HomeMy WebLinkAboutCDP 2017-0043; FRANCIS RESIDENCE; GEOTECHNICAL SUMMARY OF ROUGH GRADING; 2020-02-24Geotechnical • Geologic • Coastal • Environmental
5741 Palmer Way • Carlsbad, California 92010 • (760) 438-3155 • FAX (760) 931 -0915 • www.geosoilsinc.com
February 24, 2020
W.O. 7279-B/F-SC
Mr. Mark Francis
3385 Blodgett Drive
Colorado Springs, Colorado 80919
Subject: Interim Geotechnical Report of Rough Grading and Retaining Wall
Construction, Planned Single-Family Residence, 1585 Triton Street,
Carlsbad, San Diego County, California, Assessor's Parcel Number (APN)
215-070-51, City of Carlsbad Project No.: CDP2017-0043, Drawing
No.: 507-5A
Dear Mr. Francis:
In accordance with your request and authorization, GeoSoils, Inc. (GSI), is providing this
interim geotechnical report of rough grading and retaining wall construction within the
subject property, as shown on the project grading plans (Engineering Design Group
[EOG], 2019 [seethe Appendix]). During grading and retaining wall construction, line and
grade was the responsibility of others, and not GSI. A comprehensive final compaction
report, presenting the tabulated compaction test results and a map showing the
approximate locations of the compaction tests, and the as-graded geotechnical conditions
will be provided at the conclusion of all earthwork construction activities within the subject
property. Unless specifically superseded herein, the conclusions and recommendations
provided in the referenced geotechnical reports (see the Appendix), are still considered
valid and applicable, and should be appropriately implemented during the balance of
project design and construction.
SUMMARY OF GRADING AND RETAINING WALL CONSTRUCTION
Grading and retaining wall construction within the subject property began around the
middle of January 2020 and was generally completed on February 21, 2020. Geotechnical
. observation and field density testing during rough grading and retaining wall construction
were performed on an as-needed part-time basis as requested by the project general
contractor.
Initial earthwork operations involved the excavations for the San Diego Regional Standard
(SDRSD) C-04 retaining wall foundation along the southerly and westerly property lines,
and the SDRSD C-02 retaining wall foundation near a portion of the easterly property
margin. The retaining wall foundation excavations were observed to extend into suitable
bearing materials and were completed in general accordance with GSI recommendations.
Following construction of the retaining wall footings and stem, subdrains were installed
behind the retaining walls and the walls were backfilled. Where performed, our
observations indicated that the wall subdrain construction generally conformed to GSI
recommendations. Observations and field density testing indicated that the retaining wall
backfill was compacted to at least 90 percent of the laboratory standard (per ASTM D
1557), where tested.
Remedial grading in the existing building pad was performed concurrently with the
retaining wall backfill. This included the removal and recompaction of undocumented
artificial fill as well as weathered, near-surface structural fill materials placed during the
original phase of site grading in early 2004 (GSI, 2004). In general, remedial grading
excavations within the existing building pad extended to depths on the order of 18 inches
below the existing grades. Following backfill of the SDRSD C-04 retaining
walls, 2:1 (horizontal:vertical [h:v]) fill slopes were constructed above these walls and
along a portion of the northerly side of the lot. Prior to constructing the 2: 1 (h:v) fill slope
along the northerly side of the property, approximately 1 foot of weathered, near surface
fill materials were removed to expose the underlying, suitable fill materials placed during
the original phase of site grading, conducted in early 2004 (GSI, 2004). Import fill materials
consisting of manufactured sand were blended with the onsite earth materials in order to
achieve the planned grades. Where conducted, our observations and field density testing
indicated that remedial grading was performed in general accordance with GSI
recommendations and fills were compacted to at least 90 percent of the laboratory
standard (per ASTM D 1557).
LABORATORY TEST RESULTS
General
GSI evaluated the expansion potential of soils exposed near pad grade within the building
pad area. The results of the expansion index testing are summarized in the following
section. Testing to evaluate the corrosion potential of the soils exposed near pad grade
is currently in progress. Corrosion test results will be provided under a separate cover
when they become available.
Expansion Index Testing
A representative sample of compacted fill material, exposed near pad grade was evaluated
in the laboratory for expansion potential. Expansion Index (E.1.) testing and expansion
potential classification were performed in general accordance with ASTM Standard D 4829.
The results of the expansion index testing are presented in the following table:
I EXPANSION INDEX I EXPANSION POTENTIAL I
I <5 I Very Low
E.I. = 0-20 -Very Low Expansion Potential, E.I. = 21 to 50 -
Low Expansion Potential, E.I. = 51 to 90 -Medium
Expansion Potential, E.I. = 91 to 130 -High Expansion
Potential, E.I. > 131 -Very High Expansion Potential
Francis
1585 Triton Street, Carlsbad
File:e:\wp12\7200\7279bf.igr GeoSoils, In~.
I
W.O. 7279-8/F-SC
February 24, 2020
Page 2
CONCLUSIONS
Based on our observations and testing, grading, retaining wall foundation and subdrain
construction, and fill compaction within the subject property were performed in general
accordance with the recommendations contained in GSI (2017) and the requirements of
EOG (2019). Therefore, it is our opinion that the prepared lot is suitable for its intended use
from a geotechnical engineering perspective. The expansion potential of the compacted
fill, exposed near pad grade is very low. Thus, the foundation design shown on Specialty
Steel (2018) is appropriate for the as-graded soil conditions described in this report.
RECOMMENDATIONS
The follow geotechnical recommendations should be incorporated into the balance of
project design and construction:
• Remedial grading should be performed in the planned driveway area prior to
driveway subgrade preparation.
• Pad grade soils should moisture conditioned to a depth of at least 12 inches
within 72 hours prior to the placement of the underlayment sand and vapor retarder.
• The building foundation excavations should be observed by a representative of this
firm prior to placement of the reinforcement and concrete.
• All additional earthwork within the subject property should be performed under the
observation and testing of GSI.
• The onsite earth materials are considered erodible. Thus, surface drainage should
be directed away from the building foundations and the tops of slopes. Surface
drainage should be properly maintained throughout the life of the project. In the
respite between the conclusion of grading and final landscaping, all slopes should
received the approved erosion control measures.
LIMITATIONS
Inasmuch as our study is based upon our review and engineering analyses and laboratory
data, the conclusions and recommendations are professional opinions. These opinions
have been derived in accordance with current standards of practice, and no warranty,
either express or implied, is given. Standards of practice are subject to change with time.
GSI assumes no responsibility or liability for work or testing performed by others, or their
inaction; or work performed when GSI is not requested to be onsite, to evaluate if our
recommendations have been properly implemented. Use of this report constitutes an
agreement and consent by the user to all the limitations outlined above, notwithstanding
any other agreements that may be in place. In addition, this report may be subject to
review by the controlling authorities.
Francis
1585 Triton Street, Carlsbad
File:e:\wp12\7200\7279bf.igr GeoSoils, Inc.
W.O. 7279-8/F-SC
February 24, 2020
Page 3
The opportunity to be of service is appreciated. If you should have any questions, please
do not hesitate to contact our office.
Respectfully submitt
Ge0S01ls, Inc.
b:1.7::!
Engineering Geologi
/[~·
R/4n-B. Boehmer
Project Geologist
ee
Civil Engineer, RCE
RBB/JPF /DWS/mn
Attachments: Appendix -References
Distribution:
Francis
(1) Addressee (wet signed via US mail and email)
(2) Coble Homes, Attention: Mr. Matt Coble
1585 Triton Street, Carlsbad
File:e:\wp12\7200\7279bf.igr GeoSoils, Inc.
W.O. 7279-B/F-SC
February 24, 2020
Page 4
APPENDIX
REFERENCES
American Concrete Institute, 2014, Building code requirements for structural concrete (ACI
318-14), and commentary (ACI 318R-14): reported by ACI Committee 318, dated
September.
American Concrete Institute (ACI) Committee 302, 2004, Guide for concrete floor and slab
construction, ACI 302.1 R-04, dated June.
American Society for Testing and Materials (ASTM), 1998, Standard practice for installation
of water vapor retarder used in contact with earth or granular fill under concrete
slabs, Designation: E 1643-98 (Reapproved 2005).
__ , 1997, Standard specification for plastic water vapor retarders used in contact with
soil or granular fill under concrete slabs, Designation: E 17 45-97 (Reapproved
2004).
California Building Standards Commission, 2016, California Building Code, California Code
of Regulations, Title 24, Part 2, Volume 2 of 2, based on the 2015 International
Building Code, 2016 California Historical Building code, Title 24, Part 8, 2016
California Existing Building Code, Title 24, Part 10, and the 2015 International
Existing Building Code.
Engineering Design Group, 2019, Grading plans for: Francis Residence, Sheets 1 through
3 of 5, various scales, City of Carlsbad Project No.: CDP2017-0043, City of Carlsbad
Drawing No.: 507-5A, dated November 13.
GeoSoils, Inc., 2018, Geotechnical review of grading and post-tension foundation plans,
planned single-family residence, 1585 Triton Street, Carlsbad, San Diego County,
California, Assessor's Parcel Number (APN) 215-070-51, W.O. 7279-A-SC, dated
April 13.
__ , 2017, Geotechnical update evaluation, proposed single-family residence off of
Triton Street, Carlsbad, San Diego County, California, Assessor's Parcel Number
(APN) 215-070-51, W.O.7279-A-SC, dated June 9.
__ , 2004, Final compaction report of grading, Parcels 1 and 3, 6575 Black Rail Road,
Carlsbad, San Diego County, California, W.O. 3460-B-SC, dated March 9.
__ , 2002a, Soil corrosivity test results, 6575 Black Rail Road, City of Carlsbad, San
Diego County, California, W.O. 3460-A 1-SC, dated December 20.
__ , 2002b, Preliminary geotechnical evaluation, 6575 Black Rail Road, proposed
subdivision, Carlsbad, San Diego County, California, W.O. 3460-A-SC, dated
November 27.
Specialty Steel, 2018, Francis residence, 1585 Triton Street, Carlsbad, California, Sheets
PTO, PTHD, and PT-1, scale: ¼-inch = 1 foot, dated March 29.
GeoSoils, Inc.