HomeMy WebLinkAboutCT 83-15; CAMINO POINTE; REGRADING AND TESTING OF COMPACTED FILL; 1984-10-30o
3467 Kurtz Street
San Diego, California 92110
(619)224-2911
Woodward- Consultants
October 30, 1984
Project No. 59331A-FC01
G & G Enterprises Incorporated
2204 Garnet Avenue
San Diego, California 92109
Attention: Mr. Mark H. Cohen
FINAL REPORT OF ENGINEERING OBSERVATION OF
REGRADING AND TESTING OF COMPACTED FILL
PADS 7 THROUGH 10 AND SLOPE REPAIR
CAMINOPOINTE (CARLSBAD TRACT 79-27),
CARLSBAD, CALIFORNIA
Gent-men:
-
In accordance with your request, we have provided engineering services in
conjunction with th regrading of the subject site.
SCOPE OF WORK' \
Our services included:
Providing periodic engineering observation of the grading operation
Performing field density tests in the placed and compacted fill
O Performing laboratory tests on representative samples of the
material used for fill
Providing professional opinions regarding the contractor's general
adherence to plans and specifications
SUMMARY OF GENERAL EARTHWORK AND TESTING
Current site preparation, compaction, and testing were done between
September 19 and October 24, 1984. In our opinion, based on our
observation and testing, the work performed during that period was in
general conformance with the Guide Specifications for Controlled Fill attached
to our report entitled "Update Site. Reconnaissance and Update Soil Report,
Camino Pointe (Carlsbad Tract 79-27), Carlsbad, California," dated June 8,
1984 and with a letter prepared by Forsum/Summers & Partners, Inc. entitled
"Procedures for Repairing and Replanting Slopes Steeper than 2:1," dated
August 14, 1984. . .
Consulting Engineers. Geologists
and Environmental Scientists
Offices in Other Principal Cities
- G & G Enterprises I•rpora ted Wclwàrd.Clyde Consultants
Project No. 59331A-FC01
October 30, 1984
Page 2
Previous grading of the subject site was completed in September 1981 and is
summarized in our report dated June 8, 1984. During the current grading
period, fill was placed, compacted and tested on Pads 8 and 10. The depth
of fill ranged from 2 to 6 feet. Pads 7 and 9 are cut pads; Pad 7 has
natural ground at grade while Pad 9 is still underlain by compacted fill as a
result of previous grading.
Compacted fill was also placed in various slope areas on the project. Prior to
placing fill, the areas to receive fill were scarified, watered and compacted
On the slopes, the areas of sloughing were excavated to firm compacted
material or natural ground and then replaced with properly moisturized
compacted fill.
During the regrading operation, compaction procedures were observed, and
field density tests were made to help evaluate the relative compaction of the
placed fill. Field observation and the results of field density tests indicate
that the fill has been generally compacted to 90 percent or more of maximum
dry laboratory density as determined in accordance with ASTM Test Method
No. D1557-78. For reference, the approximate location of field density tests
and the limits of compacted fill have.been.. 9corded on a copy of the grading
plan. The results of 'field density tests, expressed as a percent of maximum
laboratory dry density (relative compaction), are given on the attached
forms.
Laboratory tests were 'made on representative samples of the materials used
for fill. The tests were performed to evaluate moisture-density relationships,
maximum dry density, optimum moisture content, grain size distribution, and
plasticity. The results •of laboratory tests are attached.
,
SUMMARY OF FINISH GRADE SOIL.' CONDITIONS
Observation and laboratory tests indicate that, nonexpansive fill was placed
within 2 feet of rough grade on Pads 8 and 10. An examination of Pads 7
and 9 did not reveal the presence of -expansive soil at rough pad grade.
RECOMMENDATIONS
Foundations for Structures on Nonexpansive Soil
We recommend that foundations for single-story structures placed on
nonexpansive, undisturbed soil or on nonexpansive, properly compacted fill
be designed for a bearing pressure not exceeding 2000 psf (dead plus live
load). We recommend that footings be founded at 'least 12 inches below
finished grade, and have a minimum width of 12 inches. In our opinion, this
bearing pressure can be increased by no more than one-third for loads that
include wind or seismic forces. We recommend that footings for two-story
structures in similar soils be 18 inches in depth. '
G & G Enterprises Incorporated
Project No. 59331A-FC01
October 30, 1984
Page 3
Wdward.Clyde Consultants
Slopes
Fill slopes at the site have inclinations of approximately 1:1 (horizontal to
vertical), and are approximately 8 to 10 feet high. Fill slopes were treated
by compacting areas of repair with mechanical tampers. Fill slopes steeper
than 2 to 1 are susceptible to shallow slope sloughing in periods of rainfall or
if subjected to over irrigation; periodic rebuilding of the slopes may be
required.
We recommend that structures that will not tolerate differential settlements
(such as foundations, swimming pools, concrete decks, walls, etc.) not be
located within 8 feet of the top of a slope. We recommend that footings that
are located within 8 feet of the top of a slope be extended in depth until the
outer bottom edge of the footing is 8 feet horizontally from the outside face of
the slope.
Additional Fill and Utility Trenches
This report discusses the fill placement observed by 'personnel from. our firm
during the periods' specified. .We recommend, that any additional . fill placed,
as well as backfill placed in utility trenches located within 5 feet of a building
and 'deeper than 12 inches, or backfill placed in any trench located 5 feet or
more from, a building and deeper than 5 feet, be compacted under our
observation and tested to verify compliance with the earthwork specifications
for the project. We should be contacted at least 24 hours prior to backfilhing
operations.
Drainage
We recommend that positive measures be taken to properly finish grade each
pad after structures and other improvements are in place, so that drainage
waters from the pad and adjacent properties are directed off the pad and'
away from foundations, floor slabs, and slope tops. Even when these
measures are taken, a shallow ground-water or surface-water condition can
and may develop in areas' where no such water condition existed prior to site
development; this is particularly true where a substantial increase in
surface-water infiltration results from landscape irrigation.
LIMITATIONS
The elevations of compaction tests shown as finished grade (FG) tests on the
attached forms correspond to the elevations shown on the grading plans for
Camino Pointe dated July 3, 1984, prepared by Pinney Engineering
Associates, Inc. Elevations and locations used in this report were based on
field surveys done by others. '
The soil conditions described in this report are based on observations and
periodic testing. This office should be notified of any indications that soil
G & G Enterprises Incorporated Adward-Clycle Consultants
Project No. 59331A-FC01
October 30, 1984
Page 4
conditions are not as described herein. We will examine foundation
excavations for each lot if we are requested to do so.
For this report, rough 'lot grade is defined as that grade set in the field by
the grade checker from reference stakes established by the surveyor, and
represents rough grade at the time we were observing the grading operation.
The . conclusions and opinions drawn from the test results and site
observations apply only to our work with respect to regrading, and represent
conditions at the date of our final site visit.. We will accept no responsibility
for any subsequent changes made to this site by others, or by uncontrolled
action of water, or. by failure of others to properly repair damages by
uncontrolled action of water.
Professional judgment represented in this report are based partly on our
evaluations of the technical information gathered, partly on our understanding
of the proposed construction, and partly on our general experience in the
geotechnical field. Our engineering work and judgments rendered 'meet or
exceed the standard of care of our profession at this time. We do not
guarantee the performance of the project in any respect.
If you have any questions, please give us a call.
Very truly yours,
WOODWARD-CLYDE CONSULTANTS
Richard P. While
R.E. 21992 .
RPW / D T / ks
Attachments
(4) G & G Enterprises Inc.
(1) City of Carlsbad Engineer
OMPACTION TEST RESULT•
Joa NAME CAMINO POINTE DATE REPORTED 10/30/84
JOB NUMBER 59331A-FC01 (BUILDING PADS)
DATES COVERED SEPTEMBER 28, 1984 THROUGH OCTOBER 24, 1984 PAGE 1 OF 1
DATE TEST
NUMBER RETEST OP LOCATION ELEVATION
MOISTURE
CONTENT FIELD
DENSITY LABORATORY
DENSITY
RELATIVE
COMPACTION OF TEST % DRY WY. PC? PC? % or LAB. DENS.
SEPT 28 1 PAD #1 FG 137.5' 9.3 119.2 1260 94
1984 2 PAD #2 FG 136.0' 10.5 122.8 126.0 97
OCT 5 3 PAD #8 146' 8.7 120.2 126.0 95
4 I' 148' 9.9 121.7 126.0 96
OCT 8 5 PAD #6 134' 10.5 118.0 126.0 93
6 " " 136' 11.7 123.l 126.0 97
7 11 139' 10.5 125.2 126.0 99
OCT 10 8 MINOR RECREATION
PAD 150' 12.3 127.1 128.0 99
9 PAD #10, N.E. CORNER 157' 11.1 127.3 128.0 99
OCT -11 10 PAD #10, N.E. COR. FG 159.5' 10.5 123.7 126.0 98
OCT 12 11 MINOR REC. AREA FG 152.0' 11.1 119.7 126.0 95
OCT 24 12 PAD #10 FG 159.0' 8.7 120.1 126.0 95 -
13 PAD #8 FG 152.0' 7.5 122.3 126.0 97
OMPACTION TEST RESULTO
Joi NAME CAMINO POINTE DATE REPORTED 10/30/84
JOB NUMBER 59331A-FC01 (SLOPE REPAIR)
DATES COVERED SEPTEMBER 19, 1984 THROUGH OCTOBER 4, 1984 PAGE or
DATE TEST RETEST
NUMBER OF
SEPT 19 1
1984 2
3
4
SEPT 22 5
6
SEPT 24 7
SEPT 26 8
SEPT 27 9
10
SEPT 28 11
12
OCT3 13
OCT4 14
MOISTURE YIELD LABORATORY RELATIVE ELEVATION CONTENT DENSITY DENSITY COMPACTION OF TEST % DRY WT. PCF PCP % or LAB. DENS.
+3' 9.8 122.2 131.0 93
+5' 8.7 119.9 128.0 93
+8' 9.3 116.3 128.0 90
+11' 11.1 126.3 128.0 96
+3' 9.0 125.7 131.0 95
+61 8.7 124.2 131.0 94
+8' 10.5 124.7 131.0 95
+3' 13.5 125.4 128.0 98
+6' 9.3 118.2 128.0 92
+8' 10.5 122.4 128.0 95
±3' 10.5 129.8 131.0 99
+6' 9.9 127.8 131.0 97
+3' 11.1 127.5 128.0 99
+6' 9.9 121.4 126.0 . 96
LOCATION
AREA #6
II II
I, II
'I
AREA #4
II II
AREA #4
AREA #5
AREA #5
AREA #3
I, II
AREA #1
AREA #1
Woodward-Clyde Consultants
- CONSULTING ENGINEERS. GEOLOGISTS
AND ENVIRONMENTAL SCIENTISTS
1001-
PLASTICITY CHARACTERISTICS 1 2 3
Liquid Limit, % 21 27 31
Plasticity Index, % 6 13 20 Classification by Unified Soil
SC SC SC Classification System
[oIiI.J.]R*lflUflUI
___ •ULI __I
150
140
ZERO AIR VOIDS CURVES
—2.80 SG
- 2.70 SG
- 2.60 SG
2.50 SG
60
I— z w 40 0 cc a- 20
0 1 1 Iii 11 If liii III I I
1000 100 10 1.0 0.1 J 0.01 0.001
GRAIN SIZE. mm
MECHANICAL ANALYSIS
130
120
DIRECT SHEAR TEST DATA 1 2 3
DryDensity,pcf - - -
initial Water Content, % - - -
FinalWaterContent,% - - -
ApparentCohesion,psf - - -
ApparentFrictionAngle,degrees - - -
SWELL TEST DATA
. 1 2 3
InitialDryDensity,pcf - - -
InitialWaterContent,% - - -
FinalDryDensity,pcf - - -
FinalWaterContent,% - - -
Load,psf - - -
Swell,percent - - -
9O
Maximum Dry Oi 0 2 0 3
Density, pcf 131.0 128.0 126.0
Optimum Moisture
Content,% 1 9.01 9.5 8.5
80 I I MOISTURE CONTENT,%
o 10 20 30
LABORATORY COMPACTION TEST
SAMPLE LOCATION
1 STOCKPILE
3 FILL AREA
MECHANICAL/MOIST.
40 LABORATORY COMPACTION
TEST METHOD: ASTMD 155778A
- . FILL SUITABILITY TESTS
CAMINO POINTE
DRAWN BY: ch CHECKED BY: 444/I PROJECT NO: 59331A—FC01 DATE: 10/30/84 J FIGURE NO: 1
W000WARDCLYDE CONSULTANTS