HomeMy WebLinkAbout; Aviara Local Coastal Program- Permit Grading; Aviara Local Coastal Program- Permit Grading; 1991-11-01COASTAL COMMISSION
PERMIT No. 6-61-46 (A)
PHASE II
45 Day Winter Grading
Extension Request
NOVEMBER 1991
AVIARA
Prepared for:
AVIARA LAND ASSOCIATES LIMITED PARTNERSHIP
2011 Palomar Airport Road, Suite 206
Carlsbad, California 92009
TABLE OF CONTENTS
I. INTRODUCTION
II. NEED FOR WINTER GRADING EXTENSION
III. REQUEST FOR WINTER GRADING PERMIT.
IV. WINTER GRADING PROGRAM .
ARE A OF WINTER GRADING .
EROSION CONTROL PROVISIONS
• DESILTATION BASIN DESIGN .
• PHASE II WINTER GRADING EXHIBIT
V. CONCLUSION
ATTACHMENTS
ICG INCORPORATED
• P&D TECHNOLOGIES .
page 2
pageS
page 4
page 4
pageS
page 6
AVIARA
Phase II Winter Grading Extension Booklet
Prepared By:
PLANNING SYSTEMS
2111 Palomar Airport Road, Suite 100
Carlsbad, California 92009
(619) 931-0780
7 November 1991
#911046
/. INTRODUCTION
The Aviara Local Coastal Program (East Batiquitos Lagoon/Hunt Properties LCP) and coastal
permit (6-87-680) were approved by the Coastal Commission in April of 1988. The LCP uses
the City of Carlsbad's Master Plan as implementing ordinances.
Since project approval, the Commission has reviewed and approved a number of amendments
to the LCP and permit documents. Additionally, Aviara has occasionally provided the Com-
mission with updates on progress of master plan implementation relative to erosion control
and other matters.
A coastal permit for Phase II was issued on May 7,1991 (No. 6-911-46.) Grading was allowed
only during the period of April 1 through November 15.
Phase II is located along the western side of the Aviara Master Plan, and consists of single
family residential area and undisturbed, deed restricted, coastal resource areas. The site is 247
total acres and bounded by Alga Road on the north, residential and agricultural uses to the
east (outside of the Master Plan,) Batiquitos lagoon on the south and the Aviara/Four Seasons
Golf Course to the east.
Much of Phase II's mass grading has been completed. Some areas, including most of the areas
south of Batiquitos Drive, will not be graded until the spring of 1992. The coastal resource
areas will, of course, remain undisturbed permanently.
AVIARA LOCATION MAP
PHASE II
PACIFIC OCEAN
AVIARA
Page 2
J /. NEED FOR WINTER GRADING
As a result of a delay in achieving the city grading permit for Phase II, and a problem with the
quantity of reclaimed water utilized in the grading operation, grading of Phase II is behind
schedule.
Although the Phase n coastal permit was issued on May 7,1991, final engineering plans were
not signed by the City Engineer until some weeks later. Once grading did commence, the op-
eration immediately began to experience low reclaimed water volumes from the City's plant.
This resulted in a slower than anticipated grading operation. The water volume problem has
since been resolved.
Unfortunately, these problems have resulted in a circumstance where mitigation of the Phase
II ancient landslide problem cannot be fully corrected (the grading cannot be completed in the
landslide buttress area) during the existing (Nov. 15) grading season limit. The soils engineers
have concluded that the necessary stability factor must be achieved by full grading per the
approved plans (letter attached at end of this booklet.)
PHASE II LOCATION MAP
ANCENTT
LANDSUDE
AREA ^-PLANNING AREA
CTYPJ
WINTER GRADING AREAS
(TYPICAL SYMBOL)
FOUR SEASONS
HOTEL
PHASE II
Page 3
III. REQUEST FOR WINTER GRADING PERMIT
Aviara is requesting a 45 day exemption (from November 15 until December 31,1991) to the
winter grading prohibition contained in the Coastal Permit The purpose of the exemption is
to provide time to complete land stabilization work in the ancient landslide area. Grading will
be limited to a limited portion of Phase n and the grading program described herein. No sedi-
mentation of Batiquitos Lagoon or other coastal areas will result from this operation.
IV. WINTER GRADING PROGRAM
• AREA OF WINTER GRADING
Four specific areas of grading are proposed.
Three areas will be cut to provide fill for a single
fill site. The fill site is the location of the
landslide stabilization effort.
These areas are all located over 1/3 of a mile
from Batiquitos Lagoon, the prominent envi-
ronmental feature of the area and the ultimate
designation of the site's runoff. Sedimentatio n
and erosion control systems will be provided as
outlined below.
• EROSION CONTROL PROVISIONS
A tiered drainage and erosion control system
has been permanently installed. Extensive
temporary erosion control devices are also used.
Drainage and erosion control devices are cur-
rently in place and will be maintained through-
out grading operations. The comprehensive
program is demonstrated graphically on the
following page.
The tiered system employs the following de-
vices and techniques:
* Localized systems
- Surface grading and bladed swales
provide runoff control
- Check dams reduce runoff velocity
- Localized desiltation basins collect sedi-
mentation from runoff
* Off site systems
- Closed storm drains prevent erosion
- Open storm channels collect runoff and
prevent erosion
- Existing fully landscaped golf course
and mature tree groves prevent erosion
and filter runoff
- Batiquitos Drive (grading of which is
completed) is configured as a large dike,
separating winter grading areas from
Batiquitos Lagoon
* Project wide desilting structures
- Permanent desiltation basins at lagoo-
wetlands collect sedimentation
- Enclosed desiltation basin outflows dis-
charge water only
- Silt fences and energy dissipaters slow
discharge velocity
• DESILTATION BASIN DESIGN
The project wide desilta tion basin located within
Phase II is noteworthy as to its current size and
configuration. The basin has been constructed
temporarily in a size which greatly exceeds its
final design. The temporary configuration of
the basin provides a capacity of 11,120 cubic
yards (CY) where 860 CY is required, and an
area of 80,800 square feet (SF) where 13,160 SF
is required. Moreover, the required sizes are
based upon a 96.4 acre grading area, where
only 78.6 acres will be disturbed pursuant to
the revised Phase n mass grading plans.
The basin is oversized by a factor exceeding 5,
while the area of disturbance has been de-
creased by 23%. The project engineer has docu-
mented the basin's size in a letter
attached at the end of this booklet. A
AVIARA
Page 4
PHASE II WINTER GRADING EXHIBIT
PHASE II
WINTER GRADING
PROGRAM
NOV. 15 • DEC. 31, 1991
• COMMENCEMENT AFTE
BATIOUITOS LAGOON
\ LOCALIZED TEMPORARY DESILT BASIN
PERMANENT PROJECT DESILT BASIN
SECTION A
Page 5
V. CONCLUSION
• Certain unexpected delays in the anticipated grading program have been experienced.
• Aviara is requesting a 45 day exemption from the winter grading prohibition, from November
15th through December 31st, 1991.
• The purpose of the winter grading exemption is to complete landslide stabilization improve-
ments.
• Existing erosion control structures and devices will mitigate runoff and sedimentation. These
structures have effectively serviced the site for three years.
AVIARA
Page 6
ATTACHMENTS
The following letters, submitted by the geotechnical and civil engineer respectively, document to
the need for landslide stabilization and the size of the temporary desiltation basin.
S>n DiegoCounty OHIe*:
9740 Trad* Place.
Suit* 100
San Dirg'i
619536-110?
la« 619/S36-1306
Inland Empire OMce
1906 Orange Tree Lane.
Suite 240
Rrrtands. C» 92374
714/792-4222
lax 714/798-1644
Orange County Oirices
Construction Inspection
and Testing
2992 La Raima.
Suite A
Anaheim CA 92606
714<632?«80
la< 714/632-9209
Geolechnicat
15 Mason
Irvine. CA 92718
714/9518668
lai 714/951-7969
Coachella Valley Ollice:
77-775 Jackal Drive.
Suite C
Bermuda Dunes. CA 92201
619772-3162
la» 619.772 3184
Corporate Olfice
15 Mason
Irvine. CA 92718
7I4»95I 8G66
lai 714/951-7969
ICGincofyotiated
October 21, 1991
Aviara Land Associates
Limited Partnership
2011 Palomar Airport Road, Suite 206
Carlsbad, California 92130
Job No. 04-3179-012-00-00
Log No. 1-2151
Attention:
SUBJECT:
Gentlemen:
Mr. Curt Noland
EXTENDED GRADING OPERATIONS
PA 25 and 26N
Aviara, Phase 2
Carlsbad, California
It is our understanding that due to Costal Commission regulations grading operations for
Phase II in the vicinity of Planning Areas 25 and 26N at Aviara will be terminated on
November 15, 1991 for the winter season. As we all know these two planning areas are
in a very sensitive landslide area. If grading ends on November 15 is originally planned
these areas will not be near completion and the slope stabilization measures planned will
not be in place. In their present state these areas exhibit a factor of safety of between
1.2 and 1.5 which is considered stable for temporary conditions but not for long term.
It is our opinion that grading operations should continue in these areas after November
15 in order to enhance the stability of these two planning areas. Leaving these two areas
in a partially completed condition could, in the event of a long wet winter, result in
damage to the homes and property located at the top of the slide area.
Should any questions arise please contact our office.
Very truly yours,
ICG Incorporated
Anthony F. Belfast, P.E. 40333
Expiration Dale: 3-31-95
Chief Engineer
EJN/AFB/
(Votwrhnirnl Spfvi . Construction Inspection
PHASE II
Page?
401 W A" Situ*&HW2500San Diego. C* 92101FAX 619/234 3022
619/2324466
Planning
Engineering
Transportation
Environmental
fconomics
Landscape
Architecture
October 14, 1991 An Employee-Owned Company
OCT i 5
Mr. Curt Noland
Aviara Land Associates
2011 Palomar Airport Road
Suite 206
Carlsbad, California 92009
Dear Curt:
RE: AVIARA, DESILTING BASIN #5
Per your request I have reviewed the capacity of temporary desilting basin #5 within Phase II of
Aviara.
Due to the configuration of the basin, the resulting capacity of 11,120 CY for sediment and water
far exceeds the required amount of 860.2 CY as calculated in the desilling basin study prepared
by VTN Southwest. Inc., dated July 21, 1988 (pages 31-42). The same holds true for the basin
area capacity of 80,800 SF vs. only 13,160 SF required per the calculations.
The study was prepared using a worst case scenario where grading occurs simultaneously over
96.4 AC. The approved grading plans for Phase It mass excavation show a disturbed area of
78.6 AC, a 23% decrease from the original assumption.
It. therefore, seems that the basin was sized larger than required for the temporary condition and
should accommodate the grading effort now underway on Phase II.
If you have any questions concerning the above, please call.
Sincerely,
P&D TECHNOLOGIES
JohK W. Norman
^Director of Engineering
JWN:pc
AVIARA
Page 8