Monthly Status Report
April 2006
Prepared by Dudek & Associates, Inc.
DUDEK
& ASSOCIATES, INC.
SCORECARD
Mole I'ar lloie BackTee Par
1 435 4 10 Ul, 4
2 377 4 11 ;T. 4
3 4i: 4 12 436 4
4 3 13 342 4
5 584 5 14 1.10 3
6 440 4 15 541 5
7 5 1ft 540 5
8 160 3 17 192 3
9 355 4 18 414 4
Oul 3512 3ft In ;; u 36
Oul 3512 36
Iblal 6846
CITY OF CARLSBAD MUNICIPAL GOLF COURSE
Table of Contents
Section 1:
Mass Grading Contract
^ Executive Summary
> Contract Status - Change Orders
^ Cash Flow Projection
> Project Schedule
> Potentiallssues
> Project Photographs
Section 2:
Golf Course Construction Contract
> Executive Summary
> Contract Status - Change Orders
> Cash Flow Projection
> Project Schedule
> Potentiallssues
> Project Photographs
Section 3:
Golf Course Buildings Contract
> Executive Summary
> Contract Status - Change Orders
> Cash Flow Projection
> Project Schedule
> Potential Issues
> Project Photographs
Section 4:
> Overall Golf Course Project Financials
Section 1 - Mass Grading
Contract No. 3972M
General Contractor:
Sema Construction
6 Orchard #150
Lake Forrest, CA 92630
Construction Start Date:
September 8, 2005
DUDEK
& ASSOCIATES, INC,
City of Cadsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Executive Summary
Work Summary for April
The Grading Contractor is essentiaUy complete with the contract work and continues to
complete the punchlist items. The Contractor has completed approximately half of the items on
the list with the remaining items scheduled for completion in May.
Work on the Cribwall for the West Industrial Pad continues to be slow with completion now
scheduled for May.
Planned work for the month of May
• Complete the Cribwall at the West Industrial Pad.
• Continue with Punchlist work and close-out procedures.
Contract Status -Change Orders
A draft of contract Change Order (No.7) was prepared for review in AprU and includes several
contract Bid Items that have exceeded their estimated quantities listed in the Bid Schedule. The
increase in quantities and cost were previously approved by the City Council in February 2006,
and now that the actual quantities have been exceeded, it's necessary to execute the Change
Order to unencumber the funds. This Change Order is listed in the report as pending until it's
executed.
Cash Flow Projection
With this project almost being complete there was no progress billing in AprU as there was very
little work done, except punchlist work. We anticipate that there will be a May progress biUing
and then a final billing in June for retention.
Project Schedule
Work is substantiaUy complete so there wUl be no further Baseline Schedule up-dates or 3-Week
look Ahead Schedules. The Project Team (CM, City and Contractor) continue to meet regularly
to discuss progress and schedule completion of the remaining Punchlist work activities and
closeout of the project.
There has been no further discussion regarding a time extension. Staff anticipates any time
extension requests to be negotiated with future Change Order requests.
Potential Issues
Last month we reported that the delay in securing funding for the CribwaU at the overflow
parking lot has made the work substantially more difficult and that Sema Construction will not
be doing the work. Staff is currently evaluating a Geogrid Retaining Wall which is currently
being priced by Jayne's Corporation. We hope to report on the cost in next month's report.
DUDEKI
& ASSOCIATES, INC.
City of Cadsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Sema Contract No 39721-1
Commercial Pad Crib Wall
04-28-06
DUDEK
& ASSOCIATES. INC.
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Project 7^39724 MASS GRADING
CONTRACT STATUS/CHANGE ORDERS
Original Contract Amount:
Approved Change Orders:
Revised Contract Amount:
Percent Change Orders (on Original Contract):
Potential Change Orders (Estimate):
Potential Revised Contract Amount:
7,721,463.48
2,827,918.43
10,549,381.91
26.39%
10,549,381.91
Description Approved
Projected Project
Total
C lange Orders $ 7,721,463.48
1 Remedial Grading ($2.22/yd.) $ 932,400.00 $ 8,653,863.48
2 Increase SWPPP Measures $ 825,413.10 $ 9,479,276.58
3 Cap Archeological Site/Creek Crossing $ 48,192.33 $ 9,527,468.91
4 PVC Pipe Change/Clearing/Boxes $ (7,254.00) $ 9,520,214.91
5 Additional Surveying $ 25,000.00 $ 9,545,214.91
6 Increase Compaction from 90"/o to 95% $ 224,000.00 S 9,769,214.91
7 Adjustments to estimated quantities to reflect the actual quantities of
materials installed in the field* $ 780,167.00 $ 10,549,381.91
8
Total Approved Change Orders: $ 2,827,918.43
Revised Contract Amount: $ 10,549,381.91
* Pending Final Execution
Potential Change Orders Estimate
Total Estimated Potential Changes: •S
Projected Budget (w/potential Changes): $ 10,549,381.91
City of Carlsbad Municipal Golf Course Project #3972
April 2006 Monthly Status Report
Municipal Golf Course Project 3972-1
Contract 1 - Mass Grading Cash Flow Projection
$2,500,000
$2,000,000
$1,500,000
$1,000,000
$500,000
f / y /
0 Monthly Projection
• Monthly Actual
City of Carlsbad Municiapl Golf Course Project #3972
April 2006 Monthly Status Report
Section 2 - Golf Course Construction
Contract No. 39721-2
General Contractor:
Wadsworth Golf Construction Company
600 N. 195'^ Avenue
Buckeye, AZ 85326
Construction Start Date:
March 1, 2006
DUDEK & ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Executive Summary
Work Summary for April
Wadsworth GoU Construction Company (Wadsworth) continues to make great progress
shaping and instaUing irrigation on the Golf Course. At the end of April Wadsworth has
completed fine-shaping of GoU IToles M through M7 and are currently working on the final Golf
Hole #18 and the Driving Range. Wadsworth continues to make progress installing the irrigation
system with Holes M through #13 nearing completion. The Architect made three site visits in
AprU and approved fine shaping of GoU Holes M through #17. Construction activities for the
month include the foUowing:
• Approval of fine shaping and Golf features for Golf Holes M through #17.
• Completion of the irrigation system for GoU Holes #1 through #14 - currently in the
flushing, cleaning and testing phase.
• InstaUed Parson's Rock WaUs on Hole #7, #10 & #13.
• Continued layout of hard lines for Turf and Rough areas.
• Installed Bunker Sand in Holes #4, #5 & #6.
• Began Lake Liner installation and Pump Station wet weUs.
• Began work on the Lake Waterfall feature.
Planned Work for May
• Completion of fine shaping of Hole #18 & Driving Range.
• Continue installation of the irrigation system Holes # 15 - #18.
• Continue with construction of Green's, Tee's and Bunker's.
• Begin installation of sod on Holes #5 & #6.
• Continue Lake Liner and Pump Station work.
• Continue WaterfaU construction on Lake for Holes #7, #10, #13 & #15.
• Continue Rock waU instaUation on GoU Course.
Contract Status- Change Orders
There have been several Potential Change Orders (PCO's) that have been previously discussed
verbaUy, and have now been submitted by the Contractor, and are currently under review. The
good news is that several of the PCO's are credits and offset additional cost items. Several of the
PCO's wUl be converted to contract Change Orders next month, and submitted for execution.
Cash Flow Projection
Actual cash flow has outpaced projections partially due to the fact that Wadsworth has made
great progress fine shaping the GoU Course and installing the irrigation system. Based on
Wadsworth's schedule we expect this trend to continue.
DUDEK
& ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Project Schedule
Wadsworth appears to be ahead of schedule according to their Baseline Schedule. The key
mUestone worth watching next month wiU be the instaUation of sod on the GoU Course, which is
scheduled for mid-May. At this point Wadsworth wiU meet this schedule.
Potential Issues
• None to report.
DUDEK
& ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Grass Planting Equipment
04-04-06
Hole # 5
Greg Nash Reviewing Final Bunker Shaping
04-10-06
& ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
DUDEI^
Hole # 4
Typical Reclaimed Water Mainline InstaUation
04-12-06
Hole # 4
Typical Potable Water Green's Sprinkler Head InstaUation
04-12-06
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Hole # 7
Water Fall Construction
04-27-06
IDUDEKI
Hole #18
Irrigation Lake Liner InstaUation
04-27-06
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Project #3972-2 GOLF COURSE CONSTRUCTION
CONTRACT STATUS/CHANGE ORDERS
Original Contract Amount:
Approved Change Orders:
Revised Contract Amount:
Percent Change Orders (on Original Contract):
Potential Change Orders (Estimate):
Potential Revised Contract Amount:
$ 16,727,761.00
$
$ 16,727,761.00
$ (17,399.00)
$ 16,710,362.00
Description Approved
Projected Project
Total
C lange Orders $ 16,727,761.00
Total Approved Change Orders: $
Revised Contract Amount: $ 16,727,761.00
* Pending Final Execution
Potential Change Orders Estimate
Irrigation &r Pump Station Changes $ (150,000.00)
Drainage Pipe Change $ 125,000.00
Concrete Path Fibermesh $ (30,399.00)
Reshaping of Hole #7 $ 37,320.00
clubhouse Parking Lot Water Main Revisions to Relocate Abo\'e Ground Double Check Vah'e Assembly $ 30,000.00
Additional Bunker Sand Work $ 23,928.00
Revise Grassing/Seed Placing .? (73,598.00)
Installation of Lateral Sewer Line from Comfort Station A' to Maintanence Building $ 20,350.00
Total Estimated Potential Clianges: $ (17,399.00)
Projected Budget (w/potential Changes): $ 16,710,362.00
City of Carfsbad Municipal Golf Course Project #3972
April 2006 Monthly Status Report
Municipal Golf Course Project 3972-2
Contract 2 - Golf Course Cash Flow Projection
$2,500,000
$2,000,000
$1,500,000
$1,000,000
$500,000
$- -
# # cs^*^
y y y' y y> y> ^ y J ^^"^ ^<f^ ^f
I Monthly Projection
I Monthly Actual
City of Carlsbad Municiapl Golf Course Project #3972
April 2006 Monthly Status Report
10 Task Name Duration Start Finish
0 Wadsworth Revised 03-261 days Wed 3/1/06 Wed 2/28/07
y MoWllzatton 14 days Wed 3/1/06 Mon 3/20/06
- 2 Shaping 9S days Wed 3/8(06 Tue 7/18/06
3 Hcdel 5 days Wed 3/8rtl6 TUB 3/14/06 ;
4 h4olee Sdays Wed 3/15/06 Tue 3/21/06 :
5 Ho)o9 Sdays Wed 3/22/06 Tue 3/28/06
"6 Hote 6 Sdays Wed 3/29/06 Tue 4/4^6
7 Hote 5 S days Wed 4/SrtD6 Tue 4/11/06
8 Hole 4 5 days Wed 4/12/06 Tue 4/16/06
9 Hote3 Sdays Wed 4/19/06 Tue 4/25/06
10 Hote 2 Sdays Wed 4/26/06 Tue 5/2«6
H Hole 7 5 days Wed 5/3/06 Tue S/9/06
12 Driving Range Sdays Wed 5/10/06 Tue S/16/06
13 ; Hole 16 Sdays Wed 5/17/06 Tue 5/23/06
14 Hote 17 Sdays Wed 5/2*06 Tue 5/30/06
15 Hote IB 5 days Wed 5/31/06 Tue 6/6/06
16 Hote 11 5 days Wed 6/7/06 Tue 6/13/06
t7 i HOelO Sdays Wed 6/14/06 Tue 6/20/06
IB Hcrie12 Sdays Wed 6/21/06 Tue 6/27/06
19 Hotels Sdays Wed 6/26/06 Tue 7/4/06
20 Hote 14 S days Wed 7/5/06 Tue 7/11/06
21 Hotels Sdays Wed 7/12/06 Tue 7/18/06
~~22 Clubhouse Water Line todays Tue 3/21/06 Mon 4/3/06
Irrigation 9G days Wed 3/1B/06 Tue 7/25/06
24 Hote 1 Sdays Wed yi5!06 Tue 3/21/06
~~25~ Hole 8 Sdays Wed 3/22/06 Tue 3/28/06
26 Holes Sdays Wed 3/29/06 Tue 4/4/06
27 Hote 6 Sdays Wed4re'06 Tue 4.11 /oe
23 Hote 5 5 days Wed 4/12/06 Tue 4/18/06
29 Hote 4 Wed 4/19/06 Tue 4/25/06
30 Hote3 Sdays Wed 4/26/06 Tue5/2W
31 Hote2 Sdays WedS™36 Tue 5/9/06
— Hole 7 Sdays Wed 5/10/06 Tue S/16/06
33 Driving Range Sdays Wed 5/17/06 Tue 5/23/06
34 Hotels Sdays Wed S/24/06 Tue S'30/06
35 Hote 17 Sdays Wed 5/31/06 Tue 6/6/06
36 Hole 18 Sdays Wed 6/7/06 Tue 6'13/06
37 Holell Sdays Wed 6/14/06 Tue 6/20)06
—3j—i Hole 10 Sdays Wed 6/21/06 Tue 6/27/06
39 Hote 12 Sdays Wed 6/28/06 Tue 7/4/06
40 Hote 13 Sdays Wed7/s™ Tue 7/11/06
" "41" • Hote14 S days Wed 7/12^6 Tue 7/18/06
Hotels Sdays Wed 7/19/06 Tue 7/25/06
43 l^akes / Water Features Mdays Mon 4/3/Ofi Fr) 8/4/06
44 Lake at Hote 7 30 days Mon 4/3/06 Ftl S/12i06
45 Water Feature Hole 7 30 days MonS/1S/06 Fri 6/23/06
46 Irrigation Lake 30 daya Mon 6/26/06 Frl8/4(tl6
47 Pump Station ISU days Mon 4/17/oe Fri 11/10/06
52 Feature Construction 83 days Mon 4/17/06 Wed 8/9/06
53 Greens Construction 74 days Mon 4/17/06 Thu 7/27/06
_ Tee Conslruction 38 days Thu 6/1S/06 Mon 8/7/06
93 Artificial Tee Construct Sdays Thu 7/13/06 Wed 7/19/06
94 Bunkei Construction 36 days Mon 6/19/OE Wed 8/9/06
114 Landscaping - Tree Planti 95 days Wed4/12n>6 Tue 8/22/06
" r34~" Bridges B - E 49 days Ttiu 6/8/06 Tue 6/IS/06
139 Cart Paths 6S days Wed S/17/06 Wed 8/16/06
146 Brkige A - Over Road Cross 75 days Wed 3/1/06 Tue 6/13/06
147 i Bridge A 106 days Wed 4/5/06 Wed 8/30/06
169 Landscaping - Reveg & M 98 days Mon 6/13/06 Wed 10/25/06
" 169 Rock Stope Retaining Wa 72 days Mon 4/17/06 Tue 7/25/06
" 193 • Cart Protection Fence 21 days Mon 5/15/06 Mon 6/12/06
IM" Trail Head Mini Park 21 days Thu 6115106 Thu 7/13/06
195 Driving Range Lighting IS days Wed SrZ4l06 Tue 6/13/06
196 Palomar Airport Rd Improve 21 days Mar. 7117106 Mon B/l 4/06
~197"-Grassing 97 days Mon 6/19/06 Tue 10/31/06
^17~^ Grassing Maintenance Pe 107 days FH 6/23/06 Mon 11/20/06
-•237'"' Landscaping • Maintenan 183 days Mon 6/19/06 Wed 2/28/07
; Apr '06 May '06 Jun '06
26 5 ( 2 f9 26 2 B 16 23 30 7 14 21 28 4
Jul '06 Aug '06 Sep '06
; 25 2 : 9 "• i6~\23 ^30 I "6""| "l3""["20 T'ZfT"^T ^7 j 24 ']
Nov '06 Dec '06 Jan '07 Feb '07
IS 22 29 5 12 19 26 3 • 10 17 24 31 7 14 21 28 4 11 16 25
Task
Split
Progress
Milestone
Summary
Project Summary
Exlernai Tasks
EKtemal Mlleetorte
Section 3 - Golf Course Buildings
Contract # 39721-3
General Contractor:
Jaynes Corporation
111 Elm Street, Fourth Floor
San Diego, CA 92101-2649
Construction Start Date:
November 1, 2005
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Executive Summary
Work Summary for April
Maintenance Building
The Contractor made good progress completing the interior and exterior structural elements
of the building including installation of the roof trusses. The buUding has been "Dryed-in"
thereby allowing the start of interior dry waUing. The Contractor also completed framing
with steel studs in the interior of the buHding and rough-in of the plumbing and electrical.
Clubhouse BuHding
As mentioned last month, the completion of the pre-cast deck over the lower building floor
allowed the Contractor to move forward with installing the structural elements for the second
floor. Most of the steel columns and beams have been set for the second story. The main steel
truss, which is an architectural focal point for the building, has been set and masonry block for
the two octagon towers are complete. Steel stud framing for the second floor walls will begin
shortly.
Planned work for May
Maintenance Buflding
• Begin metal Roofing System.
• Continue with instaUation of interior framing.
• Complete instaUation of interior rough plumbing and electrical.
• Continue with exterior underground piping.
• Begin exterior EFIS plastering.
Clubhouse BuUding
• Continue with upper slab buUding footings.
• Continue with exterior underground piping.
• Complete upper floor structural steel posts and columns.
• Continue with Half-Way House.
• Continue work on Comfort Stations "A" and "B".
• Begin second floor metal waU stud framing.
Contract Status-Change Orders
Change Order No. 1 has been prepared and routed for review, ft contains nine items for an
estimated total of $115,023 representing 1% of the overaU contract value. There has been several
other potential Change Order Requests (PCO's) that are currently under review by Staff and wiU
result in the preparation of Change Order No.2 next month.
DUDEKI
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 3972
Apnl 2006 Monthly Status Report
Cash Flow^ Projection
When averaged over the first five months of the contract actual cash flow met projections. The
CM Staff expects this trend to continue through-out the remainder of the project.
Project schedule
The Contractor provided a schedule up-date through April 2006, which shows they're about four
weeks behind schedule. A meeting was conducted between the Contractor and CM Staff to
review progress, confirm dates, and discuss delays and ways to expedite the project. One key
item will be the delivery of the trusses for the second floor. If this can be expedited and installed
earlier than estimated the Contractor can pick-up some time on the overaU schedule. We'U report
on this issue next month.
Potential Issues
The potential issue mentioned last month regarding the wrong structural bid set is closer to
being resolved regarding both time and schedule impacts. The Contractor has submitted three
Potential Change Order requests from their structural metal supplier and Framing Contractor for
a total amount of $95,000, which is currently under review by the CM Team.
DUDEK
& ASSOCIATES, INC.
City of Cartsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Clubhouse Upper Level
Start of 1st. Floor Octagon
4-10-06
DUDEK
&ASSOCL\TES,lNC.
Clubhouse Upper Level - Grouting 1st. Lift Elevator & StairweU
4-12-06
City of Cartsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Clubhouse Structural Steel Going Up
4-18-06
Clubhouse Fireplace
4-24-06
DUDEK
&ASSOCL\TES, INC.
City of Cartsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
IBHilHHHHHHBiHH
Clubhouse
4-28-06
DUDEK
&ASSOCL?LTES, INC.
Maintenance BuUding
4-24-06
City of Carisbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Project #3972-3 GOLF COURSE BUILDINGS
CONTRACT STATUS/CHANGE ORDERS
Original Contract Amount;
Approved Change Orders:
Revised Contract Amount:
Percent Change Orders (on Original Contract):
Potential Change Orders (Estimate):
Potential Revised Contract Amount:
$ 10,660,864.00
$
$ 10,660,864.00
$ 114,792.00
$ 10,775,656.00
Description Approved
Projected Project
Total
C lange Orders $ 10,660,864.00
Total Approved Change Orders: $
Revised Contract Amount: $ 10,660,864.00
* Pending Final Execution
Potential Change Orders Estimate
Elevator Modification to Hole less $ 2,000.00
Parking Lot Structural Changes $ 63,063.00
Delta 8 Structural Changes $ 38,050.00
Additional Concrete for Stepped Footing $ J,060.00
Demo Rock and Perineter Wall Footing at Maintenance Building $ J,0J200
Duct Above West Side of Clubhouse Mechanical Room Door $ 436.00
H-Vac Relocation $ 1,693.00
Modify Switchgear with Two Electric Meters at Halfway House $ 7,478.00
Total Estimated Potential Changes: $ 114,792.00
Projected Budget (w/potential Changes): $ 10,775,656.00
City of Carlsbad Municipal Golf Course Project #3972
April 2006 Monthly Status Report
Municipal Golf Course Project 3972-3
Contract 3 - Buildings Cash Flow Projection
$1,200,000
$1,000,000
$800,000
$600,000
$400,000
$200,000
$-
^ ^ ^# 4
0 Monthly Projection
• Monthly Actual
City of Carlsbad Municiapl Golf Course Project #3972
April 2006 Monthly Status Report
Carlsbad Golf Course Buildings Look Ahead Schedule
Pending Excess Dirt removal and new loG IInspection Required
Activity Planned
Weekend or Holiday
Section 4
Overall Golf Course Project Financials
Contract 7^ 3972M, 39721-2, and 39721-3
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report
Carlsbad Municipal Golf Course - Project 3972
Budget, Expenditures and Contracts through 4/30/2006
This table summarizes expenditures and contracts authorized as of the July 26, 2005 Agenda which approved the construction budget ofthe Golf Course in the amount
of $43,320,789.
Original budget and budget changes Original
Estimate Increases (necreases) Revised
Budget
Grading 7.721,463 S 2.055.005 S 9,776,468
Construction 16.727.761 .S 16.727.761
Buildings 10.661.052 .S 10.661.052
Construction contingency 1.755.514 2.936.700 (2.080.005) S 2.612.209
Construction misc. 5.855.000 25.000 S 5.880.000
Grow in/pre opening costs 1.100.000 $ 1.100.000
Start up costs 1.500.000 S 1.500.000
Total Estimated Cost $ 45,320.790 $ 5,016,705 i (2,080.005) $ 48.257.490
A B c D E
EXPENDITURES / Budget Total Contract Expenditures Contract Remaining
CONTRACTS Budget / Oibligation Expenditures Balance Budget
(A - C ' O)
* Grading - SEMA Construction (VS Bank-Escrow) $ 9,776,468 9.776,468 9.759,787 16.681
* Construction - Wadsworth (Califomia Bank & Trust) 16.727,761 16.727761 1.511.101 15,216.660 -
* Buildings - Jaynes Corporations (Califomia Bank) 10,661,052 10.661.052 4.337.765 6.323.287 -
Contingency 2,612,209 2.612.209 2.612.209
Subtotal Construction 39.777.490 39,777.490 15.608.653 21.556.628 2,612,209
* Construction management & miscellaneous 2.315,000
Dudek 1.500.000 493.043 1.006.957
* Geotechnical testing (I) 150,000
TJ Dixon & James Nelson (Artwork) 128.000 70.400 57.600
Simon Wong (inspection) 1,600 968 632
Engineering overhead 47.958 47.958
Construction Analysts 2.880 2.880
Misc. (shipping, copies, etc) 46.246 46.246
VVater Meters (estimate not in original budget) 500.000 500.000
(2) Mark Mojado (San Louis Rey Band of Indians) 25.000 20.330 4.670
Testing Engineers 55.000 26.086 2S,9|.|
Subtotal construction management/support 2,465.000 2.306.684 707,910 1.598,773 158,316
* Design Team - construction phase services 250.000 230,000
Greg Nash 75.000 31.600 41.400 (75.000)
Douglas Frederikson Architects 85.000 19.884 65.116 (85.000)
* Environmental monitoring and special studies 350,000 350.000 157.871 192.129 -
* Lltility fees 25.000 25.000
* SDG&E (Jndei^rounding 1,150,000 1.130,000
* Furniture Fixtures & Equipment 1,640.000 1.640,000
* Grow-In and Pre-opening maintenance 1.100,000 1.100,000
* Start-Up Budget to open and operate 1,500.000 1,300,000
Total Expenditures and Commitments $ 48,257,490 $ 42.594.174 $ 16.525,918 S > 23,436.046 $ 8,273,525
(1) Geotechnical testing is subcontracted by Dudek.
(2) From contingency.
City of Carlsbad Municipal Golf Course Project /^3972
April 2006 Monthly Status Report
Carlsbad Municipal Golf Course Project
Construction Contracts - Monthly Cash Flow Project
Cash Flow Projection by Month
Month
Mass Grading
Contract Billings
Golf Course Building
Monthly
Total
Cumulative
Total
September - 2005
October - 2005
November - 2005
December - 2005
January - 2006
February - 2006
March - 2006
April' 2006
May' 2006
June' 2006
July - 2006
August' 2006
September - 2006
October - 2006
November - 2006
December - 2006
January - 2007
February - 2007
March - 2007
1,700,000.00
1,100,000.00
1,500,000.00
1,500,000.00
900,000.00
500,000.00
521,463.48
300,000.00
700,000.00
1,000,000.00
1,500,000.00
2,000,000.00
2,000,000.00
2,500,000.00
2,500,000.00
1,000,000.00
1,000,000.00
1,000,000.00
1,000,000.00
727,761.00
500,000.00
1,100,000.00
1,100,000.00
800,000.00
800,000.00
1,000,000.00
1,200,000.00
1,000,000.00
1,000,000.00
800,000.00
700,000.00
660,864.00
1,700,000.00
1,100,000.00
2,000,000.00
2,600,000.00
2,000,000.00
1,600,000.00
2,021,463.48
2,000,000.00
2,700,000.00
3,000,000.00
3,000,000.00
3,300,000.00
3,200,000.00
1,660,864.00
1,000,000.00
1,000,000.00
1,000,000.00
727,761.00
1,700,000.00
2,800,000.00
4,800,000.00
7,400,000.00
9,400,000.00
11,000,000.00
13,021,463.48
15,021,463.48
17,721,463.48
20,721,463.48
23,721,463.48
27,021,463.48
30,221,463.48
31,882,327.48
32,882,327.48
33,882,327.48
34,882,327.48
35,610,088.48
35,610,088.48
35,610,088.48
35,610,088.48
35,610,088.48
35,610,088.48
Totals: $ 7,721,463.48 $ 17,227,761.00
Contract Values:
1. Mass Grading: $ 7,721,463.48
2. Golf Course: $ 17,227,761.00
3. Buildings; $ 10,660,864.00
City of Carlsbad Municipal Golf Course Project # 3972
April 2006 Monthly Status Report