HomeMy WebLinkAboutCT 83-19; CALAVERA HEIGHTS, VILLAGE Q; REPORT OF ROUGH GRADING; 1998-09-02REPORT OF ROUGH GRADING
CALAVERA HILLS, VILLAGE Q,
LOTS 104 THROUGH 124 (INCLUDING MODEL LOTS)
BLUFF COURT, TALUS WAY AND TAMARACK AVENUE,
STATION 119+80 TO 131+00
CITY OF CARLSBAD, CAUFORNIA
FOR
CYPRESS VALLEY LLC
2727 HOOVER AVENUE
NATIONAL CITY, CALIFORNIA 91950
W.O. 2393-B-SC SEPTEMBER 2,1998
Geotechnical • Geologic • Environmental
5741 Palmer Way • Carlsbad, California 92008 • (760)438-3155 • FAX (760) 931-0915
September 2,1998
W.O. 2393-B-SC
Cypress Valley LLC
2727 Hoover Avenue
National City, California 91950
Attention: Mr. Tliom Fuller
Subject: Report of Rough Grading, Calavera Hills, Village Q, Lots 104 througii 124
(including Model Lots), Bluff Court, Talus Way and Tamarack Avenue, Station
119+80 to 131 +00, City of Carlsbad, California
Dear Sir:
Tliis report presents a summary of the geotechnical testing and observation services
provided by GeoSoils, Inc. (GSI) during the rough earthwork phase of development at the
subject site. Earthwork commenced on February 2,1998 and was generally completed
on April 28,1998. Utility and pavement construction is in progress as ofthe date ofthis
report and is therefore not included under the purview of tliis report.
PURPOSE OF EARTHWORK
The purpose of grading was to prepare relatively level pads for the construction of 21
residential structures and access roadways. Cut and fill grading, and drill and shoot
blasting techniques were utilized to attain the desired graded configurations. Cut lots and
the cut portion of transition lots were overexcavated in order to provide for more uniform
foundation support. Existing topsoils and colluvium were removed to suitable bedrock
material and recompacted. The grading plans for this portion of Calavera Hills, Village Q,
prepared by Hunsaker & Associates Inc., San Diego, dated October 30,1997, are included
with this report as Plates 1 and 2.
EARTH MATERIALS
Subsurface geologic conditions exposed during the process of rough grading were
observed by a representative of GSI. Earth materials onsite generally consist of dense
granitic rock with a thin, discontinuous surficial veneer of topsoil/colluvium. Dense surficial
outcrops of granitic/volcanic bedrock were noted throughout the area.
GROUNDWATER
Naturally occurring groundwater was not encountered during rough grading ofthe building
pads and should not affect the proposed building construction provided that the
recommendations contained in this report and/or provided by GSI are incorporated into
final design and construction and that prudent surface and sulDsurface drainage practices
are incorporated into the construction plans.
Based on the fractured and dense nature of the granitic/volcanic bedrock, perched
groundwater conditions may develop in the future due to excess irrigation, homeowner
altered drainage or damaged utilities. Should manifestations of perched conditions (i.e.,
seepage) develop in the future, this office could assess the conditions and provide
mitigative recommendations as necessary.
EARTHWORK CONSTRUCTION
Earthwork operations have been completed in general accordance with the City of
Carlsbad grading ordinance and the guidelines provided in the field by this office.
Observations during grading included removals, overexcavation and subdrain construction
along with general grading procedures and placement of compacted fills by the contractor.
Rough Grading
Preparation of Existing Ground:
1. Deleterious material such as concentrated organic matter and miscellaneous debris
were stripped from the surface and disposed of beyond the limits of grading for the
subject area, prior to placing any fill.
2. Loose surficial materials (i.e., existing topsoils and colluvium) were removed to
expose competent bedrock in all areas to receive fill.
3. In order to provide for more uniform support of structures, the cut portion of
transition lots were overexcavated to a minimum depth of 3 feet below pad grade,
then brought to grade with compacted fill. Cut lots exposing dense granitic/volcanic
rock were overexcavated a minimum of 3 feet below pad grade in order to facilitate
foundation and utility construction. Where possible, an attempt was made to slope
the overexcavated bottom toward the street area. Subdrainage of these areas does
not appear necessary at this time.
4. In areas where conventional cut and fill grading techniques were not feasible due
to rock hardness, drill and shoot blasting techniques were utilized. These
techniques were used where dense, non-rippable rock occurred within a minimum
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
Flle:e:\wp7\2300\2393b.ror Page 2
GeoSoils, Inc.
of three feet of finish pad grade and above local street elevations equivalent to
approximately 1 foot below the lowest utility invert elevation. Shot rock generated
from the blasting operations was exported to rock fill areas outside the subject area.
Blasting operations occurred in the general vicinity of Lots 104-108,110-113 and
120-122; within Tamarack Avenue stations 121 +00 to 129+00; and Bluff Court
stations 10+00 to 12+00 and 14+00 to 14+50.
5. Subsequent to completing removals, areas to receive compacted fill were scarified
to a minimum depth of 12 inches, moisture conditioned to at least optimum
moisture content, and then compacted to attain a minimum relative compaction of
90 percent. These areas were then brought to grade with fill compacted to a
minimum 90 percent relative compaction.
6. All processing of original ground in areas to receive fill, shown on Plates 1 and 2,
was observed by a representative of GSI.
Fill Placement:
Fill consisted of onsite and import materials which were placed in thin lifts, approximately
four to eight inches in thickness, brought to at least optimum moisture content and
compacted to attain a minimum 90 percent relative compaction. Compaction test results
on fills are presented in the attached Table 1. Approximate As-built fill thicknesses are
presented in the attached Table 2. Canyon subdrains were not necessary, based on the
natural topography and overall fill depths. However, slope subdrainage was constructed
and is discussed in the following section.
Slopes
Planned Slopes:
In general, graded slopes constructed under the purview of this report should perform
satisfactorily with respect to gross and surficial stability, provided that these slopes are
properly maintained. Fill slopes constructed under the pun/iew of this report were provided
witii a keyway excavated into suitable bedrock material in accordance with
recommendations presented in SCST (1988) and as provided in the field by this office. Cut
slopes were constructed using cut and fill grading techniques and/or blasting, and expose
dense igneous and/or metavolcanic rock. A detailed analysis of slope stability has been
completed under separate cover (GSI, 1998a).
Temporary Slopes:
Temporary construction slopes may generally be constructed at a gradient of 1:1
(horizontal to vertical) or flatter in compacted fill, and V^•.^ (horizontal to vertical) in suitable
bedrock material (provided adverse geologic structures are not present). Utility trenches
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 3
GeoSoils, Inc.
may be constructed in accordance with guidelines presented in Title 8 of the California
Code of Regulations for Excavation, Trenches and Earthwork with respect to Type B soil
(compacted fill) and stable rock (bedrock). Construction materials and/or stockpiled soil
should not be stored within 5 feet from the top of any temporary slope.
Temporary/permanent provisions should be made to direct any potential runoff away from
the top of temporary slopes.
Natural Slopes:
Natural slopes should perform satisfactorily with respect of gross and surficial stability. A
detailed analysis of slope stability has been completed under separate cover (GSI, 1998).
Slope Subdrainage:
Subdrains, consisting of perforated plastic pipe (Schedule 40) embedded in gravel then
wrapped in filter fabric, were placed in perimeter fill slope keys beneath lots 109 through
111 and lots 112 through 114. Approximate drain locations and drain outlets are shown
on Plates 1 and 2.
As discussed in the groundwater section of this report, perched groundwater conditions
may develop due to future irrigation, rainfall, homeowner altered site drainage or other
conditions. Subdrain systems are recommended for all walls constructed below soil
grades. While wall drains and key drains should perform adequately, the need for
additional subdrainage onsite may not be precluded.
Field Testing
1. Field density tests were performed using the sand cone method (ASTM D-1556-90)
and nuclear method (ASTM D-2922). Test results are attached as Table 1 at the end
of this report. The approximate locations of field density tests are shown on the
Compaction Test Location Maps, Plates 1 and 2, which utilize the 1"=40' scale
grading plans (sheets 3 and 4), prepared by Hunsaker & Associates, San Diego,
Inc. as a base map.
2. Field density tests were taken at periodic intervals and random locations to check
the compactive effort provided by the contractor. Based on the operations
observed, test results presented herein are considered representative of the fills
observed under the purview of this report.
3. Visual classification of the soils in the field as well as random laboratory testing was
the basis for determining which maximum dry density value to use for a given
density test.
4. Testing was performed on a full time basis.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 4
GeoSoils, Inc.
LABORATORY TESTING
Moisture-Density Relations
The laboratory maximum dry density and optimum moisture content for each major soil
type was determined according to test method ASTM D-1557-91. The following table
presents the test results:
SOIL TYPE MAXIMUM DRY DENSITY
(PCF)
OPTIMUM MOISTURE
CONTENT (%)
A - Dk Br Silty Sand (Topsoil) 123.0 12.0
B - Yellow Br Sandy Clay 109.5 19.5
C - Gray Br Silty Sand 126.0 11.5
D - Br Sandy Clay 118.0 14.5
E - Gray Br Silty Sand w/Gravel 130.5 10.0
F - Gray Br Silty Sand w/Gravel 135.0 8.0
Expansive Soils
Expansive soil conditions have been evaluated for the site. Representative samples of soil
near pad grade were recovered for classification and expansion testing. Expansion Index
(E.l.) testing was performed in general accordance with Standard 18-2 of the Uniform
Building Code.
Representative expansion indices of less than 20 (very low) were determined for soils near
pad grade within the subject lots. A summary of soil expansion results are present in the
attached Table 2.
Soil Sulfate
The soluble sulfate content of site soils was evaluated. The results of this testing is
presented in the attached Table 2. Based on the testing performed, sulfate resistant
concrete is not required.
RECOMMENDATIONS - FOUNDATIONS
General
The foundation design and construction recommendations are based on laboratory testing
and engineering analysis of onsite earth materials by GSI. Recommendations for
Cypress Valley LLC
Calavera Hills, Village Q, Lots 104 -124
File:e:\wp7\2300\2393b.ror
W.O. 2393-B-SC
September 2,1998
Page 5
GeoSoils, Inc.
conventional foundation systems are provided in the following sections. The foundation
systems may be used to support the proposed structures, provided they are founded in
competent bearing material. The proposed foundation systems should be designed and
constructed in accordance with the guidelines contained in the Uniform Building Code.
All footing designs should be reviewed by the project structural engineer.
Conventional Foundation Design
1. Conventional spread and continuous footings may be used to support the proposed
residential structures provided they are founded entirely in properly compacted fill
or other competent bearing material (i.e., bedrock). Footings should not
simultaneously bear directly on bedrock and fill soils.
2. Analyses indicate that an allowable bearing value of 2000 pounds per square foot
may be used for design of continuous footings 12 inches wide and 12 inches deep
and for design of isolated pad footings 24 inches square and 18 inches deep into
properly compacted fill or bedrock. The bearing value may be increased by one-
third for seismic or other temporary loads. This value may be increased by 20
percent for each additional 12 inches in depth, to a maximum of 2500 pounds per
square foot. No increase, in bearing, for footing width is recommended.
3. For lateral sliding resistance, a 0.4 coefficient of friction may be utilized for a
concrete to soil contact when multiplied by the dead load.
4. Passive earth pressure may be computed as an equivalent fluid having a density of
300 pounds per cubic foot with a maximum earth pressure of 2500 pounds per
square foot.
5. When combining passive pressure and frictional resistance, the passive pressure
component should be reduced by one-third.
6. Footings should maintain a horizontal distance or setback between any adjacent
slope face and the bottom outer edge of the footing. The horizontal distance may
be calculated by using h/3, where (h) is the height of the slope. The horizontal
setback should not be less than 7 feet, nor need not be greater than 40 feet (per
code). The setback may be maintained by simply deepening the footings.
Flatwork, utilities or other improvements within a zone of h/3 from the top of slope
may be subject to lateral distortion. Footings, flatwork, and utilities setbacks should
be constructed in accordance with distances indicated in this section, and/or the
approved plans.
7. Provided that the recommendations contained in this report are incorporated into
final design and construction phase of development, a majority (>50 percent) ofthe
anticipated foundation settlement is expected to occur during construction.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 6
GeoSoils, Inc.
Maximum settlement is not expected to exceed approximately Vz-inch and should
occur below the heaviest loaded columns. Differential settlement is not anticipated
to exceed y4-inch between similar elements, in a 20 foot span.
Conventional Foundation/Concrete Slab Construction
The following construction recommendations are based on generally very low to low
expansive bearing soils and maximum fill thicknesses of less than approximately 30 feet.
1. Conventional continuous footings should be founded at a minimum depth of 12
inches below the lowest adjacent ground surface for one-story structures and 18
inches below the lowest adjacent ground surface for two-story structures. Interior
footings may be founded at a depth of 12 inches below the lowest adjacent ground
surface. Foundation widths may be constructed per the Uniform Building Code
guidelines.
All footings should be reinforced with a minimum of one No. 4 reinforcing bar
placed near the top and one No. 4 reinforcing bar placed near the bottom of the
footing.
2. Detached isolated interior or exterior piers and columns should be founded at a
minimum depth of 18 inches below the lowest adjacent ground surface and tied to
the main foundation with a grade beam. Reinforcement should be properly
designed by the project structural engineer.
3. A grade beam, reinforced as above, and at least 12 inches square, should be
provided across the garage entrances. The base of the reinforced grade beam
should be at the same elevation as base of the adjoining footings.
4. The residential floor and garage slabs should have a minimum thickness of 4
inches. Concrete used in floor slab construction should be at least ASTM 520-C-
2500.
5. Concrete slabs should be underlain with a minimum of 4 inches of sand. In
addition, a vapor barrier consisting of a minimum of 10-mil, polyvinyl-chloride
membrane, with all laps sealed, should be provided at the mid-point of the sand
layer. The slab subgrade should be free of loose and uncompacted material prior
to placing concrete.
6. Concrete floor slabs (residence and garage) may be minimally reinforced with 6-
inch by 6-inch, No. 10 by No. 10 (6 x 6 - Wl .4 x W1.4) welded-wire mesh (i.e.,
industry standard). We understand that the client utilizes No. 3 reinforcement bars
placed on 18-inch centers, in two horizontally perpendicular directions (i.e., long
axis and short axis) as their company standard. This company standard should
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
Rle:e:\wp7\2300\2393b.ror Page 7
GeoSoils, Inc.
exceed the industry standard and is also recommended by GSI. All slab
reinforcement should be supported to ensure proper mid-slab height positioning
during placement ofthe concrete. "Hooking" of reinforcement is not an acceptable
method of positioning.
7. Presaturation is not considered necessary for these soil conditions; however, the
moisture content of the subgrade soils should be equal to or greater than optimum
moisture to a depth of 12 inches belowthe adjacent ground grade in the slab areas,
and verified by this office within 72 hours of the vapor barrier placement.
8. Soils generated from footing excavations to be used onsite should be compacted
to a minimum relative compaction 90 percent ofthe laboratory standard, whether
it is to be placed inside the foundation perimeter or in the yard/right-of-way areas.
This material must not alter positive drainage patterns that direct drainage away
from the structural areas and toward the street.
9. Proposed pools and other appurtenant structures should consider that excavation
difficulties will likely be encountered in lots at depths greater than approximately 3
feet below existing building pad grades due to the presence of dense granitic rock.
10. Rigid block wall designs located along the top of slopes should be reviewed by a
soils engineer, prior to construction.
11. As an alternative, an engineered post-tension foundation system may be used.
Recommendations for post-tensioned slab design are presented in the following
Section.
Post-Tensioned Slab Foundation Systems
1. Post-tensioned (PT) slabs may be utilized for construction of typical one (1) and two
(2) story residential structures onsite. The information and recommendations
presented in this section are not meant to supersede design by a registered
structural engineer or civil engineer familiar with post-tensioned slab design or
corrosion engineering consultant.
2. From a soil expansion/shrinkage standpoint, a fairly common contributing factor to
distress of structures using post-tensioned slabs is a significant fluctuation in the
moisture content of soils underlying the perimeter of the slab, compared to the
center, causing a "dishing" or "arching" of the slabs. To mitigate this possible
phenomenon, a combination of soil presaturation (if necessary, or after the project
has been dormant for a period of time) and construction of a perimeter "cut off' wall
grade beam may be employed.
3. For very low (E.l.= 0 through 20) expansive soils, perimeter and mid span beams
should be a minimum 12 inches deep below lowest adjacent pad grade. The
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 8
GeoSoils, Inc.
perimeter foundations may be integrated into the slab design or independent of the
slab. The perimeter beams should be a minimum of 12 inches in width.
In moisture sensitive slab areas, a vapor barrier should be utilized and be of
sufficient thickness to provide a adequate separation of foundation from soils (10
mils, thick). The vapor barrier should be lapped and adequately sealed to provide
a continuous water-resistant barrier under the entire slab. The vapor barrier should
be sandwiched between two 2-inch thick layers of sand (SE>30) for a total of 4
inches of sand.
4. Isolated piers should be incorporated into the post tension slab system.
5. Specific soil presaturation for slabs is not required for very low expansive soils;
however, the moisture content ofthe subgrade soils should be at or above the soils'
optimum moisture content to a minimum depth of 18 inches below grade
depending on the footing embedment.
6. Post-tensioned slabs should be designed using sound engineering practice and be
in accordance with the Post-Tension Institute (PTI), local and/or national code
criteria and the recommendations of a structural or civil engineer qualified in post-
tension slab design. Alternatives to PTI methodology may be used if equivalent
systems can be proposed which accommodate the angular distortions, expansion
parameters, and settlements noted for this project. If alternatives to PTI are
suggested by the structural consultant, consideration should be given for additional
review by a qualified structural PT-designer. Soil related parameters for post-
tensioned slab design, are presented in the following:
Perimeter Footing Embedment* 12"
Allowable bearing value lOOOpsf**
Modules of subgrade reaction 125 psi/inch
Coefficient of friction 0.35
Passive pressure 275 pcf
Soil Suction (PO 3.6
Depth to Constant Soil Suction 5 feet
Thornthwaite moisture -20.0
e„ edge 2.5
e,„ center 5.0
my edge 0.25
my center 1.00
Minimum Slab Thickness 5 inches
* Lab data indicates E.l. 0-20 for this site.
**Bearing for slab on grade only, bearing value for interior or perimeter beams
should be in accordance with parameters provided for conventional continuous
and isolated spread footings.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills. Village Q, Lots 104 -124 September 2,1998
Flle:e:\wp7\2300\2393b.ror Page 9
GeoSoils, Inc.
7. Provided that the recommendations contained in this report are incorporated into
final design and construction phase of development, a majority (>50 percent) ofthe
anticipated foundation settlement is expected to occur during construction.
Maximum settlement is not expected to exceed approximately y2-inch and should
occur below the heaviest loaded columns. Differential settlement is not anticipated
to exceed Vi-inch between similar elements, in a 20 foot span.
Designers of PT slabs should review the parameters provided for post-tensioned
slabs, and compare using a span distance of 5 feet, using a modules of subgrade
reaction of 125 psi in their evaluation.
8. In accordance with guidelines presented in the Uniform Building Code,
improvements and/or footings should maintain a horizontal distance, X, between
any adjacent descending slope face and the bottom outer edge of the improvement
and/or footing. The horizontal distance, X, may be calculated by using X = h/3,
where h is the height of the slope. X should not be less than 7 feet, nor need not
be greater than 40 feet. X may be maintained by deepening the footings.
Improvements constructed within a distance of h/3 from the top of slope may be
subject to lateral distortion.
Foundations for any adjacent structures, including retaining walls, should be
deepened (as necessary) to below a 1:1 projection upward and away from any
proposed lower foundation system. This recommendation may not be considered
valid, if the additional surcharge imparted by the upper foundation on the lower
foundation has been incorporated into the design ofthe lower foundation.
Additional setbacks, not discussed or superseded herein, and presented in the UBC
are considered valid.
EXTERIOR FLATWORK
Exterior driveways, walkways, sidewalks, or patios, using concrete slab on grade
construction should be designed and constructed in accordance with the following criteria:
1. Driveway slabs should be a minimum 4 inches in thickness; all other exterior slabs
should be a nominal 4 inches in thickness. A thickened edge should be considered
for all flatwork adjacent to landscape areas.
2. Driveway slabs may be reinforced with No. 6 by No. 6 (w2.9 by w2.9) welded wire
mesh placed upon chairs to ensure mid-height positioning. Hooking or pulling of
the reinforcement is not an acceptable method of placement.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 10
GeoSoils, Inc.
3. Slab subgrade should be compacted to a minimum 90 percent relative compaction
and moisture conditioned to at or above the soils optimum moisture content.
4. The use of transverse and longitudinal control joints should be considered to help
control slab cracking due to concrete shrinkage or expansion. Two of the best
ways to control this movement is; 1) add a sufficient amount of reinforcing steel,
increasing tensile strength of the slab, and/or 2) provide an adequate amount of
control and/or expansion joints to accommodate anticipated concrete shrinkage
and expansion. We would suggest that the maximum control joint spacing be
placed on 5 to 8 foot centers or the smallest dimension of the slab, whichever is
least.
5. No traffic should be allowed upon the newly poured concrete slabs until they have
been properly cured to within 75 percent of design strength.
6'. Positive site drainage should be maintained at all times. Adjacent landscaping
should be graded to drain into the street, parking area, or other approved area. All
surface water should be appropriately directed to areas designed for site drainage.
7. Concrete used to construct flatwork should be at least ASTM 520-C-2500.
RETAINING WALLS
General
Foundations may be designed using parameters provided in the "Design" section of
Foundation Recommendations presented herein. Wall sections should adhere to the
County of San Diego and/or City of Carlsbad guidelines. All wall designs should be
reviewed by a qualified structural engineer for structural capacity, overturning, and seismic
resistance stability per the UBC.
The design parameters provided assume that onsite or equivalent low expansive soils are
used to backfill retaining walls. If expansive soils are used to backfill the proposed walls
within this wedge, increased active and at-rest earth pressures will need to be utilized for
retaining wall design. Heavy compaction equipment should not be used above a 1:1
projection up and away from the bottom of any wall.
The following recommendations are not meant to apply to specialty walls (cribwalls, loffel,
earthstone, etc.). Recommendations for specialty walls will be greater than those provided
herein, and can be provided upon request. Some movement of the walls constructed
should be anticipated as soil strength parameters are mobilized. This movement could
cause some cracking dependent upon the materials used to construct the wall. To reduce
wall cracking due to settlement, walls should be internally grouted and/or reinforced with
steel.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 11
GeoSoils, Inc.
Restrained Walls
Any retaining walls that will be restrained prior to placing and compacting backfill material
or that have re-entrant or male corners, should be designed for an at-rest equivalent fluid
pressures of 60 pcf, plus any applicable surcharge loading. For areas of male or re-entrant
corners, the restrained wall design should extend a minimum distance of twice the height
of the wall laterally from the corner. Building walls below grade, should be water-proofed
or damp-proofed, depending on the degree of moisture protection desired. Refer to the
following section for preliminary recommendations from surcharge loads.
Cantilevered Walls
These recommendations are for cantilevered retaining walls up to fifteen (15) feet high.
Active earth pressure may be used for retaining wall design, provided the top of the wall
is not restrained from minor deflections. An empirical equivalent fluid pressure (EFP)
approach may be used to compute the horizontal pressure against the wall. Appropriate
fluid unit weights are provided for specific slope gradients of the retained material. These
do not include other superimposed loading conditions such as traffic, structures, seismic
events or adverse geologic conditions.
SURFACE SLOPE OF EQUIVALENT
RETAINED lUtATERIAL FLUID WEIGHT
HORIZONTAL TO VERTICAL P.CF.
(Verv Low to Low Expansive Soih
Level 35
2 to 1 45
The equivalent fluid density should be increased to 60 pounds per cubic foot for level
backfill at the angle point ofthe wall (corner or male re-entrant) and extended a minimum
lateral distance of 2H (two times the wall height) on either side of the corner. Traffic loads
within a 1:1 projection up from the wall heel, due to light trucks and cars should be
considered as a load of 100 psf per foot in the upper 5 feet of wall in uniform pressure. For
preliminary design purposes, footing loads within a 1:1 backfill zone behind wall will be
added to the walls as Va of the bearing pressure for one footing width, along the wall
alignment.
Wall Backfill and Drainage
All retaining walls should be provided with an adequate gravel and pipe back drain and
outlet system to prevent buildup of hydrostatic pressures, and be designed in accordance
with minimum standards presented herein. Retaining wall drainage and outlet systems
should be reviewed by the project design civil engineer, and incorporated into project
Cypress Valley LLC
Calavera Hills, Village Q, Lots 104 -124
File:e:\wp7\2300\2393b.ror
W.O. 2393-B-SC
September 2,1998
Page 12
GeoSoils, Inc.
plans. Pipe should consist of schedule 40 perforated PVC pipe. Gravel used in the back
drain systems should be a minimum of 3 cubic feet per lineal foot of % to 1 Vz-inch clean
crushed rock encapsulated in filter fabric (Mirafi 140 or equivalent). Perforations in pipe
should face down. The surface ofthe backfill should be sealed by pavement or the top 18
inches compacted to 90 percent relative compaction with native soil. Proper surface
drainage should also be provided.
As an alternative to gravel back drains, panel drains (Miradrain 6000, Tensar, etc.) may be
used. Panel drains should be installed per manufacturers guidelines. Regardless of the
back drain used, walls should be water proofed where they would impact living areas or
where staining would be objectionable.
Retaining Wall Footing Transitions
Sjte walls are anticipated to be supported on footings designed in accordance with the
recommendations in this report. Wall footings may transition from bedrock to fill. If this
condition is present the civil designer may specify either:
a) A minimum of a 2-foot, overexcavation and recompaction of bedrock
materials, as measured for a distance of two times the height of the wall from
the transition in the direction of the wall. Overexcavations should be
completed for a minimum lateral distance of 2 feet beyond the footing,
measured perpendicular to the wall.
b) Increase of the amount of reinforcing steel and wall detailing (i.e., expansion
joints or crack control joints) such that a angular distortion of 1/360 for a
distance of 2H on either side of the transition may be accommodated.
Expansion joints should be sealed with a flexible grout.
c) Embed the footings entirely into native formational material. If transitions
from cut to fill transect the wall footing alignment at an angle of less than 45
degrees (plan view), then the designer should follow recommendation "a"
(above) and until such transition is between 45 and 90 degrees to the wall
alignment.
PAVEMENTS
Pavements may be designed and constructed in accordance with recommendations
presented in GSI (1998b). Pavement design for streets not indicated in GSI (1998b) has
not been performed to date. Concrete driveway pavements, a minimum 4 inches in
thickness, may be constructed per the exterior concrete slab recommendations presented
in this report.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 13
GeoSoils, Inc.
DEVELOPMENT CRITERIA
Graded Slope Maintenance and Planting
Water has been shown to weaken the inherent strength of all earth materials. Slope
stability is significantly reduced by overly wet conditions. Positive surface drainage away
from graded slopes should be maintained and only the amount of irrigation necessary to
sustain plant life should be provided for planted slopes. Over watering should be avoided
as it can adversely affect site improvements. Graded slopes constructed within and
utilizing onsite materials would be erosive. Eroded debris may be minimized and surficial
slope stability enhanced by establishing and maintaining a suitable vegetation cover soon
after construction. Compaction to the face of fill slopes would tend to minimize short-term
erosion until vegetation is established. Plants selected for landscaping should be light
weight, deep rooted types that require little water and are capable of surviving the
prevailing climate.
Landscape Maintenance
Only the amount of irrigation necessary to sustain plant life should be provided. Over
watering the landscape areas could adversely affect proposed site improvements. We
would recommend that any proposed open-bottom planters adjacent to proposed
structures be eliminated for a minimum distance of 10 feet. As an alternative, closed-
bottom type planters could be utilized. An outlet placed in the bottom ofthe planter, could
be installed to direct drainage away from structures or any exterior concrete flatwork. The
slope areas should be planted with drought resistant vegetation. Consideration should be
given to the type of vegetation chosen and their potential effect upon surface
improvements (i.e. some trees will have an effect on concrete flatwork with their extensive
root systems).
From a geotechnical standpoint, leaching is not recommended for establishing
landscaping. If the surface soils are processed for the purpose of adding amendments
they should be recompacted to 90 percent minimum relative compaction.
Drainage
Positive site drainage should be maintained at all times. Drainage should not flow
uncontrolled down any descending slope. Water should be directed away from
foundations and not allowed to pond and/or seep into the ground. Pad drainage should
be directed toward the street or other approved area. Roof gutters and down spouts
should be considered to control roof drainage. Down spouts should outlet a minimum of
three feet from proposed structures and/or in accordance with the recommendations of the
design civil engineer. We would recommend that any proposed open bottom planters
adjacent to proposed structures be eliminated for a minimum distance of 10 feet. As an
alternative, closed bottom type planters could be utilized. An outlet placed in the bottom
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
Flle:e:\wp7\2300\2393b.ror Page 14
GeoSoils, Inc.
of the planter could be installed to direct drainage away from structures or any exterior
concrete flatwork.
Footing Trench Excavation
All footing excavations should be observed by a representative ofthis firm subsequent to
trenching and prior to concrete form and reinforcement placement. The purpose of the
observations is to verify that the excavations are made into the recommended bearing
material and to the minimum widths and depths recommended for construction. If loose
or compressible materials are exposed within the footing excavation, a deeper footing or
removal and recompaction ofthe subgrade materials would be recommended at that time.
All excavations should minimally conform to CAL-OSHA and local safety codes.
Footing trench spoil and any excess soils generated from utility trench excavations should
b.e compacted to a minimum relative compaction of 90 percent if not removed from the
site.
Additional Site Improvements
If in the future, any additional improvements are planned for the site, recommendations
concerning the geological or geotechnical aspects of design and construction of said
improvements could be provided upon request. Proposed pools or other appurtenant
structures should consider that excavation difficulties will likely be encountered in some
lots (see Table 2) at depths greater than 3 feet below existing building pad grade. Rigid
block wall designs located along the top of slopes should be reviewed by a soils engineer.
Additional Grading
This office should be notified in advance of any additional fill placement, regrading of the
site, or trench backfilling after rough grading has been completed. This includes any
grading, utility trench and retaining wall backfills. All excavations should be obsen/ed by
one of our representatives and conform to CAL-OSHA and local safety codes.
Utility Trench Backfill
1. All interior utility trench backfill should be brought to at least two percent above
optimum moisture content and then compacted to obtain a minimum relative
compaction of 90 percent ofthe laboratory standard. As an alternative for shallow
(12 inch to 18 inch) under-slab trenches, sand having a sand equivalent value of 30
or greater may be utilized and jetted or flooded into place. Obsen/ation, probing
and testing should be provided to verify the desired results.
2. Exterior trenches adjacent to, and within areas extending below a 1:1 plane
projected from the outside bottom edge of the footing, and all trenches beneath
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 15
GeoSoils, Inc.
hardscape features and in slopes, should be compacted to at least 90 percent of
the laboratory standard. Sand backfill, unless excavated from the trench, should
not be used in these backfill areas. Compaction testing and obsen/ations, along
with probing, should be accomplished to verify the desired results.
3. All trench excavations should conform to CAL-OSHA and local safety codes.
PLAN REVIEW
Final foundation and improvement plans should be submitted to this office for review and
comment, as they become available, to minimize any misunderstandings between the
plans and recommendations presented herein. In addition, foundation excavations and
earthwork construction performed on the site should be obsen/ed and tested by this office.
If. conditions are found to differ substantially from those stated, appropriate
recommendations would be offered at that time.
REGULATORY COMPLIANCE
Removals, processing of original ground, cuts and fills have been obsen/ed and
compaction testing performed underthe pun/iew ofthis report have been completed using
the selective testing and observations services of GeoSoils, Inc. Earthwork was found to
be in compliance with the Grading Code of the City of Carlsbad, California. Our findings
were made and recommendations prepared in conformance with generally accepted
professional engineering practices and no further warranty is implied nor made. This
report is subject to review by the controlling authorities for this project. GeoSoils, Inc.
should not be held responsible nor liable for work, testing or recommendations performed
or provided by others.
Cypress Valley LLC W.O. 2393-B-SC
Calavera Hills, Village Q, Lots 104 -124 September 2,1998
File:e:\wp7\2300\2393b.ror Page 16
GeoSoils, Inc.
The opportunity to be of service is sincerely appreciated. If you should have any
questions, please do not hesitate to call our office.
Respectfully submitted,
GeoSoils, Inc.
Robert G. unsman
Project Geologist,
hn P. Franklin
1034 %
David W. Skelly
Civil Engineer, RCE
Engineering Geologist, CEG~13i
RGC/DWS/JPF/mo
Attachments: Appendix - Refere
Table 1- Field DensTty^Mfiesults
Table 2- Lot Characteristics
Plates 1 and 2 - As Graded Geotechnical Map
Distribution: (4) Addressee
Cypress Valley LLC
Calavera Hills, Village Q, Lots 104 -124
Flle:e:\wp7\2300\2393b.ror
GeoSoils, Inc.
W.O. 2393-B-SC
September 2,1998
Page 17
APPENDIX
REFERENCES
Cypress Valley LLC, 1998, Report of Rough Grading, Calavera Hills, Village Q Model Sites,
including Bluff Court, Talus Way and Tamarack Avenue, Station 119+80 to 131 +00,
City of Carlsbad, California, W.O. 2393-B-SC, June 1,1998.
, 1997b, Plans forthe grading of Calavera Hills Village "Q", Carlsbad Tract 83-32,
Sheets 1-8, Drawing No. 303-2A, Project No. 2.89.33, dated November 17.
Southern California Soil and Testing, Inc., 1988, Supplemental soil investigation, Calavera
Hills Village Q and T, College Boulevard, Carlsbad, California, job no. 8821142,
report no.l, dated October 6.
, 1984, Report of geotechnical investigation for Village Q, Calavera Hills subdivision,
Cartsbad, job no. 14112, report no.4, dated January 10.
, 1983a, Report of geotechnical investigation for Village Q, Calavera Hills subdivision,
Carlsbad, job no. 14112, report no.4, dated January 10.
, 1983b, Report of preliminary geotechnical investigation forthe Calavera Hills areas
El, E2, H, I, Kand Pthrough Z2, Carlsbad, job no. 14112, report no.l, dated July
29.
GeoSoils, Inc., 1998a, Preliminary review of slope stability, Calavera Hills, Villages "Q" and
"T", City of Carlsbad, California, W.O. 2393-B-SC dated February 16.
, 1998b, Pavement design report. Talus Way, Bluff Court and Tamarack Avenue,
Station 119+80 to 131 +00, Calavera Hills, Village Q, Carlsbad, California, W.O.
2393-B-SC, dated May 5,1998.
GeoSoils, Inc.
Table 1
FIELD DENSITY TEST RESULTS
TEST
NO.
DATE TEST LOCATION ELEVATION
OR
DEPTH (ft.)
MOISTURE
CONTENT
(%)
DRY
DENSITY
(pcf)
REWTJVE
COMPACTION
(%>
TEST
METHOD
SOIL
TYPE
218 04/09/98 VILLAGE Q BLUFF COURT 13+90 423.0 19.7 99.2 90.6 ND B
219 04/09/98 VILLAGE Q BLUFF COURT 13+00 417.0 13.6 112.4 91.4 ND A
220 04/09/98 VILLAGE 0 BLUFF COURT 11 +50 413.0 19.8 100.0 91.3 ND B
221 04/09/98 VILLAGE Q BLUFF COURT 12+50 417.0 13.1 111.7 90.8 ND A
222 04/09/98 VILLAGE Q BLUFF COURT 12+75 419.0 13.4 113.7 92.4 ND A
223 04/09/98 VILLAGE Q LOT 115 420.0 11.2 117.6 90.1 ND E
224 04/09/98 VILLAGE Q OPEN SPACE LOT 422.0 10.8 117.8 90.3 ND E
225 04/09/98 VILLAGE Q LOT 117 423.0 10.4 120.6 92.4 ND E
226 04/09/98 VILLAGE Q LOT 118 427.0 10.5 121.0 92.7 ND E
227 04/14/98 VILLAGE QT/U.US WAY 414.0 13.2 112.7 91.6 ND A
228 04/14/98 VILLAGE Q EASMENT 108-107 406.0 9.5 124.3 92.1 ND F
229 04/14/98 VILLAGE Q EASMENT 108-107 409.0 8.3 122.6 90.8 ND F
230 04/14/98 VILLAGE Q EASMENT 108-107 411.0 12.5 112.4 91.4 ND A
231 04/14/98 VILLAGE CLOT 109 400.0 13.9 112.2 91.2 ND A
232 04/14/98 VILLAGE 0 LOT 109 405.0 14.2 110.8 90.1 ND A
233 04/14/98 VILLAGE CLOT 110 395.0 12.6 110.7 90.0 ND A
234 04/14/98 VILLAGE CLOT 110 400.0 12.2 112.3 91.3 ND A
235 04/14/98 VILLAGE Q LOT 111 397.0 12.5 111.8 90.9 ND A
236 04/15/98 VILLAGE Q LOT 110 401.0 12.4 111.1 90.3 ND A
237 04/15/98 VILLAGE CLOT 112 402.0 13.3 110.8 90.1 ND A
238 04/15/98 VILLAGE Q LOT 111 404.0 13.8 110.7 90.0 ND A
239 04/15/98 VILLAGE CLOT 113 404.0 13.4 111.4 90.6 ND A
240 04/15/98 VILLAGE CLOT 111 408.0 13.9 111.9 91.0 ND A
241 04/15/98 VILLAGE Q LOT 114 407.0 13.6 110.8 90.1 ND A
242 04/15/98 VILLAGE CLOT 113 411.0 13.4 111.6 90.7 ND A
243 04/15/98 VILLAGE Q LOT 111 410.0 13.2 111.2 90.4 ND A
244 04/16/98 VILLAGE Q TAMARACK 128+40 420.0 15.9 110.7 93.8 ND D
245 04/16/98 VILLAGE 0 TAMARACK 127+00 417.0 14.7 112.3 95.2 ND D
246 04/16/98 VILUGE Q TAMARACK 125+50 400.0 16.2 111.9 94.8 ND D
247 04/16/98 VILLAGE Q TAMARACK 126+50 416.0 15.1 109.9 93.1 ND D
260 04/17/98 VILLAGE Q TALUS WAY 10+95 418.0 11.8 118.8 94.3 ND C
261* 04/20/98 VILLAGE Q TALUS WAY 10+30 422.0 12.9 103.6 84.2 ND A
261-A 04/20/98 VILLAGE Q TALUS WAY 10+30 422.0 12.6 110.9 90.2 ND A
262 04/20/98 VILLAGE Q LOT 120 425.0 13.1 112.3 91.3 ND A
263 04/20/98 VILLAGE Q LOT 122 428.0 12.2 113.8 92.5 ND A
264 04/20/98 VILLAGE Q LOT 124 429.0 11.9 114.2 90.6 ND C
265 04/20/98 VILLAGE CLOT 124 430.0 12.4 114.0 90.5 ND C
271 04/21/98 VILLAGE Q TAMARACK 121 +00 352.0 11.1 122.0 93.5 ND E
272 04/21/98 VILLAGE 0 TAMARACK 122+50 369.0 10.2 122.9 94.2 ND E
273 04/21/98 VILLAGE Q TAMARACK 124+00 386.0 12.4 116.7 92.6 ND C
274-S 04/21/98 VILLAGE Q LOT 109 SLOPE 410.0 11.8 114.9 91.2 ND C
275-S 04/21/98 VILLAGE Q LOT 110 SLOPE 406.0 11.3 114.2 90.6 ND C
Cypress Valley LLC
e:\excel\tables\2300\2393bq
GeoSoils, Inc.
W.O. 2393-B-SC
Page 1
Table 1
FIELD DENSITY TEST RESULTS
TEST
NO.
DATE TEST LOCATION ELEVATION
OR
DEPTH (ft.)
MOISTURE
CONTENT
(%)
DRY
DENSITY
(pcf)
RELATIVE
COMPACTION
(%)
TEST
METHOD
SOIL
TYPE
276-S 04/21/98 VILLAGE Q LOT 110 SLOPE 408.0 11.5 114.5 90.9 ND C
277-S 04/21/98 VILLAGE Q LOT 110 SLOPE 400.0 11.6 113.5 90.1 ND C
278-S 04/21/98 VILLAGE Q LOT 111 SLOPE 411.0 11.5 113.8 90.3 ND C
279-S 04/21/98 VILLAGE Q LOT 112 SLOPE 411.0 11.2 114.7 91.0 ND c
280-S 04/21/98 VILLAGE Q LOT 113 SLOPE 406.0 12.0 114.2 90.6 ND c
281-S 04/21/98 VILLAGE Q LOT 113 SLOPE 410.0 11.6 114.4 90.8 ND c
282-S 04/21/98 VILLAGE Q LOT 114 SLOPE 405.0 11.9 114.5 90.9 ND c
283-S 04/21/98 VILLAGE Q LOT 110 SLOPE 404.0 11.7 113.5 90.1 ND c
285 04/21/98 VILLAGE Q TAMARACK 123+00 380.0 11.9 116.0 92.1 ND c
286 04/22/98 VILLAGE Q TAMARACK 120+60 357.0 12.8 116.4 92.4 ND c
287 04/22/98 VILLAGE Q TAMARACK 119+60 348.0 12.6 116.0 92.1 ND c
288 04/22/98 VILLAGE Q TAMARACK 121 +90 365.0 11.4 115.2 91.4 ND c
289 04/22/98 VILLAGE Q TAMARACK 124+80 399.0 11.9 115.7 91.8 ND c
290 04/22/98 VILLAGE Q TAMARACK 127+40 420.0 12.2 113.8 90.3 ND c
296 04/23/98 VILLAGE Q LOT 119 431.0 10.1 118.6 90.9 ND E
297 04/23/98 VILLAGE Q LOT 118 430.0 10.6 119.5 91.6 ND E
298 04/23/98 VILLAGE Q LOT 117 428.0 12.0 115.7 91.8 ND c
299 04/23/98 VILLAGE CLOT 116 426.0 11.8 116.3 92.3 ND c
300 04/23/98 VILLAGE Q OPEN SPACE 143 423.0 11.9 115.8 91.9 ND c
301 04/23/98 VILLAGE Q LOT 115 421.0 12.3 115.4 91.6 ND c
302 04/23/98 VILUGE CLOT 114 419.0 13.1 113.5 92.3 ND A
303 04/23/98 VILUGE CLOT 113 416.0 13.4 113.8 92.5 ND A
304 04/23/98 VILUGE Q LOT 112 414.0 12.8 113.3 92.1 ND A
305 04/23/98 VILUGE Q LOT 111 413.0 12.4 114.3 90.7 ND c
306 04/23/98 VILUGEQLOT110 413.0 11.8 113.9 90.4 ND c
307 04/23/98 VILUGE Q LOT 109 413.0 11.9 114.8 91.1 ND c
308 04/23/98 VILUGE Q TAMARACK 127+80 422.0 13.2 113.5 92.3 ND A
312 04/23/98 VILUGE 0 TAMARACK 129+00 424.0 11.2 118.6 90.9 ND E
313 04/24/98 VILUGE Q TAMARACK 130+00 422.0 10.5 120.3 92.2 ND E
314 04/24/98 VILUGE 0 TAMARACK 130+75 424.0 10.8 119.5 91.6 ND E
315 04/24/98 VILUGE Q TAMARACK 130+50 426.0 10.2 120.6 92.4 ND E
316 04/24/98 VILUGE Q LOT 107 413.0 11.7 115.5 91.7 ND c
317 04/24/98 VILUGE LOT 106 415.0 11.3 116.3 92.3 ND C
318 04/24/98 VILUGE LOT 105 417.0 11.5 116.0 92.1 ND C
319 04/24/98 VILUGE LOT 104 419.0 11.9 114.4 90.8 ND c
320 04/24/98 VILUGE LOT 108 413.0 12.2 115.4 91.6 ND c
321 04/24/98 VILUGE LOT 120 426.0 12.4 112.4 91.4 ND A
322 04/24/98 VILUGE LOT 121 429.0 12.8 113.8 92.5 ND A
323 04/24/98 VILUGE LOT 122 430.0 12.7 113.3 92.1 ND A
324 04/24/98 VILUGE LOT 123 431.0 12.9 115.3 93.7 ND A
325 04/24/98 VILUQE LOT 124 431.0 12.4 114.3 92.9 ND A
Cypress Valley LLC
e:\excel\tabies\2300\2393bq
GeoSoils, Inc.
W.O. 2393-B-SC
Page 2
Table 1
FIELD DENSITY TEST RESULTS
TEST DATE TEST LOCATION ELEVATION MOISTURE DRY RELATIVE TEST SOIL
NO. CONTENT DENSITY COMPACTION METHOD TYPE
DEPTH (ft.) iiiiiiiiiiii (pcf)
326 04/28/98 VILUGE Q TAMARACK 122+00 370.0 10.7 119.8 91.8 ND E
327 04/28/98 VILUGE Q TAMARACK 124+00 391.0 10.2 120.3 92.2 ND E
328 04/28/98 VILUQE Q TAMARACK 126+00 407.0 10.3 118.8 91.0 ND E
330 04/28/98 VILUGE Q TAMARACK 129+40 426.0 10.9 120.5 92.3 ND E
331 04/28/98 10+00 BLUFF COURT 406.0 11.1 113.5 90.1 ND C
332 04/28/98 11+00 BLUFF COURT 412.0 12.6 113.8 90.3 ND C
333 04/28/98 10+25 BLUFF COURT 409.0 11.3 114.4 90.8 ND C
334 04/28/98 13+00 BLUFF COURT 421.0 13.1 116.0 92.1 ND c
335 04/28/98 13+70 BLUFF COURT 426.0 13.3 114.2 90.6 ND c
LEGEND .
* - FAILED TEST
A-RETEST
ND - NUCLEAR DENSOMETER
8 - SLOPE TEST
Cypress Valley LLC
e:\excel\tables\2300\2393bq
GeoSoils, Inc.
W.O. 2393-B-SC
Page 3
TABLE 2
LOT CHARACTERISTICS
LOT
#
EXPANSION
INDEX (per
UBC
standard
18-2)
EXPANSION
POTENTIAL"^)
SOLUBLE
SULFATE
(ppm)
SULFATE
EXPOSURE***
DEPTH OF
FILL (RANGE
IN FT.)
CLIENT
FOUNDATION
CATEGORY
104 15 Very Low 51 Negligible 3-4 l/ll
105 15 Very Low 51 Negligible 3-4 l/ll
106 15 Very Low 51 Negligible 3-4 l/ll
107 15 Very Low 51 Negligible 3-4 l/ll
.108 10 Very Low 40 Negligible 3-5 l/ll
109 10 Very Low 40 Negligible 3-10 l/ll
110 10 Very Low 40 Negligible 4-15 l/ll
111 10 Very Low 40 Negligible 4-15 l/ll
112 10 Very Low 40 Negligible 3-6 l/ll
113 10 Very Low 40 Negligible 3-8 l/ll
114 12 Very Low 36 Negligible 3-6 l/ll
115 12 Very Low 36 Negligible 3-6 l/ll
116 12 Very Low 36 Negligible 3-6 l/ll
117 12 Very Low 36 Negligible 3-6 l/ll
118 12 Very Low 36 Negligible 3-6 l/ll
119 5 Very Low 14 Negligible 3-6 l/ll
120 5 Very Low 14 Negligible 3-4 l/ll
121 5 Very Low 14 Negligible 3-4 l/ll
122 5 Very Low 14 Negligible 3-4 l/ll
123 5 Very Low 14 Negligible 3-4 l/ll
124 5 Very Low 14 Negligible 3-4 l/ll
Per Table 18-I-B of the Uniform Building Code (1997 ed.)
'2' Per Table 19-A-4 of the Uniform Building Code (1997 ed.)
Client Foundation Category added at request. Foundation should be constructed in accordance with
recommendations developed by GSI and presented in this report.
GeoSoils, Inc.