HomeMy WebLinkAboutCT 04-06; PALOMAR POINTE; REPORT OF GEOTECHNICAL OBSERVATION; 2005-04-26NorCal Engineering ° - Soils and Geotechnical Consultants 10641 Humbolt Street Los Alamitos, CA 90720 (562) 799-9469 Fax (562) 799-9459 a April 26, 2005 Project Number 9623-01 Lanikai Management Corporation P.O. Box 455 Santa Ynez, California 93460 Attn: Larry Jett RE: Report of Geotechnical Observation and Testing of Rough Grading Operations - Proposed Palomar Point Development (Buildings A, B and C) - Located at 1930 Palomar Point Way, in the City of Carlsbad, California Dear Mr. Jett: Pursuant to your request, this firm has provided this geotechnical report to summarize the observation and testing performed during rough grading operations at the above referenced project. The geotechnical aspects of the grading were conducted in accordance with our report titled "Geotechnical Engineering Investigation", dated November 5, 2001, Project Number 9623-01. Our geotechnical services pertaining to the grading of the project development are summarized in the subsequent sections of • this report. Site Grading The purpose of the grading operations was for the placement of fill to provide structural support of the proposed development. All vegetation and demolition debris was stripped and removed from the fill area prior to the placement of any fill soils. The upper low density surface soils were removed to competent native soils or bedrock material, the exposed surface scarified, moisture conditioned and then recompacted to a minimum of f 90% relative compaction. 0 April 26, 2005 Project Number 9623-01 Page 2 Keyways were excavated into competent bedrock material at four locations on the site. The approximate locations of the keyways are shown on the attached plan. In addition, foundation areas for Building A were overexcavated in order to permit the placement of a one foot thick compacted fill blanket beneath foundations. Foundation areas for Buildings B and C were overexcavated in order to permit the placement of a three feet thick compacted fill blanket beneath the foundations. In the opinion of this firm, the native soils are suitable to support the placement of fill material. Grading extended a minimum of five horizontal feet or to the depth of fill placed whichever is greater, beyond the edge of the proposed foundations. Fill soils placed were compacted to a minimum 90% of the laboratory standard in lifts not in excess of eight inches in thickness. The maximum depth of fill soils placed was approximately 13 feet. The upper one foot of the building pads were compacted to a minimum of 95% of the laboratory standard. Conventional earthmoving equipment was utilized for compaction control. A water truck provided moisture control. Our services did not include any surveying of excavation bottoms, building corners, or subgrade elevations during grading operations. Grading operations were not completed for the slope area adjacent to the north property line. A crib wall is currently under construction in this area. The slope area will be graded after construction and backfill of the crib wall is completed. The proposed street area (Palomar Point Way) was rough graded and left approximately 1 to 11/2 feet below grade. Grading in this area will be completed at a later date. NorC al Engineering April 26, 2005 Project Number 9623-01 Page 3 Laboratory/Field Testing The relative compaction was determined by Sand Cone Method (ASTM: D1556-00) and by the Drive Tube Method (ASTM: D2937-00). The maximum density of the fill soils was obtained by the laboratory standard (ASTM: D1557-00) and results are shown on Table .1. Tests were performed a minimum of every 500 cubic yards placed and every two feet in depth of fill placed. A summary of the compaction tests of the rough grading operations are described in Appendix B with locations shown on the accompanying plan. Additional laboratory tests were performed on representative bulk bag samples of the near surface soils at the completion of precise grading operations. The tests consisted of the following: Expansion index tests in accordance with the Uniform Building Code Standard No. 0 18-2 were performed on remolded samples of the upper soils to determine the expansive characteristics and to provide any necessary recommendations for reinforcement of the slabs-on-grade and the foundations. Results of these tests are provided on Table II in Appendix A. Soluble sulfate tests in accordance with California Test Method 417 were performed on representative soils samples to estimate the potential for corrosion of concrete in contact with the on-site soils. Results are provided on Table Ill in Appendix A. Foundation Design All foundations may be designed utilizing the following allowable soil bearing capacities for an embedded depth of 24 inches, into approved fill materials with the corresponding widths:. Allowable Soil Bearing Capacity (psf) Continuous Isolated Width (ft) Foundation Foundation 1.5 2000 2500 2.0 2075 2575 4.0 2375 2875 0 NorCal Engineering April 26, 2005 Project Number 9623-01 Page 4 .' The bearing value may be increased by 500 psf for each additional foot of depth in excess of the 24 inch minimum depth, up to a maximum of 4,000 psf. A one-third increase may be used when considering short term loading and seismic forces. Any foundations located along the property lines or where lateral overexcavations is not possible may utilize a soil bearing capacity of 1,500 psf. A representative of this firm shall inspect all foundation excavations prior to pouring concrete. All foundations shall be reinforced with a minimum of one No. 5 bar, top and bottom. Slab Design All concrete slabs-on-grade shall be at least five inches in thickness and placed on approved subgrade soils compacted to a minimum of 95% relative compaction in the upper one foot. Reinforcement requirements and an increase in thickness of the slabs- on-grade may be necessary based upon proposed loading conditions in the structures. A vapor barrier overlain by a two-inch thick sand layer should be utilized in areas which would be sensitive to the infiltration of moisture. All concrete slab areas to receive floor coverings should be moisture tested to meet all manufacturer requirements prior to placement. All slabs-on-grade shall be reinforced with a minimum of No. 3 bars at 18 inches on-center in both directions positioned in the center of the slab. The upper 18 inches of the subgrade soils shall be moistured to 130% of the optimum moisture content prior to pouring concrete. All concrete slabs to be utilized for pavement shall be a minimum of six inches in thickness and placed on approved subgrade soils. Corrosion Design Criteria Representative samples of the surficial soils revealed negligible sulfate concentrations. Therefore, all concrete in contact with on site soils shall be designed in accordance with i Table 19A-A-4 of the 1997 Uniform Building Code. Sulfate test results may be found on the attached Table Ill. NorCal Engineering April 26, 2005 Project Number 9623-01 Page 5 Limitations It should be noted that our work does not warrant or guarantee that the contractor responsible for each phase of the project has performed his work in accordance with the project specifications. 0 We appreciate this opportunity to be of service to you. If you have any further questions, please do not hesitate to contact the undersigned. Respectfully submitted, NORCALENGINEE OFESS,04, No. 841 - Keith D. Tucker cc Exp. 12/31/0 M Walter K. Mott Project Engineer * \.. Project Manager 0 NO R.G.E. 841 0 S NorCal Engineering APPENDICES - (In order of appearance) Appendix A— Laboratory Tests Table I - Maximum Density Tests Table H - Expansion Index Tests Table Ill - Sulfate Tests Appendix B - Summary of Compaction Tests Site Plan Summary of Compaction Tests L7 fl NorCal Engineering • Appendix A • r. L NorCal Engineering April 26, 2005 Project Number 9623-01 Page 6 TABLE • MAXIMUM DENSITY TESTS (ASTM: D1557-00) Optimum Maximum Dry Sample Classification Moisture Density (Ibs./cu.ft.) O I Clayey SAND 13.5 117.5 II Silty SAND 12.5 122.0 III Silty SAND 12.0 . 124.0 IV Silty SAND 11.0 128.0 V Silty SAND 10.0 130.0 ' VI Clayey SAND 10.5 120.5 VII Silty SAND 14.0 115.0 VIII Silty SAND 11.0 120.5 TABLE II EXPANSION INDEX TESTS (U.B.C. STD. 18-2) Expansion Sample Classification Index • Pad Subgrade Clayey SAND 40 Pad Subgrade Silty SAND 15 Pad Subgrade Silty SAND 11 TABLE III SULFATE TESTS (CA. TEST METHOD 417) Sample Sulfate (% by Weight) Pad Subgrade 0.014 Pad Subgrade 0.013 Pad Subgrade 0.018 Pad Subgrade 0.006 NorC a! Engineering Appendix B n NorCal Engineering April 26, 2005 Project Number 9623-01 Page SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No Location Elevations Moisture Ibs./cu.ft. Compaction Type SO 3/29/05 101 Site Grading 253.0 14.6 109.1 93 I D 3/29/05 102 Site Grading 271.0 13.9 108.8 93 I D 3/29/05 103 Site Grading 256.0 14.4 106.6 91 I . D • 3/29/05 104 Site Grading 261.0 14.1 110.6 94 I S 3/29/05 105 Site Grading 265.0 12.9 114.2 94 II D 3/29/05 106 Site Grading 258.0 13.4 111.9 92 II D 3/29/05 107 Site Grading 260.0 14.3 103.2 88 I D 3/29/05 107A** Site Grading 260.0 14.6 105.8 90 I D 3/29/05 108 Site Grading 261.0 14.1 106.1 90 I S 3/29/05 109 Site Grading 258.0 13.2 111.3 91 II 3/29/05 110 Site Grading 261.0 14.2 108.6 92 I, D 3/29/05 111 Site Grading 270.0 14.6 107.3 91 I D • 3/29/05 112 Site Grading 267.0 14.9 109.3 93 I S 3/29/05 113 Site Grading 263.0 13.2 109.8 90 II D 3/29/05 114 Site Grading 266.0 12.9 111.6 91 II D 3/29/05 115 Site Grading 265.0 13.9 112.3 92 Il S 3/30/05 116 Site Grading 267.0 19.1 100.7 83 II D . 3/31/05 116A** Site Grading 267.0 13.9 111.6 91 II D 3/31/05 117 Site Grading 268.0 13.2 110.4 90 Il D. 3/31/05 118 Site Grading 272.0 13.1 112.0 92 II D 3/31/05 119 Site Grading 270.0 12.9. 113.6 93 II S 3/31/05 120 Site Grading 274.0 12.2 112.3 92 II D 4/1/05 121 Site Grading 266.0 12.9 113.3 91 III D 4/1/05 122 Site Grading 272.0 12.7 112.6 91 III D 4/1/05 123 Site Grading 275.0 13.4 105.8 90 I S 4/1/05 124 Site Grading 279.0 13.0 112.3 92 II D 4/1/05 125 Site Grading 285.0 13.2 111.3 91 II D 4/4/05 126 Site Grading 279.0 12.0 111.6 90 III D 4/4/05 127 Site Grading 277.0 12.3 119.2 93 IV S 4/4/05 128 Site Grading 275.0 17.8 104.8 85 III D 4/4/05 128A** Site Grading 275.0 13.3 115.7 93 III D 4/4/05 129 Site Grading 281.0 11.5 119.3 93 IV D **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method NorCal Engineering [] C i• April 26, 2005 Project Number 9623-01 Page SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No. Location Elevations Moisture Ibs./cu.ft. Compaction Type S/D 4/4/05 130 Site Grading 288.0 14.6 108.4 92 I S 4/4/05 131 Site Grading 294.0 15.4 108.3 92 I D 4/4/05 132 Site Grading 268.0 16.5 105.6 85 III D 4/4/05 132A** Site Grading 268.0 13.2 113.9 92 III D 4/4/05 133 Site Grading 273.0 12.9 112.5 91 III D 4/4/05 134 Site Grading 277.0 14.2 106.2 87 II S 4/4/05 134A** Site Grading 277.0 12.5 113.3 93 II S 4/4/05 135 Site Grading 271.0 13.4 110.2 90 II D 4/4/05 136 Site Grading 278.0 13.2 112.2 90 Ill D 4/4/05 137 Site Grading 279.0 13.0 114.2 92 III D 4/4/05 138 Site Grading 291.0 14.3 107.2 91 I S 4/4/05 139 Site Grading 304.0 14.1 107.8 92 I D 4/4/05 140 Site Grading 295.0 13.9 109.0 93 I D 4/4/05 141 Site Grading 299.0 14.2 106.8 91 I D 4/4/05 142 Site Grading 297.0 13.2 110.2 90 II S 4/4/05 143 Site Grading 288.0 13.0 111.5 91 II D 4/4/05 144 Site Grading 285.0 13.3 112.1 92 II D 4/5/05 145 Site Grading 309.0 13.7 109.4 93 I D 4/5/05 146 Site Grading 276.0 13.1 110.8 91 II S 4/5/05 147 Site Grading 283.0 12.9 112.5 92 II D 4/5/05 148 Site Grading 287.0 13.3 111.2 91 II D 4/5/05 149 Site Grading 299.0 17.7 105.8 87 II S 4/5/05 149A** Site Grading 299.0 13.6 113.0 93 II S 4/6/05 150 Site Grading 294.0 13.1 110.6 91 II D 4/6/05 151 Site Grading 299.0 13.0 112.4 91 III D 4/6/05 152 Site Grading 300.0 12.8 117.4, 92 IV D 4/6/05 153 Site Grading 298.0 12.9 112.3 91 III S 4/6/05 154 Site Grading 303.0 13.1 112.2 92 II D 4/6/05 155 Site Grading 308.0 11.7 115.5 90 IV D 4/6/05 156 Site Grading 315.0 11.4 115.7 90 IV D 4/6/05 157 Site Grading 303.0 13.0 113.7 93 II S 4/6/05 158 Site Grading 303.0 12.8 112.6 92 II D **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method NorCal Engineering El fl April 26, 2005 Project Number 9623-01 Page 9 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No. Location Elevations Moisture lbs./cu.ft. Compaction L S/D 4/7/05 159 Site Grading 302.0 12.9 109.8 90 II D 4/7/05 160 Site Grading 307.0 13.2 112.2 ' 92 II D 4/7/05 161 Site Grading 309.0 13.6 110.7 91 II S 4/7/05 162 Site Grading 308.0 12.8 111.7 92 II D 4/7/05 163 Site Grading 294.0 10.8 112.8 88 IV D 4/7/05 163A** Site Grading 294.0 10.9 116.3 91 IV D 4/7/05 164 Site Grading 306.0 11.5 122.1 95 IV S 4/7/05 165 Site Grading 299.0 10.6 115.4 90 IV D 4/7/05 166 Site Grading 288.0 11.0 117.1 91 IV D 4/7/05 .167 Site Grading 298.0 10.6 116.6 91 IV D 4/7/05 168 Site Grading 290.0 10.3 115.3 90 IV S 4/7/05 169 Site Grading 276.0 12.7 113.7 93 II D 4/7/05 170 Site Grading 282.0 11.2 117.8 92 IV D 4/7/05 171 Site Grading 308.0 10.8 116.4 91 IV D 4/7/05 172 Site Grading 312.0 10.4 110.2 86 IV S 4/7/05 172A** Site Grading 312.0 11.2 117.1 91 IV S 4/7/05 173 Site Grading 311.0 10.7 116.5 91 IV D 4/7/05 174 Site Grading 308.0 9.3 119.8 92 V D 4/7/05 175 Site Grading 297.0 9.7 117.6 90 V D 4/7/05 176 Site Grading 307.0 12.9 113.8 92 Ill S 4/7/05 177 Site Grading 312.0 13.2 112.2 90 III D 4/7/05 178 Site Grading 315.0 13.0 113.2 91 III D 4/8/05 179 Site Grading 310.0 11.2 115.2 90 IV D 4/8/05 180 Site Grading 313.0 10.2 117.1 90 V S 4/8/05 181 Site Grading 303.0 10.4 117.7 92 IV D 4/8/05 182 Site Grading 300.0 11.3 118.5 91 V D 4/8/05 183 Site Grading 304.0 11.4 115.3 90 IV D 4/8/05 184 Site Grading 303.0 10.2 121.3 93 V S 4/8/05 185 Site Grading 306.0 10.7 114.7 88 V D 4/8/05 185A** Site Grading 306.0 10.2 118.8 91 V D 418/05 186 Site Grading 309.0 11.3 115.2 90 IV D 4/8/05 187 Site Grading 314.0 12.6 111.5 91 II S **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method 0 NorCal Engineering April 26, 2005 . Project Number 9623-01 Page 10 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No Location Elevations Moisture lbs./cu.ft. Compaction Type S/D 4/8/05 188 Site Grading 322.0 11.5 112.1 92 II D 4/8/05 189 Site Grading 315.0 11.2 116.0 91 IV D 4/8/05 190 Site Grading 309.0 11.3 117.4 92 IV S 4/8/05 191 Site Grading 306.0 11.5 117.5 92 IV D 4/8/05 192 Site Grading 317.0 14.4 109.3 93 I D 4/8/05 193 Site Grading 317.0 13.9 107.9 92 I D 4/11/05 194 Site Grading 310.0 11.6 118.2 92 IV S 4/11/05 195 Site Grading 315.0 12.2 113.2 91 III . D 4/11/05 196 Site Grading 320.0 12.5 114.6 92 III D 4/11/05 197 Site Grading 310.0 12.9 111.7 92 II D 4/11/05 198 Site Grading 314.0 14.9 103.4 85 II S 4/11/05 198A** Site Grading 314.0 13.1 113.1 93 II S 4/11/05 199 Site Grading 317.0 1.8 110.8 91 II . D 4/11/05 200 Site Grading .317.0 15.0 106.9 91 I D 4/11/05 201. Site Grading 317.0 14.8 106.2 90 I D 4/11/05 202 Site Grading 318.0 11.8 109.8 90 II . S 4/11/05 203 Site Grading 316.0 12.5 112.8 91 III D 4/11/05 204 Site Grading 321.0 13.2 111.3 91 II D 4/11/05 205 Site Grading 312.0 12.4 112.9 91 III D 4/11/05 206 Site Grading 322.0 12.6 114.6 92 .. III S 4/11/05 207 Site Grading 310.0 11.8 115.3 90 IV D 4/11/05 208 Site Grading 312.0 11.0 117.1 91 IV D 4/11/05 209 Site Grading 314.0 12.4 116.0 94 III S 4/11/05 210 Site Grading 314.0 12.9 111.6 91 II D 4/11/05 211 Site Grading 320.0 13.1 114.0 93 II D 4/11/05 212 Site Grading 319.0 14.5 107.4 88 II D 4/11/05 212A** Site Grading 319.0 13.2 111.3 91 II D 4/11/05 213, Site Grading 314.0 12.4 115.8 90 . IV S 4/11/05 214 Site Grading 312.0 13.0 111.5 91 II D 4/12/05 215 Site Grading 319.0 10.1 120.7 93 . V D 4/12/05 .216 Site Grading 318.0 10.6 124.0 95 V S 4/12/05 217 Site Grading 315.0 11.1 115.2 90 IV D **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method NorCal Engineering April 26, 2005 Project Number 9623-01 Page 11 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No. Location Elevations Moisture lbs./cu.ft. Compaction ]: 4/12/05 218 Site Grading 320.0 10.1 120.7 93 V D 4/12/05 219 Site Grading 319.0 10.8 114.6 95 VI D 4/12/05 220 Site Grading 321.0 12.9 109.9 90 II S • 4/12/05 221 Site Grading 318.0 13.6 107.3 91 I D 4/12105 222 Site Grading 319.0 9.4 117.9 91 V D 4/12/05 223 Site Grading 320.0 12.7 112.6 92 II D 4/12/05 224 Site Grading 320.0 12.4 112.1 92 II S 4/12/05 225 Site Grading 312.0 9.4 123.6 95 V D 4/12/05 226 Site Grading 313.0 10.8 119.1 93 IV D 4/12/05 227 Site Grading 313.0 13.5 113.6 92 III . D 4/13/05 228 Site Grading 306.0 10.6 120.6 93 V D 4/13/05 229 Site Grading 309.0 10.8 118.2 91 V S 4/13/05 230 Site Grading 312.0 10.2 119.7 92 V D 4/13/05 231 Site Grading 314.0 11.2 116.0 91 IV D 4/13/05 232 Site Grading 315.0 10.5 117.1 90 V D 4/13/05 233 Site Grading 317.0 10.9 117.3 90 V S 4/13/05 234 Site Grading 311.0 10.8 120.0 92 V D 4/13/05 235 Site Grading 310.0 10.1 119.8 94 IV D • 4/13/05 236 Site Grading 311.0 11.2 115.2 90 IV D 4/13/05 237 Site Grading 314.0 10.9 116.3 91 IV S 4/13/05 238 Site Grading 315.0 14.2 114.2 88 V S 4/13/05 238A** Site Grading 315.0 10.8 120.0 92 V S 4/13/05 239 Site Grading 316.0 14.5 106.5 91 I D 4/13/05 240 Site Grading 316.0 13.2 112.2 92 II D 4/13/05 241 Site Grading 321.0 10.9 118.0 91 V D .4/13/05 242 Site Grading 320.0 13.0 115.7 93 III S 4/13/05 243 Site Grading 318.0 10.2 121.5 93 V D 4/13/05 244 Site Grading 319.0 9.8 117.5 92 IV D 4/13/05 245 Site Grading 319.0 11.2 118.1 91 V D 4/13/05 246 Site Grading 319.0 10.6 . 117.3 90 V S 4/13/05 247 Site Grading 319.0 9.2 123.8 95 V S 4/13/05 248 Site Grading 321.0 17.3 107.9 87 III D **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method NorCal Engineering April 26, 2005 Project Number 9623-01 Page 12 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No. Location Elevations Moisture Ibs./cu.ft. Compaction Type S/D 4/13/05 248A** Site Grading 321.0 12.9 112.5 91 III b 4/13/05 249 Site Grading 319.0 13.4 111.9 92 II S 4/13/05 250 Site Grading 320.0 13.2 109.8 90 II D • 4/14/05 251 Site Grading 322.0 12.9 109.9 90 II D 4/14/05 252 Site Grading 322.0 13.3 111.2 91 II D 4/14/05 253 Site Grading 322.0 12.8 112.6 92 II S 4/14/05 254 Site Grading 318.0 14.3 104.1 91 VII D 4/14/05 255 Site Grading 318.0 13.8 105.4 92 VII D 4/14/05 256 Site Grading 314.0 12.2 121.8 95 IV S 4/14/05 257 Site Grading 316.0 10.3 109.7 91 VI D 4/14/05 258 Site Grading 320.0 10.0 115.4 90 IV D 4/14/05 259 Site Grading 322.0 11.1 115.2 90 IV D 1• 4/14/05 260 Site Grading 321.0 10.9 118.3 92 IV 5 4/14/05 261 Site Grading 322.0 11.3 110.5 92 VI D 4/14/05 262 Site Grading 317.0 13.1 109.8 90 II D 4/14/05 263 Site Grading 322.0 15.6 101.2 63 II D 4/14/05 263A** Site Grading 322.0 13.3 109.8 90 II D . 4/14/05 264 Site Grading 316.0 12.2 118.3 95 III S 4/14/05 265 Site Grading 317.0 12.6 111.0 91 II D 4/14/05 266 Site Grading 318.0 12.1 113.3 91 III D 4/14/05 267 Site Grading 314.0 12.8 111.7 90 III D 4/14/05 268 Site Grading 323.0 9.4 118.6 91 V S 4/14/05 269 Site Grading 323.0 10.6 115.7 90 IV D 4/14/05 270 Site Grading 321.0 9.7 115.4 90 IV D 4/14/05 271 Site Grading 321.0 10.7 116.2 91 IV D 4/14/05 272 Site Grading 324.0 11.2 107.3 84 IV S 4/14/05 272A** Site Grading 324.0 11.0 116.2 91 IV S 4/14/05 273 Site Grading 324.0 10.8 111.9 93 VI D 4/14/05 274 Site Grading 223.0 10.6 115.7 90 IV D 4/15/05 275 Site Grading 322.0 14.3 105.8 90 I D 4/15/05 276 Site Grading 324.0 10.8 116.4 91 IV S 4/15/05 277 Site Grading 324.5 10.5 113.1 88 IV D **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method A NorCal Engineering April 26, 2005 Project Number 9623-01 Page 13 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No Location Elevations Moisture lbs.Icu.ft. Compaction Type SO 4/15/05 277A** Site Grading 324.5 10.8 115.5 90 IV D 4/15/05 278 Site Grading 323.0 11.2 116.9 91 IV D 4/15/05 279 Site Grading 320.0 9.8 118.9 91 V S 4/15/05 280 Site Grading 294.0 13.5 111.8 90 III D 4/15/05 281 Site Grading 299.0 13.3 112.9 91 III D 4/15/05 282 Site Grading 280.0 13.9 111.5 91 II D 4/15/05 283 Site Grading 284.0 12.8 110.8 91 II D 4/15/05 284 Site Grading 322.0 9.1 120.7 93 V S 4/15/05 285 Site Grading 321.0 10.3 115.3 90 IV D 4/18/05 286 Site Grading 316.0 6.8 109.4 84 V D 4/18/05 286A** Site Grading 316.0 9.5 117.2 90 V D 4/18105 287 Site Grading 326.0 10.6 113.8 92 III S 4/18/05 288 Site Grading 328.0 10.1 115.3 90 IV D 4/18/05 289 Site Grading 318.0 11.2 113.3 94 VIII D 4/18/05 290 Site Grading 319.0 11.1 111.6 93 VIII D 4/18/05 291 Site Grading 320.0 10.8 113.5 94 VIII S 4/18/05 292 Site Grading 318.0 11.2 112.4 93 VIII D 4/18/05 293 Site Grading 322.0 10.9 110.9 92 VIII D 4/18/05 294 Site Grading 321.0 11.1 115.2 90 IV D 4/18/05 295 Site Grading 322.5 10.9 118.6 91 V S 4/18/05 296 Site Grading 322.5 10.7 118.1 91 V D 4/18/05 297 Site Grading 320.0 10.9 108.6 90 VIII S 4/19/05 298 Site Grading 320.0 10.2 118.2 91 V S 4/19/05 299 Site Grading 321.0 11.1 113.4 94 VIII D 4/19/05 300 Site Grading 322.0 8.7 111.3 86 V D 4/19/05 300A** Site Grading 322.0 10.8 118.5 91 V D 4/19/05 301 Site Grading 323.0 10.4 110.4 92 VIII S 4/19/05 302 Site Grading 324.0 10.8 111.9 93 VIII D 4/19/05 303 Site Grading 319.0 11.2 110.6 92 VIII D 4/19/05 304 Site Grading 324.0 10.7 110.2 91 VIII D 4/19/05 305 Site Grading 322.5 10.3 112.3 93 VIII S 4/19/05 306 Site Grading 322.5 10.5 117.1 90 V D C **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method C NorCal Engineering April 26, 2005 Project Number 9623-01 Page 14 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No. Location Elevations Moisture Ibs./cu.ft. Compaction IYQ 4/19/05 307 Site Grading 324.0 10.8 111.0 92 VIII D 4/19/05 308 Site Grading 324.0 10.5 110.4 92 VIII D 4/19/05 309 Site Grading 324.5 10.9 118.6 91 V S • 4/19/05 310 Site Grading 323.0 10.3 112.4 93 VIII D 4/19/05 311 Site Grading 321.0 10.6 110.3 92 VIII D 4/19/05 312 Site Grading 325.0 10.8 108.8 90 VIII D 4/19/05 313 Site Grading 324.0 10.3 117.6 90 V S 4/20/05 314 Site Grading 324.0 10.6 111.2 92 VIII D 4/20/05 315 Site Grading 323.5 11.1 103.5 86 VIII D 4/20/05 315A** Site Grading 323.5 10.9 110.0 91 VIII D 4/20/05 316 Site Grading 325.0 11.2 111.5 93 VIII D 4/20/05 317 Site Grading 324.5 10.8 110.1 91 VIII S . 4/20/05 318 Site Grading 325.0 11.0 109.0 90 VIII D 4/20/05 319 Site Grading 326.0 11.2 110.8 92 VIII D 4/20/05 320 Site Grading 324.0 10.7 110.2 91 VIII S 4/20/05 321 Site Grading 264.0 6.6 111.6 87 IV D 4/22/05 321A** Site Grading 264.0 10.5 116.7 91 IV D 4/20/05 322 Site Grading 299.0 9.9 111.9 93 VIII D 4/20/05 323 Site Grading 302.0 10.2 113.6 94 VIII S 4/20/05 324 Site Grading 322.0 10.9 110.0 91 VIII D 4/20/05 325 Site Grading 324.0 11.2 111.5 93 VIII D 4/20/05 326 Site Grading 326.0 10.8 116.2 91 IV D 4/21/05 327 Site Grading 302.0 10.5 112.4 93 VIII S 4/21/05 328 Site Grading 270.0 7.2 108.9 85 IV D 4/22/05 328A** Site Grading 270.0 11.3 115.2 90 IV D 4/21/05 329 Site Grading 300.0 10.8 117.5 92 IV D 4/21/05 330 Site Grading 304.0 10.4 116.7 91 IV S 4/21/05 331 Site Grading 313.0 10.2 117.1 91 IV D 4/21/05 332 Site Grading 327.0 10.4 115.4 90 IV D 4/21/05 333 Site Grading 330.0 9.5 118.7 91 V D 4/21/05 334 Site Grading 328.0 10.4 123.8 95 V S 4/21/05 335 Site Grading 323.0 10.8 113.7 94 VIII D **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method NorCal Engineering April 26, 2005 Project Number 9623-01 Page 15 SUMMARY OF COMPACTION TEST RESULTS Date of Test Percent Unit Wt. Relative Soil Test Test No. Location Elevations Moisture Ibs./cu.ft. Compaction IY2 4/21/05 336 Site Grading 324.5 11.4 117.5 92 IV D 4/21/05 337 Site Grading 326.5 10.8 111.9 93 VIII D 4/21/05 338 Site Grading 323.0 10.1 102.3 85 VIII S . 4/21/05 338A** Site Grading 323.0 10.6 109.5 91 VIII S 4/21/05 339 Site Grading 318.0 11.2 110.6 92 VIII D 4/21/05 340 Site Grading 322.0 11.6 112.1 93 VIII D 4/21/05 341 Site Grading 314.0 11.4 110.4 92 VIII. D 4/22/05 342 Site Grading 380.0 11.0 116.6 91 IV S 4/22/05 343 Site Grading 314.0 10.7 115.6 90 IV D 4/22/05 344 Site Grading 302.5 11.2 111.5 93 VIII D 4/22/05 345 Site Grading 326.5 11.1 110.7 92 VIII S 4/22/05 345A** Site Grading 326.5 10.8 116.6 97 VIII S 4/22/05 346 Site Grading 326.0 10.3 123.1 96 IV S 4/22/05 347 Site Grading 326.5 10.7 115.1 96 VIII S 4/22/05 348 Site Grading 326.5 10.5 114.5 95 VIII D 4/22/05 349 Site Grading 304.0 10.8 111.0 92 VIII D 4/22/05 350 Site Grading 324.5 11.3 109.6 91 VIII D . 4/22/05 351 Site Grading 323.0 9.9 118.2 91 V S 4/22/05 352 Site Grading 324.0 9.5 110.5 92 VIII D 4/22/05 352A** Site Grading 324.0 10.4 114.5 95 VIII D 4/22/05 353 Site Grading 325.0 10.2 116.1 96 VIII S 4/22/05 354 Site Grading 325.0 10.7 115.6 96 VIII D 4/22/05 355 Site Grading 325.0 9.5 123.8 95 V S 4/22/05 356 Site Grading 323.0 9.8 121.6 94 V S 4/22/05 357 Site Grading 283.0 10.9 115.4 90 IV D 4/22/05 358 Site Grading 322.0 10.1 117.2 90 V D 4/22/05 359 Site Grading 324.5. 9.8 118.4 91 V D 4/22/05 360 Site Grading 324.5 10.3 125.7 97 V S 4/22/05 361 Site Grading 324.0 10.5 123.5 95 V D 4/22/05 362 Site Grading 324.5 10.8 114.5 95 VIII S 4/22/05 363 Site Grading 324.5 11.5 112.1 93 VIII D 4/22/05 363A** Site Grading 324.5 10.9 114.5 95 VIII D - 4/22/05 364 Site Grading 324.5 10.4 125.7 97 V S **Retest of failing tests after area reworked S= Sand Cone Method D= Drive Tube Method NorCal Engineering