetings: GSI field personnel are directed to attend contractors regularly
scheduled and documented safety meetings.
Safety Vests:
Safety Flags:
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
Safety vests are provided for and are to be worn by GSI personnel at
all times when they are working in the field.
Two safety flags are provided to GSI field technicians; one is to be
affixed to the vehicl~ when on site, the other is to be placed atop the
spoil pile on all test pits.
Geo.Soils, Ine.
r.
Appendix D
Page?
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
·1
I I
I
Flashing Lights: All vehicles stationary in the grading area shall use rotating or flashing
amber beacon, or strobe lights, on the vehicle during all field testing.
While operating a vehicle in the grading area, the emergency flasher
on the vehicle shall be activated.
In the event that the contractor's representative observes any of our personnel not following
the above, we request that it be brought to the attention of our office.
Test Pits Location, Orientation and Clearance
The technician is responsible for selecting test pit locations. ·A primary concern should be
the technicians's safety. Efforts will be made to coordinate locations with the grading
contractors authorized representative, and to select locations following or behind the
established traffic pattern, preferably outside of current traffic. The contractors authorized
representative (dump man, operator, supervisor, grade checker, etc.) should direct
excavation of the pit and safety during the test period. Of paramount concern should be the
soil technicians safety and obtaining enough tests to represent the fill.
Test pits should be excavated so that the spoil pile is placed away form oncoming traffic,
whenever possible. The technician's vehicle is to be placed next to the test pit, opposite the
spoil pile. This necessitates the fill be maintained in a driveable condition. Alternatively, the
contractor may wish to park a piece of equipment in front of the test holes, particularly in
small fill areas or those with limited access.
A zone of non-encroachment should be established for all test pits. No grading equipment
should enter this zone during the testing procedure. The zone should extend approximately
50 feet outward from the center of the test pit. This zone is established for safety and to
avoid excessive ground vibration which typically decreased test results.
When taking slope tests the technician should park the vehicle directly above or below the
test location. If this is not possible, a prominentflag should be placed atthe top of the slope.
The contractor's representative should effectively keep all equipment at a safe operation
· distance (e.g., 50 feet) away from the slope durin_g this testing.
The technician is directed to withdraw from the active portion of the fill as soon as possible
following testing. The technician's vehicle should be parked at the perimeter of the fill in a
highly visible location, well away from the equipment traffic pattern.
The contractor should inform our personnel of all changes to haul roads, cut and fill areas
or other factors that may affect site access and site safety.
In the event that the technicians safety is jeopardized or compromised as a result of the
contractors failure to comply with any of tne above, the technician is required, by company
policy, to immediately withdraw and notify his/her supervisor. The grading contractors
representative will eventually be contacted in an effort to effect a solution. However, in the
interim, no further testing will be performed until the situation is rectified. Any fill place can
be considered unacceptable and subject to reprocessing, recompaction or removal.
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
GeoSoils, Ine ..
Appendix D
Pages
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
In the event that the soil technician does not comply with the above or other established
safety guidelines, we request thatthe contractor brings this to his/her attention and notify this
office. Effective communication and coordination between the contractors representative
and the soils technician is strongly encouraged in order to implement the above safety plan.
Trench and Vertical Excavation
It is the contractor1s responsibility to provide safe access into trenches where compaction
testing is needed.
Our personnel are directed not to enter any excavation or vertical cut which: 1) is 5 feet or
deeper unless shored or laid back; 2) displays any evidence of instability, has any loose
rock or other debris which could fall into the trench; or 3) displays any other evidence of any
unsafe conditions regardless of depth,
All trench excavations or vertical cuts in excess of 5 feet deep, which any person enters,
should be shored or laid back.·
Trench access should be provided in accordance with CAL-OSHA and/or state and local
standards. Our personnel are directed not to enter any trench by being lowered or 11riding
down11 on the equipment.
If the contractor fails to provide safe access to trenches for compaction testing, our company
policy requires that the soil technician withdraw and notify his/her supervisor. The
contractors representative will eventually be contacted in an effort to effect a solution. All
backfill not tested due to safety concerns or other reasons could be subject to reprocessing
and/or removal.
If GSI personnel become aware of anyone working beneath an unsafe trench wall or vertical
excavation, we have a legal obligation to put the contractor and owner/developer on notice
to immediately correct the situation. If corrective steps are not taken, GSI then has ·an
obligation to notify CAL-OSHA and/or the proper authorities.
Mr. Ed Hendrix
File:e:\wp7\3300\3344a.pge
· GeoSoils, Jne.
Appendix D
Page9
I
·" rl
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
,.
CANYON SU BO RAIN DETAIL
TYPE A
PROPOSED COMPACTED FILL
TYPE B -...-.----------------------------------
, PROPOSED COMPACTED Fill
' ' ' . _, ', _ _,.-NATURAL GROUND =~ '* .
11,\~/) ',
NOTE: ALTERNATIVES, LOCATION ANO EXTENT OF SUBDRAINS SHOULD BE DETERMINED
9y· TH-E SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST·O URING GRADING.
PLATE EG-1
I
I CANYON SUBDRAIN ALTERNATE DETAILS
I
I
I
I
·1
I
I
I
I
I
I
·1
I
I
I.
I
I
:
ALTERNATE 1: PERFORATED PIPE AND FILiER MATERIAL
·A-1
·FILTER MATERIAL. .
SIEVE SIZE PERCENT PASSING
1 INCH ,100
·3/4 INCH 90-:-:100
3/8 INCH 40-100
NO. 4 25-40.
NO. 8 18-33
.NO. 30 :S-15
"NO. 50 .0-7.
NO. 200 0-3
ALTERNATE 2: PERFORATED PIPE, GRAVEL AND.FILTER FABRIC
~Nl~UM OVERLAP 5• MINIMUM OVER~~,
A-2
PERFORATEO PIPE: SEE ALTERNATE 1
GRAVEL: CLEAN 3/ 4 IND-I ROCK OR APPROVED SUBSTITUTE
FILTER FABRIC: MIRAFI 140 OR APPROVED SUBSTITUTE
PLATE EG-2
I
.1
I
I
I
I
·1
I
I
I
I
I
I
I
I
I
I
I
-I·
DET All FOR FILL. SLOPE TOEING OUT
ON FLAT ALLUVlA TED CANYON
TOE OF SLOPE AS SHOWN ON GRADING PLAN
ORIGINAL GROUND SURFACE TO BE
RESTORED WITH COMPACTED FILL . -:2-::0~IGl:L_:a_:~u~~
BACKCU~ VARIES. FOR DEEP REMOVALS,~~ r
BACKCUT ~~SHOULD s·E MADE NO ($-~
STEEPER·THA~:1 OR AS NECESSARY.,~) ANTICIPATED ALLUVIAL REMOVAL FOR SAFETY .........._~,cONSIDERATIONS7 '
1 ~ DEPTH PER SOIL ENGINEER.
~}k~ ,,/ . -
~1th.,/\ . --
·1/\'\vj~rf~---PROVIOEA 1:1 ;;,MUMPRo:iEcnoNFROM T; OF
SLOPE AS SHOWN ON GRADING PLAN TO THE RECOMMENDED
REMOVAL DEPTH. SLOPE HEIGHT, SITE CONDITIONS ANO/OR
LOCAL CONDITIONS COULD DICTATE FLATTER PROJECTIONS.
REMOVAL ADJACENT TO EXISTING FILL
ADJOINING CANYON FILL
----------:------------
PROPOSED ADDITIONAL COMPACTED F.ILL
. COMPACTED FILL LIMITS LIN!;\
~ TEMPORARY .COMPACTED FILL --...~ ---
. ), FOR DRAINAGE ONLY ------
Oaf ..,.:r;0, Oaf /'Clal (TO BE REMOVED>
IEXISTING,COMPACTEO ALU ~',, ~.,, ~'\\~~//~\ k~~R1'~ ' LEGEND
'7/J5.f/j~'/\ . :...-\\ TO BE REMOVED BEFORE Oaf ARTIFICIAL FILL
PLACING ADDITIONAL
COMPACTED FILL . Qa( ALLUVIUM
PLATE EG-3
--· ----· -·--. ----· ------·-
-u r )> -; m
m G')
I
+-
TYPICAL STABILIZATION / BUTTRESS. FILL DETAIL
15" TYPICAL
1-2' v1..&..n1~ ,....,. >>JC I> ,,_, t.
OUTLETS TO BE SPACED AT 100' MAXIMUM INTERVALS, AND SHALL EXTEND
1r BEYOND THE FACE PF SLOPE AT TIME OF .R.OUGH GRADING COMPLETION.
le · ti .
15' MINIMUM
BLANKl:T FILL IF RECOMMENDED
BY THE SOIL ENGINEER
DESIGN· FINISH SLOPE
L. ,,, »K\
'\\Vifillb _____ _
~ I ~ .,, , 4 i
· · ·--1 -4• DIAMETER NON-PERFORATED OUTLET PIPE
_J_ . ANO BACKDRAIN,(SEE ALTERNATIVESJ
~)''
3' MINIMUM KEY DEPTH
------·---· --... -----.. --. . .. \. . . . .
TYPICAL STABILIZATION /_ BUTTRESS SUB·DRAIN DETAIL
L • MINIMUM r MINIMUM
PIPE
L. MINIMUM
-u r
)>
-I m
m
G)
I
U1
PIPE
:E :::,
~
~ :E .
N
r MINIMUM
FILTER f:tATERIAL: MINIMUM OF FIVE Fl,/LINEAR Fl OF PIPF.
OR FOUR FP/LINEAR Ft OF PIPE WHEN PLACED IN SQUARE
CUT TRENCH.
AI.I~RNATIVE IN LIEU OF FILTER MATERIAL: GRAVEL MAY e
EHCA~EO IN APPROVED FILTER FABRIC. FILTER FABRIC
SHALL ~E MIRAFI 140 OR EQUIVALENT. FILTER FABRIC
SJJALL BE LAPPED A MINIMUM OF 1r ON ALL JOINTS.
MINIMUM 4• DIAMETER PIPE: ABS-ASTM D-2751. SOR 35
OR ASTM D-1527 SCHEDULE 40 PVC-ASTM D-3034,
SPR _35_ OR ASTM D-1785 SCHEDULE 40 WI.TH A CRUSHING
STRE~OTH OF 1,000 POUNDS MINIMUM, ANO A MINIMUM OF
8 UNIFORMLY SPACED PERFORATIONS PER FOOT OF PIPE
INSTALLED WITH PERFORATIONS OF BOTTOM OF PIPE.
PROVIDE CAfl AT UPSTREAM END OF PIPE_. SLOPE AT 2%
TO OUTLET P.IPE. OUTLET PIPE TO BE CONNECTED TO
SUBDRAIN PIPE WITH TEE OR ELBOW. .
NlTE:: 1. TRENCH FOR OUTLET PIPES TO BE BACKFILLED
' WITH ON-SITE SOIL.
2. BACKORAINS ANO LATERAL DRAINS SHALL BE
LOCATED AT ELEVATION OF EVERY BENCH DRAIN.
FIRST DRAIN LOCATED AT ELEVATION JUST ABOVE
LOWER LOT GRADE. ADDITIONAL DRAINS MAY BE
REQUIRED AT THE DISCRETION OF THE SOILS
ENGINEER AND/OR ENGINEERING QEOLOGIST.
FILTER MATERIAL SHALL BE OF
THE FOLLOWING SPECIFICATION
OR AN APPROVED EQUIVALENT:
SIEVE SIZE PERCENT PASSING
1 INCH 100
3/4 INCH ~0-100
3/8 INc;:H 40-100
NO. 4 25-40
N0.8 18-33
NO. JO 5-15
NO. 50 0-7
N0.200 o-~
GRAVEL SHALL BE OF THE
FOLLOWING SPECIFICATION OR .
AN APPROVED E~UIVALENT: .
SIEVE SIZE PERCENT PASSING
1 1 /2 IN CH.. 1 0 0
NO. 4 50
N0.200 8
SAND EQUIVALENT: MINIMUM OF 51
,,
----·--· --·-----·---·---
FILL OVER NATURAL DETAIL
SIDEHILL FILL
TOE OF SLOPE AS SHOWN ON GRADING PLAN
PROVIDE A 1:1 MINIMUM PROJECTION FROM
DESIGN' TOE OF SLOPE TO TOE OF l<~Y
AS SHOWN ON AS BUILT
NATURAL SLOPE TO
BE RESTORED WITH
~
-1 I ~:MINIM~M
BENCH WIDTH MAY VARY
COMPACTED FILL
~
NOTE: 1. WHERE THE NA'tURAL, SLOPE APPROACHES OR EXCEE-0S THE
-0 r
)>
-I m
m G>
I
Ol
15"MINIMUM KEY WIDTH DESIGN SLOPE RATIO. SPECIAL RECOMMENDATIONS WOULD BE
2'X 3' MINIMUM KEY DEPTH
2· MINIMUM IN BEDROCK OR
APPROVED MATERIAL.
I
PROVIDED BY THE SOILS ENGINEER.
2. THE NEED FOR AND DISPOSl:TION OF DRAINS WOULD BE DETERMINED
BY THE SOILS ENGINEER BASED UPON EXPOSED CONDITIONS.
------·-------------
FILL OVER CUT DETAIL
CUT/FILL CONTACT
1. AS SHOWN ON GRADING PLAN
MAINTAIN MINIMUM .15" FILL SECTION FROM
BACKCUT TO FACE OF FINISH SLOPE ,_ ________ __
2. AS SHOWN ON AS· BUILT
H
ORIGINAL TOPOGRAPHY
"'' l r~'
'1fv' BEDROCK OR APPROVED MATERIAL
7J r )>
-i m
m G)
I
'-l
LOWEST BENCH WIDTH
15' MINIMUM OR H/2
COMPACTED FILL
NOTE: THE CUT PORTION OF THE SLOPE SHOULD BE EXCAVATED AND
EVALUATED BY THE SOILS ENGINEER ANO/OR ENGINEERING
GEOLOGIST PRIOR TO CONSTRUCTING THE FILL PORTION.
----· --·------------1111 -
7J r )>
-I m
m G)
I
CX)
STABILIZATION Fl.LL FOR UNSTABLE MATERIAL
EXPOSED I.N PORTION OF CUT SLOPE
NAT.URAL SLOPE
REMOVE: UNSTABLE MATEIJIAL
~
~
t 15'.MINIMUM ,~~QSED FltllSHEP GRADE
OR APPROVED MATERIAL
REMOVE: UNSTABLE
MATERIAL
\\vii~~WiA:f ..:=IJ'MINIMUM TILTED BACK ' .
. IF RECOMMENDED BY THE SOILS ENGINEER AND/OR ENGINEERING
t4a,a--,.-W~ GEOLOGIST, THE REMAINING CUT PORTION OF THE SLOPE MAY
I arf/ = REQUIRE REMOVAL AND REPLACEMENT WITH COMPACTED FILL --
NOTE: 1. SUBDRAINS ARE HOT REQUIRED UNLESS SPECIFIED BY SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST,
. 2. ·wr SHALL BE EQUIPMENT WIDTH (15") FOR SLOPE HEIOHTS LESS THAN 25 FEET. FOR SLOPES GREATER·
THAN 25 FEET ·w· SHALL BE DETERMINED BV THE PROJECT SOILS ENGINEER ANO /OR ENGINEERING
GEOLOGIST. AT NO TIME SHALL •w• BE LESS THAN H/2.
---·---·--------------
-u
~ -I rn rn .
Gl
I
lO
SKIN FILL OF NATURAL GROUND
ORIGINAL SLOPE
15" MINIMUM TO BE MAINTAINED FROM
PROPOSED· FINISH SLOPE FAC·E TO BACKCUT -
/
~~ · , ~ t J" Ml~IMUM KEY DEPTH
~ ...»"' .,J\ "m V#JWAA\vh{,Q:?jll~· ---
NOTE: 1. THE NEED AND DISPOSITION OF DRAINS WILL BE DETERMINED! BY THE SOILS ENGINEER AND/OR
ENGINEERING GEOLOGIST BASED ON FIELO CONDITIONS.
2. PAD OVEREXCAVATION AND RECOMPACTION SHOULD BE PERFORMED IF DETERMINED TO BE
NECESSARY BY THE SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST.
--· ----·-------------
-u r )>
-I rn
m G)
I
-Jo.
0
DAYLIGHT CUT LOT DETAIL ____,-
RECONSTRUCT COMPACTED FILL SLOPE AT 2:1 OR FLATTER
(MAY INCREASE OR DECREASE·PAD AREA).
OVEREXCAVATE AND RECOMPACT --"""
REPLACEMENT FILL
AVOID AND/OR CLEAN UP SPILLAGE OF
MATERIALS ON THE NATURAL SLOPE
t ·t
!
~
NATURAL GRADE~
~
/ ~------
/
NOTE: 1. SUBORAIN AND KEY .WIDTH REQUIREMENTS WILL BE DETERMINED BASED ON EXPOSED SUBSURFACE
CONDITIONS AND THICKN~SS OF OVERBURDEN.
2. PAD OVER EXCAVATION AND RECOMPACTION SHOULD BE PERFORMED IF DETERMINED NECESSARY BY
TH(i. SOILS ENGINEER AND/OR THE ENGINEERING GEOLOGIST.
I
I
I
I
I
I
I
I
I
I
:I
I
I
I
I
I
I
I
I .
TRANSITION LOT DETAIL
CUT LOT (MATERIAL TYP.E TRANSITION)
------.
--------·------------
~
PAD GRADE
TYPICAL BENCH ING
CUT-FILL LOT (DA YUGHT TRANSITION)
MUM
PAD GRADE
NOTE: * DEEPER OVEREXCAVATION MAY BE RECOMMENDED BY THE SOILS ENGINEER
. ANO/OR ENGINEERING GEOLOGIST IN STEEP CUT-FILL TRANSITION AREAS.
-
PLATE EG-11"
I
I
1·
I
I-
I
I
. I
I
I
I
I
1-
I
I
I
·I
I
I
SETTLEMENT PLATE AND RISER DETAIL
2"X 2'X 114• STEE·L PLATE
STANDARD 3/4· PIPE NIPPLE WELDED TO TOP
OF PLATE.
~---+--3/ 4 • X 5" GALVANIZED PIPE. STANDARD PIPE
THREADS TOP AND.BOTTOM. EXTENSIONS
THREADED ON BOTH ENDS AND ADDEO IN 5•
INCREMENTS.
3 INCH SCHEDULE 40 PVC PIPE SLEEVE, ADD IN
5" INCREMENTS WITH GLU~ JOINTS •
FINAL GRADE -! r. ! MAINTAIN 5' CLEARANCE OF HEAVY EQUIPMENT.
--L+ ...L.A,,-MECHANICALLY HANO COMPACT IN 2"VERTICAL
-r+ -r'\r LIFTS OR ALTERNATIVE SUITABLE TO AND
L..__----:-.,. 111-__ _.,., ACCEPTED BY THE SOILS ENGINEER.
1 s· -~ s·
I
I
I
I
5• . I I . MECHANICALLY HAND COMPACT THE INITIAL s•
VERTICA~ WITHIN A 5" RADIUS OF PLATE BASE.
/
/
NOTE:
I /
/ ' ' / '
. . . . . .. -. . . . .... .. . . . .. ' '• .. ·. . . . . . . .· . . .. ·-· . . . . . . . . . . . .
' ' "'
BOTTOM OF CLEANOUT
PROVIDE A MINIMUM 1• BEDDING OF COMPACTED SAND
1. LOCATIONS OF SETTLEMENT PLATES SHOULD BE CLEARLY MARKED ANO READILY
VISIBLE (RED FLAGGED) TO EQUIPMENT OPERATORS.
2. CONTRACTOR SHOULD MAINTAIN CLEARANCE OF A S"RADIUS OF PLATE BASE ANO
WITHIN 5' !VERTICAL) FOR HEAVY "EQUIPMENT. FILL WITHIN CLEARANCE AREA SHOULD
BE HANO'COMPACTED TO PROJECT SPECIFICATIONS OR COMPACTED BY ALTERNATIVE
APPROVED BY THE SOILS ENGINEER.
3. AFTER S'(VERTICALl OF F1LL IS IN PLACE, CONTRACTOR SHOULD MAINTAIN A 5.:RADIUS
EQUIPMENT CLEARANCE FROM RISER.
4. PLACE ANO MECHANICALLY HAND COMPACT INITIAL 2' OF FILL PRIOR TO ESTABLISHING
THE INITIAL READING.
5. IN THE EVENT OF DAMAGE TO THE SETTLEMENT PLATE OR EXTENSION RESULTING
FROM EQUIPMENT OPERATING WITH IN THE SPECIFIED CLEARANCE AREA, CONTRACTOR
SHOULD IMMEDIATELY NOTIFY THE SOILS ENGINEER ANO SHOULD BE RESPONSIBLE
FOR RESTORING THE SETTLEMENT-P.t~l-E·S TO WORKING ORDER.
6. AN ALTERNATE DESIGN AND METHOD OF INSTALLATION MAY BE PROVIDED AT THE
DISCRETION OF THE SOILS ENGINEER.
PLATE EG-14
I
I TYPICAL SURFACE SETTLEMENT MONUMENT
I
I
I
I
I
I
I
I.
•I
I
I
I
I
I
I
I
I
FlNISH GRADE
..___... 3/8.-DIAMETER X s• LENGTH
CARRIAGE BOLT OR EQUIVALENT
• DIAMETER X 3 112• LENGTH HOL:.E
,.._-+-CONCRETE BACKFILL
.. ------".f.c,-
PLATE EG-15
I
I
I
I
I
·1
I
I
I
I
I
I
I
I
I
I
I
I
·I
~
TEST PIT SAFETY DIAGRAM
50 FEIT
SPOIL
P1LE
SJOE VIEW
{ NOT TO SCALE )
TOP·VfE.W
100 FET
t-w u.
C,
1ft
APPROXIMAlc; CEITER /
CF TEST PIT
. t-FLAG
Hf u.
C
In
50 FEET
--·-:-__ ..... --~_
l NOT TO SCALE )
-P_LATE EG-16
I
I
I
I
I
I
I
I
1.
I
I
I
I
I
I
·I
I
I
I
OVERSIZE ROCK DISPOSAL
VIEW NORMAL TO SLOPE FACE
PROPOSED FINISH GRADE
1 O' MINIMUM (E)
0:::, . r:J:J 00 co
~ 151 MINIMUM (A)
(BJ 00 ~ oO 201 MINIMUM
D (GJ
00 c:o ~ cc
oO oo(FJ
ViEW PARALLEL TO SLOPE FACE
PROPOSED FINISH GRADE
10' MINIMUM (E)
15• MINIMUM
<::• Oot ~~~ ~ (GJ o:;,,::,o
15• MINIMUM
~~ffl~~~--.."t"'C-?;~~ I
BEDROCK OR APPROVED MATERIAL
NOTE: IA) ONE EQUIPMENT WIDTH OR A. MINIMUM OF 15 FEET.
18) HEIGHT ANO WIDTH MAY VA.RY DEPENDING ON ROCK SIZE AND TYPE OF
EQUIPMENT. LENGTH OF WINDROW SHALL BE NO GREATER THAN 100· MAXIMUM.
IC) IF APPROVED BY THE SOILS ENGINEER ANO/OR ENGINEERING GEOLOGIST,
WINDROWS MAY BE PLACED DIRECTLY ON COMPETENT MATERIAL OR BEDROCK
PROVIDED ADEQUATE SPACE IS AVAILABLE FOR COMPACTION. ~
IDl ORIENTATION OF WINDROWS MAY VARY BUT SHOULD BE AS RECOMMENDED BY
THE SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST. STAGGERING OF
WINDROWS IS NOT NECESSARY UNLESS RECOMMENDED. .
~
(El CLEAR AREA FOR UTILITY TRENCHES, FOUNDATIONS AND SWIMMING POOLS.
(Fl ALL FILL OYER AND AROUND ROCK WINDROW SHALL BE COMPACTED TO 90%
RELATIVE COMPACTION OR AS RECOMMEND-ED.
(GI AFTER FILL BETWEEN WINDROWS IS PLACED ANO COMPACTED WITH THE LIFT OF
FILL COVERING WINDROW, WIN.DROW SHOULD BE PROOF ROLLED WITH A
D-9 DOZER OR EQUIVALENT~ .
VIEWS ARE DIAGRAMMATIC ONLY. ROO< SHOULD NOT TOUCH
AND VOIDS SHOULD 8F COMPLETELY FILLED IN. PLATE RD-1
I
I
I
I
I
I
I
I
I
I
I
I
·1
I
I
I
I
'I
I.
ROCK DISPOSAL PITS
VIEWS ARE OIAGRAMMA TIC ONLY. ROO< SHOULD NOT TOUCH
ANO VOIDS SHOULD BE COMPLETELY FILLED IN,
FILL LIFTS COMPACTED OVER
ROCK AFTER EMBEDMENT r----------1
I
I .--~
I 1 COMPACTED FILL
I
I
I
I
GRANULAR MATERIAL
------,
SIZE OF EXCAVATION TO BE
COMMENSURATE WITH ROCK SIZE
ROCK DISPOSAL LAYERS
GRANULAR SOIL TO FILL VOIDS.~ . / COMPACTED FILL
DENSIFIED BY FLOODING A---,-------
LAYER ONE ROCK HIGH {10~{ --. -----------...... -------
PROFILE ALONG LAYER
FILL SLOPE
ICLEAR ZONE 20' MINIMUM
LAYER ONE ROCK HIGH
PLATE RD-2
. , ,.