HomeMy WebLinkAbout; Bristol Cove Drainage Area Study; Bristol Cove Drainage Area Study; 1973-06-01BRISTOL COVE
DRAINAGE AREA STUDY
June, 1973
SHUIRMAN • SIMPSON
r irr
CONSULTING CIVIL ENGINEERS
NEWPORT CENTER BUILDING
359 San Miguel Drive
Newport Beach, Celifornis 9266O
BRISTOL COVE
DRAINAGE AREA STUDY
I. Purpose of Report
Substantial quantities of silt are deposited during
rainstorms in the northerly portion of the improved channel
at Bristol Cove at the outlet of the 60" diameter storm drain
pipe. The deposition of the silt causes the formation of a
small bar or delta that renders the northerly portion of the
channel unusable. The periodic removal of the deposited silt
is expensive because it is all or partially under water
necessitating the use of a drag line.
The purpose of this report is therefore as follows:
1. Advise as to the scope of the problem.
2. Comment on alternative solutions to the problem.
3. Provide cost estimates for the alternative
solutions.
4. Recommend a solution for review and consideration.
II. Field Investigations
Two separate field trips were made to observe the
condition in the channel at the outlet of the 60" storm drain
and to search for sources of erosion within the watershed
that were contributing to the problem. On the second trip we
were accompanied by Mr. Hunter Cook, City Engineer of the
City of Carlsbad.
O
- 1 -
On our first trip we were not able to observe the
extent of the silt in the channel because of the high tide
stage. However, on the second trip the tide was out and
the delta formed by the silt was quite apparent. No measure-
ments were taken, but from observation it is estimated that
the quantity of silt in the channel at the present time is
in excess of 5,000 cubic yards. The extent of the delta or
bar renders the northerly 100 feet or so of the channel
unusable for boat storage.
The entire watershed is overlain with a highly erod-
able marine terrace deposit. Practically all erosion
observed of any appreciable amount is located on presently
undeveloped property. The principal locations of erosion
within the watershed are shown on the enclosed map and are
designated as A, B, C, and D. These are locations where
it is obvious that substantial erosion has occurred within
the last few years. In addition to these point sources of
erosion there is", general overall surface erosion throughout
the watershed. However, the general surface erosion that
contributes most to the problem in Bristol Cove is attribut-
able to the steeper slopes of the undeveloped areas in the
southeasterly portion of the watershed. Another source of
silt from erosion is the unimproved channel on the westerly
side of Park Drive northerly of Adams Street. However,
/^\ except in the vicinity of Point C, the total amount,of erosion
for this reach of unimproved channel does not appear to be
substantial.
III. .Principal Points of Erosion
A general description of principal points of erosion is
as follows:
Point A: The erosion at this location is at the head
of a natural channel. This is a natural process where major
erosion normally occurs in the uppermost portions of a canyon
where the slopes are steepest. There does not appear to be
any recent man-made improvements that are contributing factors.
Point B: This again, like Point A, is erosion occurring
at the head end of a natural channel. However, the slope of
this channel is substantially less than the channel in which
Point A is located. Point B is located immediately downstream
from the outlet^of a storm drain, and the water discharging
from this storm drain at a high rate of velocity is probably
the major cause of this erosion.
Point C; This erosion is occurring in the natural channel
on the" westerly side of Park Drive immediately downstream from
a culvert that crosses beneath a private driveway. Again, as
at Point B, the increased velocity from the culvert discharge
is a major contributing factor. The erosion at this point,
unlike that at Points A and B, if allowed to continue will
undermine the existing culvert causing a washout of the drive-
way and could also progress to the point where Park Drive
could be undermined.
Point D: The erosion at this point is occurring in a
natural channel at a point in the change of grade of the flow
line of the channel. Upstream from Point B, the slope of the
channel is relatively flat as it traverses a grassy meadow.
Downstream from Point D, the channel is substantially steeper.
The channel through the grassy meadow is apparently stable
under the velocities occurring, while the channel:downstream
is not stable when subjected to the increased velocities. If
no corrective measures are taken at this location, the erosion
will continue to progress upstream into the grassy meadow.
There are no man-made improvements in the immediate vicinity
of this erosion that are contributing factors. However, the
new subdivisions and other improvements upstream have
undoubtedly increased the storm flow in this channel which
results in a greater rate of erosion.
IV. Theoretical Quantities of Silt
In order to determine the magnitude of the erosion that
might be occurring within the watershed, calculations were
made based on the methods described in "Debris Dams and Basins"
prepared by the Los Angeles County Flood Control District.
The amount of debris and silt that can be expected varies widely
- 4 -
from one watershed to another depending upon soil types,
slopes and amount and type of development. The area of the
watershed tributary to Bristol Cove is approximately 0.7
square miles. Based on these calculations, it appears that
the average annual quantity of debris and silt could be
approximately 19,000 cubic yards. A debris basin designed
to intercept this estimated total quantity of debris and
silt, if it has surface area of one acre, would need to have
an overall average depth of 12 feet.
V. Corrective Measures
A. Erosion at Points A and B
Tentative Maps 72-18 and 72-28 have been filed with
the City of Carlsbad. The erosion at Points A and B is
included within these proposed subdivisions, and the grading
and storm drains proposed within these developments will
essentially eliminate all of the erosion that is occurring at
these points. However, the grading and drainage systems for
these proposed developments should be carefully reviewed to
make certain that new points of erosion are not created. For
instance, if any storm drains are discharged into the channel
downstream from Point A, the City should require that properly
designed energy dissipators are placed on the outlets in order
to minimize erosion in the downstream channel. Also, steps
should be taken to require that adequate interim desilting
O
basins be installed downstream to intercept any silt from
grading operations that are performed during the winter or
before adequate planting can be established on the constructed
slopes.
If these subdivisions are constructed to generally
accepted standards, then for all intents and purposes there
will be very little erosion occurring in the watershed easterly
of Park Drive that will contribute to the problem at Bristol
Cove.
These:two subdivisions, however, will cause an increase
in the quantity and concentration of storm runoff. This
increased flow and concentration will manifest itself in
additional erosion in the vicinity of Point C unless protec-
v_y tive devices are constructed.
B. Point_C
The erosion that is occurring at Point C can be
corrected in one of two ways. One or more check dams can be
constructed downstream of the existing culvert outlet, or the
Master Plan underground storm drain could be constructed along
Park Drive from Adams Street to Hillside Drive. .The Master
Plan storm drain that is required to handle the design flows
will need to be 48" in diameter. This drain could either be
located along the existing channel or within the present or
future right-of-way of Park Drive. The flow line of the
O — 6 —
existing channel is located approximately 60 to 80 feet
westerly of the easterly right-of-way line of Park Drive.
A storm drain of this importance should be located entirely
within the future right-of-way of Park Drive. It is our
understanding that the City contemplates a widening and
improvement of Park Drive sometime in the future. This
improvement would probably include the construction of the
parallel storm drain. The 48" storm drain from the upstream
end of the 72" pipe at Adams Street to the downstream end of
the 60" pipe under Park Drive southerly of ,Hillside Drive
would have a length of approximately 930 feet. It is esti-
mated that the cost of this drain will be approximately
$50/000. This storm drain should not be constructed unless
the future improvement of Park Drive is considered in the
design.
The alternative to the construction of the underground
storm drain would be the installation of one or more combina-
tion check dams and desilting basins downstream of Point C.
The nature of these check dams could vary from structures
constructed of concrete to more temporary devices constructed
of riprap or timber. The type of structure should be consist-
ent with the life expectancy which, in this case, will be
until the underground storm drain is constructed.
Plate I is a sketch showing a suggested check dam and
desilting basin that could be constructed downstream of
- 7 -
Point C. The basin as shown would have a capacity of approxi-
mately 6,000 C.Y. The material for constructing the dam
should be obtained on-site within the proposed basin area.
This would increase the capacity to about 9,000 C.Y. The
estimated cost of the basin is $10,000.
Although the basin is located on private property, it
may be possible to obtain permission from the owner for a
temporary permit for use of the area until ;such time as
development occurs. This basin would halt the continuing
erosion as well as virtually eliminate the -silting problem
in the channel.
C. Point D
The only practical solution for correcting the
erosion that is occurring at Point D would be the construc-
tion of a combination check dam and desilting basin. The
construction of the Master Plan storm drain at this location
would not be practical until development occurs because the
location of the underground storm drain would need to be
compatible with the contemplated development.
Plate II is a sketch showing a suggested check
dam and desilting basin.that could be constructed downstream
of Point D. The basin as shown would have a capacity of
approximately 2,700 C.Y. If the material for constructing
the dam is obtained from within the basin area, then the
- 8 -
capacity could be increased, to approximately 5,200 C.Y.
The estimated cost of the basin is $10,000.
The construction of the basin will effectively
halt the erosion that is occurring at this location and
will decrease the quantity of silt reaching the channel
at Bristol Cove.
The erosion that is occurring at Point D is on
private property, and therefore the construction of any
erosion control devices would need to have the concur-
rence of the property owner. However, since the erosion
is causing serious damage to the property, the owner
should be cooperative. Whether or not the City can require
the private property owner to construct and pay for the
necessary erosion control devices has not been explored.
D. Existing 60" Bypass Along Westerly Side of Channel
The 60" bypass which was constructed at the time of
the channel improvement apparently is presently inoperative
due to siltation. If upstream erosion were controlled to the
point to where the silt load was substantially reduced at the
upstream end of this pipe, then it might be possible to bypass
some of the flow through this pipe that is presently discharg-
ing into the northerly end of the channel. However, this
pipe, even if free of siltation, has a limited capacity. At
low tide this pipe can handle approximately 170 cfs and at
O
mean high tide, approximately 105 cfs. The design flow is
approximately 343 cfs. Since the design flow is so much
larger than the capacity of this pipe, it does not appear
feasible to make use of this facility in correcting the silt-
ing problem that is occurring at'the northerly end of the
channel.
E. Debris Basin at Northerly End of the Channel
The possibility of constructing a permanent debris
basin in the vicinity of the outlet of the 60" pipe at the
northerly end of the channel was investigated. It does not
appear feasible to construct this debris basin immediately
downstream of the existing outlet within the confines of the
channel. In order that equipment could work within the debris
^^ 'basin in a relatively dry condition, the floor of the basin
would need to be at or above mean sea level. Since the
bottom of the channel is designed to be at an elevation of
-9, the outer walls of the basin would need to be 17 or 18
feet high. In addition to the extremely high cost of con-
structing a basin at this location, a large portion of the
existing channel would also be obstructed.
Enclosed in this report are sketches on Plates III
and IV showing a plan and section for a basin constructed
adjacent to the channel in Lots 42 and 43. If these lots are
still controlled by the developer, a temporary or permanent
- 10 -
basin could be constructed at this location at a cost substan-
tially less than at a location within the channel. The basin,
as shown, would have a capacity of 800 cubic yards and would
cost approximately $40,000.
The basin construction at the location shown is
expensive because of the restricted site that necessitates
the use of concrete retaining walls around the perimeter.
A less restrictive site could result in a substantial cost
reduction. The locations suggested at Points C and D result
in less expensive basin construction and substantially
greater capacity.
If another location cannot be obtained for the
construction of a desilting basin, then it may be more economi-
cal to continue periodically removing the silt from the channel.
A basin constructed with a concrete floor, as
suggested in the sketch, could be cleaned periodically by
loading the material into trucks with a front end loader..
The cost of loading and transporting the material to a dis-
posal area will cost from $1.00 to $1.50 per cubic yard,
depending upon the length of haul. A portion of this cost
might be recoverable from the disposal site.
VI. Recommendations .
1. Construct temporary check dams at Point D.
2. Construct temporary check dams at Point C.
- 11 -
o
o
3. Impose requirements on the development of Tenta-
tive Maps 72-18 and 72-28 to insure that downstream erosion
is prevented.
4. Delay the construction of the debris basin at the
northerly end of the channel until one year after Recommenda-
tions 1, 2 and 3 above have been put into effect. After
this time, consider the construction of the desilting basin
if warranted by the quantity of siltation that is still
occurring.
*******
- 12
o
o
o
o
OKz
Q
HU