HomeMy WebLinkAboutCT 77-02; HOSP GROVE UNIT 5; ENGINEERING OBSERVATIONS OF GRADING AND TESTING; 1981-05-13. 3467 Kurtz Sireel San Diego, California 92110 714-224-2911 Telex 697-841 WoodwarcAlyde Consultants May 13, 1981 Project No. 592072-FC02 Broadmoor Homes, Inc. 3911 Sorrento Valley Boulevard San Diego, California 92126 Attention: Mr. James Carter FINAL REPORT OF ENGINEERING OBSERVATION OF GRADING AND TESTING OF COMPACTED FILL WOODRIDGE PHASE II CARLSBAD TRACT 77-2, UNIT 5 LOTS 130 THROUGH 143 CARLSBAD, CALIFORNIA Gentlemen: In accordance with your request, and our proposal dated January 22, 1981, we have provided engineering services in conjunction with the grading of the subject site. SCOPE OF WORK Our services included: Providing engineering observation of the qradina operation, ^ Providing engineering and geologic observation of alluvial removal and buttress construction. Performing field density tests in the placed and compacted fill. Performing laboratory tests on representative samples of the material used for fill, and Providing professional opinions regarding the con- tractor's general adherence to plans and specifications, Consulting Engineers. Geologists and Environmental Scientists Ollices in Olher Principal Cities •Broadmoor Homes, May 13, 1981 Project No. 592072-FC02 Page 2 Wo^iward-Clyde Consultants SUMMARY OF GENERAL EARTHWORK AND TESTING Site preparation, compaction, and testing were done between December 22, 1980 and April 30, 1981, In our opinion, based on our observation and testing, the work performed during that period was in general conformance with the Specifications for Controlled Fill attached to our report entitled "Soils and Geologic Investigation for the Proposed Carlsbad Tract No. CT 77-2," dated July 19, 1979. During the grading period, fill was placed, compacted, and tested on Lots 13 0 through 143 along the western edge of Monroe Street, and a private roadway parallelling Monroe Street. A buttress fill was constructed at the rear of Lots 136 through 141 in accordance with the recommendations of the preliminary report. A 3 to 1 inclined fill slope was constructed northward from Lot 130 in accordance with a report dated April 22, 1981. The grading operation gener- ally consisted of removing alluvial and loose fill soils, installing subdrains under the buttress slope and on the bottom of the draw along Monroe Street, scarifying, watering and compacting areas to receive fill, and making cuts and fills to design grade. During the grading operation, compaction procedures were observed, and field density tests were made to help evaluate the relative compaction of the placed fill. Field observations and results of field density tests indicate that the fill has been generally compacted to 90 percent or more of maximum laboratory dry density as determined in accordance with ASTM Test Method No. D1557-70. For re- ference, the approximate locations of field density tests and the limits of compacted fill have been recorded on a copy of the grading plan. The results of field density tests, expressed as a percent of laboratory dry density (relative compaction), are given on the attached forms. [nc. Broadmoor Homes^jki May 13, 1981 ^ Project No. 592072-FC02 Page 3 W^dward-Clyde Consultants Laboratory tests were made on representative samples of the materials used for fill. The tests were performed to evaluate moisture density relationships, maximum dry density, optimum moisture content, grain size distribution, plas- ticity and swell characteristics. The results of laboratory tests are attached. SUMMARY OF FINISH GRADE SOIL CONDITIONS Inspection and laboratory tests indicate that non- expansive fill was placed within 2 feet of rough grade on all lots noted herein. The soils at finish grade in our opinion can be classed as SM soils. They meet the HUD criteria for slab underlay in that they swell less than 2 percent under a surcharge load of 150 psf, have less than 35 percent passing the No. 200 sieve, and the plasticity index is less than 15. RECOMMENDATIONS Foundations for Structures on Nonexpansive Soils We recommend that foundations for single- or two-story, multi-dwelling, residential structures placed on nonex- pansive, properly compacted fill be designed for a bearing pressure not exceeding 2,000 psf (dead plus live loads). We recommend that footings be founded at least 12 inches below finished grade and have a minimum width of 12 inches. In our opinion, this bearing pressure can be increased by no more than one-third for loads that include wind or seismic forces. Slopes Fill Slopes at the site have inclinations varying from approximately 3:1 to 2:1 (horizontal to vertical), and are Broadmoor Homes ^Hnc. May 13, 1981 W Project No. 592072-FC02 Page 4 W^||piward-Clyde Consultants approximately 80 feet high maximum. Fill slopes were treated by overfilling, periodically backrolling with a sheepsfoot compactor, track rolled and then trimmed back to grade. Additional Fill and Utility Trenches This report discusses the fill placement observed by personnel from our firm during the periods specified. We recommend that any additional fill placed, as well as backfill placed in utility trenches located within 5 feet of a building and deeper than 12 inches, or backfill placed in any trench located 5 feet or more from a building and deeper than 5 feet, be compacted under our observation and tested to verify compliance with the earthwork specifications for the project. We should be contacted at least 24 hours prior to backfilling operations. Drainage We recommend that positive measures be taken to prop- erly finish grade each lot after structures and other improve- ments are in place, so that drainage waters from the lot and adjacent properties are directed off the lot and away from foundations, floor slabs, and slope tops. Even when these measures are taken, a shallow ground water or surface water condition can and may develop in areas where no such water condition existed prior to site development; this is partic- ularly true where a substantial increase in surface water infiltration results from landscape irrigation. LIMITATIONS The elevations of compaction tests shown as finished grade (FG) tests on the attached forms correspond to the Broadmoor Homes Jpnc. May 13, 1981 Project No. 592072-FC02 Page 5 W4|llward-Clyde Consultants elevations shown on the "Grading Plan for Carlsbad Tract 77-2, Unit 5," dated March 4, 1980, revised April 10, 1981, prepared by Roy L. Klema Engineers, Inc. Elevations and locations used in this report were based on field surveys done by others. The soil conditions described in this report are based on observations and periodic testing. This office should be notified of any indications that soil conditions are not as described herein. We will inspect foundation excavations for each lot if we are requested to do so. For this report, rough lot grade is defined as that grade set in the field by the grade checker from reference stakes established by the surveyor, and represents rough grade at the time we were inspecting the grading operation. Likewise, the indicated depths of placement of nonexpansive soil were based on the measurements made by and grades set by the contractor's grade checker. The conclusions and opinions drawn from the test results and site inspections apply only to our work with respect to grading, and represent conditions at the date of our final inspection. We will accept no responsibility for any subsequent changes made to this site by others, or by uncontrolled action of water, or by failure of others to properly repair damages by uncontrolled action of water. If you have any questions, please give us a call. Very truly yours. WOODWARD-CLYDE CONSULTANTS Richard P. While R.E. 21992 RPW/DT/rs Attachments (4) JOti NAME JOB NUMBER DATES COVEHEO OMPACJION TEST RESULTS ^ WOODRIDGE PHASE II, UNIT #5 592072-FCO2 (BUTTRESS FILL-PREVIOUS LOT NUMBERS) MARCH 10, 1981 THROUGH MARCH 26, 1981 -mar NUMBCn B-l B-2 B-3 B-4 B-5 B-6 B-7 B-8 B-9 B-10 B-11 B-12 B-13 B-14 B-15 B-16 B-17 B-18 B-19 B-20 B-21 B-22 B-23 B-24 B-25 B-26 B-27 B-28 B-29 B-30 B-31 B-32 B-33 B-34 B-35 B-36 NKTCtT or LOCATION B-12 LOT 139 LOT 136 WEST OF LOT 138 136 II It II 137 WEST OF LOT 135 138 136 WEST OF LOT 135 " " 137 136 136 " " 136 WEST OF LOT 134 •135 " " " 134 " " 134 WEST OF LOT 135 " " 133 ' 133 " " 132 II II II X33 WEST OF LOT 134 136 " " 132 LOT 130 LOT 131 LOT 132 LOT 130 LOT 134 LOT 133 LOT 132 LOT 130 LOT 134 LOT 131 LOT 133 CLCVATION Of TItT 94 i 98' 100' 104' 108' 86' 116' 120' DATE REPORTED 5/14/81 PAGE B-l Or B-2 MOKTUm CONTINT % DKT WT. 11.7 14.3 11.7 13.6 13.0 13.6 11.7 13.0 PICUO OCNtlTr PCF 111.8 112.6 114. 3 115,4 116.0 115. 1 114.4 113.4 LAIOHATOMV KCLATIVI DINIirV COMrACTIOM PCP % or LAS. DIN*. 123.0 123.0 123.0 123.0 123.0 123.0 123.0 123.0 90 91 92 •93 94 93 93 92 124' 11.7 114.4 126.0 90 128' 13.0 117.3 128.5 91 132' 11.7 117.8 128.5 91 136' 13.6 108.2 126.0 85 136' 13.0 118.1 126.0 93 92' 12. 3 115. 1 123.0 93 128' 13.0 111.0 123.0 90 96' 13.6 112.2 123,0 91 102' 11.7 118.3 128.0 92 126' 12.3 118.3 128, 5 92 112' 12.3 120.6 128,5 93 118' 12.3 117.1 128.5 91 122' 11.7 119.8 128,5 93 130' 10. 5 123.1 128.5 95 136' 12.3 122. 3 128. 5 95 140' 11.7 122. 1 128.5 95 142' 11.7 118.3 128. 5 92 70* 11.1 112.6 123.0 91 74 • 10.5 118.5 126.0 94 78' 12. 3 115.0 126.0 91 82 ' 13.6 114.9 123.0 93 78* 13.0 112.0 123.0 91 84' 13.6 114.0 123.0 92 86' 13.0 116. 3 126.0 92 90' 12.3 118.3 126.0 93 94 • 11.7 118.0 121. 5 93 98' 13.6 115.4 126.5 93 102' 12. 3 117.1 126. 5 92 5/11/81 Woodward-Clyde Consultants CONSULTi*>S CNGIHKCNt bCOLOCrSTft »NO KM « <*ONMCNT*L ftClCNTlST* PACTION TEST RESULTS Joa NAME WOODRIDGE PHASE II, UNIT #5 JOB NUMBER 592072-FC02 (BUTTRESS FILL) DATE*COVERED MARCH 10, 1981 THROUGH MARCH 26, 1981 DATE REPORTED 5/14/81 PAGE B-2 B-2 DAT! T««T NUMBER nlTCIT or LOCATION CLCVATION or TC«T HOIITUm CONTINT % OUT WT. riCLO DINalTY rcr LASOHATOnT OINIITT rcr • ILATIVI COMrACTION % or LA*. DKNI. lAR 24 B-37 LOT 130 106' 13.0 116.7 126.5 92 B-38 LOT 132 108' 12. 3 117.3 126.5 92 B-39 LOT 131 112' 11.7 118.3 126.5 93 lAR 25 , B-40 SOUTH LOT 132 116' 13.0 120.4 126.5 94 B-41 II " 130 120' 13,6 122.0 126.5 96 B-42 11 " 131 124" 12.3 114,4 126.5 90 B-43 11 " 130 128' 12,3 117.8 126.5 93 lAR 26 B-44 SOUTH LOT 132 132' 13.6 119.7 126.0 95 B-45 II " 131 136' 11.7 116.8 126.0 92 B-46 II " 130 140' 12,3 117.1 126.0 92 It 5/11/81 Woodward-Clyde Consultants LONSULtINC CNCINCLftS CCOLOCI»TS Joa NAME WOODRIDGE PHASE W! UNIT 5 JOB NUMBER 592072-FC02 :.OMPACTION TEST RESULT ^ tINTT ^ DATE* COVERED DECEMBER 23, 1980 THROUGH APRIL 30, 1981 DEC 23 DEC 24 DEC 29 DEC 30 DEC 31 JAN 5 JAN 6 JAN 8 JAN 9 JAN 27 FEB 2 JAN 3 T«»T NUMIcn 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 •CTIIT or LOT 130* PRIVATE ST., OPP. L-133* PRIVATE ST., OPP, L-131 L-134 L-137 PRIVATE ST,, OPP. L-132* L-132 L-136 PRIVATE ST., OPP. L-131* LOT 134* PRIVATE ST., OPP. L-133 LOT 130* PRIVATE ST., OPP. L-131 •L-133 PRIVATE ST., LOT 130* LOT 130 LOT 136 16 LOT 130 LOT 130* LOT 132* LOT 134* LOT 137 LOT 134 LOT 135 LOT 138 LOT 141 LOT 139 LOT 137 LOT 139 LOT 140 LOT 142 LOT 133* LOT 130 LOT 133 CLCVATION or TC»T 52* 60' 72' 76" 80' 64' 76' 82' 58' 66' 80' DATE REPORTED 5/14/81 PAGE OF MOIITUni CONTINT % OUT WT. 10.5 11.7 13.0 10.5 10. 5 11.7 12. 3 13.0 10.5 11.1 riiLO DINIITT rcr 119.5 114.4 115.2 119.9 116.3 115.9 113.8 119.9 113.4 119.3 112.6 LAaOIIATORT KCLATIVI oiNiinr COMrACTION % or LA*, DIM: 126,0 126.0 126.0 126.0 126.0 126.0 126.0 126.0 123.0 123,0 123.0 94 90 91 95 92 91 90 95 92 96 91 56' 13.0 124,9 126.0 99 64' 13,6 125,3 126.0 99 66' 13.0 124.2 126.0 98 62' 10,5 123,1 126.0 97 72' 6.0 109.2 123.0 88 76' 10,5 110.2 123.0 90 72' 11.7 110.8 123.0 90 66' 11.7 115.8 123,0 94 68' 11.7 114.8 123,0 93 70' 12.3 117.8 123,0 95 82' 11.7 114.6 123.0 93 80' 11.1 112,4 123.0 91 82' 13.6 120.8 126.0 95 86' 13.0 112.8 123. 5 91 88' 12.3 111.3 123.5 90 90' 11.7 111.9 123. 5 90 90' 13.0 113.3 123.5 91 92 • 13.6 112.2 119.5 93 94 ' 13.0 111.1 119.5 93 102' 13,0 113.4 119.5 94 72' 13.6 122.0 126.0 96 74 • 13.0 120.4 126.0 95 76 ' 12.3 115.6 126.0 91 PREVIOUS LOT NUMBERS wt 5/8/81 Woodward-Clyde Consultants CON&UITINC CNCINtEMl CCOLOCIftTi **<D KNVinONMCNTAL tCICNTItTl ATA Joa NAME JOB NUMBER WOODRIDGE PHASE II, UNIT 5 MPACTION TEST RESULTS. DATE REPORTED 5/14/81 592072-FCO2 DATE* COVERED DECEMBER 23, 1980 THROUGH APRIL 30, 1981 PACE 2 OF DAT! T«»T NUMSCK nCTKT or LOCATION CLEVATtON or TEST HOIITUni CONTINT % 0«T WT. riiLO DCNaiTT rcr LAIOKATORY OINIITT rcr KCLATIVI COMrACTION % or LAC. DIM*. FEB 25 35 LOT 140 96' 12.3 115.1 123.0 93 36 LOT 138 92' 11.7 118. 3 128.0 92 37 LOT 141 100' 14.3 112.6 123.0 91 38 LOT 139 94 ' 13.0 114.2 123.0 . 92 39 LOT 131 80' 12, 3 115.1 123.0 ' 93 MAR 10 40 LOT 132 82' 11.7 114.3 123.0 92 41 LOT 134 86' 12.3 115.1 123.0 93 42 LOT 136 90' 13.0 116.6 123.0 94 APR 17 43 LOT 130 84 • 13,0 112.8 123.0 91 44 LOT 132 86' 11,7 118.0 123.0 95 APR 20 45 LOT 135 88' 13.0 112.3 123.0 91 46 LOT 140 100' 12.3 116.1 123.0 94 APR 21 47 LOT 141 FG 101.3' 13.0 116,8 123.0 94 48 LOT 140 FG 101.3' 13.6 114.4 123.0 93 49 LOT 139 FG 96.3' 13.6 114.0 123.0 92 50 LOT 138 FG 96.3' 12. 3 115,9 123.0 94 APR 22 51 LOT 137, LOWER FG 92.0' 13.0 112.8 123.0 91 52 LOT 137, UPPER FG 101.0* 13.6 113,0 123.0 91 53 LOT 136, LOWER FG 92.0' 13.0 113.9 123.0 92 54 LOT 136, UPPER FG 101.0' 11.7 111.7 123.0 90 APR 27 55 LOT 135, LOWER FG 90.0' 12,3 119.0 128.5 92 56 LOT 135, UPPER FG 99.0* 13.6 120,5 128.5 93 57 LOT 134, UPPER FG 99.0' 13.6 124,2 128.5 96 58 LOT 134, LOWER FG 90.0' 13,0 119.2 128.5 92 APR 28 59 LOT 133, LOWER FG 88.0' 13.0 117.2 128.5 91 60 LOT 133, UPPER FG 97.0' 13.6 119. 3 128.5 92 61 LOT 132, UPPER FG 97.0' 14.3 117.1 128.5 91 62 LOT 132, LOWER FG 88.0' 13.0 112.9 128.5 87 APR 29 63 LOT 131, LOWER FG 85.0' 11.7 116.5 128.5 90 64 LOT 130, LOWER FG 85.0' 12. 3 118.5 128.5 92 65 62 LOT 132, LOVVER FG 88.0 • 13.0 117.1 128.5 91 APR 30 66 LOT 131, UPPER FG 94.0' 12. 3 118.9 128.5 92 67 LOT 130, UPPER FG 94.0-13.6 115.9 128.5 90 68 LOT 142 FG 105.0' 13,0 114.0 123.0 92 PREVIOUS LOT NUMBERS wt 5/8/81 Woodward-Clyde Consultants CONSULTING tNGIHCCNt btOLOCISTS *MO CN Vt MONMLNT AL «CICNTI&T« iCMPACTION TEST RESULTi JOJ NAME WOODRIDGE PHASE II, UNIT 5 JOB NUMBER 592072-FCO2 (STREET) DATE* COVERED DECEMBER 22, 1980 THROUGH APRIL 26, 1981 DATE REPORTED 5/14/81 PAGE S-1 S-1 TCIT NUM*CII RITCIT or CLCVATION or TCST MOISTURC CONTINT % DRY WT. ricLO DINIITT rcr LABORATORY DIN*ITT rcr RILATIVI COMrACTION % or LA*. OCN*. DEC 22 S-1 MONROE ST.,OPP. L-130* 50' 10.5 116.6 126.0 92 S-2 tl It 11 L-131* 56' 11.7 118.9 126.0 94 DEC 24 S-3 MONROE ST.,OPP, L-130 70' 10.5 118.5 126.0 . 94 DEC 29 S-4 MONROE ST,, OPP . L-137 78* 12,3 115.8 126.0 91 DEC 31 S-5 MONROE ST,,OPP. L-133* 64* 10,5 114.1 126.0 90 JAN 5 S-6 MONROE ST.,OPP. L-133 76' 11,1 115.6 126.0 91 JAN 6 S-7 MONROE ST.,OPP. L-138 84' 12, 3 115,1 126,0 91 APp 26 S-8 PRIVATE ST,,OPP . L-140 95' 11,1 116. 3 128,5 90 APp S-9 M II 11 L-137 88" 13.6 118,1 128.5 91 S-IO 11 II II L-132 82' 13.0 118.4 128.5 92 * PREVIOUS LOT NUMBER Wt 5/11/81 Woodward-Clyde Consultants CONSTINC CNCINEKnS CCOLOClKTft • NO IN . IHONMENT AL »C(INTI4T» PLASTICITY CHARACTERISTICS 1 2 3 Liquid Limit, % 32 22 24 Plasticity Index, % 16 3 12 Classification by Unified Soil Classification System SC SM SC 150 ZERO AIR VOIDS CURVES -2.80 SG 2.70 SG 2.60 SG 2.50 SG 130 120 110 100 COBBLES GRAVEL SANO SILT i CLAY COBBLES = 1 ' c| m f SILT i CLAY 100 'i 80 < 60 lii 40 o cc 20 3 1 2 \^ \ - -1 -J. 1. 1 _L,1, 1 1 1000 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS DIRECT SHEAR TEST DATA 1 2 3 Dry Density, pcf _ Initial Water Content, % --- Final Water Content, % --— Apparent Cohesion, psf -_ Apparent Friction Angle, degrees --- SWELL TEST DATA 1 2 3 Initial Dry Density, pcf --118 Initial Water Content, % -_ 11 Final Dry Density, pel -— 116 Final Water Content, % --15 Load, psf --160 Swell, percent --1.5 SAMPLE LOCATION 1 LOT 130, CANYON ROTTnw 2 CUT LOTS 123-128 3 CUT LOTS 90-98 10 20 30 LABORATORY COMPACTION TEST LABORATORY COMPACTION TEST METHOD: ^STM 61S57 70 A FILL SUITABILITY TESTS WOODRIDGE PHASE II, UNIT 2 DRAWN BY: J CHECKED BY:jVX2f^ PROJECT NO: 592072-FC02 | DATE: 4/13/81 1 FIGURE NO: 1 WT 3/30/81 WOODWARD-CLYDE CONSULTANTS PLASTICITY CHARACTERISTICS 4 5 6 Liquid Limit, % -44 34 Plasticity Index, % NP 27 18 Classification by Unified Soil Classification System SM SC SC 150 140 130 120 110 100 ZERO AIR VOIDS CURVES •2.80 SG 2.70 SG 2.60 SG 2.50 SG COBBLES GRAVEL SAND SILT ( CLAY c f cl m 1 f SILT ( CLAY 100 1000 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS DIRECT SHEAR TEST DATA 4 5 6 Dry Density, pcf -- Initial Water Content, % --- Final Water Content, % --- Apparent Cohesion, psf --- Apparent Friction Angle, degrees --- SWELL TEST DATA 4 5 6 Initial Dry Density, pcf 109 111 114 Initial Water Content. % 11 11 10 Final Dry Density, pcf 109 108 112 Final Water Content, % 15 18 16 Load, psf 160 160 160 Swell, percent .01 3.1 1.5 SAMPLE LOCATION 4 CUT LOTS 36-39 5 LOTS 42 S 43 6 BUTTRESS CUT W. OF 10 20 30 LABORATORY COMPACTION TEST LOTS 130-139 LABORATORY COMPACTION^ ASTM D 1557 70 A TEST METHOD: FILL SUITABILITY TESTS WOODRIDGE PHASE II, UNIT 2 DRAWNBY: ch | CHECK ED BY: ,\WlL} PROJECT NO: 592072-FCO2 DATE: 4/13/81 FIGURE NO: 2 WT 3/30/81 WOODWARD-CLYDE CONSULTANTS PLASTICITY CHARACTERISTICS 7 Liquid Limit, % - Plasticity Index, % NP Classification by Unified Soil Classification System SM 150 ZERO AIR VOIDS CURVES -2.80 SG 2.70 SG 2.60 SG 2.50 SG COBBLES GRAVEL SAND c f c| m i f SILT k CLAY 1000 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS DIRECT SHEAR TEST DATA 7 Dry Density, pcf - Initial Water Content, % - Final Water Content, % - Apparent Cohesion, psf - Apparent Friction Angle, degrees - SWELL TEST DATA 7 Initial Dry Density, pcf 115 Initial Water Content. % 9 Final Dry Density, pcf 115 Final Water Content, % 14 Load, psf 160 Swell, percent 0.4 SAMPLE LOCATION 7 BUTTRESS LOTS 130-139 10 20 30 LABORATORY COMPACTION TEST LABORATORY COMPACTION TEST METHOD: ASTM D 1557 70 A FILL SUITABILITY TESTS WOODRIDGE PHASE II, UNIT 2 DRAWN BY: 1 CHECKED BY: Vie£| PROJECT NO: 592072-FC02 DATE: 4/13/81 1 FIGURE NO: 3 WT 3/30/81 WOODWARD-CLYDE CONSULTANTS PLASTICITY CHARACTERISTICS 1 2 3 Liquid Limit, % 27 33 28 Plasticity Index, % 6 15 10 Classification by Unified Soil Classification System 3M-SC SC SC 150 140 ZERO AIR VOIDS CURVES -2.80 SG 2.70 SG 2.60 SG 2.50 SG 130 120 110 100 COBBLES GRAVEL SAND c 1 f c| m f SILT ( CLAY 1000 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS DIRECT SHEAR TEST DATA 1 2 3 Dry Density, pcf --— Initial Water Content, % --— Final Water Content, % --— Apparent Cohesiori, psf --- Apparent Friction Angle, degrees --- SWELL TEST DATA 1 2 3 Initial Dry Density, pcf -107 114 Initial Water Content, % -12 10 Final Dry Density, pcf -100 113 Final Water Content, % -23 14 Load, psf -160 160 Swell, percent 6.9 0.3 SAMPLE LOCATION X CUT SLOPE,S.W. COR. SITE 2 S.W. CORNER 3 BUTTRESS CUT, S.W. COR. 10 20 30 LABORATORY COMPACTION TEST 40 LABORATORY COMPACTION TEST METHOD: ASTM D 1557 70 A FILL SUITABILITY TESTS PUEBLO DEL ORO DRAWN BY: ch 1 CHECKED BYi^^gf^ PROJECT NO: 59331W-FC01 DATE: 5/14/fli 1 FIGURE NO: Wt 5/13/81 WOODWARD-CLYDE CONSULTANTS PLASTICITY CHARACTERISTICS 4 5 6 Liquid Limit, % 34 35 46 Plasticity Index, % 17 18 27 Clasiification by Unified Soil Classification System SC CL CL 150 140 130 120 110 100 ZERO AIR VOIDS CURVES -2.80 SG 2.70 SG 2.60 SG 2.50 SG COBBLES GRAVEL SANO SILT t CLAY COBBLES c f c m i f SILT t CLAY 100 ING 80 ISS PA 60 1- z UJ 40 o oc UJ 20 0. 20 0 c --A X o — A —5 \ -L- 1. J.. , JUL-1 1 1 1 1000 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS DIRECT SHEAR TEST DATA 4 5 6 Dry Density, pcf -— _ Initial Water Content, % -- Final Water Content, % --- Apparent Cohesion, psf --- Apparent Friction Angle, degrees --- SWELL TEST DATA 4 5 6 Initial Dry Density, pcf 114 111 102 Initial Water Content, % 10 13 16 Final Dry Density, pcf 111 106 94 Final Water Content, % 17 21 29 Load, psf 160 160 160 Swell, percent 2.7 4.8 9.2 SAMPLE LOCATION 4 HOSP. WAY BUTTRESS 5 NORTH SIDE. LOT 10 6 LOT 11 10 20 30 LABORATORY COMPACTION TEST LABORATORY COMPACTION TEST METHOD: A.qTM n 1557 70 A FILL SUITABILITY TESTS PUEBLO DEL ORO DRAWN BY: ch 1 CHECKED BY:^t^c| PROJECT NO: 59331W-FC01 OATE: 5/14/81 1 FIGURE NO: 2 Wt 5/14/81 WOODWARD-CLYDE CONSULTANTS