HomeMy WebLinkAboutCDP 03-10; JOHANNSEN RESIDENCE; FINAL COMPACTION REPORT OF ROUGH GRADING; 2005-08-01• ?F
---.
:H:. -:•:
4 -
F.. T
• 1,.
4: ...... .;; .-•' 4 F
•
-F
F• - - 4
- Geotechnucal -,Coastal • Geologic Environmental
- -S F
-
• -
r
¼
/ - '• 'S
-• S •.• -
IS . S 14
- ,• - '. I 4 S • -.
- •, - -
F
1 -S -r F F F . -I ¼ . V - &
F-... I .-
p 3
._4 , - 4'
,
•1
. . •i . Geotechnical 'Coastal • Geologic.' Environmental
5741 Palmer Way Carlsbad California 92008 (760) 438-3155 FAX (760) 931-0915
August 1,2005 .
W. 0. 4340-BSC
..: Mr. LanceJohanrisen
. P.O. Box 300
San Jacinto, California 92581
I Subject Final Compaction Report of Rough Grading, Lot 129 of Map 3312,
Johannsen Residence Carlsbad Boulevard, Carlsbad San Diego County,
California . .. . .
1 Dear Mr. Johannsen
This report presents a summary of the geotechhical testing and-observation services
11 provided by GeoSoils, Inc (GSl) during the rough earthwork phase of development at the
subject site. Earthwdrk commenced on July 12, 2005, and was generally completed on
July 18, 2005. Survey of line and grade and location of the building footprints were
performed by others'and not performed by GSI. The purpose of grading was to, prepare
a relatively level pad for the construction of a single-farniiy residential structure. Based on
the observations and testing perfrméd by. GSl, it is our opinion that the building pad
appears suitable for its intended use Unless superceded by recommendations presented
herein the recommendations contained in the referenced reports (see the Appendix)
remain pertinent and applicable
ENGINEERING GEOLOGY..
The geologic conditions exposed during the process of grading wee regularly observed
by 'a representative from our firm k Paleoliquefaction features were not observed The
geologic conditions encountered generally were as anticipated and presented in
, GSl(2004d). .:. .. ..
GROUNDWATER • .
:
- Regional groundwater was not encountered during site 'rading, nor is anticipated to
- significantly affect site development, provided that the recommendations contained in'this
report are incorporated into final design and construction and that prudent surface
- drainae practices are incorporated into the construction "plans . A subdrainage system
(i e canyon subdrain, etc) vas not constructed due to the general lack of adequate fill
cover (less than 10 feet), the relatively.flat gradient acro'ss the site, lack of a suitable outlet
at flowline grade, and property line restrictions
Perched groundwater conditions along zones of contrasting permeabilities (i.e., fill/terrace
contact) may not be precluded from occurring in the future due to site irrigation, poor
drainage conditions, or damaged utilities, and should be anticipated This information
should be provided to the homeowners Should perched groundwater conditions develop,
this office could assess the affected area(s) and provide the appropriate recommendations
to mitigate the observed groundwater conditions Groundwater conditions may change
with the introduction of Irrigation, rainfall or other factors
GEOTECHNICAL ENGINEERING
Preparation of Existing Ground
1. Prior, to grading, the major surficial vegetation was stripped and hauled offsite.
2 Unsuitable topsoil/colluvium and existing undocumented fill were removed to
expose suitable bearing granitic bedrock
3 Removals depths within the limits of the project were on the order of ±2 to ±3 feet
below pre-construction grades. Once removals were completed, the exposed
bottom was reprocessed and compacted prior to fill placement.
4 All removals and processing of original ground were observed by representatives
of GSI.
Where removals would not provide for at least 3 feet of compacted fill, that portion
of the pad area was undercut to provide at least 3 feet of compacted fill below finish
grade.
The approximate limits of fill placement are shown on the Field Density Test
Location Map (Plate 1) included in this report Plate 1 uses the 40-scale grading
plan, prepared by the client (Johannsen, undated), as a base
Fill Placement
1. Fill materials, consisting of native onsite soils and compatible import soils, were
placed in 47 to 8-inch lifts, Watered, mixed to achieve at least optimum moisture
conditions, and compacted using earth-moving equipment.
2. The approximate maximum depth of fill at the subject site, placed under purview of
this report, is on the order of approximately 3 feet to 4 feet across the lot.
3. All fills placed within the subject site were observed and selectively tested by a field
representative of this firm.
Mr. Lance Johannsen • • W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. • August 1, 2005
File:e:\wpl2\4300\4340b.fcr Page 2
GeoSoils, Inc. •
4. Oversize material (i.e., greater than 12 inches in maximum dimension), was not
observed to have been included in the fill
Slopes
Graded Slopes.
Significant graded slopes were not constructed during this phase of site grading..Minor
slopes (i.e., less than 5 feet in height) are anticipated to perform adequately, provided that
they are properly landscaped and maintained, under normal rainfall conditions.
Temporary Slopes
Temporary construction slopes may generally be constructed at a gradient of
1:1 (horizontal vertical [h v]) or flatter (provided adverse geologic structures are not
present, as evaluated by GSI prior to workers entering trenches). Utility trenches may be
excavated in accordance with guidelines presented in Title 8 of the California Code of
Regulations for Excavation, Trenches, and Earthwork with respect to Type B soil
Construction materials and/or stockpiled soil should not be stored within a minimum lateral
distance of 5 feet from the top of any temporary slope. Temporary/permanent provisions
should be made to direct any potential runoff away from the top of temporary slopes
FIELD TESTING
Field density tests were performed using nuclear densometer ASTM Test
Methods D-2922 and D-3017. The test results taken during grading are presented
in the attached Table 1, and the locations of the tests taken during grading are
presented on Plate 1
Field density tests were taken at periodic intervals and random locations to check
the compactive effort provided by the contractor. Based upon the grading
operations observed, the test results presented herein are considered
representative of the compacted fill.
3.1 Visual classification of the soils in the field was the basis for determining which
maximum density value to use for a given density test
Mr. Lance Johannsen W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. August 11 2005
File: e:\wpl 2\4300\4340b.fcr Page
GeoSoils, me.
LABORATORY TESTING
Maximum Density Testing
The laboratory maximum dry density and optimum moisture content for the major soil type
within this construction phase were determined according to test method ASTM D-1 557.
The following.table presents the results:
MAXIMUM DENSITY MOISTURE CONTENT
6.
A - Reddish Brown Silty Sand 127.0 I 9.5
-
Expansion Index
Expansive soil conditions have been evaluated for the site. Representative samples of the
soils near pad grade were recovered for Expansion Index ([.1.) testing. E.I. testing was
performed in general accordance with Standard 18-2 of, the Uniform Building Code
([UBC], International Conference of Building Officials [lCBO], 1997). The test results
indicate an [.1: of less than 10, and the corresponding expansion classification of very low.
Corrosion/Sulfate • ':
A soil sample from the property was analyzed for corrosion/sbluble sulfate content. Sulfate
testing indicates that site soils have a negligible exposure to concrete, per Table 19-A-4 Of
the 1997 UBC. Corrosion testing (i.e., pH, resistivity) indicates that the soils are essentially
neutral to mildly alkaline. Testing further indicates that soils are corrosive to ferrous metals '
when saturated.. The results of chemical testing are attached as Figure 1. Based on the
test results a qualified corrosion engineer should be retained for consultation for
recommendations, with respect to foundations,: piping, etc..
CONCLUSIONS AND 'RECOMMENDATIONS
Unless superceded by, recommendations presented herein or by the soils corrosion
engineer, the conclusions and recommendations includedin GSI (2004a through 2004d)
remain valid and applicable All settlement-sensitive improvements should be minimally
;.. designed in accordance with those reports and the recommendations presented herein.
. , .
Mr. Lance Johannsen W.O. 4340-B-SC 'I
Lot 129, Carlsbad Blvd. . August 1, 2005 '
File:e:\wpl2\4300\4340b.fcr * ' Page 4
•. . •• GeoSoits, Inc. • ,
.•
DEVELOPMENT CRITERIA
Slope Maintenance and Planting
Water has been shown to weaken the inherent strength of all earth materials. Slope
stability is significantly reduced by overly wet conditions. Positive surface drainage away
from slopes should be maintained and only the amount of irrigation necessary to sustain
plant life should be provided for planted slopes. Over-watering should be avoided as it
adversely affects site improvements, and causes perched groundwater conditions. Graded
slopes constructed utilizing onsite materials would be erosive. Eroded debris may be
minimized and surficial slope stability enhanced by establishing and maintaining a suitable
vegetation cover soon after construction. Compaction to the face of fill slopes would tend
to minimize short-term erosion until vegetation is established. Plants selected for
landscaping should be light weight, deep rooted types that require little water and are
capable of surviving the prevailing climate. Jute-type matting or other fibrous covers may
aid in allowing the establishment of a sparse plant cover. Utilizing plants other than those
recommended above will increase the potential for perched water, staining, mold, etc., to
develop. A rodent control program to prevent burrowing should be implemented.
Irrigation of natural (ungraded) slope areas is generally not recommended. These
recommendations regarding plant type, irrigation practices, and rodent control should be
provided to each homeowner. Over-steepening of slopes should be avoided during
building construction activities and landscaping.
Drainage
Adequate lot surface drainage is a very important factor in reducing the likelihood of
adverse performance of foundations, hardscape, and slopes. Surface drainage should be
sufficient to prevent ponding of water anywhere on a lot, and especially near structures and
tops of slopes. Lot surface drainage should be carefully taken into consideration during
fine grading, landscaping, and building construction. Therefore, care should be taken that
future landscaping or construction activities do not create adverse drainage conditions.
Positive site drainage within lots and common areas should be provided and maintained
at all times. Drainage should not flow uncontrolled down any descending slope. Water
should be directed away from foundations and not allowed to pond and/or seep into the
ground. In general, the area within 5 feet around a structure should slope away from the
structure. We recommend that unpaved lawn and landscape areas have a minimum
gradient of 1 percent sloping away from structures, and whenever possible, should be
above adjacent paved areas. Consideration should be given to avoiding construction of
planters adjacent to structures (buildings, pools, spas, etc.). Pad drainage should be
directed toward the Street or other approved area(s). Although not a geotechnical
requirement, roof gutters, down spouts, or other appropriate means may be utilized to
control roof drainage. Down spouts, or drainage devices should outlet a minimum of 5 feet
from structures or into a subsurface drainage system. Areas of seepage may develop due
to irrigation or heavy rainfall, and should be anticipated. Minimizing irrigation will lessen
Mr. Lance Johannsen W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. August 1, 2005
File:e:\wpl2\4300\4340b.fcr Page 5
GeoSoils, Inc.
this potential. If areas of seepage develop, recommendations for minimizing this effect
could be provided upon request.
Erosion Control
CUt and fill slopes will be subject to surficial erosion during and after grading. Onsite earth
materials have a moderate to high erosion potential. Consideration should be given to
providing hay bales and silt fences for the temporary control of surface water, from a
geotechnical viewpoint.
Landscape Maintenance
Only the amount of irrigation necessary to sustain plant life should be provided.
Over-watering the landscape areas will adversely affect proosed site improvements. We
would recommend that any proposed open-bottOm planters adjacent to proposed
structures be eliminated for a minimum distance of 10 feet.. 'As .an alternative,
closed-bottom type planters could be utilized. An outlet placed in the bottom of the
planter, could be installed to direct drainage away from structures or any exterior concrete
flatwork. If planters are constructed adjacent to structures, the sides and bottom of the
planter should be provided with a moisture barrierto prevent penetration of irrigation water
into the subgrade. Provisions should be made to drain the excess irrigation water from the
planters without saturating the subgrade below or adjacent to the planters. Graded slope
areas should be planted with drought resistant vegetation. Consideration should be given
to the type of vegetation chosen and their potential effect upon surface improvements (i.e.,
some trees will have an effect on concrete flatwork with their extensive root systems).
From a geotechnical standpoint leaching is not recommended for establishing
landscaping. If the surface soils are processed for the purpose of adding amendments,
they should be recompacted to 90 percent minimum relative compaction.
Gutters and Downspouts
As previously discussed in the drainage section, the installation of gutters and downspouts
should be considered to collect roof water that may otherwise infiltrate the soils adjacent
to the structures. If utilized, the downspouts should be drained into PVC collector pipes
or other non-erosive devices (e.g., paved swales or ditches; below grade, solid tight-lined
PVC pipes; etc.), that will carry the water away from the house, to an appropriate outlet, in
accordance with the recommendations of the design civil engineer. Downspouts and
gutters are not a requirement; however, from a geotechnical viewpoint, provided that
positive draihage is incorporated into project design (as discussed 'previously).
Subsurface and Surface Water
Subsurface and surface water are not anticipated to affect site development, provided that
the recommendations contained in this report are incorporated into final design and
Mr. Lance Johannsen . W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. August 1, 2005
FiIe:e:\wpl2\4300\4340b.fcr . . ' . Page 6
GeoSoils, Inc. . .
construction and that prudent surface and subsurface drainage practices are incorporated
into the construction plans. Perched groundwater conditions along zones of contrasting
permeabilities may not be precluded from occurring in the future due to site irrigation, poor
drainage conditions, or damaged utilities, and should be anticipated. Should perched
groundwater conditions develop, this office could assess the affected area(s) and provide
the appropriate, recommendations to mitigate the observed groundwater conditions.
Groundwater conditions may change with the introduction of irrigation, rainfall, or other,
factors.
Site Improvements
If in the future, any additional improvements (e.g., pools, spas, etc.) are planned for the
site, recommendations concerning the geological or geotechnical aspects of design and
construction of said improvements could be provided upon request. Pools and/or spas
should not be constructed without specific design and construction recommendations from
GSl, and this construction recommendation should be provided to' the homeowners, any
homeowners association, and/or other interested parties. This office should be notified in
advance of any fill placement, grading of the site, 'or trench backlilling after rough grading
has been completed. This includes any grading, utility trench and retaining wall backfills,
flatwork, etc.
Tile Flooring
Tile flooring can crack, reflecting cracks in the concrete slab below the tile, although small
cracks in a conventional slab may not be significant. Therefore, the designer should
consider additional steel reinforcement for concrete slabs-on-grade where tile will be
placed. The tile installer should consider installation methods that reduce possible
cracking of the tile such as slipsheets. Slipsheets or a vinyl crack isolation membrane
(approved by the Tile Council of America/Ceramic Tile Institute) are recommended
between tile and concrete slabs on grade.
Additional Grading
This office should be notified in advance of any fill placement, supplemental regrading of
the site, or trench backfilling after rough grading has been completed. This includes
completion of grading in the street, driveway approaches, driveways, parking areas, and
utility trench and retaining wall backfills.
Footing Trench Excavation
All footing excavations should be observed by a representative of this firm subsequent to
trenching and prior to concrete form and reinforcement placement. The purpose of the
observations is to evaluate that the excavations have been made into the recommended
bearing material and to the minimum widths and depths recommended for construction.
Mr. Lance Johannsen W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. August 1, 2005
File:e:\wp12\4300\4340b.fcr Page 7
GeoSoils, Inc.
If loose or compressible materials are exposed within the footing excavation, a deeper
footing or removal and recompaction of the subgrade materialswould be recommended
at that time. Footing trench spoil and any excess soils generated from utility trench
excavations should be compacted to a minimum relative compaction of 90 percent, if not
removed from thesite.
Trenching/Temporary Construction Backcuts
Considering the nature of the onsite earth materials, it should be anticipated that caving
or sloughing could be a factor in subsurface excavations and trenching. Shoring or
excavating the trench walls/backcuts at the angle of repose (typically 25 to 45 degrees
[except as specifically superceded within the text of this report]), should be anticipated.
AM excavations should be observed by an engineering geologist or soil engineer from GSI,
prior to workers entering the excavation or trench, and minimally conform to CAL-OSHA,
state, and local safety. codes.. Should adverse conditions exist, appropriate
recommendations would be offered at that time. The above recommendations should be
provided to any contractors and/or subcontractors, or homeOwners, etc., that may perform•
such work.
Utility Trench Backfill
All interior utility trench backfill should be brought to at least 2 percent above
optimum moisture content and then compacted to obtain a minimum relative
compaction of 90 percent of the laboratory standard. As an alternative for shallow
(12-inch to 18-inch) under-slab trenches, sand having a sand equivalent value of
30 or greater may be utilized and jetted or flooded into place. Observation, probing
and testing should be provided to evaluate the desired results.
Exterior trenches adjacent to, and within areas extending below a 1:1 plane
projected from the outside bottom edge Of the footing,and all trenches beneath
hardscape features and in slopes, should be compacted to at least 90 percent of
the laboratory standard. Sand backfill, unless excavated from the trench, should
not be used in these backfill areas. Compaction testing and observations, along
with probing, should be accomplished to evaluate the desired results.
3 All trench excavations should conform to CAL-OSHA, state and local safety codes
4. Utilities crossing grade beams, perimeter beams, or footings should either pass
below the footing or grade beam utilizing a hardened collar or foam spacer, or pass
through the footing or grade beam in accordance with the recommendations of the
structural engineer.
Mr. Lance Johannsen W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. August 1, 2005
File:e:\wpl2\4300\4340b.fcr Page 8
GeoSoils, Inc.
0
0
0
0
SUMMARY OF RECOMMENDATIONS REãARDING S
GEOTECHNICAL OBSERVATION AND TESTING
We recommend that observation and/or testing be performed by GSI at each of the
following construction stages: ..
During grading/recertification
During excavation.
During placement of subdrains, toe drains, or other subdrainage devices, prior to
placing fill and/or backfill
After excavation of building footings, retaining wall footings, and free standing walls
footings, prior to the placement of reinforcing steel or concrete.
Prior to pouring any slabs or flatwork, after presoaking/presaturation of building
pads and other flatwork subgrade, before the placement of concrete, reinforcing
'steel, capillary break (i.e., sand, pea-gravel, etc.), or. vapor barriers (i.e., visqueen,
etc.).
During retaining wall subdrain installation, prior to backfill placement.
During placement of backfill for area drain, interior plumbing, utility line trenches,
and retaining wall backfill.
During slope construction/repair.
When any unusual soil conditions are encountered during, any construction
operations, subsequent to the issuance of this report.
When any developer or homeowner improvements, such as flatwork, spas, 'pools,
walls, etc., are constructed, prior to construction GSI should review and approve -'
the plans .for such improvements prior to constructicn.
A report of geotechnical observation and testing should be provided at the
conclusion of each of the above stages, in order to provide concise and clear ,
documentation of site work, and/or to comply with code requirements:
GSI should review project sales documents to homeowners/homeowners
associations for geotechnical aspects, including irrigation practices, the conditions
outlined above, etc., prior to any sales. At that stage, GSI will provide homeowners
maintenance guidelines -which should be incorporated into such documents.
Mr. Lance Johannsen W.O. 4340-B-SC-;
Lot 129, Carlsbad Blvd. August 1, 2005
Fi!e:e:\wp12\43OO434Ob.fcr Page 9
GeoSoils, Inc.
OTHER DESIGN PROFESSIONALS/CONSULTANTS
The design civil engineer, structural engineer, post-tension designer, architect, landscape
architect, wall designer, etc., should review the recommendations provided herein,
incorporate those recommendations into all their respective plans, and by explicit
reference, make this report part of their project plans. This report presents minimum
design criteria for the design of slabs, foundations and other elements possibly applicable
to the project. These criteria should not be considered as substitutes for actual designs
by the structural engineer/designer. Please note that the recommendations contained
herein are not intended to preclude the transmission of water or vapor through the slab or
foundation. The structural engineer/foundation and/or slab designer should provide
recommendations-to not allow water or vapor to enter into the structure so as to cause
damage to another building component, or so as to limit the installation of the type of
flooring materials typically used for the particular application.
The structural engineer/designer should analyze actual soil-structure interaction and
consider, as needed, bearing, expansive soil influence, and strength, stiffness and
deflections in .the various slab, foundation, and other elements in order to develop
appropriate, design-specific details. As conditions dictate, it is possible that other
influences will also have to be considered. The structural engineer/designer should
consider all applicable codes and authoritative sources where needed. If analyses by the
structural engineer/designer result in less critical details than are provided herein as
minimums, the minimums presented herein should be adopted. It is considered likely that
some, more restrictive details will be required.
If the structural engineer/designer has any questions or requires further assistance, they
should not hesitate to call or otherwise transmit their requests to GSI. In order to mitigate
potential distress, the foundation and/or improvement's designer should confirm to GSI
and the governing agency, in writing, that the proposed foundations and/or improvements
can tolerate the amount of differential settlement and/or expansion characteristics and
other design criteria specified herein.
PLAN REVIEW
Any additional project plans (grading, precise grading, foundation, retaining wall,
landscaping, etc.), should be reviewed by this office prior to construction, so that
construction is in accordance with the conclusions and recommendations of this report.
Based on our review, supplemental recommendations and/or further geotechnical studies
may be warranted.
Mr. Lance Johannsen W.O. 4340-B-SC
Lot 129, Carlsbad Blvd. August 1, 2005
File:e:\wpl2\4300\4340b.fcr Page 10
GeoSoils, Inc.
LIMITATIONS
The materials encountered on the project site and utilized for our analysis are believed
representative of the area; however, soil and bedrock materials vary in character between
excavations and natural outcrops or conditions exposed during mass grading Site
conditions may vary due to seasonal changes or other factors.
Inasmuch as our study is based upon our review and engineering analyses and laboratory
data, the conclusions and recommendations are professional opinions. These opinions
have been derived in accordance with current standards of practice, and no warranty,
either express or implied, is given. Standards of practice are subject to change with time.
GSI assumes no responsibility or liability for work or testing performed by others, or their
inaction; or work performed When GSI is not requested to be onsite, to evaluate if our
recommendations have been properly implemented. Use of this report constitutes an
agreement and consent by the user to all the limitations outlined above, notwithstanding
any other agreements that may be in place. In addition, this report may be subject to
review by the controlling authorities. Thus, this report brings to completion our scope of
services for this portion of the project. All samples will be disposed of after 30 days, unless
specifically requested by the client, in writing. -
The opportunity to be of service is sincerely appreciated. If you should have any
questions, please do not hesitate to contact our office.
Respectfully submitted
/ 0AL Q 0N
(9G.C(o
gineering
GeOlOgist
Fn Engineering Geologist, q
RGC/JPF/DWS/jh
GeoSoils, Inc
Attachments: •Figure 1 - Corrosion Test Report'
Table 1 - Field Density Test Results
Appendix - References
Plate 1 - Field Density Test Location Map
Distribution: (4) Addressee
Mr. Lance Johannsen
Lot 129, Carlsbad Blvd.
File: e:\wpl 2\4300\4340b.fcr
GeoSoils, Inc.
W.O. 4340-B-SC
August 1, 2005
Page 11
M. J. Schiff & Associates, Inc.
Consulting Corrosion Engineers - Since 1959 - Phone: (909) 626-0967 Fax: (909) 626-3316
431 W. Baseline Road E-mail lab@mjschiff corn
Claremont, CA 91711 website: rnjschiff corn
Table 1 - Laboratory Tests on Soil Samples
Johnson
Your #4340-A-SC, MJS&A #04-0680LAB
14-May-04
Sample ID
B-i
Resistivity Units
as-received ohm-cm 11,000,000
saturated ohm-cm 2,400
pH 5.9
Electrical
Conductivity MS/cm 0.23
Chemical Analyses
Cations
calcium. Ca 2+ mg/kg 80
magnesium Mg 2+ mg/kg 19
1+sodium Na I mg/kg ND
Anions
carbonate C032 mg/kg ND
bicarbonate HC031 mg/kg 95
chloride Cl' mg/kg 65
sulfate so, 2 mg/kg 85
Other Tests
ammonium NH4 mg/kg na
nitrate NO3 mg/kg na
sulfide S 2-qual na
Redox mV na r
Electrical conductivity in millisiemens/cm and chemical analysis were made on a 1:5 soil-to-water extract.
mg/kg = milligrams per kilogram (parts per million) of dry soil.
Redox = oxidation-reduction potential in millivolts
ND = not detected
na = not analyzed
4340-B--SC
Figure 1
Mr. Lance Johannsen
Lot 129 Carlsbad Blvd
File: C:\excel\tables\4300\4340bJcr GeoSoils, Inc.
TEST DATE TEST LOCATION TRACT ELEV MOISTURE DRY REL TEST SOIL
NO. NO. OR CONTENT DENSITY COMP METHOD TYPE
DEPTH (ft) (%) lncf) (%)
1 7/12/05 Far NW Lot 129 49.0 9.8 1163 91.6 ND A
2 7/12/05 Far NW . Lot 129 50.0 10.6 1154 90.9 ND A
3 7/13/05 .W Middle Pad Lot 129 49.0 9.6 1184 93.2 ND A
4 7/13/05 SW @ Pad Lot 129 51.0 9.9 1176 92.6 ND A
5 7/13/05 SW @ Pad Lot 129 52.0 10.2 117.1 92.2 ND A
6 7/13/05 NE Middle Pad Lot 129 51.0 10.8 116.9 92.0 ND A
7 7/14/05 NE @ Pad Lot 129 52.0 10.0 117.4 92.4 ND A
.8 7/14/05 NE @ Pad Lot 129 53.0 9.8 117.6 92.6 ND A
9 7/15/05 W @ Pad Lot 129 53.0 . 10.8 116.9 92.0 ND A
.10 7/15/05 W@ Pad Lot 129 52.0 10.2 117.8 92.8 ND A
11 7/18/05 E @ Pad Lot 129 FG 9.8 117.3 92.4 ND A
12 7/18/05 W@Pad .Lot 129 FG 10.0 117.1 92.2 ND A
APPENDIX
REFERENCES
Carlsbad, City of, 1993, Standards for design and construction of public works
Improvements in the City of Carlsbad
GeoSoils, Inc., 2004a, Grading plan review, Lot 129, Map 3312, Johannsen residence,
Carlsbad Boulevard, Carlsbad, San Diego County, California, W.O. 4340-A-SC,
dated December 20
2004b, Geotechnical plan review of grading and drainage plans, sections, and wall
elevations and section, vacant lot located in the 5400. Block of Carlsbad Boulevard,
City of Carlsbad, San Diego County, California, W.O. 4340-Al-SC, dated June 30.
2004c, Soil corrosivity results vacant lot located in 5400 block of Carlsbad
Boulevard, city of Carlsbad, San Diego County, California, W.O. 4340-A-SC, dated
May 27.
2004d, Preliminary geotechnical evaluation, vacant lot located in 5400 block of
Carlsbad Boulevard city of Carlsbad San Diego County, California,
W.O. 4340-A-SC', dated May 18. . .
International Conference of Building Officials, 1997, Uniform Building Code
Johannsen, L, Undated, Grading plans for Lot 129, Map 3312, Carlsbad Boulevard,
Johannsen Residence, Project No CDP03-1 0 Drawing No 423-5A, undated
GeoSoils,. Inc.
-:
$ 4
-
4L
44 4 I
4 4
I I
4 4 4 4 4
14
Cl
4 4 f
I 1 I 4 I 4 I 4
4 4 i
4 1 r I /