HomeMy WebLinkAboutCT 02-11; TUSCANY BY THE SEA TOWNHOMES; GEOTECHNICAL UPDATE; 2005-03-29RECEIVED
ENGINEERING
DEPARTMENT
Geotechnical • Geologic • Environmental
5741 Palmer Way • Carlsbad, California 92008 • (760)438-3155 • FAX (760) 931-0915
March 29, 2005
W.0.3111-A2-SC
Mr. Randall K. Locket
391 Tannarack Avenue
Carlsbad, California 92008
Subject: Geotechnical Update, 391 Tamarack Avenue, Tuscany by the Sea Town
Homes, Carlsbad, San Diego County, California
Dear Mr. Locket
In accordance with a request and authorization, GeoSoils, Inc. (GSI), has prepared this
letter for the purpose of updating our previous referenced reports (seethe Appendix). This
update is based on visual observations made during a site reconnaissance, performed on
March 28,2005, and a review ofthe referenced plans and GSI's previous reports (see the
Appendix).
Recommendations contained in the previous reports, which are not specifically
superceded by this review, should be properly incorporated into the design and
construction phases of site development.
CONCLUSiONS AND RECOMMENDATIONS
Geotechnically, the subject site is in essentially the same condition as it appeared during
the preparation of our previous reports (see the Appendix). Based upon our review of the
current plans (see the Appendix), the proposed development ofthis site is consistent with
that described in our previous reports. Therefore, the referenced geotechnical reports are
considered relevant and applicable to the proposed construction.
The conclusions and recommendations presented herein are professional opinions. These
opinions have been derived in accordance with current standards of practice and no
warranty is expressed or implied. Standards of practice are subject to change with time.
GSI assumes no responsibility for work, testing or recommendations performed or
provided by others.
The opportunity to be of service is greatly appreciated. If you have any questions, please
do not hesitate to call our office.
Respectfully submitted^
loils, inc.
n P. Franklin
gineering Geologist, CET
BV/DWS/JPF/jk
Attachment: Appendix - References
David W. Skelly
Civil Engineer, RCE 47857
Distribution: (2) Addressee
(2) Snipes-Dye Associates, Attention: Mr. Son Nguyen
Mr. Randall K. Locket
391 Tamarack Avenue, Carlsbad
File:e:\wp9\3100\3111 a2.gum3
W.O. 3111-A2-SC
March 29. 2005
Page 2
GeoSoils, Inc.
APPENDIX
REFERENCES
GeoSoils, Inc., 2005, Geotechnical review of grading plans, 391 Tamarack Avenue,
Carlsbad, San Diego County, California, W.O. 3111-A1-SC, dated February 22.
, 2001, Preliminary geotechnical evaluation, 391 Tamarack Avenue, Carlsbad,
California, W.O. 3111-A-SC, dated August 31.
International Conference of Building Officials, 2001, California building code, California
code of regulations title 24, part 2, volume 1 and 2.
, 1997, Uniform building code: Whittier, California, vol. 1, 2, and 3.
Snipes-Dye Associates, 2005, Grading and erosion plans for: Tuscany by the Sea Town
Homes, Project no. CT-02-11, dated January 13.
GeoSoils, Inc.
2S
PRELIMINARY GEOTECHNiCAL EVALUATION
391 TAMARACK AVENUE
CARLSBAD, CALIFORNIA
FOR
RANDALU K. LOCKETT
391 TAMARACK AVENUE
CARLSBAD, CALiFORNIA 92008
W.O. 3111-A-SC
jp
r 0 j .1^
Geotechnical • Geologic • Environmental
5741 Palmer Way • Carlsbad, California 92008 • (760)438-3155 • FAX (760) 931-0915
August 31,2001
W.O. 3111-A-SC
Randall K. Lockett
391 Tamarack Avenue
Carlsbad, California 92008
Subject: Preliminary Geotechnical Evaluation, 391 Tamarack Avenue, Carlsbad,
California
Dear Mr. Lockett:
In accordance with your authorization and request, GeoSoils, Inc. (GSI) has performed a
preliminary geotechnical investigation of the subject property. The purpose of the study
was to evaluate the onsite soils and geologic conditions and their effects on the proposed
site development from a geotechnical viewpoint.
EXECUTIVE SUMMARY
Based on our review of the available data (Appendix A), field exploration, laboratory
testing, and geologic and engineering analysis, the proposed development appears to be
feasible from a geotechnical viewpoint, provided the recommendations presented in the
text ofthis report are properly incorporated into the design and construction ofthe project.
The most significant elements of this study are summarized below:
• Removals of all existing fill and the upper 1 to 2 feet of weathered terrace deposits
are recommended. Removal depths are anticipated to be on the order of 2 to 3 feet
in areas proposed for settlement sensitive improvements.
• Our laboratory test results indicate that soils onsite are generally low in expansion
potential. Sulfate testing indicates that site soils have a negligible exposure to
concrete per Table 19-A-4 ofthe 1997 UBC (sample=0.000 percent by weight).
Corrosion testing (ph, resistivity) indicates that the soils are essentially neutral
(pH=7.2) and moderately corrosive to ferrous metals (saturated
resistivity=3,450 ohms-cm). Alternative methods and additional comments should
be obtained by a qualified corrosion engineer.
Subsurface water is not anticipated to affect site development, provided that
recommendations contained in this report are incorporated into final design and
construction and that prudent surface and subsurface drainage practices are
incorporated into the construction plans. Perched groundwater may be
encountered during grading, or may occur after site development.
Based on field mapping in the vicinity of the site, the presence of numerous
paleoliquefaction features ("sand blows," liquefaction craters, sand filled fissures
and injection dikes, sand vents, etc.), may exist within the site. Potential liquefaction
of such areas in the future that may impact surface improvements is considered
very low, provided that the recommendations presented in this report are
incorporated into the design and construction of the project. Mitigation for
structures may be provided by the use of post tensioned slabs. Mitigation in other
areas may be accomplished by overexcavation and/or geotextiles, as evaluated in
the field during grading, based on proposed development and use.
Based on the presence of paleoliquefaction features that likely may exist, and
potentially liquefiable soils in areas of the site, post tensioned foundations are most
suitable for this project. However, conventional foundations may be suitable in
some areas, based on conditions disclosed during grading.
The seismicity acceleration values provided herein should be considered during
the design of the proposed developmenL
The geotechnical design parameters provided herein should be considered during
project planning, design and construction by the project structural engineer and/or
architects.
Randall K. Lockett W.O. 3111 -A-SC
File:e:\vi/p7\3100\3111 a.pge Page Two
GcoSoils, Inc.
The opportunity to be of service is greatly appreciated. If you have any questions
concerning this report or if we may be of further assistance, please do not hesitate to
contact any of the undersigned.
Respectfully submitted,
GeoSoils, Inc.
Jryan voss
Staff Geologist
Reviewed by
Engineering Geologist,
BV/JPF/DWS/jh
Distribution: (4) Addressee
Reviewed by
/DaMid W. Skel Skelly
Civil Engineer, RCE
Randall K. Lockett
File:e:\wp7\3100\3111 a.pge
W.O. 3111-A-SC
Page Three
GcoSoils, Inc.
TABLE OF CONTENTS
SCOPE OF SERVICES 1
SITE DESCRIPTION 1
PROPOSED DEVELOPMENT 1
FIELD STUDIES 3
REGIONAL GEOLOGY 3
EARTH MATERIALS 3
Artificial Fill - Undocumented (Not Mapped) 3
Terrace Deposits (Map Symbol - Qt) 4
FAULTING AND REGIONAL SEISMICITY 4
Faulting 4
Seismicity 6
Seismic Shaking Parameters 6
GROUNDWATER 7
UQUEFACTION 7
OTHER GEOLOGIC HAZARDS 8
LABORATORYTESTING .• 8
Classification 8
Laboratory Standard 8
Direct Shear Tests 9
Expansion Potential 9
Corrosivity 9
DISCUSSION AND CONCLUSIONS 10
General 10
Earth Materials 10
Expansion Potential 10
Corrosion/Sulfate Testing 11
Subsurface and Surface Water 11
Liquefaction 11
Regional Seismic Activity 11
GcoSoils, Inc.
EARTHWORK CONSTRUCTION RECOMMENDATIONS 12
General 12
Site Preparation 12
Removals (Unsuitable Surficial Materials) 12
Fill Placement 13
Erosion Control 13
FOUNDATION RECOMMENDATIONS 13
Preliminary Foundation Design 14
Bearing Value 14
Lateral Pressure 14
Construction 14
Very Lowto Low Expansion Potential (Expansion Index 0 to 50) 14
PRELIMINARY POSTTENSIONED SLAB FORMATION SYSTEM RECOMMENDATIONS
15
General 15
Foundation Settlements 17
Subgrade Preparation 17
Perimeter Footings and Pre-Wetting 17
CONVENTIONAL RETAINING WALL RECOMMENDATIONS 18
General 18
Restrained Walls 19
Cantilevered Walls 19
Wall Backfill and Drainage 19
Retaining Wall Footing Transitions 23
FLATWORK AND ASSOCIATED IMPROVEMENTS 23
Tile Flooring 24
Gutters and Downspouts 24
Exterior Slabs and Walkways 25
ADDITIONAL RECOMMENDATIONS/DEVELOPMENT CRITERIA 25
Additional Site Improvements 25
Landscape Maintenance and Planting 26
Drainage 26
Footing Trench Excavation 27
Trench Backfill 27
PLAN REVIEW 28
LIMITATIONS 28
Randall K. Lockett Table of Contents
File: e:\wp7\3100\3111 a.pge Page ii
GcoSoils, Inc.
FIGURES:
Figure 1 - Site Location Map 2
Figure 2 - California Fault Map 5
Figure 3 -Schematic of Site Wall Drain Option A 20
Figure 4 -Schematic of Site Wall Drain Option B 21
Figure 5 -Schematic of Site Wall Drain Option C 22
ATTACHMENTS:
Appendix A - References Rear of Text
Appendix B - Boring Logs Rear of Text
Appendix C - Laboratory Test Results Rear of Text
Appendix D - General Earthwork and Grading Guidelines Rear of Text
Plate 1 - Boring Location Map Rear of Text in Pocket
Randall K. Lockett Table of Contents
Rle: e:\wp7\3100\3111 a.pge Page iii
GcoSoils, Inc.
PREUMINARY GEOTECHNICAL EVALUATION
391 TAMARACK AVENUE
CARLSBAD, CAUFORNIA
SCOPE OF SERVICES
The scope of our services has included the following:
1. Review of available soils and geologic data for the site area (Appendix A).
2. Geologic site reconnaissance and geologic mapping.
3. Subsurface exploration consisting of four hand auger exploratory borings for
geotechnical logging and sampling (Appendix B).
4. Pertinent laboratory testing of representative soil samples collected during our
subsurface exploration program (Appendix C).
5. General areal seismicity and liquefaction evaluation.
6. Appropriate engineering and geologic analysis of data collected and preparation
of this report.
SITE DESCRIPTION
The subject site is located on the south side of Tamarack Avenue near Washington Street,
in Carisbad, California (Figure 1). A residence, garage, and corrugated storage structure
currently exist on the site. The lot is generally flat lying. According to a USGS 1968 (photo
revised 1975) San Luis Rey Quadrangle map, the subject site is approximately 50 feet
above Mean Sea Level (MSL).
PROPOSED DEVELOPMENT
It is our understanding that the structures will be demolished and proposed development
would consist of a two-story 13 unit condominium complex and underground parking
(three-story structure overall). Cut and fill grading techniques would be utilized to create
design grades. It is anticipated that the planned development will consist of a three-story
structure with continuous footings and slab-on-grade floors with wood-frame construction
and/or masonry block construction. Building loads are assumed to be typical for this type
of relatively light structures. Sewage disposal is proposed to be accommodated by tying
into the regional system. The need for import soil is unknown.
GcoSoils, Inc.
Base Map: San Luis Rey Quadrangle, California—San Diego Co.,7.5 Minute Series (Topographic),
1968, (photo revised 1975), by USGS, 1"=2000"
N
2000
Scale
4000
Feet
W.O. 3111-A-SC
SITE LOCATION MAP
Figure 1
FIELD STUDIES
Field studies conducted during our evaluation of the property for this study consisted of
geologic reconnaissance, geologic mapping, and excavation of four exploratory hand
auger borings for evaluation of near-surface soil and geologic materials. The borings were
logged by a geologist from our firm, who collected representative samples from the
excavations for appropriate laboratory testing. The logs of the borings are presented in
Appendix B. Boring locations are presented on Plate 1. ^
REGIONAL GEOLOGY
The subject property is located within a prominent natural geomorphic province in
southwestern California known as the Peninsular Ranges. It is characterized by steep,
elongated mountain ranges and valleys that trend northwesteriy. The mountain ranges are
underlain by basement rocks consisting of pre-Cretaceous metasedimentary rocks,
Jurassic metavolcanic rocks, and Cretaceous plutonic rocks of the southern California
batholith.
In the San Diego region, deposition occurred during the Cretaceous period and Cenozoic
era in the continental margin of a forearc basin. Sediments, derived from Cretaceous-age
plutonic rocks and Jurassic-age volcanic rocks, were deposited into the narrow, steep,
coastal plain and continental margin ofthe basin. These rocks have been uplifted, eroded
and deeply incised. During early Pleistocene time, a broad coastal plain was developed
from the deposition of marine terrace deposits. During mid to late Pleistocene time, this
plain was uplifted, eroded and incised. Alluvial deposits have since filled the lower valleys,
and young marine sediments are currently being deposited/eroded within coastal and
beach areas.
EARTH MATERIALS
Earth materials underlying the site consist of artificial fill underlain by Quaternary-age
terrace deposits. These earth materials are described below:
Artificiai Fill - Undocumented (Not Mapped)
Artificial fill onsite was found to be discontinuously present, and generally consist of a
brown, dry, loose, silty sand. Thickness of the material is approximately 2V2 feet. Artificial
fill existing at the subject site is considered unsuitable for support of settlement sensitive
improvements in its present state. Accordingly, these soils are considered unsuitable for
support of additional fill and/or settlement sensitive improvements in their existing state.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111a.pge Page 3
GcoSoils, Inc.
Terrace Deposits (Map Svmbol - Qt)
The Quaternary-age terrace deposits underiie the entire site at depth. As encountered, the
terrace deposits generally consist of red brown, dry to very moist, silty sand, and is
medium dense. Due to the relatively soft and weathered condition of the upper ±1 to
2 feet, these materials should be removed, moisture conditioned, and recompacted and/or
processed in place, should settlement-sensitive improvements be proposed. This unit
typically has a low to medium expansion potential.
FAULTING AND REGIONAL SEISMICITY
Faulting
The site is situated in an area of active as well as potentially-active faults. Our review
indicates that there are no known active faults crossing the site within the areas proposed
for development (Jennings, 1994), and the site is not within an Earthquake Fault Zone
(Hart and Bryant, 1997).
There are a number of faults in the southern California area that are considered active and
would have an effect on the site in the form of ground shaking, should they be the source
of an earthquake. These include-but are not limited to-the San Andreas fault, the
San Jacinto fault, the Elsinore fault, the Coronado Bank fault zone, and the
Newport-lnglewood-Rose Canyon fault zone. The location of these and other major faults
relative to the site are indicated on Figure 2. The possibility of ground acceleration or
shaking at the site may be considered as approximately similar to the southern California
region as a whole.
The following table lists the major faults and fault zones in southern California that could
have a significant effect on the site should they experience significant activity.
ABBREVIATED
FAULT NAME
APPROXIMATE DISTANCE
MILES (KM)
Coronado Bank- Agua Bianca 21 (33)
Elsinore 25 (40)
La Nacion 24 (39)
Newport-lnglewood-Offshore 7(11)
Rose Canyon 4(6)
San Diego Trough-Bahia Sol 30 (48)
Randall K. Lockett
391 Tamarack Avenue
File: e:\wp7\3100\3111 a.pge
W.O. 3111-A-SC
August 31,2001
Page 4
GcoSoils, Inc.
SAN Ff^NCISCO
SITE LOCATION (-f):
Latitude •
Longitude
Lockett
W.O. 3111-A-SC
33.1492 N
117.3414 W
CALIFORNIA FAULT
Figure 2
GcoSoils, Inc.
Seismicity
The acceleration-attenuation relations of Joyner and Boore (1982) and Campbell and
Bozorgnia (1994) have been incorporated into EQFAULT (Blake, 1997). For this study,
peak horizontal ground accelerations anticipated at the site were determined based on the
mean plus 1 sigma attenuation curves developed by Joyner and Boore (1982) and
Campbell and Bozorgnia (1994). These acceleration-attenuation relations have been
incorporated in EQFAULT, a computer program by Thomas F. Blake (1997), which
performs deterministic seismic hazard analyses using up to 150 digitized California faults
as earthquake sources. The program estimates the closest distance between each fault
and a user-specified file. If a fault is found to be within a user-selected radius, the program
estimates peak horizontal ground acceleration that may occur at the site from the upper
bound ("maximum credible") and "maximum probable" earthquakes on that fault. Site
acceleration as a percentage of the acceleration of gravity (g) is computed by any of the
14 user-selected acceleration-attenuation relations that are contained in EQFAULT. Based
on the above, peak horizontal ground accelerations from an upper bound event may be
on the order of 0.42 g to 0.72 g, and a maximum probable event may be on the order of
0.23 g to 0.46 g on the Rose Canyon fault zone, located approximately 4 miles from the
subject site.
Seismic Shaking Parameters
Based on the site conditions. Chapter 16 of the Uniform Building Code (International
Conference of Building Officials, 1997) the following seismic parameters are provided.
Seismic zone (per Figure 16-2*) 4
Seismic Zone Factor (per Table 16-1*) 0.40
Soil Profile Type (per Table 16-J*) SD
Seismic Coefficient C^ (per Table 16-Q*) 0.44 N;^
Seismic Coefficient Cy (per Table 16-R*) 0.64 Nv
Near Source Factor N^ (per Table 16-S*) 1.0
Near Source Factor Ny (per Table 16-T*) 1.15
Seismic Source Type (per Table 16-U*) B
Distance to Seismic Source 4 mi. (6.4 km)
Upper Bound Earthquake Mw 6.9
* Figure and table references from Chapter 16 ofthe Uniform Building Code (1997).
Randall K. Lockett
391 Tamarack Avenue
File: e:\wp7\3100\3111 a.pge
W.O. 3111-A-SC
August 31, 2001
Page 6
GcoSoils, Inc.
GROUNDWATER
Groundwater was not encountered feet during our investigation. Subsurface water is not
anticipated to adversely affect site development, provided that the recommendations
contained in this report are incorporated into final design and construction. These
observations reflect site conditions at the time of our investigation and do not preclude
future changes in local groundwater conditions from excessive irrigation, precipitation, or
that were not obvious, at the time of our investigation.
Perched groundwater conditions along fill/bedrock contacts and along zones of
contrasting permeabilities should not be precluded from occurring in the future due to site
irrigation, poor drainage conditions, or damaged utilities. Should perched groundwater
conditions develop, this office could assess the affected area(s) and provide the
appropriate recommendations to mitigate the observed groundwater conditions.
LIQUEFACTION
Liquefaction describes a phenomenon in which cyclic stresses, produced by earthquake
induced ground motion, create excess pore pressures in relatively cohesionless soils.
These soils may thereby acquire a high degree of mobility, which can lead to lateral
movement sliding, consolidation and settlement of loose sediments, sand boils, and other
damaging deformations. This phenomenon occurs only below the water table, but after
liquefaction has developed, it can propagate upward into overiying, non-saturated soil, as
excess pore water dissipates.
Liquefaction susceptibility is related to numerous factors and the following conditions must
exist for liquefaction to occur: 1) sediments must be relatively young in age and not have
developed large amount of cementation: 2) sediments must consist mainly of medium to
fine grained relatively cohesionless sands; 3) the sediments must have low relative density;
4) free groundwater must be present in the sediment; and 5) the site must experience
seismic event of a sufficient duration and large enough magnitude, to induce straining of
soil particles. At the subject site, three of the five conditions which are necessary for
liquefaction to occur exist, and the site may experience the other two.
One ofthe primary factors controlling the potential for liquefaction is depth to groundwater.
Uquefaction susceptibility generally decreases as the groundwater depth increases for two
reasons: 1) the deeper the water table, the greater normal effective stress acting on
saturated sediments at any given depth and liquefaction susceptibility decreases with
increased normal effective stress; and 2) age, cementation, and relative density of
sediments generally increase with depth. Thus, as the depth to the water table increases,
and as the saturated sediments become older, more cemented, have higher relative
density, and confining normal stresses increase, the less likely they are to liquefy during
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 7
GcoSoils, Inc.
a seismic event. Typically, liquefaction has a relatively low potential where groundwater
is greater than 30 feet deep and virtually unknown below 60 feet.
OTHER GEOLOGIC HAZARDS
Numerous sediment-defomriing features were mapped by Gerald Kuhn in the vicinity ofthe
site. As indicated in Obermeier (1996), these features have: sedimentary characteristics
that are consistent with an earthquake-induced liquefaction origin; namely, there is
evidence of an upward-directed hydraulic force that was suddenly applied and was of short
duration; sedimentary characteristics consistent with historically documented observations
of the earthquake-induced liquefaction processes, in a similar physical setting (dikes, sills,
vented sediment, lateral spreads, and some types of soft sediment deformations); occur
in groundwater settings where suddenly applied, strong hydraulic forces of short duration
could not be reasonably expected except from earthquake-induced liquefaction (i.e., non-
artesian conditions and non-seismic landsliding are not present); similar features occur at
multiple locations, in similar geologic and groundwater settings (Kuhn, et al, 1996); and
the evidence for the age of the features supports the interpretation that they formed in one
or more discreet, short episodes that individually affected a large area and that the
episodes were separated by relatively long time periods during which no such features
were formed. Based on our review, the sediment-deforming features are classified as
paleoliquefaction features.
LABORATORYTESTING
Laboratory tests were performed on representative samples of representative site earth
materials in order to evaluate their physical characteristics. Test procedures used and
results obtained are presented below.
Classification ^
Soils were classified visually in accordance with ASTM D-2487. The soil classifications are
shown on the boring logs. Appendix B.
Laboratorv Standard
The maximum density and optimum moisture content was determined for the major soil
type encountered in the borings. The laboratory standard used was ASTM D-1557. The
moisture-density relationship obtained for this soil is shown on the following table:
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge PageB
GcoSoils, Inc.
LOCATION SOILTYPE
. MAXIMUM
DENSITY (PCF)
OPTIMUM MOISTURE
CONTENT (%)
B-2 @ 0-1.5' Silty SAND, Brown 129.0 10.0
Direct Shear Tests
Shear testing was perfomned on a representative undisturbed sample of terrace deposits
in general accordance with ASTM test method D-3080. Test results are presented on the
following table.
SAMPLE
LOCATION
PRIMARY RESIDUAL
SAMPLE
LOCATION COHESION
(PSF)
FRICTION
ANGLE
(DEGREES)
COHESION (PSF) FRICTION ANGLE
(DEGREES)
B-1 @ 2.5' 403 27 396 27
Expansion Potential
Expansion index testing was performed on representative samples of the site materials in
general accordance with Standard 18-2 ofthe Uniform Building Code (UBC). Results are
presented in the following table.
LOCATION SOIL TYPE EXPANSION INDEX EXPANSION POTENTIAL
B-1 @ 0-2.0' Silty SAND, Brown <5 Very Low
Corrosivity
Sulfate testing indicates that site soils have a negligible exposure to concrete per Table 19-
A-4 ofthe 1997 UBC (sample=0.000 percent by weight). Corrosion testing (ph, resistivity)
indicates that the soils are essentially neutral (pH=7.2) and moderately corrosive to ferrous
metals (saturated resistivity=3,450 ohms-cm). Alternative methods and additional
comments should be obtained by a qualified corrosion engineer. Laboratory test results
are presented in Plate C-1.
Randall K. Lockett
391 Tamarack Avenue
File: e:\wp7\3100\3111a.pge
W.O. 3111-A-SC
August 31.2001
Page 9
GcoSoils, Inc.
DISCUSSION AND CONCLUSIONS
General
Based on our field exploration, laboratory testing and geotechnical engineering analysis,
it is our opinion that the subject lots appear suitable for the proposed manufacturing
development from a geotechnical engineering and geologic viewpoint, provided that the
recommendations presented in the following sections are incorporated into the design and
constnjction phases of site development. The primary geotechnical concerns with respect
to the proposed development on the site are:
• Depth to competent bearing material.
• Expansion and corrosion potential of site soils.
• Subsurface and perched water.
• Liquefaction potential.
• Regional seismic activity.
The recommendations presented herein considerthese as well as other aspects ofthe site.
The engineering analyses performed concerning site preparation and the
recommendations presented herein have been completed using the information provided
and obtained during our field work. In the event that any significant changes are made to
proposed site development, the conclusions and recommendations contained in this
report shall not be considered valid unless the changes are reviewed and the
recommendations of this report verified or modified in writing by this oflice. Foundation
design parameters are considered preliminary until the foundation design, layout, and
structural loads are provided to this office for review.
Earth Materials
Artificial fill and terrace deposits will be encountered during site earthwork. The artificial
fill and the upper 1 to 2 feet of the weathered terrace deposits should be removed.
Recommendations for the treatment ofthese soils are presented in the earthwork section
of this report.
Expansion Potential
Our laboratory test results indicate that soils with a very low expansion potential underiie
the site. This should be considered during project design. Foundation design and
con.struction recommendations are provided herein for very low expansion potential
classification.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\vi/p7\3100\3111 a.pge Page 10
GcoSoils, Inc.
Corrosion/Sulfate Testing
Sulfate testing indicates that site soils have a negligible exposure to concrete per Table 19-
A-4 of the 1997 UBC (sample=0.000 percent by weight). Corrosion testing (i.e., pH,
resistivity) indicates that the soils are essentially neutral (pH=7.2) and moderately corrosive
to ferrous metals (saturated resistivity=3,450 ohms-cm). Alternative methods and
additional comments should be obtained by a qualified corrosion engineer.
Subsurface and Surface Water
Subsurface and surface water, as discussed previously, are not anticipated to significantly
affect site development, provided that the recommendations contained in this report are
incorporated into final design and construction and that prudent surface and subsurface
drainage practices are incorporated into the construction plans. Perched groundwater
conditions along fill/bedrock contacts and along zones of contrasting permeabilities,
should not be precluded from occurring in the future due to site irrigation, poor drainage
conditions, or damaged utilities. Should perched groundwater conditions develop, this
office could assess the affected area(s) and provide the appropriate recommendations to
mitigate the observed groundwater conditions.
The groundwater conditions observed and opinions generated were those at the time of
our investigation. Conditions may change with the introduction of irrigation, rainfall, or
other factors that were not obvious at the time of our investigation.
Liquefaction
Liquefaction potential throughout a majority of the site is considered relatively low,
assuming that the recommendations presented in this report are properly incorporated into
the design and construction of the project.
Previous liquefaction of terrace deposits, evidenced by the previous mapped
paleoliquefaction features by Gerald Kuhn, is not anticipated to recur, primarily due to the
observed cementation of the earth materials comprising the features and surrounding
terrace deposits and the lack of groundwater. Design and construction within areas
underiain by these features will likely need to consider additional subdrainage, as
necessary, and/or other mitigative measures such as overexcavation and the use of
geotextiles, or post tension slabs.
Regional Seismic Activity
The seismicity acceleration values provided herein should be considered during the design
of the proposed development.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111a.pge Page 11
GcoSoils, Inc.
EARTHWORK CONSTRUCTION RECOMMENDATIONS
General
All grading should conform to the guidelines presented in Appendix Chapter A33 of the
Uniform Building Code (adopted and current edition), the requirements of the City of
Carisbad, and the Grading Guidelines presented in this report as Appendix D, except
where specifically superseded in the text of this report. Prior to grading, GSI's
representative should be present at the preconstruction meeting to provide additional
grading guidelines, if needed, and review the earthwork schedule. Earthwork beyond the
limits of the surficial, remedial overexcavations or those indicated on the grading plan
should be reviewed by the geologist and/or geotechnical consultant prior to and following
these additional removals.
During earthwork construction all site preparation and the general grading procedures of
the contractor should be observed and the fill selectively tested by a representative(s) of
GSI. If unusual or unexpected conditions are exposed in the field or if modifications are
proposed to the rough grade or precise grading plan, they should be reviewed by this
office and if warranted, modified and/or additional recommendations will be offered. All
applicable requirements of local and national construction and general industry safety
orders, the Occupational Safety and Health Act, and the Construction Safety Act should
be met. GSI does not consult in the area of safety engineering. Excavations into the
granular material on this site may be unstable.
Site Preparation
Debris, vegetation, and other deleterious material should be removed from the
improvement(s) area prior to the start of construction.
Removals (Unsuitable Surficial Materials)
Removals should consist of all existing fill or backfill (utilities), and the upper 1 to 2 feet of
weathered terrace deposits, to competent formational sediments within areas proposed
for settlement-sensitive improvements. Removals should be completed below a 1:1
(horizontal to vertical) projection down and away from the bottom outside edge of any
settlement-sensitive improvement or fill area. Care should be taken when removing soil
adjacent to or in close proximity to an existing foundation.
Once these materials are removed, the bottom ofthe excavations should be observed and
approved by a representative of GSI. The bottom areas approved to receive fill should be
scarified in two perpendicular directions and moisture conditioned (at or above the soils
optimum moisture content) to a depth of 12 inches and compacted to a minimum 90
percent relative compaction. At that time, the removed existing earth materiais may be re-
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 12
GcoSoils, Inc.
used as fill, provided the materials are moisture conditioned at or above the soils optimum
moisture and compacted in accordance with the recommendations of this report.
Fill Placement
Subsequent to ground preparation, onsite soils may be placed in thin (6± inch) lifts,
cleaned of vegetation and debris, brought to a least optimum moisture content, and
compacted to achieve a minimum relative compaction of 90 percent.
if fill materials are imported to the site, the proposed import fill should be submitted to
GSI, so laboratory testing can be performed to verify that the intended import material is
compatible with onsite material. At least three business days of lead time should be
allowed by builders or contractors for proposed import submittals. This lead time will allow
for particle size analysis, specific gravity, relative compaction, expansion testing, and
blended import/native characteristics, as deemed necessary.
Erosion Control
Onsite soils and formational sediments have a moderate erosion potential. Use of hay
bales, silt fences, and/or sandbags should be considered, as appropriate during
construction. Temporary grades should be constructed to drain at a minimum of 1 to 2
percent to a suitable temporary or permanent outlet. Precise grades should be evaluated
by the design civil engineer to reduce concentrated flows to less than 6 feet per second
and into lined or landscaped swales. Evaluation of cuts during grading will be necessary
in order to identify any areas of loose or non-cohesive materials. Should any significant
zones be encountered during earthwork construction, additional remedial grading may be
recommended; however, only the remedial measures discussed herein are anticipated at
this time.
FOUNDATION RECOMMENDATIONS
In the event that the information concerning the proposed development is not correct or
any changes in the design, locafion, or loading conditions of the proposed structures are
made, the conclusions and recommendations contained in this report are for the subject
parcel only and shall not be considered valid unless the changes are reviewed and
conclusions of this report are modified or approved in writing by this office.
The information and recommendations presented in this section are considered minimums
and are not meant to supersede design(s) by the project structural engineer or civil
engineer specializing in structural design. Upon request, GSI could provide additional
consultation regarding soil parameters, as related to foundation design. They are
considered preliminary recommendations for proposed construction, in consideration of
our field investigation, laboratory testing, and engineering analysis.
Randall K. Lockett W.O. 3111-A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111a.pge Page 13
GcoSoils, Inc.
Preliminarv Foundation Design
Our review, field work, and laboratory testing indicates that onsite soils have a very low
expansion potential. Final foundation recommendations should be provided at the
conclusion of grading based on laboratory testing of fill materials exposed at finish grade.
Bearing Value
1. The foundation systems should be designed and constructed in accordance with
guidelines presented in the latest edition of the Uniform Building Code.
2. An allowable bearing value of 1500 pounds per square foot may be used for design
of continuous footings 12 inches wide and 12 inches deep and for design of
isolated pad footings 24 inches square and 24 inches deep founded entirely into
compacted fill or competent bedrock material and connected by grade beam or tie
beam in at least one direction. This value may be increased by 20 percent for each
additional 12 inches in depth to a maximum value of 2500 pounds per square foot.
The above values may be increased by one-third when considering short duration
seismic or wind loads. No increase, in bearing, for footing width is recommended.
Lateral Pressure
1. For lateral sliding resistance, a 0.35 coefficient of friction may be utilized for a
concrete to soil contact when multiplied bythe dead load.
2. Passive earth pressure may be computed as an equivalent fluid having a density of
250 pounds per cubic foot with a maximum earth pressure of 2500 pounds per
square foot.
3. When combining passive pressure and frictional resistance, the passive pressure
component should be reduced by one-third.
Construction
The following foundation construction recommendations are presented as a minimum
criteria from a soils engineering standpoint. The onsite soils expansion potentials are
generally in the Very Low to Low (expansion index 0 to 50) range.
Very Low to Low Expansion Potential (Expansion Index 0 to 50)
1. Exterior and interior footings should be founded at minimum depths of 12,18, or 24
inches for one, two, or three-story loads, respectively, below the lowest adjacent
surface. Isolated column and panel pads or wall footings should be founded at a
minimum depth of 24 inches and connected in one direction by a grade beam. All
Randall K. Lockett """"" W.O. 3111-A-SC
391 Tamarack Avenue August 31. 2001
File: e:\wp7\3100\3111a.pge Page 14
GcoSoils, Inc.
footings should be reinforced with a minimum of two No. 4 reinforcing bars, one
placed near the top and one placed near the bottom of the footing, and in
accordance with the recommendations width per UBC 1997.
2. A grade beam, reinforced as above, and at least 12 inches wide should be provided
across large (e.g. doon/vays) entrances. The base ofthe grade beam should be at
the same elevation as the bottom of adjoining footings.
3. Residential concrete slabs, where moisture condensation is undesirable, should be
underiain with a vapor barrier consisting of a minimum of 6 mil polyvinyl chloride or
equivalent membrane with all laps sealed. This membrane should be covered
above and below with a minimum of 2 inches of sand (total of 4 inches) to aid in
uniform curing ofthe concrete and to protect the membrane from puncture.
4. Residential concrete slabs should be a minimum of 4 inches thick, and should be
reinforced with No. 3 reinforcing bar at 18 inches on center in both directions, per
the UBC. All slab reinforcement should be supported to ensure placement near the
vertical midpoint of the concrete. "Hooking" is not considered an acceptable
method of positioning the reinforcement.
5. Residenfial garage slabs should be reinforced as above and poured separately from
the structural footings and quartered with expansion joints or saw cuts. A positive
separation ft'om the footings should be maintained with expansion joint material to
permit relafive movement.
6. Presaturation is not required for these soil conditions. The moisture content of the
subgrade soils should be equal to or greater than optimum moisture content in the
slab areas. Prior to placing visqueen or reinforcement, soil moisture content should
be verified by this office within 72 hours of pouring slabs.
PRELIMINARY POST TENSIONED SLAB FOUNDATION
SYSTEM RECOMMENDATIONS
Post tensioned slab foundation systems may be used to support the proposed buildings.
Based on the potential differential settlement within areas ofthe site underiain by alluvium,
post-tensioned slab foundations are recommended exclusively.
General
The information and recommendations presented in this section are not meant to
supersede design by a registered structural engineer or civil engineer familiar with post-
tensioned slab design or corrosion engineering consultant. Upon request, GSI could
provide additional data/consultation regarding soil parameters as related to post-tensioned
slab design during grading. The post tensioned slabs should be designed in accordance
Randall K. Lockett W.O. 3111-A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 15
GcoSoils, Inc.
with the Post-Tensioning Institute (PTI) Method. Alternatives to the PTI method may be
used if equivalent systems can be proposed which accommodate the angular distortions,
expansion potential and settlement noted for this site.
Post-tensioned slabs should have sufficient stiffness to resist excessive bending due to
non-uniform swell and shrinkage of subgrade soils. The differential movement can occur
at the corner, edge, or center of slab. The potential for differential uplift can be evaluated
using the 1997 Uniform Building Code Section 1816, based on design specifications ofthe
Post-Tensioning Institute. The following table presents suggested minimum coefficients
to be used in the Post-Tensioning Institute design method.
Thornthwaite Moisture Index -20 inches/year
Correction Factor for Irrigation 20 inches/year
Depth to Constant Soil Suction 5 feet
Constant Soil Suction (pf) 3.6
The coefficients are considered minimums and may not be adequate to represent worst
case conditions such as adverse drainage and/or improper landscaping and maintenance.
The above parameters are applicable provided structures have gutters and downspouts
and posifive drainage is maintained away from structures. Therefore, it is important that
information regarding drainage, site maintenance, settlements, and effects of expansive
soils be passed on to future owners.
Based on the above parameters, design values were obtained ft'om figures or tables of the
1997 Uniform Building Code Section 1816 and presented in Table 1. These values may
not be appropriate to account for possible differential settlement of the slab due to other
factors (i.e. fill settlement). If a stiffer slab is desired, higher values of ym may be warranted.
TABLE 1
POSTTENSION FOUNDATIONS
Expansion Potential Very Low''' to Low Expansive
(EI = 0-50)
em center lift 5.0 feet
em edge lift 2.5 feet
Ym center lift 1.1 inch
Ym edge lift 0.35 inch
Randall K. Lockett
391 Tamarack Avenue
File: e:\wp7\3100\3111a.pge
W.O. 3111-A-SC
August 31, 2001
Page 16
GcoSoils, Inc.
Expansion Potential Very Low**' to Low Expansive
(El = 0-50)
em center lift 5.0 feet
Bearing Value 1200 psf
Lateral Pressure 225 psf
Subgrade Modulus (k) 100 pci/inch
Minimum Slab Thickness 4.5 inches
Perimeter footing embedment 12 inches
'^'Internal bearing values within the perimeter of the post tension slab may be
increased by 300 psf for each foot of embedment below the bottom of the slab, to
a maximum of 2,500 psf.
As measured below the lowest adjacent compacted subgrade surface.
Foundations for very low expansive soil conditions may use the California Method
(spanability method)
Foundation Settlements
In addifion to designing slab systems (PT or other) for the soil condifions, described herein,
the esfimated settlement and angular distortion values that an individual structure could
be subject to should be evaluated by a structural engineer. The levels of angular distortion
were evaluated on to 40-feet length assumed as minimum dimension of single-family
buildings and are anficipated to be on the order of inch in a 20-foot span. Although
unlikely, should a large seismic event occur on blind thrust faults offshore, differential
settlement may be on the order of 1 inch in 20 feet. If, from a structural standpoint, a
decreased or increased length over which the differential is assumed to occur is justified,
this change should be incorporated into the design. The settlement values should be
revised and verified during grading.
Subgrade Preparation
The subgrade material should be compacted to a minimum 90 percent of the maximum
laboratory dry density. Prior to placement of concrete, the subgrade soils should be well
moistened to at least optimum moisture content and verified by our field representative.
Perimeter Footings and Pre-Wetting
From a soil expansion/shrinkage standpoint, a fairiy common contribufing factor to distress
of structures using post tensioned slabs is a significant fluctuation in the moisture content
of soils underiying the perimeter ofthe slab, compared to the center, causing a "dishing"
Randall K. Lockett
391 Tamarack Avenue
File: e:\wp7\3100\3111 a.pge
W.O. 3111-A-SC
August 31, 2001
Page 17
GcoSoils, Inc.
or "arching" ofthe slabs. To mitigate this possible phenomenon, a combination of soil pre-
wetting and construction of a perimeter cut-off wall grade beam should be employed.
Deepened footings/edges around the slab perimeter must be used to minimize non-
uniform surface moisture migration (from an outside source) beneath the slab.
Embedment depths are presented in Table 1 for various soil expansion conditions. The
bottom of the deepened footing/edge should be designed to resist tension, using cable
or reinforcement per the structural engineer. Other applicable recommendations
presented under conventional foundation recommendations in the referenced report
should be adhered to during the design and construction phase of the project.
Floor slab subgrade should be at, or above the soils optimum moisture content to a depth
of 24 inches prior to pouring concrete, for exisfing soil conditions. Pre-wetting of the slab
subgrade soil prior to placement of steel and concrete will likely be recommended and
necessary, in order to achieve optimum moisture conditions. Soil moisture contents
should be verified at least 72 hours prior to pouring concrete.
CONVENTIONAL RETAINING WALL RECOMMENDATIONS
General
The design parameters provided below assume that very low expansive soils are used to
backfill any standard retaining walls (i.e. no specialty walls, including crib walls, earthstone
walls). The equivalent fluid pressure parameters provide for the use of very low expansive
select granular backfill to be utilized behind the proposed walls. The very low expansive
granular backfill should be provided behind the wall at a 1:1 (h:v) projection from the heel
of the foundation system. Very low expansive fill is Class 3 aggregate baserock or Class 2
permeable rock. Wall backfilling should be performed with relatively light equipment within
the same 1:1 projection (i.e., hand tampers, walk behind compactors). Highly expansive
soils should not be used to backfill any proposed walls. During construction, materials
should not be stockpiled behind nor in front of walls for a distance of 2H where H is the
height of the wall.
Foundation systems for any proposed retaining walls should be designed in accordance
with the recommendations presented in the Foundation Design section of this report.
Building walls, below grade, should be water-proofed or damp-proofed, depending on the
degree of moisture protection desired. All walls should be properiy designed in
accordance with the recommendations presented below.
Some movement of the walls constructed should be anticipated as soil strength
parameters are mobilized. This movement could cause some cracking depending upon
the materials used to construct the wall. To reduce the potential for wall cracking, walls
should be internally grouted and reinforced with steel. To mitigate this effect, the use of
Randall K. Lockett W.O. 3111-A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 18
GcoSoils, Inc.
vertical crack control joints and expansion joints, spaced at 20 feet or less along the walls
should be employed. Vertical expansion control joints should be infilled with a flexible
grout. Wall footings should be keyed or doweled across vertical expansion joints. Walls
should be internally grouted and reinforced with steel.
Restrained Walls
Any retaining walls that will be restrained prior to placing and compacting backfill material
or that have re-entrant or male corners, should be designed for an at-rest equivalent fiuid
pressures (EFP) of 65 pcf, plus any applicable surcharge loading. Expansive soils should
not be used as backfill, only granular (very low expansive) backfill should be used. For
areas of male or re-entrant corners, the restrained wall design should extend a minimum
distance of twice the height of the wall laterally from the corner.
Building walls below grade or greater than 2 feet in height should be water-proofed or
damp-proofed, depending on the degree of moisture protection desired. The wall should
be drained as indicated in the following section. For structural footing loads within the 1:1
zone of influence behind wall backfill, refer to the following section.
Cantilevered Walls
These recommendations are for cantilevered retaining walls up to 10 feet high. Active
earth pressure may be used for retaining wall design, provided the top of the wall is not
restrained from minor deflections. An empirical equivalent fluid pressure approach may
be used to compute the horizontal pressure against the wall. Appropriate fluid unit weights
are provided for specific slope gradients of the retained material. These do not include
other superimposed loading conditions such as traffic, structures, seismic events,
expansive soils, or adverse geologic conditions.
If traffic is within a distance H behind any wall or a 1:1 projection from the heel of the wall
foundation a pressure of 100 psf per foot in the upper 5 feet should be used. Structural
loads ft'om adjacent properties and their influence on site walls should be reviewed by the
structural engineer, if within a 1:1 projection behind any site wall. However, for preliminary
planning purposes, one third of the footing contact pressure should be added to the wall
in pounds per square foot below the bearing elevation and for a distance ofthree times the
footing width along the wall alignment. Alternatively, a deepened footing beyond the 1:1
projection (up from the heel) behind the wall may be utilized.
Wall Backfill and Drainage
All retaining walls should be provided with an adequate backdrain and outlet system
(a minimum two outlets per wall and no greater than 100 feet apart), to prevent buildup of
hydrostatic pressures and be designed in accordance with minimum standards presented
herein. See site wall drain options (Figure 3, Figure 4, and Figure 5). Drain pipe should
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111a.pge Page 19
GcoSoils, Inc.
Cop drain (cut off)
18" below soil line
Waterproofing
Manufactured drainage
Geocomposite drain
( Mira drain 5000
equivalent )
Note: Filter fabric wraps completely
aroijnd perforated pipe and
behind core material, core
material wraps beneath
bottom of pipe.
4" dio. min. perforated
pipe placed with holes
down and sloped at 1-2%
to suitable outlet
4 min. granular material —
(class 2 permeable or
3/8-1" clean crushed
rock wrapped in a
filter fabric)
Site retaining wall
(structural design
by others)
Pavement section per
t>SI recommendations
— Parking lot
surface
i—Wall footing
(designed by others)
LOS ANGELES CO.
RIVERSIDE CO.
ORANGE CO.
SAN OIEGO CO.
^SCHEMATIC OF SITE WALL DRAIN
OPTION A Figure 3
w.o.. 3111-A-SC DATE 8/01 SCALE Kone
12 thick (min.) drain rock
(class 2 permeable) or
other acceptable granular
material. 1/8-1" clean
crushed rock wrapped in
a filter fabric (Mirafi 140
or* equivalent)
4 dia. min. perforated
pipe placed with holes
down and sloped at 1-2%
to a suitable outlet
1-" Min. —J
Cap drain (cut off)
18' below soil line
-Site retaining wall
(structural design
by others)
Pavement section per
GSI recomendations —
Parking lot
-surface
3
-VQU footing
(designed by others)
T
LOS ANGELES CO.
RIVERSIDE CO.
ORANGE CO.
SAN DEGO CO.
^SCHEMATIC OF
SITE WALL DRAIN
OPTION B Figure 4
w.o. 3111-A-SC DATE 8/01 SCALE rfone
If^ finished surface is within
8 of top of footing wall drains
shall be at 6' intervals along
the length of the wall and
located at the level of the
bottom course of block. The
drains shall be 4" in diameter
24" thick (min.) drain rock
(class 2 permeable) or
other acceptable granular
material. 1/8-1" clean
crushed rock wrapped in
o filter fabric (Mirafi 140
or equivalent)
Waterproofing
X
'4 • * tJ
, • • »
Cop drain (cut
18' below soii
off)
line
-Site retaining wall
(structural design
by others)
Pavement section per
GSI recomendations
•4" dia. pipe
Parking lot
surface
, ».1o o, /'•«>, o» i
. 4 *
I ^ ' : rz 1
I
-VQU. footing
Cdesigned by others)
LOSANGELES CO.
RIVERSIDE CO.
ORANGE CO.
SAN DIEGO CO.
SCHEMATIC OF SITE WALL DRAIN
OPTION 0 Figure 5
consist of 4-inch diameter perforated schedule 40 PVC pipe embedded in gravel. Gravel
used in the backdrain systems should be a minimum of 3 cubic feet per lineal foot of %-
to 1-inch clean crushed rock wrapped in filter fabric (Mirafi 140 or equivalent) and 12
inches thick behind the wall. Where the void to be fitted is constrained by lot lines or
property boundaries, the use of panel drains (Mirafi 5000 or equivalent) may be considered
with the approval ofthe project geotechnical engineer. The surface ofthe backfill should
be sealed by pavement or the top 18 inches compacted to 90 percent relative compaction
with native soil. Proper surface drainage should also be provided. Weeping ofthe walls
in lieu of a backdrain is not recommended for walls greater than 2 feet in height. For walls
2 feet or less in height, weepholes should be no greater than 6 feet on center in the bottom
coarse of block and above the landscape zone.
A paved drainage channel (v-ditch or substitute), either concrete or asphaltic concrete,
behind the top of the walls with sloping backfill should be considered to reduce the
potential for surface water penetration. For level backfill, the grade should be sloped such
that drainage is toward a suitable outlet at 1 to 2 percent.
Retaining Wall Footing Transitions
Site walls are anticipated to be founded on footings designed in accordance with the
recommendations in this report. Wall footings may transition from sedimentary bedrock
to select fill. If this condition is present the civil designer may specify either:
a) If transitions ft'om rock fill to select fill transect the wall footing alignment at an angle
of less than 45 degrees (plan view), then the designer should perform a minimum
2-foot overexcavation for a distance of two times the height of the wall and increase
overexcavation until such transition is between 45 and 90 degrees to the wall
alignment.
b) Increase of the amount of reinforcing steel and wall detailing (i.e., expansion joints
or crack control joints) such that an angular distortion of 1/360 for a distance of 2H
(where H=wall height in feet) on either side of the transition may be
accommodated. Expansion joints should be sealed with a flexible, non-shrink
grout.
c) Embed the footings entirely into a homogeneous fill.
FLATWORK AND ASSOCIATED IMPROVEMENTS
1. Planters and walls should not be tied to building(s).
2. Driveways, sidewalks, and patios adjacent to the building(s) should be separated
from the building(s) with thick expansion joint filler material. In addition, all
Randall K. Lockett ~ W.O. 3111-A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 23
GcoSoils, Inc.
sidewalks and driveways should be quartered and poured with expansion joints no
farther apart than 8 feet for 4-inch slabs or 10 feet for 5-inch slabs, respectively.
Consideration should additionally be given for the areas of the driveways and
sidewalks adjacent to planters, lawns, and other landscape areas to have thickened
edges, such that the edge is 4 to 6 inches thick and at least 6 inches below the
adjacent landscaping zone (section).
3. Overhang structures should be structurally designed with continuous footings or
grade beams tied in at least two directions. Footings that support overhang
structures should be embedded a minimum of 24 inches from the lowest adjacent
finished subgrade.
4. Any masonry landscape walls that are to be constructed throughout the property
should be fully grouted and articulated in segments no more than 20 feet long.
5. Utilities should be enclosed within a closed vault or designed with flexible
connections to accommodate differential settlement and expansive soil conditions.
6. Finish grade (Precise Grade Plan) on the lot should provide a minimum of 1 to 2
percent fall to the street. It should be kept in mind that drainage reversals could
occur if relatively flat yard drainage gradients are not maintained due to landscaping
work, modiflcations to flatwork, or post-sale owner modifications.
Tile Flooring
Tile flooring can crack, reflecting cracks in the concrete slab below the tile. Therefore, the
designer should consider additional steel reinforcement of concrete slabs on-grade where
tile will be placed. The tile installer should consider installation methods that reduce
possible cracking of the tile such as slipsheets. Slipsheets or a vinyl crack isolation
membrane (approved by the Tile Council of America/Ceramic Tile Institute) is
recommended between tile and concrete slabs on grade.
Gutters and Downspouts
Consideration should be given to the installation of gutters and downspouts to collect roof
water that may otherwise infiltrate the soils adjacent to the structures. The downspouts
should be drained away from the foundation and collected in drainage swales or other
approved non-erosive drainage systems designed by a registered civil engineer
(specializing in drainage) to convey water away from the foundation. Gutters and
downspouts are not a geotechnical requirement, however, provided positive drainage is
maintained in accordance with the recommendations of the design civil engineer.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 24
GcoSoils, Inc.
Exterior Slabs and Walkways
Exterior concrete slab on grade construction should be designed and constructed in
accordance with the following criteria:
1. Driveway pavement and all other exterior flatwork should be a minimum 4 inches
thick. A thickened edge should be considered for all flatwork adjacent to irrigated
and landscape areas.
2. Slab subgrade should be scarified, moisture conditioned and compacted to a
minimum 90 percent relative compaction. Subgrade should be moisture
conditioned based on the representative expansion potential of the subgrade
exposed (i.e. at or above optimum for low expansive. The subgrade moisture
content should be maintained until the slab is poured.
3. The use of transverse and longitudinal control joints should be considered to help
control slab cracking due to concrete shrinkage or expansion. Two of the best
ways to control this movement is; 1) add a sufficient amount of reinforcing steel,
increasing tensile strength of the slab, and/or 2) provide an adequate amount of
control and/or expansion joints to accommodate anticipated concrete shrinkage
and expansion.
4. No traffic should be allowed upon the newly poured concrete slabs until they have
been properiy cured to within 75 percent of design strength.
5. Positive site drainage should be maintained at all times. Adjacent landscaping
should be graded to drain into the street, parking area, or other approved area. All
surface water should be appropriately directed to areas designed for site drainage.
6. Concrete compression strength should be a minimum of 2,500 psi.
ADDITIONAL RECOMMENDATIONS/DEVELOPMENT CRITERIA
Additional Site Improvements
If in the ftjture, any additional improvements are planned for the site, recommendations
concerning the geological or geotechnical aspects of design and construction of said
improvements could be provided upon request this includes but not limited to appurtenant
structures.
This office should be notified in advance of any additional fill placement, regrading of the
site, or trench backfilling after rough grading has been completed. This includes any
grading, utility trench, and retaining wall backfills.
Randall K. Lockett W.O. 3111-A-SC
391 Tamarack Avenue August 31, 2001
Rle: e:\wp7\3100\3111a.pge Page 25
GcoSoils, Inc.
Landscape Maintenance and Planting
Water has been shown to weaken the inherent strength of soil, and slope stability is
significantly reduced by overly wet conditions. Positive surface drainage away ft'om graded
slopes should be maintained and only the amount of irrigation necessary to sustain plant
life should be provided for planted slopes. Over-watering should be avoided. Onsite soil
materials should be maintained in a solid to semisolid state.
Brushed native and graded slopes (constructed within and utilizing onsite materials) would
be potentially erosive. Eroded debris may be minimized and surficial slope stability
enhanced by establishing and maintaining a suitable vegetation cover soon after
construction. Plants selected for landscaping should be light weight, deep rooted types
that require little water and are capable of surviving the prevailing climate. Planting of large
trees with potential for extensive root development should not be placed closer than
10 feet from the perimeter of the foundation or the anticipated height of the mature tree,
whichever is greater. It order to minimize erosion on the slope face, an erosion control
fabric (i.e. jute matting) should be considered.
From a geotechnical standpoint, leaching is not recommended for establishing
landscaping. If the surface soils area processed for the purpose of adding amendments
they should be recompacted to 90 percent minimum relative compaction. Moisture
sensors, embedded into fill slopes, should be considered to reduce the potential of
overwatering from automatic landscape watering systems. The use of certain fertilizers
may affect the corrosion characteristics of soil. Review of the type and amount
(pounds per acre) of the fertilizers by a corrosion specialist should be considered.
Recommendations for exterior concrete flatwork design and construction can be provided
upon request. If in the future, any additional improvements are planned for the site,
recommendations concerning the geological or geotechnical aspects of design and
construction of said improvements could be provided upon request. This office should be
notified in advance of any additional fill placement, regrading of the site, or trench
backfilling after rough grading has been completed. This includes any grading, utility
trench, and retaining wall backfills.
Drainage
Positive site drainage should be maintained at all times. Drainage should not flow
uncontrolled down any descending slope. Water should be directed away from
foundations and not allowed to pond and/or seep into the ground. Pad drainage should
be directed toward the street or other approved area. Landscaping should be graded to
drain into the street, or other approved area. All surface water should be appropriately
directed to areas designed for site drainage.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 26
GcoSoils, Inc.
Roof gutters and down spouts are recommended to control roof drainage. Down spouts
should outlet a minimum of 5 feet firom proposed structures or tightiined into a subsurface
drainage system. We recommend that any proposed open bottom planters adjacent to
proposed structures be eliminated for a minimum distance of 10 feet. As an alternative,
closed bottom type planters could be utilized. An outlet placed in the bottom of the
planter, could be installed to direct drainage away ft'om structures or any exterior concrete
flatwork. Drainage behind top of walls should be accomplished along the length of the wall
with a paved channel drainage v-ditch or substitute.
Footing Trench Excavation
All footing trench excavations should be observed and approved by a representative ofthis
office prior to placing reinforcement. Footing trench spoil and any excess soils generated
from utility trench excavations should be compacted to a minimum relative compaction of
90 percent, if not removed from the site.
Trench Backfill
All excavations should be observed by one of our representatives and conform to OSHA
and local safety codes. Exterior trenches should not be excavated below a 1:1 projection
from the bottom of any adjacent foundation system. If excavated, these trenches may
undermine support for the foundation system potentially creating adverse conditions.
1. All utility trench backfill in slopes, structural areas and beneath hardscape features
should be brought to near optimum moisture content and then compacted to obtain
a minimum relative compaction of 90 percent of the laboratory standard.
Observations, probing and, if deemed necessary, testing should be performed by
a representative of this office to verify compactive efforts of the contractor.
2. Soils generated from utility trench excavations should be compacted to a minimum
of 90 percent (ASTM D-1557) if not removed from the site.
3. Jetting of backfill is not recommended.
4. The use of pipe jacking to place utilities is not recommended on this site due to
the presence of gravels and cobbles.
5. Bottoms of utility trenches should be sloped away from structures.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111 a.pge Page 27
GcoSoils, Inc.
PLAN REVIEW
Final site development and foundation plans should be submitted to this office for review
and comment, as the plans become available, for the purpose of minimizing any
misunderstandings between the plans and recommendations presented herein. In
addition, foundation excavations and any additional earthwork construction performed on
the site should be observed and tested by this office. If conditions are found to differ
substantially from those stated, appropriate recommendations would be offered at that
time.
LIMITATIONS
The materials encountered on the project site and utilized in our laboratory study are
believed representative ofthe area; however, soil and bedrock materials vary in character
between excavations and natural outcrops or conditions exposed during site grading,
construction, and our post-grading study. Site conditions may vary due to seasonal
changes or other factors. GSI assumes no responsibility or liability for work, testing, or
recommendations performed or provided by others.
Inasmuch as our study is based upon the site materials observed, selective laboratory
testing and engineering analysis, the conclusion and recommendations are professional
opinions. These opinions have been derived in accordance with current standards of
practice, and no warranty is expressed or implied. Standards of practice are subject to
change with time.
During the field exploration phase of our study, odors or stained or discolored soils were
not observed onsite or in our test pits or test pit spoils. However, these observations were
made during our preliminary geotechnical study and should in no way be used in lieu of
an environmental assessment. If requested, a proposal for a phase I preliminary
environmental assessment could be provided.
Randall K. Lockett W.O. 3111 -A-SC
391 Tamarack Avenue August 31, 2001
File: e:\wp7\3100\3111a.pge Page 28
GcoSoils, Inc.
APPENDIX A
REFERENCES
APPENDIXA
REFERENCES
Blake, Thomas F., 1998, EQFAULT computer program and users manual for the
deterministic prediction of horizontal accelerations from digitized California
faults.
Campbell, K.W. and Bozorgnia, Y., 1994, Near-Source attenuation of peak horizontal
acceleration ft'om woridwide accelerograms recorded from 1957 to 1993:
Proceedings, Fifth U.S. National Conference on Earthquake Engineering, vol. Ill,
Earthquake Engineering Research Institute, pp. 293-292.
Frankel, Arthur D., Perkins, David M., and Mueller, Charies S., 1996, Preliminary and
working versions of draft 1997 seismic shaking maps for the United States
showing peak ground acceleration (PGA) and spectral acceleration response at
0.3 and 1.0-second site periods for the Design Basis Earthquake (10 percent
chance of exceedance in 50 years) for the National Earthquake Hazards
Reduction Program (NEHRP): U.S. Geological Survey, Denver, Colorado.
GeoSoils, Inc., Proprietary in-house information
Greensfelder, R. W., 1974, Maximum credible rock acceleration from earthquakes in
California: California Division of Mines and Geology, Map Sheet 23.
Hart, E.W. and Bryant, W. A., 1997, Fault-rupture hazard zones in California: California
Department of Consen/ation, Division of Mines and Geology, Special Publication
42.
Housner, G. W., 1970, Strong ground motion in earthquake engineering, Robert Wiegel,
ed., Prentice-Hall.
International Conference of Building Officials, 1997, Uniform building code: Whittier,
California, vol. 1, 2, and 3.
Jennings, C.W., 1994, Fault activity map of California and adjacent areas: California
Division of Mines and Geology, Map Sheet No. 6, scale 1:750,000.
Joyner, W.B, and Boore, D.M., 1982a, Estimation of response-spectral values as
functions of magnitude, distance and site conditions, in Johnson, J.A., Campbell,
K.W., and Blake, eds., T.F., AEG Short Course, Seismic Hazard Analysis, June
18, 1994.
, 1982b, Prediction of earthquake response spectra, in Johnson, J.A., Campbell,
K.W., and Blake, eds., T.F., AEG Short Course, Seismic Hazard Analysis, June
18, 1994.
GcoSoils, Inc.
Krinitzsky, Ellis L, Gould, J.P., and Edinger, P.H., 1993, Fundamentals of earthquake
resistant construction: John H. Wiley & Sons, Inc., 299 p.
Kuhn, G.G., Legg, M.R., Johnson, J.A., Shiemon, R.G., and Frost, E.G., 1996, Paleo-
liquefaction evidence for large pre-historic earthquakes(s) in north-coastal San
Diego County, California, in Munasinghe, T., and Rosenberg, eds.. Geology and
natural resources of coastal San Diego County, California, guidebook to
accompany the 1996 annual field trip of the San Diego Association of Geologists,
September.
Obermeier, S.F., 1996, Using liquefaction-induced features for paleoseismic analysis,
Chapter 7, in McCalpin, J.P., ed, Paleoseismology, Acedemic Press
Petersen, Mark D., Bryant, W.A., and Cramer, C.H., 1996, Interim table of fault
parameters used by the California Division of Mines and Geology to compile the
probabilistic seismic hazard maps of California.
Sadigh, K, Egan, J., and Youngs, R., 1987, Predictive ground motion equations
reported in Joyner, W.B., and Boore, D.M., 1988, "Measurement,
characterization, and prediction of strong ground motion", in Earthquake
Engineering and Soil Dynamics II, Recent Advances in Ground Motion
Evaluation, Von Thun, J.L., ed.: American Society of Civil Engineers
Geotechnical Special Publication No. 20, pp. 43-102.
Sowers and Sowers, 1979, Unified soil classification system (After U. S. WatenA/ays
Experiment Station and ASTM 02487-667) in Introductory Soil Mechanics, New
York.
Tan, S.S and Kennedy, M.P., 1996, Geologic maps ofthe Northwestern part of San
Diego County, California, DMG Open-File Report 96-02.
United States Department of Agriculture, 1953, Black and white high altitude stereo
photgraphs, AXN-14M-19 and -21.
United States Geological Survey, 1968, San Luis Rey quadrangle, California - San
Diego Co., 7.5 minute series (topographic), photo revised 1975.
Weber, Harold F., 1982, Geologic map ofthe central-north coastal area of San Diego
County, California, showing recent slope failures and pre-development
landslides: United States Geologic Survey, Open-File Report 82-12.
Randall K. Lockett Appendix A
Rle: e:\wp7\3100\3111a.pge Page 2
GcoSoils, Inc.
APPENDiX B
BORING LOGS
BORING LOG
GeoSoils, Inc.
P/?OJ£Cr; RANDALL LOCKETT
391 TAMARACK AVE.
W.O. 3111-A-SC
BORING B- 1
+-a. o a
Sample
I TJ 0 01
- n
T3 L
C 3 D -1-
\
01
3 O
o
M n
U E
3 M SM
3
L
a
o
L
3 4-01
O
L 3 +•
(0 M
DyATTfXC/IVylT-fD
SAMPLE METHOD: HAND AUGER
SHEET_±_OF 1
8-10-01
Standard Penetration Test
Undisturbed, Ring Sample
Water Seepage into hole
Description of Material
@0' - FILL: Silty fine SAND, brown, dry, loose; fine grained.
5-
10-
15
20-
25
SM 102 4 14.0 @2' - WEATHERED TERRACE DEPOSITS: Silty fine SAND,
\red brown, damp, medium dense.
Total Depth: 2 1/2'
No groundwater encountered
Backfilled 08/10/01
391 TAMARACK AVE. GeoSoils, Inc. PLATE B-1
GeoSoils, Inc.
P/?0.y£Cr; RANDALL LOCKETT
391 TAMARACK AVE.
Q.
01
a
Sample
I Tl ttl a - n •D L C 3
3 +•
10-
15-
20-
\
3
0
o
(A n
U E
W 3 3 W SM
25
3
L
O
O
391 TAMARACK AVE.
(0 L
3
4-(0 (0
BORING LOG
w.o. 3111-A-SC
BORING B- 2
o/ir£fxc>iv/irfD
SAMPLE METHOD: HAND AUGER
SHEETJ[_PF 1
8-10-01
Standard Penetration Test
Undisturbed, Ring Sample
Water Seepage into hole
Description of Material
(5)0' - WEATHERED TERRACE DEPOSITS: Silty fine SAND,
red brown, dry, medium dense; fine grained.
\@^ 1/2' - As per 0', damp to moist, medium dense.
Total Depth: 1 1/2'
No groundwater encountered
Backfilled 08/10/01
GeoSoils, Inc. PLATE B-2
GeoSoils, Inc.
BORING LOG
w.o. 3111-A-SC
PROJECT: RANDALL LOCKETT
391 TAMARACK AVE.
BORING B- 3
+-
a
ffi
D-
Sample
I Tl
U ffi
- n
XI L
C 3
\
01
3
o
o
CO Q U E
Vt 3
3 W
3
L a o
L
3
+-
(0
M
DATE EXCAVATED
SAMPLE METHOD: HAND AUGER
SHEET 1 OF 1
8-10-01
Standard Penetration Test
Undisturbed, Ring Sample
^ Wafe/" Seepage into hole
Description of Material
SM
5-
10-
15-
20-
25
@0' - WEATHERED TERRACE DEPOSITS: Silty SAND, red
brown, dry, medium dense; fine grained.
Total Depth: 2'
No groundwater encountered
Backfilled 08/10/01
391 TAMARACK AVE. GeoSoils, Inc. PLATE B-3
BORING LOG
GeoSoils, Inc.
PROJECT: RANDALL LOCKETT
391 TAMARACK AVE.
W.O. 3111-A-SC
BORING B- 4
DATE EXCAVATED
SAMPLE METHOD: HAND AUGER
SHEET 1 OF 1
8-10-01
Standard Penetration Test
Undisturbed, Ring Sample
^ Water Seepage into hole
Description of Material
g&O' - FILL (Garden): Silty SAND, red brown, moist, loose.
@2' - Tiny pieces of asphalt.
(5)2.5' - WEATHERED TERRACE DEPOSITS: Silty SAND, red
brown, very moist, medium dense.
Total Depth: 4'
No groundwater encountered
Backfilled 08/10/01
391 TAMARACK AVE GeoSoils, Inc. PLATE B-4
APPENDIX C
LABORATORY TEST RESULTS
M. J. Schiff & Associates, Inc.
Consulting Corrosion Engineers - Since 1959 1308 Monte Vista Avenue, Suite 6
Upland, CA 91786-8224
Phone: 909/931-1360
Table 1 - Laboratory Tests on Soil Samples
Locken
Your UrSni-A-SC, MJS&A #01-0705LAB
16-Aug-Ol
Sample ID
Resistivity
as-received
saturated
pH
Electrical
Conductivity
Chemical Analyses
• 2.
Units
ohm-cm
ohm-cm
mS/cm
53,000
3,450
7.2
0.14
Cations
calcium Ca^" mg/kg 56
magnesium Mg^" mg/kg 7
sodium Na'" mg/kg ND
Anions
carbonate C03^" mg/kg ND
bicarbonate HCO3' mg/kg 67
chloride ci'-mg/kg 20
sulfate S04'" mg/kg ND
er Tests
ammonium NH4'" mg/kg na
nitrate NOJ'' mg/kg na
sulfide qual na
Redox mv na
il^ti
Electrical conductivity in millisiemens/cm and chemical analysis were made on a 1:5 Soil-to-Water extract,
mg/kg = milligrams per kilogram (parts per million) of dry soil.
Redox = oxidation-reduction potential in millivolts
ND = not detected
na = not analyzed
Page 1 of 1 Plate C-1
APPENDiX D
GENERAL EARTHWORK AND GRADING GUIDELINES
GENERAL EARTHWORK AND GRADING GUIDELINES
General
These guidelines present general procedures and requirements for earthwork and grading
as shown on the approved grading plans, including preparation of areas to filled,
placement of fill, installation of subdrains and excavations. The recommendations
contained in the geotechnical report are part ofthe earthwork and grading guidelines and
would supersede the provisions contained hereafter in the case of conflict. Evaluations
performed by the consultant during the course of grading may resuft in new
recommendations which could supersede these guidelines or the recommendations
contained in the geotechnical report.
The contractor is responsible for the satisfactory completion of all earthwork in accordance
with provisions of the project plans and speciflcations. The project soil engineer and
engineering geologist (geotechnical consultant) or their representatives should provide
observation and testing services, and geotechnical consultation during the duration of the
project.
EARTHWORK OBSERVATIONS AND TESTING
Geotechnical Consultant
Priorto the commencement of grading, a qualified geotechnical consultant (soil engineer
and engineering geologist) should be employed for the purpose of observing earthwork
procedures and testing the fills for conformance with the recommendations of the
geotechnical report, the approved grading plans, and applicable grading codes and
ordinances.
The geotechnical consultant should provide testing and observation so that determination
may be made that the work is being accomplished as specified. It is the responsibility of
the contractor to assist the consultants and keep them apprised of anticipated work
schedules and changes, so that they may schedule their personnel accordingly.
All clean-outs, prepared ground to receive fill, key excavations, and subdrains should be
obsen/ed and documented by the project engineering geologist and/or soil engineer prior
to placing and fill. It is the contractors's responsibility to notify the engineering geologist
and soil engineer when such areas are ready for observation.
Laboratorv and Field Tests
Maximum dry density tests to determine the degree of compaction should be performed
in accordance with American Standard Testing Materials test method ASTM designation
D-1557-78. Random field compaction tests should be performed in accordance with test
method ASTM designation D-1556-82, D-2937 or D-2922 and D-3017, at intervals of
approximately 2 feet of fill height or every 100 cubic yards of fill placed. These criteria
GcoSoils, Inc.
would vary depending on the soil conditions and the size of the project. The location and
frequency of testing would be atthe discretion ofthe geotechnical consultant.
Contractor's Responsibility
All clearing, site preparation, and earthwork performed on the project should be conducted
by the contractor, with observation by geotechnical consultants and staged approval by
the governing agencies, as applicable. It is the contractor's responsibility to prepare the
ground surface to receive the fill, to the satisfaction of the soil engineer, and to place,
spread, moisture condition, mix and compact the fill in accordance with the
recommendations of the soil engineer. The contractor should also remove all major non-
earth material considered unsatisfactory by the soil engineer.
It is the sole responsibility ofthe contractor to provide adequate equipment and methods
to accomplish the earthwork in accordance with applicable grading guidelines, codes or
agency ordinances, and approved grading plans. Sufficient watering apparatus and
compaction equipment should be provided by the contractor with due consideration for
the fill material, rate of placement, and climatic conditions. If, in the opinion of the
geotechnical consultant, unsatisfactory conditions such as questionable weather,
excessive oversized rock, or deleterious material, insufficient support equipment, etc., are
resulting in a quality of work that is not acceptable, the consultant will inform the
contractor, and the contractor is expected to rectify the conditions, and if necessary, stop
work until conditions are satisfactory.
During construction, the contractor shall properiy grade all surfaces to maintain good
drainage and prevent ponding of water. The contractor shall take remedial measures to
control surface water and to prevent erosion of graded areas until such time as permanent
drainage and erosion control measures have been installed.
SITE PREPARATION
All major vegetation, including brush, trees, thick grasses, organic debris, and other
deleterious material should be removed and disposed of off-site. These removals must be
concluded prior to placing fill. Existing fill, soil, alluvium, colluvium, or rock materials
determined by the soil engineer or engineering geologist as being unsuitable in-place
should be removed prior to fill placement. Depending upon the soil conditions, these
materials may be reused as compacted fills. Any materials incorporated as part of the
compacted fills should be approved by the soil engineer.
Any underground structures such as cesspools, cisterns, mining shafts, tunnels, septic
tanks, wells, pipelines, or other structures not located prior to grading are to be removed
or treated in a manner recommended by the soil engineer. Soft, dry, spongy, highly
fractured, or otherwise unsuitable ground extending to such a depth that surface
processing cannot adequately improve the condition should be overexcavated down to
Randall K. Lockett Appendix D
Rle: e:\wp7\3100\3111 a.pge Page 2
GcoSoils, Inc.
firm ground and approved by the soil engineer before compaction and filling operations
continue. Overexcavated and processed soils which have been properiy mixed and
moisture conditioned should be re-compacted to the minimum relative compaction as
specified in these guidelines.
Existing ground which is determined to be satisfactory for support of the fills should be
scarified to a minimum depth of 6 inches or as directed by the soil engineer. After the
scarified ground is brought to optimum moisture content or greater and mixed, the
materials should be compacted as specified herein. If the scarified zone is grater that 6
inches in depth, it may be necessary to remove the excess and place the material in lifts
restricted to about 6 inches in compacted thickness.
Existing ground which is not satisfactory to support compacted fill should be
overexcavated as required in the geotechnical report or by the on-site soils engineer
and/or engineering geologist. Scarification, disc harrowing, or other acceptable form of
mixing should continue until the soils are broken down and free of large lumps or clods,
until the working surface is reasonably uniform and free from ruts, hollow, hummocks, or
other uneven features which would inhibit compaction as described previously.
Where fills are to be placed on ground with slopes steeper than 5:1 (horizontal to vertical),
the ground should be stepped or benched. The lowest bench, which will act as a key!
should be a minimum of 15 feet wide and should be at least 2 feet deep into firm material'
and approved by the soil engineer and/or engineering geologist. In fill over cut slope
conditions, the recommended minimum width ofthe lowest bench or key is also 15 feet
with the key founded on firm material, as designated by the Geotechnical Consultant. As
a general rule, unless specifically recommended othenwise by the Soil Engineer, the
minimum width of fill keys should be approximately equal to V2 the height ofthe slope.
Standard benching is generally 4 feet (minimum) vertically, exposing firm, acceptable
material. Benching may be used to remove unsuitable materials, although it is understood
that the vertical height ofthe bench may exceed 4 feet. Pre-stripping may be considered
for unsuitable materials in excess of 4 feet in thickness.
All areas to receive fill, including processed areas, removal areas, and the toe of fill
benches should be observed and approved by the soil engineer and/or engineering
geologist prior to placement of fill. Fills may then be properiy placed and compacted until
design grades (elevations) are attained.
COMPACTED FILLS
Any earth materials imported or excavated on the property may be utilized in the fill
provided that each material has been determined to be suitable by the soil engineer.
These materials should be free of roots, tree branches, other organic matter or other
deleterious materials. All unsuitable materials should be removed from the fill as directed
Randall K. Lockett Appendix D
File: e:\wp7\3100\3111 a.pge Page 3
GcoSoils, Inc.
by the soil engineer. Soils of poor gradation, undesirable expansion potential, or
substandard strength characteristics may be designated by the consultant as unsuitable
and may require blending with other soils to serve as a satisfactory fill material.
Fill materials derived from benching operations should be dispersed throughout the fill
area and blended with other bedrock derived material. Benching operations should not
result in the benched material being placed only within a single equipment width away
from the fill/bedrock contact.
Oversized materials defined as rock or other irreducible materials with a maximum
dimension greaterthan 12 inches should not be buried or placed in fills unless the location
of materials and disposal methods are specifically approved by the soil engineer.
Oversized material should be taken off-site or placed in accordance with recommendations
ofthe soil engineer in areas designated as suitable for rock disposal. Oversized material
should not be placed within 10 feet vertically of finish grade (elevation) or within 20 feet
horizontally of slope faces.
To facilitate future trenching, rock should not be placed within the range of foundation
excavations, ftjture utilities, or underground construction unless specifically approved by
the soil engineer and/or the developers representative.
If import material is required for grading, representative samples of the materials to be
utilized as compacted fill should be analyzed in the laboratory by the soil engineer to
determine its physical properties. If any material other than that previously tested is
encountered during grading, an appropriate analysis ofthis material should be conducted
by the soil engineer as soon as possible.
Approved fill material should be placed in areas prepared to receive fill in near horizontal
layers that when compacted should not exceed 6 inches in thickness. The soil engineer
may approve thick lifts if testing indicates the grading procedures are such that adequate
compaction is being achieved with lifts of greater thickness. Each layer should be spread
evenly and blended to attain uniformity of material and moisture suitable for compaction.
Fill layers at a moisture content less than optimum should be watered and mixed, and wet
fill layers should be aerated by scarification or should be blended with drier material.
Moisture condition, blending, and mixing of the fill layer should continue until the fill
materials have a uniform moisture content at or above optimum moisture.
After each layer has been evenly spread, moisture conditioned and mixed, it should be
uniformly compacted to a minimum of 90 percent of maximum density as determined by
ASTM test designation, D-1557-78, or as otherwise recommended by the soil engineer.
Compaction equipment should be adequately sized and should be specifically designed
for soil compaction or of proven reliability to efficiently achieve the specified degree of
compaction.
Randall K. Lockett Appendix D
File: e:\wp7\3100\3111 a.pge Page 4
GcoSoils, Inc.
Where tests indicate that the density of any layer of fill, or portion thereof, is below the
required relative compaction, or improper moisture is in evidence, the particular layer or
portion shall be re-worked until the required density and/or moisture content has been
attained. No additional fill shall be placed in an area until the last placed lift of fill has been
tested and found to meet the density and moisture requirements, and is approved by the
soil engineer.
Compaction of slopes should be accomplished by over-building a minimum of 3 feet
horizontally, and subsequently trimming back to the design slope configuration. Testing
shall be performed as the fill is elevated to evaluate compaction as the fill core is being
developed. Special efforts may be necessary to attain the specified compaction in the fill
slope zone. Final slope shaping should be performed by trimming and removing loose
materials with appropriate equipment. Afinal determination of fill slope compaction should
be based on observation and/or testing of the finished slope face. Where compacted fill
slopes are designed steeper than 2:1 (horizontal to vertical), specific material types, a
higher minimum relative compaction, and special grading procedures, may be
recommended.
If an alternative to over-building and cutting back the compacted fill slopes is selected,
then special effort should be made to achieve the required compaction in the outer 10 feet
of each lift of fill by undertaking the following:
1. An extra piece of equipment consisting of a heavy short shanked sheepsfoot should
be used to roll (horizontal) parallel to the slopes continuously as fill is placed. The
sheepsfoot roller should also be used to roll perpendicular to the slopes, and
extend out over the slope to provide adequate compaction to the face of the slope.
2. Loose fill should not be spilled out over the face of the slope as each lift is
compacted. Any loose fill spilled over a previously completed slope face should be
trimmed off or be subject to re-rolling.
3. Field compaction tests will be made in the outer (horizontal) 2 to 8 feet of the slope
at appropriate vertical intervals, subsequent to compaction operations.
4. After completion of the slope, the slope face should be shaped with a small tractor
and then re-rolled with a sheepsfoot to achieve compaction to near the slope face.
Subsequent to testing to verify compaction, the slopes should be grid-rolled to
achieve compaction to the slope face. Final testing should be used to confirm
compaction after grid rolling.
5. Where testing indicates less than adequate compaction, the contractor will be
responsible to rip, water, mix and re-compact the slope material as necessary to
achieve compaction. Additional testing should be performed to verify compaction.
Randall K. Lockett Appendix D
File: e:\wp7\3100\3111 a.pge Page 5
GcoSoils, Inc.
6. Erosion control and drainage devices should be designed by the project civil
engineer in compliance with ordinances ofthe controlling governmental agencies,
and/or in accordance with the recommendation ofthe soil engineer or engineering
geologist.
SUBDRAIN INSTALLATION
Subdrains should be installed in approved ground in accordance with the approximate
alignment and details indicated by the geotechnical consultant. Subdrain locations or
materials should not be changed or modified without approval of the geotechnical
consultant. The soil engineer and/or engineering geologist may recommend and direct
changes in subdrain line, grade and drain material in the field, pending exposed
conditions. The location of constructed subdrains should be recorded by the project civil
engineer.
EXCAVATIONS
Excavations and cut slopes should be examined during grading by the engineering
geologist. If directed by the engineering geologist, further excavations or overexcavation
and re-filling of cut areas should be performed and/or remedial grading of cut slopes
should be performed. When fill over cut slopes are to be graded, unless othenrt/ise
approved, the cut portion of the slope should be observed by the engineering geologist
prior to placement of materials for construction of the fill portion of the slope.
The engineering geologist should observe all cut slopes and should be notified by the
contractor when cut slopes are started.
If, during the course of grading, unforeseen adverse or potential adverse geologic
conditions are encountered, the engineering geologist and soil engineer should
investigate, evaluate and make recommendations to treat these problems. The need for
cut slope buttressing or stabilizing should be based on in-grading evaluation by the
engineering geologist, whether anticipated or not.
Unless OthenA/ise specified in soil and geological reports, no cut slopes should be
excavated higher or steeper than that allowed by the ordinances of controlling
governmental agencies. Additionally, short-term stability of temporary cut slopes is the
contractors responsibility.
Erosion control and drainage devices should be designed by the project civil engineer and
should be constructed in compliance with the ordinances ofthe controlling governmental
agencies, and/or in accordance with the recommendations of the soil engineer or
engineering geologist.
Randall K. Lockett Appendix D
File: e:\wp7\3100\3111 a.pge Page 6
GcoSoils, Inc.
COMPLETION
Obsen/ation, testing and consultation bythe geotechnical consuftant should be conducted
during the grading operations in order to state an opinion that all cut and filled areas are
graded in accordance with the approved project specifications.
After completion of grading and after the soil engineer and engineering geologist have
finished their observations of the work, final reports should be submitted subject to review
by the controlling governmental agencies. No further excavation or filling should be
undertaken without prior notification of the soil engineer and/or engineering geologist.
All finished cut and fill slopes should be protected from erosion and/or be planted in
accordance with the project specifications and/or as recommended by a landscape
architect. Such protection and/or planning should be undertaken as soon as practical after
completion of grading.
JOB SAFETY
General
At GeoSoils, Inc. (GSI) getting the job done safely is of primary concern. The following is
the company's safety considerations for use by all employees on multi-employer
construction sites. On ground personnel are at highest risk of injury and possible fatality
on grading and construction projects. GSI recognizes that construction activities will vary
on each site and that site safety is the prime responsibility of the contractor; however,
everyone must be safety conscious and responsible at all times. To achieve our goal of
avoiding accidents, cooperation between the client, the contractor and GSI personnel must
be maintained.
In an effort to minimize risks associated with geotechnical testing and observation, the
following precautions are to be implemented for the safety of field personnel on grading
and construction projects:
Safety Meetings: GSI field personnel are directed to attend contractors regularly
scheduled and documented safety meetings.
Safety Vests: Safety vests are provided for and are to be worn by GSI personnel at
all times when they are working in the field.
Safety Flags: Two safety fiags are provided to GSI field technicians; one is to be
affixed to the vehicle when on site, the other is to be placed atop the
spoil pile on all test pits.
Randall K. Lockett Appendix D
File: e:\wp7\3100\3111a.pge Page 7
GcoSoils, Inc.
Flashing Lights: All vehicles stationary in the grading area shall use rotating or flashing
amber beacon, or strobe lights, on the vehicle during all fleld testing.
While operating a vehicle in the grading area, the emergency flasher
on the vehicle shall be activated.
In the event that the contractor's representative observes any of our personnel not
following the above, we request that it be brought to the attention of our office.
Test Pits Location, Orientation and Clearance
The technician is responsible for selecting test pit locations. A primary concern should be
the technicians's safety. Efforts will be made to coordinate locations with the grading
contractors authorized representative, and to select locations following or behind the
established traffic pattern, preferably outside of current traffic. The contractors authorized
representative (dump man, operator, supervisor, grade checker, etc.) should direct
excavation ofthe pit and safety during the test period. Of paramount concern should be
the soil technicians safety and obtaining enough tests to represent the fill.
Test pits should be excavated so that the spoil pile is placed away form oncoming traffic,
whenever possible. The technician's vehicle is to be placed next to the test pit, opposite
the spoil pile. This necessitates the fill be maintained in a driveable condition.
Alternatively, the contractor may wish to park a piece of equipment in front of the test
holes, particulariy in small fill areas or those with limited access.
A zone of non-encroachment should be established for all test pits. No grading equipment
should enter this zone during the testing procedure. The zone should extend
approximately 50 feet outward ft'om the center of the test pit. This zone is established for
safety and to avoid excessive ground vibration which typically decreased test results.
When taking slope tests the technician should park the vehicle directly above or below the
test location. If this is not possible, a prominent flag should be placed at the top of the
slope. The contractor's representative should effectively keep all equipment at a safe
operation distance (e.g. 50 feet) away from the slope during this testing.
The technician is directed to withdraw ft'om the active portion of the fill as soon as possible
following testing. The technician's vehicle should be parked at the perimeter of the fill in
a highly visible location, well away from the equipment traffic pattern.
The contractor should inform our personnel of all changes to haul roads, cut and fill areas
or other factors that may affect site access and site safety.
In the event that the technicians safety is jeopardized or compromised as a result of the
contractors failure to comply with any ofthe above, the technician is required, by company
policy, to immediately withdraw and notify his/her supervisor. The grading contractors
representative will eventually be contacted in an effort to effect a solution. However, in the
Randall K. Lockett Appendix D
Rle: e:\wp7\3100\311 la.pge Page 8
GcoSoils, Inc.
interim, no ftjrther testing will be performed until the situation is rectified. Any fill place can
be considered unacceptable and subject to reprocessing, recompaction or removal.
In the event that the soil technician does not comply with the above or other established
safety guidelines, we request that the contractor brings this to his/her attention and notify
this office. Effective communication and coordination between the contractors
representative and the soils technician is strongly encouraged in order to implement the
above safety plan.
Trench and Vertical Excavation
It is the contractor's responsibility to provide safe access into trenches where compaction
testing is needed.
Our personnel are directed not to enter any excavation or vertical cut which 1) is 5 feet or
deeper unless shored or laid back, 2) displays any evidence of instability, has any loose
rock or other debris which could fall into the trench, or 3) displays any other evidence of
any unsafe conditions regardless of depth.
All trench excavations or vertical cuts in excess of 5 feet deep, which any person enters,
should be shored or laid back.
Trench access should be provided in accordance with CAL-OSHA and/or state and local
standards. Our personnel are directed not to enter any trench by being lowered or "riding
down" on the equipment.
If the contractor fails to provide safe access to trenches for compaction testing, our
company policy requires that the soil technician withdraw and notify his/her supervisor.
The contractors representative will eventually be contacted in an effort to effect a solution.
All backfill not tested due to safety concerns or other reasons could be subject to
reprocessing and/or removal.
If GSI personnel become aware of anyone working beneath an unsafe trench wall or
vertical excavation, we have a legal obligation to put the contractor and owner/developer
on notice to immediately correct the situation. If corrective steps are not taken, GSI then
has an obligation to notify CAL-OSHA and/or the proper authorities.
Randall K. Lockett Appendix D
File: e:\wpA3100\311 la.pge Page 9
GcoSoils, Inc.
CANYON SUBDRAIN DETAIL
TYPE A
PROPOSED COMPACTED FILL
NATURAL GROUND
COLLUVIUM AND ALLUVIUM IREMOVE)
TYPICAL BENCHING "^^^^
^ y\\V/ BEDROCK
SEE ALTERNATIVES
TYPE B
\ N N
PROPOSED COMPACTED RLL
•NATURAL GROUND
COLLUVIUM AND ALLUVIUM (REMOVE)
BEDROCK
lr
TYPICAL BENCHING
SEE ALTERNATIVES
NOTE: ALTERNATIVES. LOCATICN AND EXTENT OF SUBDRAINS SHOULD BE DETERMINED
BY THE SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST DURING GRADING.
PLATE EG-1
CANYON SUBDRAIN ALTERNATE DETAILS
ALTERNATE 1: PERFORATED PIPE AND FILTER MATERIAL
A-1
MINIMUM
12' MINIMUM
FILTER MATERIAL MINIMUM VOLUME OF 9 FT." -^i,-.
/LINEAR FT. 6'i ABS OR PVC PIPE OR APPROVED ^''.V:
SUBSTITUTE WITH MINIMUM 8 (1/A" (T) PERFS. ^'.'.'S
LINEAR FT. IN BOTTOM HALF OF PIPE. \^
ASTM D2751. SDR 35 OR ASTM D1527. SCHD, .40
ASTM D3Q3A. SDR 35 OR ASTM D1785. SCHD. AO
FOR CONTINUOUS RUN IN EXCESS OF 500 FT.
USE8"JBfPIPE
MINIMUM
FILTER MATERIAL.
SIEVE SIZE PERCENT PASSING
IINCH .100
3/4 INCH ^°"''95
3/8 INCH 40-100
NO. 4 25-40.
NO.8 18-33
NO. 30 -.5-15
"NO. 50 .0-7
NO. 200 0-3
ALTERNATE 2: PERFORATED PIPE. GRAVEL AND.FILTER FABRIC
6-MINIMUM OVERLAP
6" MINIMUM COVER
4* MINIMUM BEDDING
6' MINIMUM OVERLAP
A--2
4' MINIMUM BEDDING
GRAVEL MATERIAL 9 FP/LINEAR FT.
PERFORATED PIPE: SEE ALTERNATE 1
GRAVEL- CLEAN 3/4 INCH ROCK OR APPROVED SUBSTITUTE
FILTER FABRIC MIRAFI 140 OR APPROVED SUBSTITUTE
PLATE EG~2
DETAIL FOR FILL SLOPE TOEING OUT
ON FLAT ALLUVIATED CANYON
TOE OF SLOPE AS SHOWN ON GRADING PLAN
ORIGINAL GROUND SURFACE TO BE
RESTORED WITH COMPACTED FILL
COMPACTED RLL
ORIGINAL GROUND SURFACE
r ANTICIPATED ALLUVIAL REMOVAL
DEPTH PER SOIL ENGMEER.
BACKCUTV-VARIES. FOR DEEP REMOVALS.^
BACKCUT ^VKSHOULD BE MADE NO ^
STEEPER THAI^SI:! OR AS NECESSARY
FOR SAFETY ^.^^ONSIDERATIONS^'^
'^v//^lP^ PROVIDE A 1:1 MINIMUM PROJECTION FROM TOE OF
SLOPE AS SHOWN ON GRADING PLAN TO THE RECOHMENDEO
REMOVAL DEPTH. SLOPE HEIGHT. SITE CONDITIONS AND/OR
LOCAL CONDITIONS COULD DICTATE FLATTER PROJECTIONS.
1'
REMOVAL ADJACENT TO EXISTING FILL
ADJOINING CANYON FILL
COMPACTED RLL LIMITS LINE
(EXISTING.COMPACTED FILL)
^^^^ ' TO BE REMOVED BEFORE BEFORE
PLACING ADDITIONAL
COMPACTED RLL
LEGEND
Qaf ARTIFICIAL FILL
Qal ALLUVIUM
PLATE EG-3
TYPICAL STABILIZATION / BUTTRESS FILL DETAIL
TJ
>
H
m m o
I
OUTLETS TO BE SPACED AT 100'MAXIMUM INTERVALS, AND SHALL EXTEND
12- BEYOND THE FACE OF SLOPE AT TIME OF.ROUGH GRADING COMPLETION.
DESIGN RNISH SLOPE
15'MINIMUM
BLANKET FILL IF RECOMMENDED
BY THE SOIL ENGINEER
10'MINIMUM
25'MAXIMUM
TYPICAL BENCHING
BUTTRESS OR SIDEHILL FILL
.2% GRADIENT
RLL I V L-
HEEL
^ W = 15'MINIMUM OR H/2
BEDROCK
DIAMETER NON-PERFORATED OUTLET PIPE
AND BACKDRAIN (SEE ALTERNATIVESI
3'MINIMUM KEY DEPTH
TYPICAL STABILIZATION / BUTTRESS SUBDRAIN DETAIL
MINIMUM 2-MINIMUM
PIPE
MINIMUM
PIPE
r"
>
m
m
o
I
un
2- MINIMUM
RLTER MATERIAL: MINIMUM OF FIVE R'/LINEAR R OF PIPF
OR FOUR FP/LINEAR Fl OF PIPE WHEN PLACED IN SQUARE
CUT TRENCH.
ALTERNATIVE IN LIEU OF RLTER MATERIAL: GRAVEL MAY BE
EI^CASED IN APPROVED RLTER FABRIC. RLTER FABRIC
SHALL BE MIRAR 140 OR EQUIVALENT. RLTER FABRIC
SHALL BE LAPPED A MINIMUM OF 12" ON ALL JOINTS.
MINIMUM L-DIAMETER PIPE: ABS-ASTM D-2751. SDR 35
OR ASTM D-1527 SCHEDULE 40 PVC-ASTM D-3034,
SpR 35 OR ASTM D-17B5 SCHEDULE AO WITH A CRUSHING
STRENOTH OF 1,000 POUNDS MINIMUM. AND A MINIMUM OF
8 UNIFORMLY SPACED PERFORATIONS PER FOOT OF PIPE
INSTALLED WITH PERFORATIONS OF BOTTOM OF PIPE.
PROVIDE CAP AT UPSTREAM END OF PIPE. SLOPE AT 2%
TO OUTLET PIPE. OUTLET PIPE TO BE CONNECTED TO
SUBDRAIN PIPE WITH TEE OR ELBOW.
NOTE: 1. TRENCH FOR OUTLET PIPES TO BE BACKRLLED
WITH ON-SITE SOIL.
2. BACKDRAINS AND LATERAL DRAINS SHALL BE
LOCATED AT ELEVATION OF EVERY BENCH DRAIN.
, RRST DRAIN LOCATED AT ELEVATION JUST ABOVE
LOWER LOT GRADE. ADDITIONAL DRAINS MAY BE
REQUIRED AT THE DISCRETION OF THE SOILS
ENGINEER AND/OR ENGINEERING GEOLOGIST.
FILTER MATERIAL SHALL BE OF
THE FOLLOWING SPECIFICATION
OR AN APPROVED EQUIVALENT:
SIEVE SIZE PERCENT PASSING
1 INCH 10 0
3/4 INCH 90-100
3/8 INCH 40-100
NO. 4 25-AO
NO. 6 18-33
NO. 30 5-15
NO. 50 0--7
NO. 200 0--3
GRAVEL SHALL BE OF THE
FOLLOWING SPECIFICATION OR
AN APPROVED E.QUIVALENT:
SIEVE SIZE PERCENT PASSING
1 1/2 INCH
NO, A
NO. 200
100
50
8
SAND EQUIVALENT: MINIMUM OF 51
FILL OVER NATURAL DETAIL
SIDEHILL FILL
PROPOSED GRADE
TOE OF SLOPE AS SHOWN ON GRADING PLAN
PROVIDE A 1:1 MINIMUM PROJECTION FROM
DESION TOE OF SLOPE TO TOE OF KEY
AS SHOWN ON AS BUILT
>
m
m
o
I
cn
NATURAL SLOPE TO
BE RESTORED WITH
COMPACTED FILL
BACKCUT VARIES • \
lb'MINIMUM KEY WIDTH
2'X 3'MINIMUM KEY DEPTH
2'MINIMUM IN BEDROCK OR
APPROVED MATERIAL.
BENCH WIDTH MAY VARY
"^•.MINIMUM
f^OTE; 1. WHERE THE NATURAL SLOPE APPROACHES OR EXCEEDS THE
' DESIGN SLOPE RATIO. SPECIAL RECOMMENDATIONS WOULD BE
PROVIDED BY THE SOILS ENGINEER.
2. THE NEED FOR AND DISPOSl.TION OF DRAINS WOULD BE DETERMINED
BY THE SOILS ENGINEER BASED UPON EXPOSED CONDITIONS.
FILL OVER CUT DETAIL
f^llT/RLL CONTACT
1. AS SHOWN ON GRADING PLAN
2. AS SHOWN ON AS BUILT
MAINTAIN MINIMUM 15'RLL SECTION FROM
BACKCUT TO FACE OF RNISH SLOPE
•MINIMUM ^
_ ^
'^BEDROCK OR APPROVED MATERIAL
LOWEST BENCH WIDTH
15'MINIMUM OR H/2
^ TA'MINIMUM
BENCH WIDTH MAY VARY
>
m
m o
I
NOTE: THE CUT PORTION OF THE SLOPE SHOULD BE EXCAVATED AND
EVALUATED BY THE SOILS ENGINEER AND/OR ENGINEERING
GEOLOGIST PRIOR TO CONSTRUCTING THE RLL PORTION.
STABILIZATION FILL FOR UNSTABLE MATERIAL
EXPOSED IN PORTION OF CUT SLOPE
"D
>
m
m
o
I
oo
^^^^^RJ^Pp^SED RNISHED GRADE
j,i UNWEATHERED BEDROCK
OR APPROVED MATERIAL
"^^fH-^ COMPACTED STABILIZATION RLL
— 7'Xl' MINIMUM TILTED BACK
IF RECOMMENDED BY THE SOILS ENGINEER AND/OR ENGINEERING
GEOLOGIST. THE REMAINING CUT PORTION OF THE SLOPE MAY
REQUIRE REMOVAL AND REPLACEMENT WITH COMPACTED RLL
NOTE: 1. SUBDRAINS ARE NOT REQUIRED UNLESS SPECIFIED BY SOILS ENOINEER AND/OR ENGINEERING GEOLOGIST,
2 -Wr SHALL BE EQUIPMENT WIDTH CIS') FOR SLOPE HEIOHTS LESS THAN 25 FEET. FOR SLOPES GREATER-
THAN 25 FEET -W- SHALL BE DETERMINED BY THE PROJECT SOILS ENOINEER AND /OR ENGINEERING
GEOLOGIST. AT NO TIME SHALL "W BE LESS THAN H/2.
SKIN RLL OF NATURAL GROUND
ORIGINAL SLOPE
'ROPOSED FINISH GRADE
15'MINIMUM TO BE MAINTAINED FROM
PROPOSED RNISH SLOPE FACE TO BACKCUT
PROPOSED RNISH SLOPE
T3N MINIMUM
^ BEDROCK OR APPROVED MATERIAL
^ fei
15'MtNIMUM K :EY WIDTH
^ 3'MINIMUM KEY DEPTH
TI
H
m
m
CD
I
CD
NOTE: 1. THE NEED AND DISPOSITION OF DRAINS WILL BE DETERMINED! BY THE SOILS ENGINEER AND/OR
ENGINEERING GEOLOGIST BASED ON FIELD CONDITIONS.
2. PAD OVEREXCAVATION AND RECOMPACTION SHOULD BE PERFORMED IF DETERMINED TO BE
NECESSARY BY THE SOILS ENGINEER AND/OR ENGINEERINO GEOLOGIST.
DAYLIGHT CUT LOT DETAIL
RECONSTRUCT COMPACTED RLL SLOPE AT 2:1 OR FLATTER
IMAY INCREASE OR DECREASE PAD AREA)
OVEREXCAVATE AND RECOMPACT
REPLACEMENT RLL
AVOID AND/OR CLEAN UP SPILLAGE OF
MATERIALS ON THE NATURAL SLOPE
NATURAL GRADE
TVPII
BEDROCK OR APPROVED MATERIAL
TYPICAL BENCHING
% GRADIgNTi^x.
T)
>
m
rn o
1
NOTE: 1. SUBDRAIN AND KEY WIDTH REOUIREMENTS WILL BE DETERMINED BASED ON EXPOSED SUBSURFACE
CONDITIONS AND THICKNESS OF OVERBURDEN.
2. PAD OVER EXCAVATION AND RECOMPACTION SHOULD BE PERFORMED IF DETERMINED NECESSARY BY
THE SOILS ENGINEER AND/OR THE ENGINEERING GEOLOGIST.
TRANSITION LOT DETAIL
CUT LOT (MATERIAL TYPE TRANSITION)
NATURAL GRADE
COMPACTED RLL
^ I IMU
ij^^jT^T^;;^^^^^;^^ 3-MimMUM^
^ UNWEATHERED BEDROCK OR APPROVED MATERIAL
TYPICAL BENCHING
CUT-RLL LOT (DAYUGHT TRANSITION)
PAD GRADE
NATURAL GRADE -^^^^
-j^c.'V^J^-QYEREXCAVATE
^ AND RECOMPACT
5'MII^MUM
UNWEATHERED BEDROCK OR APPROVED MATERIAL
____ TYPICAL BENCHING
NOTE: * DEEPER OVEREXCAVATION MAY BE RECOMMENDED BY THE SOILS ENGINEER
AND/OR ENGINEERING GEOLOGIST IN STEEP CUT-RLL TRANSITION AREAS.
PLATE EG-ir
SETTLEMENT PLATE AND RISER DETAIL
2'X 2'X 1/A- STEEL PLATE
STANDARD 3/A- PIPE NIPPLE WELDED TO TOP
OF PLATE.
3/A- X 5'GALVANIZED PIPE. STANDARD PIPE
THREADS TOP AND BOTTOM. EXTENSIONS
THREADED ON BOTH ENDS AND ADDED IN 5*
INCREMENTS.
3 INCH SCHEDULE AO PVC PIPE SLEEVE. ADD IN
5" INCREMENTS WITH GLUE JOINTS.
RNAL GRADE
MAINTAIN 5'CLEARANCE OF HEAVY EQUIPMENT.
MECHANICALLY HAND COMPACT IN 2'VERTICAL
-rV LIFTS OR ALTERNATIVE SUITABLE TO AND
J ACCEPTED BY THE SOILS ENGINEER.
MECHANICALLY HAND COMPACT THE INITIALS'
VERTICAL WITHIN A 5'RADIUS OF PLATE BASE.
~ ~ \-. • • . • .. . . . • ••••./ BOTTOM DF CLEANOUT
PROVIDE A MINIMUM 1* BEDDING OF COMPACTED SAND
NOTE:
1. LOCATIONS OF SETTLEMENT PLATES SHOULD BE CLEARLY MARKED AND READILY
VISIBLE (RED FLAGGED) TO EQUIPMENT OPERATORS.
2. CONTRACTOR SHOULD MAINTAIN CLEARANCE OF A 5'RADIUS OF PLATE BASE AND
WITHIN 5'(VERTICAU FOR HEAVY EQUIPMENT. RLL WITHIN CLEARANCE AREA SHOULD
BE HAND-COMPACTED TO PROJECT SPECIRCATIONS OR COMPACTED BY ALTERNATIVE
APPROVED BY THE SOILS ENGINEER. r.^.r,....-
3. AFTER 5'(VERTICAL) OF RLL IS IN PLACE. CONTRACTOR SHOULD MAINTAIN A 5_RADIUS
EQUIPMENT CLEARANCE FROM RISER.
A. PLACE AND MECHANICALLY HAND COMPACT INITIAL 2" OF RLL PRIOR TO ESTABLISHING
THE INITIAL READING.
5. IN THE EVENT OF DAMAGE TO THE SETTLEMENT PLATE OR EXTENSION RESULTING
FROM EQUIPMENT OPERATING WITHIN THE SPECIFIED CLEARANCE AREA. CONTRACTOR
SHOULD IMMEDIATELY NOTIFY THE SOILS ENGINEER AND SHOULO BE RESPONSIBLE
FOR RESTORING THE SETTLEMENT PLATES TO WORKING ORDER.
5. AN ALTERNATE DESIGN AND METHOD OF INSTALLATION MAY BE PROVIDED AT THE
DISCRETION OF THE SOILS ENGINEER.
PLATE EG-U
TYPICAL SURFACE SETTLEMENT MONUMENT
RNISH GRADE
•3-6'
3/8" DIAMETER X 6" LENGTH
CARRIAGE BOLT OR EQUIVALENT
<-6- DIAMETER X 3 1/2* LENSTH HOLE
CONCRETE BACKRLL
PLATE EG-15
TEST PIT SAFETY DIAGRAM
SIDE YIEW
( NOT TO SCALE )
I^RJkG-
TOP VIEW
100 FEET
50 FEET
^TESTPITggiJI^^M
lii
u. a in 50 FEET
V&BCLE
APPROXIMATE CENTER
OF TEST PIT
J L
{ NOT TO SCALE )
PLATE EG-16
OVERSIZE ROCK DISPOSAL
VIEW NORMAL TO SLOPE FACE
10'MINIMUM
oo
OS
(B)
_J5'MINIMUM (AX^
oo
CX3
PROPOSED FINISH GRADE
10'MINIMUM (E)
15'MINIMUM (A)
O
oo
OO
oo
(6)
cao
oolFl
MINIMUM (C)
V // i^r^r •\ \^ \-
BEDROCK OR APPROVED MATERIAL
VIEW PARALLEL TO SLOPE FACE
PROPOSED RNISH GRADE
FROM ____;fiiNiMUM to
BEDROCK OR APPROVED MATERIAL
NOTE- (AJ ONE EQUIPMENT WIDTH OR A MINIMUM OF 15 FEET.
R HEIGHT /^ND WIDTH MAY VARY DEPENDING ON ROCK SIZE AND TYPE OF
EQUIPMENT LENGTH OF WINDROW SHALL BE NO GREATER THAN 100'MAXIMUM.
IC) IF APPROVED BY THE SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST
WINDROWS MAY BE PLACED DIRECTLY ON COMPETENT MATERIAL OR BEDROCK
PROVIDED ADEQUATE SPACE IS AVAILABLE FOR COMPACTION
(D) ORIENTATION OF WINDROWS MAY VARY BUT SHOULD BE AS RECOMMENDED BY
THE SOILS ENGINEER AND/OR ENGINEERING GEOLOGIST. STAGGERING OF
WINDROWS IS NOT NECESSARY UNLESS RECOMMENDED. IE) CLEAR AREA FOR UTILITY TRENCHES. FOUNDATIONS AND SWIMMING POOLS.
(F) ALL FILL OVER AND AROUND ROCK WINDROW SHALL BE COMPACTED TO 90%
(G) JIIE^^'F^L BTTWEE^N^^IN^ COMPACTED WITH THE LIFT OF
FILL COVERING WI^^^^^^ SHOULD BE PROOF ROLLED WITH A
D-9 DOZER OR EQUIVALENT.
VIEWS ARE DIAGRAMMATIC ONLY. ROCK SHOULD NOT TOUCH ATT^ ^
AND VOIDS SHOULD BE COMPLETELY RLLED IN. PLATE RD —1
ROCK DISPOSAL PITS
VIEWS ARE DIAGRAMMATIC ONLY. ROCK SHOULD NOT TOUCH
AND VOIDS SHOULD BE COMPLETELY RLLED IN.
RLL LIFTS COMPACTED OVER
ROCK AFTER EMBEDMENT r I
I GRANULAR MATERIAL
COMPACTED RLL
SIZE OF EXCAVATION TO BE
COMMENSURATE WITH ROCK SIZE
ROCK DISPOSAL LAYERS
GRANUUR SOIL TO RLL VOIDS.-v ^ COMPACTED RLL
DENSIRED BY FLOODING ^""^ "-f
LAYER ONE ROCK
PROPOSED RNISH GRADE PROFILE ALONG UYER
LOPE FACE
ts'MINIMUM
OOOOCOOOCXDOC5CG
CLEAR ZONE 20'MINIMUM
LAYER ONE ROCK HIGH
PLATE RD-2