City of Carlsbad
Municipal Golf Course
• Project # 39721
Monthly Status Report
February 2006
Prepared by Dudek & Associates, Inc.
DUDEK
& ASSOCIATES, INC.
SCORECARD
Hole BackTee Par Mole Back tee Par
1 4i} 4 10 346 4
2 377 4 II 393 4
3 412 4 12 436 4
4 222 13 342 4
5 -.S4 5 14 130 3
6 440 4 15 541 5
7 527 5 16 Ml)
8 160 3 17 h):
•> 355 4 18 414 4
Out .1512 36 In 3334 1(,
Oul 3512 36
Total 6846 72
CITY OF CARLSBAD MUNICIPAL GOLF COURSE
Table of Contents
Section 1:
Mass Grading Contract
> Executive Summary
> Contract Status - Change Orders
> Cash Flow Projection
> Project Schedule
> Potential Issues
> Project Photographs
Section 2:
Golf Course Construction Contract
> Executive Summary
> Contract Status - Change Orders
> Cash Flow Projection
> Project Schedule
> Potential Issues
> Project Photographs
Section 3:
Golf Course Buildings Contract
Q > Executive Summary
> Contract Status - Change Orders
> Cash Flow Projection
> Project Schedule
> Potential Issues
> Project Photographs
Section 4:
> Overall Golf Course Project Financials
Section 1 - Mass Grading
Contract No. 3972M
General Contractor:
Sema Construction
6 Orchard M50
Lake Forrest, CA 92630
Construction Start Date:
September 8, 2005
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Executive Summary
Work Summary for February
The Contractor continued to complete "Final Rough-Shaping" grading activities around the Golf
Course. The Contractor is down to a skeleton crew and only four pieces of equipment, two
dozers, one scraper and one excavator. The Golf Course Architect made two site visits in
February and approved Golf Idoles ^ 1 through 14. Subsequently, these holes were turned over to
Wadsworth Golf Construction Company for fine shaping and installation of the Irrigation
System.
The Contractor is in the process of finalizing the contract and will be concentrating on
completing punch-list items during the upcoming month. Work on the Cribwall for the West
Industrial Pad has been slower than expected and may extend into early April. The Contractor
continues to maintain the site's SWPPP and BMP measures for control of erosion. Fortunately,
there was little precipitation in February.
Planned Work for month of February
• Complete rough shaping and acceptance of the remaining Golf Holes # 15,16,17, and 18.
• Complete the Cribwall at the West Industrial Pad.
• Complete on-site Storm Drain System.
• Start Punch-list and Contract Close-out procedures.
Contract Status - Change Orders
No new change orders were prepared during February and there are no new potential change
requests .submitted by the Contractor. Change Order No.'s 1, 2 and 3 have been fully executed
and included on the Contractor's February's progress billing request. Change Order No.'s 4, 5,
and 6 have been prepared and should be fuUy executed in March. There has been no progress on
the two "Potential" Change Orders shown on the report. These two items will likely be resolved
during final close-out of the project and prepared with the final balancing Change Order.
Cash Flow Projection
Actual expenditure for January was under the projection primarily due to the fact that actual
expenditures exceeded projections in the previous three months. However, actual expenditures
for February exceeded the projections because Change Order No.'s 1, 2 and 3 were fully executed
in February and billed by the Contractor. We expect this trend to continue in March as Change
Order No.'s 4, 5 and 6 are executed and billed.
Project Schedule
The Contractor is substantially complete with the Work having moved the bulk of the dirt.
Rough shaping of Golf Holes # 1 through 14 are complete and provides Wadsworth Golf with
enough area to continue their work without delay as their contract began March 1'*^ 2006. SEMA
DUDEK
& ASSOCIATES, INC
City of Cadsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
should complete rough shaping activities for the remaining four Golf Holes (15-18) in March and
wiU not impact Wadsworth Golf's construction schedule. Cribwall construction activities are
behind schedule and will most likely not be complete until early April. However, the good news
is that this work is out of the way of the other Contractors and will not impact their work.
There has been no further discussion regarding a time extension. Staff anticipates that any time
extension requests will be negotiated with future Change Order requests.
Potential Issues
The delay in securing funding for the Cribwall at the overflow parking lot has made the work
substantially more difficult. The quantity of earthwork now required to be moved to construct
the wall has increased substantially because the lot was previously graded by SEMA.
Consequently, an additional 40,000 yards of earth has to be moved, stockpiled and returned as
compacted backfill. This has added an additional $300,000 to the cost of the wall, which staff is
not prepared to recommend be spent at this time. Staff is evaluating other alternatives that will
be discussed in next month's report.
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Project #3972M MASS GRADING
CONTRACT STATUS/CHANGE ORDERS
Original Contract Amount:
Approved Change Orders:
Revised Contract Amount;
Percent Change Orders (on Original Contract):
Potential Change Orders (Estimate);
Potential Revised Contract Amount;
$
$
$
$
$
7,721,463.48
2,037,751.43
9,759,214.91
26.397o
732,368.00
10,491,582.91
Description Approved
Projected Project
Total
Change Orders $ 7,721,463.48
1 Remedial Grading ($2.22/yd.)* $ 932,400.00 $ 8,653,863.48
2 Increase SWPPP Measures* S 815,413.10 $ 9,469,276.58
) Cap Archeological Site/Creek Cros.sing* S 48,192.33 $ 9,517,468.91
4 PVC Pipe Change/Clearing/Boxes* S (7,254.00) $ 9,510,214.91
5 Additional Surveying* $ 25,000.00 $ 9,535,214.91
6 Increase Compaction from 907o to 95%* $ 224,000.00 $ 9,759,214.91
7
8
Total Approved Change Orders; $ 2,037,751.43
Revised Contract Amount: $ 9,759,214.91
* Pending Final Execution *
Potential Change Orders Estimate
*
CribwaU Quantity Increases .$ 501,368.00
*
Increase to the Export from East to VVest $ 231,000.00
* * * * * * * * * *
Total Estimated Potential Changes; $ 732,368.00
*
Projected Budget (w/potential Changes): $ 10,491,582.91
City of Carlsbad Municipal Golf Course Project #39721-1
February 2006 Monthly Status Report
Municipal Golf Course Project 39721-1,
Contract 1 - Mass Grading Cash Flow Projection
$2,500,000
$2,000,000
$1,500,000
$1,000,000
$500,000
^ ^ ^
^r-^ .;/V
<5^
0 Monthly Projection
• Monthly Actual
City of Carlsbad Municiapl Golf Course Project #39721
February 2006 Vlonthly Status Report
Task Name Duration Start Finish
Holel 0 days Mon 1/30/06 Mon 1/30/06
Hole 2 10 days Mon 2/6/06 Fri 2/17/06 •
Finish Grading due to Changes 5 days Mon 2/6/06 Fri 2/10/06
Pipe & Minor Concrete 5 days Mon 2/13/06 Fri 2/17/06
Holes 5 days Mon 2/6/06 Fri 2/10/06
Pipe & IVIinor Concrete 5 days Mon 2/6/06 Fri 2/10/06
Hole 4 0 days Mon 1/30/06 Mon 1/30/06
Hole 5, 6 & industrial Pad 2 days Mon 1/30/06 Tue 1/31/06
Finish Ts Foilwing Water Connection 2 days Mon 1/30/06 Tue 1/31/06
Water Connection @ Palomar Oaks-Pending-1 day? Mon 2/6/06 Mon 2/6/06
Hole7 10 days Mon 2/6/06 Fri 2/17/06
Finish Grade 5 days Mon 2/6/06 Fri 2/10/06
Pipe & Minor Concrete 5 days Mon 2/20/06 Fri 2/24/06
Holes 0 days Mon 1/30/06 Mon 1/30/06
Hole 9 0 days Mon 1/30/06 Mon 1/30/06
Hole 10 0 days Mon 1/30/06 Mon 1/30/06
Hole 11 5 days Mon 1/30/06 Fri 2/3/06
Finish Grading 5 days Mon 1/30/06 Fri 2/3/06
Hole 12 0 days Mon 1/30/06 Mon 1/30/06
Hole 13 5 days Mon 1/30/06 Fri 2/3/06
Finish Grading 5 days Mon 1/30/06 Fri 2/3/06
Hole 14 0 days Mon 1/30/06 Mon 1/30/06
Hole 15 0 days Mon 1/30/06 Mon 1/30/06
Finish Grading due to changes- On Hold-0 days Mon 1/30/06 Mon 1/30/06
Hole 16 & Industrial Pad 35 days Mon 1/30/06 Fri 3/17/06
Backfill Wall & Finish 35 days Mon 1/30/06 Fri 3/17/06
Hole 17 10 days Mon 1/30/06 Fri 2/10/06
Finish Grading 5 days Mon 2/6/06 Fri 2/10/06
Pipe & Minor Concrete Work 5 days Mon 1/30/06 Fri 2/3/06
Hole 18 5 days Mon 1/30/06 Fri 2/3/06
Finish Grading 5 days Mon 1/30/06 Fri 2/3/06
* Minor Concrete Pending Engineer's recomme 1 day? Mon 1/30/06 Mon 1/30/06
Jan 29, '06
^ 1/30
Feb 5,'06 Feb 12,'06 Feb 19,'06 Feb 26,'06 Mar 5,'06 Mar 12,'06 Mar 19,'06
^ 1/30
^ 1/30
^ 1/30
^ 1/30
111
im
^ 1/30
iiii
Pll
^ 1/30
^ 1/30
^ 1/30
! i
SEMA CONSTRUCTION
CARLSBAD MASS GRADING
Kalid Dawood
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Commercial Pad Crib Wall
East Wall Section Excavation
02-02-06
DUDEK
& ASSOCIATES, INC.
Commercial Pad Crib Wall
West Section
02-10-06
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Brow Ditch Pour
Hole ?^ 11 Tee Area
02-13-06
DUDEK
& ASSOCIATES. INC.
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Section 2 - Golf Course Construction
Contract No. 39721-2
General Contractor:
Wadsworth Golf Construction Company
600 N. 195'^ Avenue
Buckeye, AZ 85326
Construction Start Date:
March 1, 2006
DUDEK
& ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Executive Summary
Work Summary for February
Wadsworth Golf Construction Company (Wadsworth) completed mobilization activities and
began fine shaping operations of the Golf Course Holes. Substantial progress was made fine
shaping the "Front Nine" Golf Holes. Fine shaping activities include detail grading of the Greens,
Tees, Bunkers, Cart Paths and Fairway Features, that upon completion, will be ready for
irrigation and grass. The Golf Course Architect made two site visits and approved the features on
Golf Holes ^ 1, 3, 4, 5, 6, 8, and 9. These Golf Holes are now ready for installation of the irrigation
system followed by grass planting. Construction activities for the month are shown below:
• Completion of mobilization activities.
• Approval of fine shaping and Golf features for Golf Holes M, 3, 4, 5, 6, 8, and 9.
• Completion of fine shaping activities for the Feature Lake and Waterfall System on Golf
Holes #2 and ^7.
• Began layout of "Hard Lines" for the Turf and Rough areas to facilitate layout of the
irrigation system.
• Completion of the water main line around the Clubhouse area.
• Conducted pre-construction meetings with Wadsworth's Landscape Bridge, Waterfall
and Lake Subcontractors.
Planned Work for March
• Continuation of fine shaping activities on Golf Holes #2, 7 and 10 through 18.
• Begin installation of the irrigation system.
• Begin Lake construction.
• Begin Green's construction.
Contract Status- Change Orders
• None to date.
Cash Flov^^ Projection
To be included in next month's report.
Project Schedule
Staff is currently reviewing Wadsworth's Baseline Construction Schedule. The schedule
currently shows the completion of grassing all Golf Holes by the end of September 2006, to take
advantage of the warm weather. This date is key to meeting the City's planned opening of the
Golf Course by early Summer 2007 as this allows plenty of time for adequate grow-in prior to the
start of play.
DUDEK
& ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Potential Issues
• None to report.
DUDEK
& ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Municipal Golf Course Project 39721-2,
Contract 2 - Golf Course Cash Flow Projection
$2,500,000
$2,000,000
$1,500,000
$1,000,000
$500,000
# C?'^ #
y y y' y y' n)^ y y
</ / ^^^^ ^-^^ r
0 Monthly Projection
• Monthly Actual
City of Carlsbad Municiapl Golf Course Project #39721
February 2006 Monthly Status Report
ID
1
Task Name
Shaping hole #7
Shaping Holes 10,11,13
~^ Irrigation Crew #1 (Holes 5,6)
2j Irrigation Crew #2(Holes 1,8,9,PG)
Drainage Crew(Holes 1,8,9,4,3,2)
6 ^ Greens Drainage{Holes 2,3,4,7,1,8,9,pg)
Gravel Blankets, Root zone install
Duration
11 days
3 wks
Start Finish
Wed 2/1/06 Wed 2/15/06
Wed 2/8/06 Tue 2/28/06
9,'06 Feb 5,'06 Feb 12,'06 Feb 19, '06 Feb 26, '06
T WT F S S M TWT F S S M T WT F S S M TWT F S S M TWT F 8
3 wks Mon 2/13/06 Fri 3/3/06
3 wks Mon 2/13/06 Fri 3/3/06
3 wks Fri 2/10/06 Thu 3/2/06
3 wks Fri 2/10/06 Thu 3/2/06
2 wks Tue 2/14/06 Mon 2/27/06
Project: look ahead schedule
Date: Thu 3/9/06
Task
Split
Progress
Milestone
Summary
Project Summary '
Page 1
Extemal Tasks
Extemal Milestone
Deadline ^
Hole # 1 Green's Complex Final Shaping
02-15-06
Green 6 Sub-Grade Slope Verification
02-15-06
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Section 3 Golf Course Buildings
Contract # 39721-3
General Contractor:
Jaynes Corporation
111 Elm Street, Fourth Floor
San Diego, CA 92101-2649
Construction Start Date:
November 1, 2005
DUDEK & ASSOCIATES, INC,
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Executive Summary
Work summary for February
Maintenance Building
Work on the Maintenance Building returned to normal in February, after January's
unfortunate plane crash. The Contractor completed installation of the perimeter security wall
and began installation of the structural elements for the building's roof trusses. Steel columns
and roof ledgers around the top of the walls have been completed.
Clubhouse Building
The majority of the Clubhouse parking lot has been paved thereby weatherizing the site,
allowing for access during inclement weather. Work continued on the building's lower and
upper floor slabs. Waterproofing of the walls has been completed.
Planned work lor March
Maintenance Building
• Continue with roof truss instaUation.
• Continue with on-site utilities.
Clubhouse Building
• Continue with lower and upper buHding floor slabs.
• Continue with under slab utilities.
• Begin installation of the pre-cast concrete deck over the lower building.
• Continue work at the Half -Way House.
• Begin work on Comfort Stations "A" and "B".
Contract Status- Change Orders
The report shows several potential Change Orders that are currently under review by staff, many
of which appear to be reasonable and will be converted to Change Order No. 1. The amount of
Change Order No. 1 will be about 1 % of the overall contract value.
Project schedule
The CM Team is currently reviewing the Contractor's Baseline Schedule up-date received at the
end of February. At this point the Contractor appears to be on schedule to complete by
November 2006.
Cash Fiov/ Projection
The progress payment for January was under projections, but from the start of the project (three
month period) it appears that actual and projections are in accord.
DUDEK
& ASSOCIATES, INC
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Potential Issues
The potential is,sue mentioned last month regarding the wrong structural bid set has yet to be
resolved regarding both time and schedule impacts. The Contractor has submitted an unofficial
potential cost increase from their structural metal supplier for the amount of $55,000, which is
currently being reviewed by the CM Team.
DUDEK
SL ASSOCIATES, INC.
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Project #39721-3 GOLF COURSE CONSTRUCTION
CONTRACT STATUS/CHANGE ORDERS
Original Contract Amount;
Approved Change Orders;
Revised Contract Amount;
Percent Change Orders (on Original Contract);
Potential Change Orders (Estimate);
Potential Revised Contract Amount;
$ 10,660,864.00
$
$ 10,660,864.00
$ 63,060.00
$ 10,723,924.00
Description Approved
Projected Project
Total
Change Orders $ 10,660,864.00
Total Approved Change Orders; $
Revised Contract Amount: $ 10,660,864.00
* Pending Final Execution
Estimate
Elc\ ator Modification to Hole les,s .S 2,000.00
Parking Lot Structural Changes $ 60,000.00
Additional Concrete for Stepped Footing S 1,060.00
Total Estimated Potential Changes; $ 63,060.00
Projected Budget (w/potential Changes): $ 10,723,924.00
City of Carlsbad Municipal Golf Course Project #39721-3
February 2006 Monthly Status Report
Municipal Golf Course Project 39721-3,
Contract 3 - Buildings Cash Flow Projection
$1,200,000
$1,000,000
$800,000
$600,000
$400,000
$200,000
$-
s.^ 4"
0 Monthly Projection
• Monthly Actual
City of Carlsbad Municiapl Golf Course Project #39721
February 2006 Monthly Status Report
M
MAINTAINENCE
Scott Michael
GK Mechanical
CLUBHOUSE
Scott Michael
Maqnasite Specialties
Quality Reinforcing
Hanson Precast
Scott Michael
So Cal Iron
Quality Reinforcing
Team C
Lawrie and Sons
Scott Michael
Jaynes
3D Paving
Comfort Station A
Scott Michael
Quality Reinforcing
Team C
HALF WAY HOUSE
Quality Reinforcing
Team C
PK Neil
Site Wall @ Maint Set Col's @ Maint
Set Ext Col's Tubes @ Maint
Rough Carpentry Beams and Trus:
Install Sand Interceptor
Fire Sprinklers
Rough Mechanical
Interior Wall Framing
Rough Electrical Walls
Prep SOG @ Clubhouse LL
Set Steel @ Clubhouse LL
Underslab @ Clubhouse
Waterproofing @ CH Walls
SOG @ Clubhouse
Pour SQG @ Clubhouse LL
Extended Footinqs <^ CH LL
Set Planks and Beams @ CH
Deck Penetrations and Drains CH
Deck Penetrations @ Clubhouse
East Footings @ CH UL
Set Steel @ Clubhouse Deck
East Footinqs @ Clubhouse UL
Topping Slab @ CH Deck
Steel Studs @ Archways
Underslab Plumbing @ CH East
Complete Backfill Wall @ CH
Pour Footings @ East CH
Prep for SOG @ Clubhouse UL
Base and Pave Site CH '
Underground Utilities Clubhouse *
Underground Utilities Maint *
Survey *
Layout and Diq Footings
Under Slab Plumbing
Footing Steel
Pour Footinqs
Masonry
Pour SOG
Interior Masonry
Wood Framing
Prep for SOG
Steel @ SOG
Interior Masonry
Wood Framinq
Rough- In Electrical
Roof Dry-i
* Activities on hold until plans are finalized
' Pendlnq Excess Dirt removal and new loc;
Carlsbad Golf Course Buildings Look Ahead Schedule
Th rss M I W Th
3/1 3/2 3/3 1 3/4 | 3/6 3/7 3/B 3/9 3/10
Maintenance Building - Ready for Roof
2-18-06
Clubhouse Lower Level - Ready for Upper Level
2-18-06
DUDEK
& ASSOCIATES. INC.
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Lower Level - Octagon - Ready for Pre-cast Beams & Planks
2-20-06
Clubhouse Lower Level Slab
2-28-06
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Rolling Base in Parking Lot
2-24-06
DUDEK
& ASSOCIATES, INC.
Paving in Parking Lot
2-25-06
City of Carisbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Section 4
Overall Golf Course Project Financials
Contract ^ 3972M, 39721-2, and 39721-3
DUDEK
& ASSOCIATES, INC.
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report
Carlsbad Municipal Golf Course
Budget, Expenditures and Contracts through 2/28/2006
This table summarizes expenditures and contracts authorized as of the July 26, 2005 Agenda which approved the construction budget of the Golf Course
in the amount of $45,320,789.
Original budget and budget changes Original
Estimate Increases (Decreases) Revised Budget
(MMcllllg 7,721,463 $ 1,806,005 ,$ 9,527,468
Golf Course Construction 16,727,761 16,727,761
Buildings 10,66I,0S2 10,661,052
Construction Contingency 1,755,514 2,936,700 (1,831,005) 2,861,209
Conslruction mi.sc. 5,855,000 25,000 5,880,000
Grow-in/pre-opening costs 1,100,000 1,100,000
Start-up costs 1,500,000 1,500,000
Total Estimated Cost $ 45,320,790 $ 4,767,705 $ (1,831,005) $ 48,257,490
A B C D E
EXPENDITURES /
CONTRACTS Total Budget Total Contract
Amount
Expenditures
to-date
Contract
Balance
Remaining
Budget
(A - C - D)
Grading - SEMA Construction S '•).527,468 9.527.468 7,967,257 1.560.211
Construction - Wadsworth Golf Construction 16,727,761 16.727.76! 228,749 16,499,012
Buildings - [aynes Corporations 10,661,052 10,661,052 2,477,188 8,183,864
Contingency 2,861,209.00 2,861,209
Subtotal Construction 39,777,490 36,916,281 10,673,194 26,243,087 2,861,209
Construction Management & Support
Dudek 1,500,000 59,065 1,440,935
TJ Dixon & James Nelson (Artwork) 128.000 32,000 96,000
Simon Wong (Inspection) 1,600 968 632
Engineering overhead 38,349 38,349 -
Construction Analysts 2,880 2,880 -
Misc. (shipping, copies, etc) 36,026 36,026 -
Testing Engineers 10,000 3.553 6,447
Subtotal Construction Management/Support 2,290,000 1,716,855 I72,.'^4I 1,544,014 573,145
Geotechnical soils testing 150,000 150,000
Design Team - construction phase services
Greg Nash 75,000 19,200 55,800
Douglas Fredrickson - Architects 85.000 19,884 65,116
Subtotal Design Team - construction phase services 250,000 160.000 39,084 120,916 90,000
Environmental - monitoring and special studies 350,000 350,000 67,256 282,744 -
Mark Mojado (San Luis Rey Band of Indians) 25,000 25,000 3,781 21,219 Mark Mojado (San Luis Rey Band of Indians)
Utility fees 25,000 25,000
SDG&E Undergrounding 1,150,000 1,150,000
Furniture Fixtures & Equipment 1,640,000 1,640,000
Grow-In and Pre-opening maintenance 1,100,000 1,100,000
Start-Up Budget to open and operate 1,500,000 1,500,000
Total Expenditures and Commitments $ 48,257,490 $ 39,168,156 $ 10,956,156 $ 28,211.980 9,089,354
City of Carlsbad Municiapl Golf Course Project # 39721
February 2006 Monthly Status Report
Carlsbad Municipal Golf Course Project
Construction Contracts - Monthly Cash Flow Project
Cash Flow Projection by Month
Month
Mass Grading
Contract Billings
Golf Course Building
Monthly
Total
Cumulative
Total
September - 2005
October - 2005
November - 2005
December - 2005
January - 2006
February - 2006
March - 2006
April - 2006
May - 2006
June - 2006
July - 2006
August - 2006
September - 2006
October - 2006
November - 2006
December - 2006
January - 2007
February - 2007
March - 2007
$ 1,700,000.00
1,100,000.00
1,500,000.00
1,500,000.00
900,000.00
500,000.00
521,463.48
300,000.00
700,000.00
1,000,000.00
1,500,000.00
2,000,000.00
2,000,000.00
2,500,000.00
2,500,000.00
1,000,000.00
1,000,000.00
1,000,000.00
1,000,000.00
727,761.00
500,000.00
1,100,000.00
1,100,000.00
800,000.00
800,000.00
1,000,000.00
1,200,000.00
1,000,000.00
1,000,000.00
800,000.00
700,000.00
660,864.00
1,700,000.00
1,100,000.00
2,000,000.00
2,600,000.00
2,000,000.00
1,600,000.00
2,021,463.48
2,000,000.00
2,700,000.00
3,000,000.00
3,000,000.00
3,300,000.00
3,200,000.00
1,660,864.00
1,000,000.00
1,000,000.00
1,000,000.00
727,761.00
1,700,000.00
2,800,000.00
4,800,000.00
7,400,000.00
9,400,000.00
11,000,000.00
13,021,463.48
15,021,463.48
17,721,463.48
20,721,463.48
23,721,463.48
27,021,463.48
30,221,463.48
31,882,327.48
32,882,327.48
33,882,327.48
34,882,327.48
35,610,088.48
35,610,088.48
35,610,088.48
35,610,088.48
35,610,088.48
35,610,088.48
Totals: $ 7,721,463.48 $ 17,227,761.00 S 10,660,864.00
Contract Values:
1. Mass Gtading:
5. Buildings:
7,721,463.48
17,227,761.00
[0,660,864.00
City of Carlsbad Municipal Golf Course Project # 39721
February 2006 Monthly Status Report