HomeMy WebLinkAboutCT 00-02; CALAVERA HILLS 2; REVISED PAVEMENT DESIGN REPORT; 2004-05-03L
Geotechnical Geologic. Environmental
5741 Palmer Way •• Carlsbad, California 92008 • (760) 438-3155 • FAX (760) 931-0915
May 3, 2004
- W.O. 3459-E-SC
Calavera Hills II, LLC
2727 Hoover Avenue
National City, California 91950
Attention: Mr. Don Mitchell
Subject: Revised Pavement Design Report, Calavera Hills 11, City of
Carlsbad, San Diego County, California
Dear Mr. Mitchell:
In accordance with your request, GeoSoils, Inc. (GSI) has prepared preliminary design and
construction recommendations for asphalt concrete (AC) pavement at the subject site. The
scope of services provided in preparation of this report included representative sampling
of the street subgrade, R-value testing, and engineering analysis of pavement design.
PAVEMENT DESIGN
Pavement section design was performed in accordance with the California Department of
Transportation (Caltrans) Highway Design Manual of Instructions and the City of Carlsbad
'Standard Drawings (see the Appendix). Pavement sections presented are based on the
aforementioned criteria and resistance value (R-value) data (see the attached
Figures 1 through 4), determined from soils exposed at, or near, final subgrade elevations
within the subject areas; A-value testing was performed in accordance with the latest
revisions to the Department of Transportation, State of California, Material & Research Test
Method No. 301. Pavement design was aided with the computer software programs PAVE
and NEWCON90.
ASPHALT CONCRETE PAVEMENT
Structural Section
R-values ranging from 27 to 54 were determined for subgrade soils onsite, and used in
pavement design. The recommended pavement sections are presented in the following
table:
:: .'. .. ... •.. .•-;....
A.C.BASE
- TRAFFIC SUBGRADE THICKNESS THICKNESS''2'
TRAFFIC AREA. INDEX . R-VALUE.. .. (lnche :-:.:4lnâhes)
Claywood Court 5.0 27 4.0 4.0
Stations 10+-00 to 1629
Traliwood Court 5.0 39 4.0 4.0
Stations 10+2 to 19+10
Earthwood Court 5.0 54 4.0 4.0
Stations 1 W to 17
Cobblecreek Court 5.0 39 4.0 4.0
Stations 1029 to 21
Greenbriar, All Stations 5.0 39 4.0 4.0
City minimum
Denotes Class 2 Aggregate Base ® >78, SE 25)
All pavement installation, including preparation and compaction of suççIe, compaction
of base material,,, and placement and rolling of asphaltic concrete,é1l4 be done in
accordance with the City guidelines and under the observation and testing of the project
geotechnical engineer and/or City.
The recommended pavement sections are meant as minimums. If thinner or highly
variable pavement sections are ppnstructed, increased maintenance and repair may be
needed. Positive site drainage-tIId-be maintained at all times. Water" not be
allowed to pond or seep into the ground. If planters or landscaping are adjacent to paved
areas, measures should be taken to minimize the potential for water to enter the pavement
section. If the ADT (average daily traffic) or ADIT (average daily truck traffic) increases
beyond that intended, as reflected by the traffic index(s) used for design, increased
maintenance and repair could be required for the pavement section.
Calavera Hills II, LLC • W.O. 3459-E-SC
Calavera Hills II, Village X May 3, 2004
FiIe:e:\wp9\3400\3459e.x.rpdr Page 2 GeoSoils, Inc.
PAVEMENT GRADING RECOMMENDATIONS
General
satC
All section changes.shotId be properly transitioned. If adverse conditions are encountered
during the preparation of subgrade materials, special construction methods may need to
be employed. A GSI representative should be present for the preparation of subgrade,
base rock, and asphalt concrete.
Subgrade
SMLL Within street and parking areas, all surficial deposits of loose soil material siettfd be
removed and recompacted as recommended. After the loose soils are removed, the
bottom is to be scarified to a depth of at least 12 inches, moisture conditioned as
necessary, and compacted to 95 percent of the maximum laboratory density, as
determined by ASTM Test Designation D-1 557.
Deleterious material, excessively wet or dry pockets, concentrated zones of ov%sLz2cljock
fragments, and any other unsuitable mt2l encountered during grading s1&1 be
removed. The compacted fill material ithen bbç9Jght to the elevation of the
proposed subgrade for the pavement. The subgradeh be proof-rolled in order to
ensure a uniform firm and unyielding surface. All grading and fill placement should be
observed by the project soil engineer and/or his representative.
Base Rock
Compaction tests are required for the recommended base section. Minimum relative
compaction required will be 95 percent of the laboratoryrimum density as determined
by ASTM Test Designation D-1557. Base aggregate 4of-be in accordance with the
"Standard Specifications for Public Works Construction" (green book), 1997 edition, or
standard Caltrans Class 2 base rock (minimum A-value = 78).
Paving
Prime coat may be omitted if all of the following conditions are met:
The asphalt pavement layer is placed within two weeks of completion of base
and/or subbase course.
Traffic is not routed over completed base before paving.
Construction is completed during the dry season of May through October.
The base is kept free of debris prior to placement of asphaltic concrete.
Calavera Hills II, LLC W.O. 3459-E-SC
Calavera Hills II, Village X May 3, 2004
File:e:\wp9\3400\3459e.x.rpdr Page 3
GeoSoils, Inc.
If construction is performed during the wet season of November through April, prime coat
may be omitted if no rain occurs between completion of base course and paving and the
time between completion of base and paving is reduced to three days, provided the base
is free of loose soil or debris. Where prime coat has .been omitted and rain occurs, traffic
is routed over base course, or paving is delayed, measures shall be taken to restore base
course and subgrade to conditions that will meet specifications as directed by the soil
engineer.
Drainage
Positive drainage eottfd be provided for all surface water to drain toward the curb and
gutter, or to an appjpve,d, drainage channel. Positive site drainage&6be maintained
at all times. Water not be allowed to pond or s j to the ground. If planters or
landscaping are adjacent to paved areas, measurest4eiM be taken to minimize the
potential for water to enter the pavement section, such as cut-off walls, etc..
LIMITATIONS
The materials encountered on the project site and utilized in our laboratory study are
believed to be representative of the total area. However, variations from the anticipated
conditions and actual field conditions should be expected. Test excavations are reflective
of the soil and rock materials only at the specific location explored. Site conditions may
vary due to seasonal changes or other factors.
Since our study is based on the earth materials obtained in the field onsite, selective
laboratory testing, and engineering analyses, the conclusions and recommendations are
professional opinions based upon those parameters. These opinions have been derived
in accordance with the current standards of practice and no warranty is expressed or
implied. Standards of practice are subject to change in time. Overall, the enclosed results
represent our professional opinions and evaluations which were performed within the
constraints of a budget. GSI assumes no responsibility or liability for work or testing
performed by others.
Caiavera Hills ii, LLC W.O.3459-E-SC
Caiavera Hills ii, Village X May 3, 2004
File:e:\wp9\3400\3459e.x.rpdr Page 4
GeoSoils, Inc.
The opportunity to be of service is greatly appreciated. If you have any questions, please
do not hesitate to call our office.
Respectfully submitt ?
GeoSoils, Inc. , . Reviewed by: /
Eyp
cu JO _
Robert G. Crisman ''Q?p D avid W. Skell
Engineering Geologist, 4 Civil Engineer, R 47
RGC/J PF/D WS/j k
Attachments: Figures 1 through 4 - R-value Test Results
Appendix - References
Distribution: (1) Addressee
(2) Jobsite, Attention: Mr. Tom LaMarca
(2) City of Carlsbad, Attention: Mr. Joe McMahon
Calavera Hills ii, LLC W.O. 3459-E-SC
Calavera Hills II, Village X May 3, 2004
File: e:\wp9\3400\3459e.x.rpdr Page 5
GeoSoils, Inc.
The opportunity to be of service is sincerely appreciated. If you should have any que
please do not hesitate to contact our office.
15
Respectfully sub r
qi
GeoSoils, Inc (f'b jg34\\\ Reviewed by
Robert G. Crisman OF ',%,A David W. Skelly
Engineering Geologist, C 1934 Civil Engineer, RICE 47857
RGC/JPF/bWS/jk
Attachments: Figures 1 through 4 - R-value Test Results
Appendix - References
Distribution: (1) Addressee
(2) Jobsite, Attention: Mr. Tom LaMarca
(2) City of Carlsbad, Attention: Mr. Joe McMahon
Calaverá Hills II, LLC - W.O. 3459-E-SC
Calavera Hills II, Village X May 3, 2004
FiIe:e:\wp9\3400\3459e.x.rpdr - Page 5
GeóSoils, Inc.
TEST SPEC IMAN A B. C b
Compactor air pressure PSI 280 160 120
Water added: % 0.9 .1 .8 2.7
Moisture at compaction % 8.0 8.9 9.9
- Heightofsañiple IN. 2.32 2.36 2A2
Dry density; PCF 134.3 131.8 128.4
R-Value by exudation 44 30 22 - R-Valueby exudation, corrected 39 27 21
Exudation pressure PSI 498 310 186
Stability thickness FT 0.651 0.811 0.90
Exansion.pressure thickness FT 0.001 0.001_.0.00
DESIGN- CALCULATION DATA
Traffic index, assumed 4.5
Gravel equivalent factor, assumed 1.25
Expansion, stability equilibrium 0
R-Valuëbyexpansion NA
R-Va!ué by exudation 27
R-Vatüeat equilibrium 27
fr -IWL
k • (41
-
Iy'ry'
'nrTrITTr r
__ I1
Traffic index, assumed . . 4.5
Gravel equivalent factor1 assumed 1.25
Expansion, stability equilibrium 0
R-Value:by expansion. NA
R-Value.by exudation . 39
R-Value at equilibrium . 39
Cl, Cl,. 50
U
I-
a U,1.00 Cl,
0
C 0.
U, C c0.50 CL
LU
___
SAMPLE INFORMATION
____
Sample Location: Trailwood 10+00-19+30
____
Sample Description: Dark Gray Silty Gravel W/ Sand
____ Notes:. RV-2
36% Retained On 3/4 inch sieve
Test Method: Cal-Trans Test 301
R-Value By Exudation
Expansion, Stability Equilibrium
2.00
80
_
0.00
70
60
50
40
30
20
10
0
0.00 0.50 . 1.00. 1.50 2.00 . 800 700 600 500 400 300 200. 100 0
Stability Thickness (ft) . Exudation Pressure (psi)
R -VALUETEST RESULTS GeoSoils, Inc. . .
5741 Palmer Way . Project: MCMILLIN
Carlsbad, CA 92008
Telephone: (760) 438-3155 Number: 3459X-E-SC
Fax: (760) 931-0915 . . . . . .
Date: Feb-04 Figure: . .2
DESIGN CALCULATION DATA
TEST SPECIMAN A B C -. ;D
Compactor air pressure PSI 350 240 20'_________ Water added % 0.0 08 2.6 -
Moisture at compaction % 6.2 7.1 .. 9.0
Height of sample IN 2.31 2.33 2.4
Dry density - PCF 136.6 135.1 125.8
R-Valueby.exudation 61 41 13
R-VaIüeby, exudation, corrected 56 37 13
Exudation pressure I PSI 5961 281 111
Stability thickness. . FT 0.451.0.68 1.00
Expansion pressure thickness FT 0.001 0.00 0.00
TEST SPECIMAN A. B .0 D
Compactor air pressure . PSI 350 . 350 350
Water added % 1.7 2.6 3.8
Moisture, at. compaction . % 8.0 9.0 . 10.4
Height of sample . IN 2.31 2.33 2.53
Dry density . . PCF 137.4 135.9 1244
R.-Valueby,exudation . . 89 79 44
R-Value by exudation, corrected 88. 78 44
Exudation.pressure. . . PSI 691 463 243
Stability thickness. . . FT 0.131. 0.24 .0.65
Expansion pressure thickness . FT 0.00 0.00 0.00
DESIGN CALCULATION DATA SAMPLE INFORMATION
Sample Location: Earthwood Ct. 10+00-17+50
Sample Description: . Dark Gray Silty Gravel W/ Sand
Notes: RV-3
40% Retained on 3/4 inch sieve
Test Method: Cal-Trans Test 301
R-Value By Exudation
00 Expansion, Stability Equilibrium
2.00
80
70
60
C)
50
40
30
20
10
0 0.00
0.00 0.50 1.00 .1 .50 2..00 800 700 600 500 400 300 200 100 0
Stability Thickness (ft) . . . Exudation Pressure (psi)
R- VALUE TEST RESULTS GeoSoils, Inc. .. .
(TZ 5741 Palmer Way Project: MCMILLIN
Carlsbad, CA 92008 . . . .
:Telephone: (760)438-3155 . . Number. 3459X-E- SC
Fax: (760)931-0915 • . . .
Date Feb-04 Figure 3
Traffic index, assumed . 4.5
Gravel equivalent factor, assumed 1.25
Expansion, "stability equilibrium 0
,R-ValUe by expansion : NA
RValue by exudation . . 54 .
R-Value at equilibrium 54
DESIGN CALCULATION DATA
index,_assumed .Traffic 4.5
Gravelequivalent factor,assumed 1.25
Expansion, stability equilibriurn 0
R.Value by expansion NA
R-Value by exudation 39
R-Value at equilibrium 39
xpansioh, Stability Equilibrium
TEST SPECIMAN A B 'C.. D 1
Cornpactor'airpressure PSI :_350 240 '130
Water added % 1.3 2.2 3.0
Moistureat_compaction % 7_1 8_1 9_0
Heightofsample ____, IN. 2.31 2.37 2.44
Dry density _______' PCF 136.9 132.9 129:1
R-Valuebyexudation _, 65 46 32
R-Value by_ exudation, corrected 60 42 30
Exudationpressure PSI 509 339 210
Stabilitythickness FT 0.40 0.62, _0.78
Expansionpressure thickness . _. FT 0.00 0;00 0.00
SAMPLE INFORMATION'.
Sample Location: Cobblecrèek10+00-21+00
Sample Description: DarkGraySiltyGravel W/ Sand
Notes: ' GreenbriarRV-4
53% Retained on 3/4 inch sieve
Test Method: :Cal-Trans Test 301.
R-Value By Exudation
100
90 2.00 .
(n. U, U. 50
I—
U
1.00
CL
0
U' C m0.50 0.
w
0.00
80"
70
60
50*
U >
40
30
20
10
0
0.00 0.50 , . 1.00 , 1.50 2.00 ' ' 800 700 600 500 400 300 200 .100 0
Stability Thickness (ft) ' Exudation Pressure (psi).
R-VALUE TEST RESULTS GeoSoils, Inc.
ç 5741 Palmer Way . Project: MCMILLIN ' 4o, . Carlsbad, CA 92008
Telephone: (760) 438-3155
, ' , Number: 3459X-E-SC
Fax: (760) 931-0915
Date: 'Feb-04 Figure: _4
APPENDIX
REFERENCES
American Public Works Association, 2000, "Greenbook" standard specification for public
works construction.
California Department of Transportation, 1995, Caltrans, standard specifications, July
printing.
Carlsbad, City of, 1993, Standards for design and construction of public works
improvements in the City of Carlsbad.
NEWCON90, 1991 Computer program for the determination of asphalt pavement sections,
version: April 30.
PAVE; Computer program for the determination of asphalt concrete pavement sections.
State of California, Department of Transportation, 1987, Highway design manual of
instructions, fourth edition:
GeoSoils, Inc.