HomeMy WebLinkAboutSUP 06-10X2A; AGUA HEDIONDA OUTER LAGGON MAINTENANCE; APPENDIX A - WEEKLY PROGRESS REPORTS AND FINAL PIPELINE DISPOSAL LOG-ENCINA 2018 OUTER LAGOON DREDGING; 2018-01-29
Appendix A
Weekly Progress Reports and
Final Pipeline Disposal Log
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
January 29 – February 4, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. None.
Beaches:
Middle Beach
1. None.
South Beach
1. None.
Equipment
Lagoon: Beaches:
Middle Beach South Beach
None None None
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 0 cy Weekly Quantity 0 cy 0 cy
Quantity to Date 0 cy Quantity to Date 0 cy 0 cy
Target 244,000 cy Target 163,480 cy 80,520 cy
% Complete 0 % % Complete 0 % 0 %
Observations
1. None
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 2 of 9
Dredging Progress
Weather
Metrologic Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
300,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – Jan 31, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – Jan 31, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – Jan 31, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – Jan 31, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – Jan 31, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – Jan 31, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – Jan 31, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – Jan 31, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – Jan 31, 2018
S. Carlsbad 2 (looking south from groin) – Jan 31, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
January 29 – February 4, 2018
Page 9 of 9
Photos (continued)
S. Carlsbad 3 (looking north from groin) – Jan 31, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
February 5 – 11, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredging contractor (Camenzind) began building crew and took delivery of equipment.
Beaches:
Middle Beach
1. None.
South Beach
1. None.
Equipment
Lagoon: Beaches:
Middle Beach South Beach
None None None
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 0 cy Weekly Quantity 0 cy 0 cy
Quantity to Date 0 cy Quantity to Date 0 cy 0 cy
Target 244,000 cy Target 163,480 cy 80,520 cy
% Complete 0 % % Complete 0 % 0 %
Observations
1. None
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 2 of 8
Dredging Progress
Weather
Metrologic Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
300,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 3 of 8
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 4 of 8
Photos
N. Carlsbad 1 (looking south from north end of seawall) – Feb 9, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – Feb 9, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 5 of 8
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – Feb 9, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – Feb 9, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 6 of 8
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – Feb 9, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – Feb 9, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 7 of 8
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – Feb 9, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – Feb 9, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 5 – 11, 2018
Page 8 of 8
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – Feb 9, 2018
S. Carlsbad 2 (looking south from groin) – Feb 9, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
February 12 – 18, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Conducted dredging test (1-hr) on Friday with discharge on Middle Beach.
Beaches:
Middle Beach
1. See above.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 250 cy Weekly Quantity 250 cy 0 cy
Quantity to Date 250 cy Quantity to Date 250 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 0 % % Complete 0 % 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = 207,261 cy
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – Feb 16, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – Feb 16, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – Feb 16, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – Feb 16, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – Feb 16, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – Feb 16, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – Feb 16, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – Feb 16, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – Feb 16, 2018
S. Carlsbad 2 (looking south from prior location of groin) – Feb 16, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 12 – 18, 2018
Page 9 of 9
Photos (continued)
Discharge Pipe on Middle Beach for Test – Feb 16, 2018
Dredge in Lagoon – Feb 16, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
February 19 – 25, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material and placed on Middle Beach. No dredging on Sunday Feb. 25.
Beaches:
Middle Beach
1. See above.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 22,158 cy Weekly Quantity 22,158 cy 0 cy
Quantity to Date 22,408 cy Quantity to Date 22,408 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 11 % % Complete 16 % 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = 207,261 cy
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – Feb 23, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – Feb 23, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – Feb 23, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – Feb 23, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – Feb 23, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – Feb 23, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – Feb 23, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – Feb 23, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – Feb 23, 2018
S. Carlsbad 2 (looking south from prior location of groin) – Feb 23, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 19 – 25, 2018
Page 9 of 9
Photos (continued)
Discharge Pipe on Middle Beach – Feb 23, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
February 26 – March 4, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material and placed on Middle Beach. No dredging on Sunday, March 4.
Beaches:
Middle Beach
1. See above.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 24,692 cy Weekly Quantity 24,692 cy 0 cy
Quantity to Date 47,100 cy Quantity to Date 47,100 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 23 % % Complete 34 % 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = 207,261 cy
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – March 2, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – March 2, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – March 2, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – March 2, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – March 2, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – March 2, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – March 2, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – March 2, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – March 2, 2018
S. Carlsbad 2 (looking south from prior location of groin) – March 2, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
February 26 – March 4, 2018
Page 9 of 9
Photos (continued)
Dredge in Lagoon – March 2, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
March 5 – 11, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material and placed on Middle Beach. No dredging on Sunday.
Beaches:
Middle Beach
1. Placed material.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 23,038 cy Weekly Quantity 23,038 cy 0 cy
Quantity to Date 70,138 cy Quantity to Date 70,138 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 34% % Complete 51% 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = 207,261 cy
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – March 8, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – March 8, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – March 8, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – March 8, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – March 8, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – March 8, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – March 8, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – March 8, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – March 8, 2018
S. Carlsbad 2 (looking south from prior location of groin) – March 8, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 5 - 11, 2018
Page 9 of 9
Photos (continued)
Material being Placed on Middle Beach – March 8, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
March 12 – 18, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material in lagoon. No dredging on Saturday or Sunday (3/17-3/18).
Beaches:
Middle Beach
1. Placed material.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 16,927 cy Weekly Quantity 16,927 cy 0 cy
Quantity to Date 87,065 cy Quantity to Date 87,065 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 42% % Complete 63% 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = 207,261 cy
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – March 15, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – March 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – March 15, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – March 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – March 15, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – March 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – March 15, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – March 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – March 15, 2018
S. Carlsbad 2 (looking south from prior location of groin) – March 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 12 - 18, 2018
Page 9 of 9
Photos (continued)
Dredge in Lagoon – March 15, 2018
Material being Placed on Middle Beach – March 15, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
March 19 – 25, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material in lagoon. No dredging on Saturday or Sunday (3/24-3/25).
Beaches:
Middle Beach
1. Placed material.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 26,257 cy Weekly Quantity 26,257 cy 0 cy
Quantity to Date 113,322 cy Quantity to Date 113,322 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 55% % Complete 82% 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – March 25, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – March 25, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – March 25, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – March 25, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – March 25, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – March 25, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – March 25, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – March 25, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – March 25, 2018
S. Carlsbad 2 (looking south from prior location of groin) – March 25, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 19 - 25, 2018
Page 9 of 9
Photos (continued)
Dredge in Lagoon – March 25, 2018
Material Placed on Middle Beach – March 25, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
March 26 – April 1, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material in lagoon. No dredging on Saturday or Sunday (3/31-4/1).
Beaches:
Middle Beach
1. Placed material.
South Beach
1. None.
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 23,980 cy Weekly Quantity 23,980 cy 0 cy
Quantity to Date 137,302 cy Quantity to Date 137,302 cy 0 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 66% % Complete 99% 0 %
Observations
1. None.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – March 30, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – March 30, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – March 30, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – March 30, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – March 30, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – March 30, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – March 30, 2018
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – March 30, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 2 (looking south from prior location of groin) – March 30, 2018
Dredge in Lagoon – March 30, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
March 26 – April 1, 2018
Page 9 of 9
Photos (continued)
Material Placed on Middle Beach – March 30, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
April 2 – 8, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material in lagoon. No dredging on Saturday or Sunday (4/7-4/8).
Beaches:
Middle Beach
1. Placed material on Monday (4/2).
South Beach
1. Placed material on Tuesday (4/3) through Friday (4/6).
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 28,533 cy Weekly Quantity 3,870 cy 24,663 cy
Quantity to Date 165,835 cy Quantity to Date 141,172 cy 24,663 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 80% % Complete 102% 36 %
Observations
1. Moved discharge pipe from Middle Beach to South Beach.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 2 of 9
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
0
50,000
100,000
150,000
200,000
250,000
4‐Feb 11‐Feb 18‐Feb 25‐Feb 4‐Mar 11‐Mar 18‐Mar 25‐Mar 1‐Apr 8‐Apr 15‐AprCumulative Dredged Quantity (cy)Week Ending
2018 Dredging Progress
Target Dredge Quantity = 207,261 cy
April 15, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 3 of 9
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 4 of 9
Photos
N. Carlsbad 1 (looking south from north end of seawall) – April 6, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – April 6, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 5 of 9
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – April 6, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – April 6, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 6 of 9
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – April 6, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – April 6, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 7 of 9
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – April 6, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – April 6, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 8 of 9
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – April 6, 2018
No Access Due to Construction
S. Carlsbad 2 (looking south from prior location of groin) – April 6, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 2 - 8, 2018
Page 9 of 9
Photos (continued)
Dredge in Lagoon – April 6, 2018
Material being Placed on South Beach – April 6, 2018
CABRILLO POWER I LLC ENCINA POWER STATION
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Report
April 9 – 15, 2018
Coastal Frontiers Corporation
Activities in Progress
Lagoon:
1. Dredged material in lagoon (4/9 through 4/13). No dredging on Saturday (4/14) or Sunday (4/15).
Beaches:
Middle Beach
1. None.
South Beach
1. Placed material on Monday (4/9) through Friday (4/13).
Equipment
Dredge “Paul Vincent” Cat 966M Loader
Workboat/Tender “Fester” Skytrak 8042 Telehandler
Safety Skiff “Walrus” Link-Belt HSP 8040 Crane
Progress
Dredged Volume: Placed Volume: Middle Beach South Beach
Weekly Quantity 39,647 cy Weekly Quantity 3,870 cy 39,647 cy
Quantity to Date 205,482 cy Quantity to Date 141,172 cy 64,310 cy
Target 207,261 cy Target 138,865 cy 68,396 cy
% Complete 99% % Complete 102% 94 %
Observations
1. End of dredging in Agua Hedionda Lagoon.
2. Final weekly report.
(continued)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 2 of 8
Dredging Progress
Weather
Meteorological Observations (Carlsbad, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 3 of 8
Weather (continued)
Wave Conditions (Oceanside, CA)
Water Levels (La Jolla, CA)
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 4 of 8
Photos
N. Carlsbad 1 (looking south from north end of seawall) – April 14, 2018
N. Carlsbad 2 (looking north from vicinity of Tower 36) – April 14, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 5 of 8
Photos (continued)
N. Carlsbad 3 (looking south from vicinity of Tower 36) – April 14, 2018
N. Carlsbad 4 (looking north from vicinity of Tower 36 stairway) – April 14, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 6 of 8
Photos (continued)
N. Carlsbad 5 (looking south from vicinity of Tower 36 stairway) – April 14, 2018
N. Carlsbad 6 (looking north from Agua Hedionda Inlet North Jetty) – April 14, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 7 of 8
Photos (continued)
Middle Beach 1 (looking south from Agua Hedionda Inlet South Jetty) – April 14, 2018
Middle Beach 2 (looking north from Agua Hedionda Outlet North Jetty) – April 14, 2018
Outer Agua Hedionda Lagoon 2018 Dredge Cycle
Weekly Progress Report
April 9 - 15, 2018
Page 8 of 8
Photos (continued)
S. Carlsbad 1 (looking south from Agua Hedionda Outlet South Jetty) – April 14, 2018
S. Carlsbad 2 (looking south from prior location of groin) – April 14, 2018
Final Pipeline Dredging Disposal Log
Camenzind Dredging, Inc.
04/14/18DateCDI Correspondence 180414a
Camenzind Dredging, Inc.
PIPELINE DISPOSAL DREDGING LOG
SPL-2001-00328-RRSPERMIT:AGUA HEDIONDA LAGOONPROJECT:
CARLSBAD BEACHESDISPOSAL SITE:
WDR-96-32RWQCB PermitEPISODE:
AREA
DISPOSAL
Volume
Cumlative
Volume
Estimated
QUADRANT
AREA DREDGED
OPERATION
TIME IN
DATEDAY
(cy) (cy)(see vicinity map)(Hours)
No Dredging00.00.000.002/03/18SATURDAY
No Dredging00.00.000.002/04/18SUNDAY
No Dredging00.00.000.002/05/18MONDAY
No Dredging00.00.000.002/06/18TUESDAY
No Dredging00.00.000.002/07/18WEDNESDAY
No Dredging00.00.000.002/08/18THURSDAY
No Dredging00.00.000.002/09/18FRIDAY
No Dredging00.0Agua Hedionda0.002/10/18SATURDAY
No Dredging00.0Agua Hedionda0.002/11/18SUNDAY
No Dredging00.0Agua Hedionda0.002/12/18MONDAY
No Dredging00.0Agua Hedionda0.002/13/18TUESDAY
No Dredging00.0Agua Hedionda0.002/14/18WEDNESDAY
No Dredging00.0Agua Hedionda0.002/15/18THURSDAY
Middle Beach250250.0Agua Hedionda0.802/16/18FRIDAY
Middle Beach2500.0Agua Hedionda0.002/17/18SATURDAY
Middle Beach2500.0Agua Hedionda0.002/18/18SUNDAY
Middle Beach1,8751,625.0Agua Hedionda5.402/19/18MONDAY
Middle Beach5,1083,233.3Agua Hedionda8.102/20/18TUESDAY
Middle Beach9,7174,608.3Agua Hedionda9.202/21/18WEDNESDAY
Middle Beach13,9004,183.3Agua Hedionda8.402/22/18THURSDAY
Middle Beach18,0084,108.3Agua Hedionda8.202/23/18FRIDAY
Middle Beach22,4084,400.0Agua Hedionda8.802/24/18SATURDAY
Middle Beach22,4080.0Agua Hedionda0.002/25/18SUNDAY
Middle Beach26,6424,233.3Agua Hedionda8.502/26/18MONDAY
Middle Beach31,6505,008.3Agua Hedionda10.002/27/18TUESDAY
Middle Beach35,1253,475.0Agua Hedionda7.002/28/18WEDNESDAY
Middle Beach38,8253,700.0Agua Hedionda7.403/01/18THURSDAY
Middle Beach43,9255,100.0Agua Hedionda10.203/02/18FRIDAY
Page 1
04/14/18DateCDI Correspondence 180414a
Camenzind Dredging, Inc.
PIPELINE DISPOSAL DREDGING LOG
SPL-2001-00328-RRSPERMIT:AGUA HEDIONDA LAGOONPROJECT:
CARLSBAD BEACHESDISPOSAL SITE:
WDR-96-32RWQCB PermitEPISODE:
AREA
DISPOSAL
Volume
Cumlative
Volume
Estimated
QUADRANT
AREA DREDGED
OPERATION
TIME IN
DATEDAY
(cy) (cy)(see vicinity map)(Hours)
Middle Beach47,1003,175.0Agua Hedionda6.303/03/18SATURDAY
Middle Beach47,1000.0Agua Hedionda0.003/04/18SUNDAY
Middle Beach51,4924,391.7Agua Hedionda8.803/05/18MONDAY
Middle Beach53,9522,460.0Agua Hedionda6.103/06/18TUESDAY
Middle Beach58,1924,240.0Agua Hedionda10.603/07/18WEDNESDAY
Middle Beach62,4524,260.0Agua Hedionda10.703/08/18THURSDAY
Middle Beach66,6184,166.7Agua Hedionda10.403/09/18FRIDAY
Middle Beach70,1383,520.0Agua Hedionda8.803/10/18SATURDAY
Middle Beach70,1380.0Agua Hedionda0.003/11/18SUNDAY
Middle Beach71,045906.7Agua Hedionda2.303/12/18MONDAY
Middle Beach75,2654,220.0Agua Hedionda10.603/13/18TUESDAY
Middle Beach79,4524,186.7Agua Hedionda10.503/14/18WEDNESDAY
Middle Beach82,7053,253.3Agua Hedionda8.103/15/18THURSDAY
Middle Beach87,0654,360.0Agua Hedionda10.903/16/18FRIDAY
Middle Beach87,0650.0Agua Hedionda0.003/17/18SATURDAY
Middle Beach87,0650.0Agua Hedionda0.003/18/18SUNDAY
Middle Beach92,2655,200.0Agua Hedionda8.703/19/18MONDAY
Middle Beach96,1323,866.7Agua Hedionda7.703/20/18TUESDAY
Middle Beach102,3926,260.0Agua Hedionda10.403/21/18WEDNESDAY
Middle Beach107,6125,220.0Agua Hedionda8.703/22/18THURSDAY
Middle Beach113,3225,710.0Agua Hedionda9.503/23/18FRIDAY
Middle Beach113,3220.0Agua Hedionda0.003/24/18SATURDAY
Middle Beach113,3220.0Agua Hedionda0.003/25/18SUNDAY
Middle Beach119,2025,880.0Agua Hedionda9.803/26/18MONDAY
Middle Beach122,1422,940.0Agua Hedionda4.903/27/18TUESDAY
Middle Beach125,4523,310.0Agua Hedionda5.503/28/18WEDNESDAY
Middle Beach131,3225,870.0Agua Hedionda9.803/29/18THURSDAY
Middle Beach137,3025,980.0Agua Hedionda10.003/30/18FRIDAY
Page 2
04/14/18DateCDI Correspondence 180414a
Camenzind Dredging, Inc.
PIPELINE DISPOSAL DREDGING LOG
SPL-2001-00328-RRSPERMIT:AGUA HEDIONDA LAGOONPROJECT:
CARLSBAD BEACHESDISPOSAL SITE:
WDR-96-32RWQCB PermitEPISODE:
AREA
DISPOSAL
Volume
Cumlative
Volume
Estimated
QUADRANT
AREA DREDGED
OPERATION
TIME IN
DATEDAY
(cy) (cy)(see vicinity map)(Hours)
Middle Beach137,3020.0Agua Hedionda0.003/31/18SATURDAY
Middle Beach137,3020.0Agua Hedionda0.004/01/18SUNDAY
Middle Beach141,1723,870.0Agua Hedionda6.504/02/18MONDAY
South Beach148,0436,871.7Agua Hedionda9.804/03/18TUESDAY
South Beach150,5522,508.3Agua Hedionda3.604/04/18WEDNESDAY
South Beach157,9837,431.7Agua Hedionda10.604/05/18THURSDAY
South Beach165,8357,851.7Agua Hedionda11.204/06/18FRIDAY
South Beach165,8350.0Agua Hedionda0.004/07/18SATURDAY
South Beach165,8350.0Agua Hedionda0.004/08/18SUNDAY
South Beach172,5616,726.0Agua Hedionda8.904/09/18MONDAY
South Beach180,1107,549.3Agua Hedionda9.904/10/18TUESDAY
South Beach188,6228,512.0Agua Hedionda11.204/11/18WEDNESDAY
South Beach196,9578,334.7Agua Hedionda11.004/12/18THURSDAY
South Beach205,4828,524.7Agua Hedionda11.204/13/18FRIDAY
LAGOONAGUA HEDIONDADREDGINGOFEND
Page 3