BALANCE HYDROLOGICS, Inc.
MEMO
To: Sherri Howard
From: Dana Jepsen
Date: January 9, 2016
Subject: Construction Observation Summary Memo
Introduction
Balance Hydrologics assisted the City of Carlsbad as an observer at the Agua Hedionda Creek
Streambank Restoration Project. Our first site visit was in the afternoon of November 2nd, 2016.
Our final site visit occurred on the morning of December 3rd, 2016.
During our time onsite, we were able to observe the installation and construction of a number of
project elements. We have outlined our observations of a number of these elements below. We
did not include a discussion of the Fabric Encapsulated Soil because this was a Dudek design
element and these have been previously summarized by others.
Keyway and Foundation Boulder Placement
With the diversion and dewatering activities normalized, boulder placement within the keyway
began in earnest on November 4th. Despite the difficulties of removing all of the water from the
excavations, the contractor appeared to achieve the placing of these boulders on top of the
approved geotextile. Note that this geotextile was not shown in the drawings but, as I
understand, it was approved by the City as an acceptable substitute for the bedding material as
drawn. This substitution of geotextile for well grading bedding occurred in additional areas as
well: below the channel boulders including the boulders that form the drops, below the outfall
boulders, and below the stilling pool.
The contractor worked diligently and effectively to assure that the top of boulder elevations
within the keyway were as indicated in the drawings, and the size of the boulders used in
construction appeared to meet the specifications. It was discovered mid-way through keyway
boulder placement that the entire keyway would be inundated once the diversion pump was
removed. This posed a problem for two reasons. First, the design intent was that base flows
within the creek be below the vegetated crib wall and the fabric encapsulated soil (FES).
Additionally, the work plan was to remove the diversion pump once the channel and keyway
boulders were in place, and to construct the remaining items from outside of the channel. The
contractor and the City agreed that the best solution was to raise the elevation of the keyway by
adding an additional course of boulders. It was agreed that the elevations for the cribwalls and
FES shown on the drawings would be adjusted in the field to fit the revised elevation at the
216127 Construction Observation Summary Memo.docx 2
foundation boulders. This solution had the benefit of decreasing the amount of elevation that
needed to be made up later through the labor intensive construction of the vegetated cribwalls.
In summary, the construction of the keyway and the foundation for the cribwalls and FES
appeared to meet the design intent and specifications even if the elevations were altered in the
field. The contractor had sufficient large material available, and placed and compacted the
boulders per the specifications.
Channel Boulders
The contractor worked from downstream to upstream when constructing the channel. Prior to
completing the keyway and foundation described above, the boulder placement began within the
channel itself. As indicated earlier, the bedding material shown on the drawings was replaced
with City approval by a geotextile. We do not have experience in the construction of channel
bed forms lined with geotextile, but the contractor appeared to place the material as per its
intended use. From my observations and spot measurements, the thickness of the channel
material met or exceeded the 4.3’ thickness called for in the drawings.
The contractor was able to reserve sufficient large material to construct the two steps shown.
The downstream step was constructed in line with the drawings, but a change was made during
construction to the elevations at the upper drop. The plug of sandy soil between the diversion
pump and the constructed channel could not be entirely removed without flooding the worksite.
As opposed to using undersized material to construct the drop, it was decided that the top of the
drop would be a foot higher than shown on the drawings. Another change to the design was the
addition boulders both upstream and along the side of the channel at the upstream end. The
boulders upstream were placed to provide additional stability for the channel and drop structure
in anticipation of the sandy soil plug eroding over time and the boulders along the side of the
channel were placed to arrest erosion observed after a rain event during construction.
In summary, the rock placement to create the channel appeared to meet the design intent and
specifications. The only change we note is the placement of additional large material at the
upstream end of the project.
Outfall and Stilling Pool
The rock slope protection at the storm drain outfall and the associated stilling pool were
constructed on November 18th, after the completion of the upstream cribwall. Once again,
geotextile was used in place of the well graded bedding material shown on the drawings. We
observed the contractor placing smaller material in the voids left after the placement of the
boulders, but we should note that some of this smaller material was washed out during the storm
event that occurred on November 20th and 21st. It is our understanding that the City’s approval
of the geotextile is intended to mitigate for loss of some of the smaller bedding material.
Although it appears to us that these elements were constructed per plan, we also believe that it is
important that these elements be monitored in the future. This monitoring is discussed below in
the section on recommendations.
216127 Construction Observation Summary Memo.docx 3
In summary, boulders associated with the stilling pool appear to have been placed per plan and
should work to assist in dissipating the energy associated with the flow out of the outfall. In
addition, the boulders serve to assist in the containment of cribwall backfill.
Vegetated Cribwalls
The upstream vegetated cribwall was constructed such that the top header log was set at the
elevations indicated on the drawings. While the log diameters are generally smaller than were
shown, the contractor did not need to add additional lifts because of the higher starting elevation
at the foundation boulders. We worked alongside the city inspector to observe and document
that the log connections were done per specifications and that the fill within the crib cells was
compacted appropriately. We do not note any deviations or irregularities in the upstream
cribwall.
There are two items worth noting regarding the downstream cribwall. First, a decision was made
jointly by the contractor and the City that installing an additional lift (two layers of logs) would
be beneficial to the project from both a performance and cost perspective. We agree that the
slope will be more stable because this decision was taken. The second item we noted is that the
alignment of the fourth layer of logs at the downstream conform is not ideal. In this case, a
decision was taken in the field in consultation with the City that corrective action was not needed
and that the FES and plantings allow for sufficient flexibility that the design intent could be
achieved without dismantling and re-constructing the cribwall.
In summary, the vegetated cribwalls appear to have been constructed in compliance with the
design intent and we have reasonable confidence that they will perform as expected.
Engineered Fill
This project benefited from the almost continuous presence of a soils technician who took
responsibility for confirming compliance with the specifications in this area. We do not have
anything to add in this regard.
Final Thoughts and Recommendations
This project was constructed later in the season than anticipated. This late start necessitated that
the team move quickly and continuously evaluate the benefits and risks associated with making
field adjustments in the anticipation of coming rain events. Given this time pressure, we are
impressed with the final product and feel that it should perform well so long as appropriate
adaptive management procedures are put in place and followed.
In our opinion, the main focus of adaptive management should be on plantings. For the
vegetated cribwall and the FES to perform as desired, the plantings called for must not only
survive, but thrive. It is not possible to overstate the importance of planting survival both within
the engineered reach and at the upstream and downstream transition zones.
The second adaptive management item to prepare for is at the outfall. The rock slope protection
between the outfall and the stilling pool should be monitored regularly during the rainy season,
and the City should be prepared to place material in this area if any becomes dislodged. The
216127 Construction Observation Summary Memo.docx 4
geotextile provides a certain amount of protection against erosion, but will not function unless it
is covered with the appropriate sized rock.
Per our observations the constructed project was completed in general conformance with the
plans and specifications.