HomeMy WebLinkAbout2050 AVENUE OF THE TREES; ; CB152200; PermitCity of Carlsbad
1635 Faraday Av Carlsbad, CA 92008
08-19-2015 Residential Permit Permit No: CB152200
Job Address:
Building Inspection Request Line (760) 602-2725
2050 AVENUE OF THE TREES CBAD
Permit Type: RESDNTL Sub Type: RAD Status: ISSUED
Applied: 07/14/2015
Entered By: SLE
Parcel No: 1562901 000 Lot #: 0
Valuation: $18,155.00 Constuction Type: 58
Occupancy Group:
# Dwelling Units: 0
0
Reference #:
Structure Type:
Plan Approved: 08/19/2015
Issued: 08/19/2015
Bedrooms:
Project Title:
Applicant:
Bathrooms: 0
Orig PC#:
EBERHART RES -527 SF EXPAND
BASEMENT STORAGE AREA
Owner:
Inspect Area:
Plan Check #:
RONALD BAKER EBERHART JUDITH E REVOCABLE TRUST 01-09-02
2050 AVENUE OF THE TREES
CARLSBAD CA 92008
Building Permit
Add'l Building Permit Fee
Plan Check
Add'l Plan Check Fee
Plan Check Discount
Strong Motion Fee
Park in Lieu Fee
Park Fee
LFM Fee
Bridge Fee
Other Bridge Fee
BTD #2 Fee
BTD #3 Fee
Renewal Fee
Add'l Renewal Fee
Other Building Fee
HMP Fee
Pot. Water Con. Fee
Meter Size
Add'l Pot. Water Con. Fee
Reel. Water Con. Fee
Green Bldg Stands (SB1473) Fee
Green Bldg Stands Plan Chk Fee
Total Fees: $426.43
LU
Inspector: "'\.. 1
$193.57
$0.00
$135.50
$0.00
$0.00
$2.36
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$1.00
$0.00
Total Payments to Date:
2050 AVENUE OF THE TREES
CARLSBAD CA 92008
Meter Size
Add'l Reel. Water Con. Fee
Meter Fee
SDCWA Fee
CFD Payoff Fee
PFF (3105540)
PFF (4305540)
License Tax (3104193)
License Tax ( 4304193)
Traffic Impact Fee (3105541)
Traffic Impact Fee (4305541)
Sidewalk Fee
PLUMBING TOTAL
ELECTRICAL TOTAL
MECHANICAL TOTAL
Housing Impact Fee
Housing lnlieu Fee
Housing Credit Fee
Master Drainage Fee
Sewer Fee
Additional Fees
Fire Sprinkler Fees
TOTAL PERMIT FEES
$426.43 Balance Due:
FINAL APPROVAL
Date: ?(-/---tU Clearance:
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$49.00
$45.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$426.43
$0.00
NOTICE: Please take NOTICE that approval of your project includes the "Imposition" of fees, dedications, reservations, or other exactions hereafter collectively
referred to as "fees/exactions." You have 90 days from the date this permit was issued to protest imposition of these fees/exactions. If you protest them, you must
follow the protest procedures set forth in Government Code Section 66020(a). and file the protest and any other required information with the City Manager for
processing in accordance with Carlsbad Municipal Code Section 3.32.030. Failure to timely follow that procedure will bar any subsequent legal action to attack,
review, set aside, void, or annul their imposition.
You are hereby FURTHER NOTIFIED that your right to protest the specified fees/exactions DOES NOT APPLY to water and sewer connection fees and capacity
changes, nor planning, zoning, grading or other similar application processing or service fees in connection with this project. NOR DOES IT APPLY to any
fees/exactions of which_ypu have oreviouslv been aiven a NOTICE similar to this or as to which the statute of limitations has oreviouslv otherwise exnired.
City of Carlsbad
1635 Faraday Av Carlsbad, CA 92008
08-19-2015
Storm Water Pollution Prevention Plan (SWPPP) Permit
Permit No:SW150279
Job Address:
Permit Type;
Parcel No:
Reference #:
CB#:
Project Title:
Priority:
Applicant:
2050 AVENUE OF THE TREES CBAD
SWPPP
1562901000 Lot#: 0
152200
EBERHART RES -SWPPP FOR 527SF
EXPANSION OF BASEMENT STORAGE AREA
L
Owner:
Status:
Applied:
Entered By:
Issued:
Inspect Area:
Tier:
ISSUED
07/23/2015
SLE
08/19/2015
RONALD BAKER EBERHART JUDITH E REVOCABLE TRUST 01-09-02
2050 AVENUE OF THE TREES
CARLSBAD CA 92008
805-698-3056
Emergency Contact:
RONALD BAKER
805-698-3056
SWPPP Plan Check
SWPPP Inspections
Additional Fees
TOTAL PERMIT FEES
Total Fees: $106.00
2050 AVENUE OF THE TREES
CARLSBAD CA 92008
$48.00
$58.00
$0.00
$106.00
Total Payments To Date: $106.00 Balance Due:
FIN
SIGNATURE
$0.00
[]ENGINEERING []BUILDING
(_City of
Carlsbad
Building Permit Application
1635 Faraday Ave., Carlsbad, CA 92008
Ph: 760-602-2719 Fax: 760-602-8558
email: building@carlsbadca .gov
www.carlsbadca.gov SWPPP IV)02..1 '\
JOB ADDRESS 2050Ave. of the Trees SUITE#/SPACE#/UNIT#
CT/PROJECT II LOT II II BEDROOMS II BATHROOMS
805) 698~3051 3 3
DESCRIPTION OF WORK: Include Square Feet of Affected Area(s)
Excavate and expand the basement~or~U~e area by 527 Sq.Ft.
see-~-_,~ o~o · · · · + I I raL/J
AIR CONDITIONING
YES0No0
Judith E. Eberhart
2050 Avenue of the Trees
CITY STATE CA CITY 92008
PHONE FAX PHONE (805) 698-3056
EMAIL ron@ronbakerpix.com
DESIGN PROFESSIONAL Kamel Zayat, Casa Engineering, Inc.
ADDRESS 247 Venture St., Ste 102 ADDRESS
CITY ZIP CITY ZIP STATE San Marcos CA 92078
PHONE FAX PHONE (760) 510-2708. (760) 510:..2772
EMAIL EMAIL
STATE LIC.II CITY BUS. LIC.II
-OD
OCC. GROUP
FIRE SPRINKLERS
YESDNc0
(Sec. 7031.5 Business and Professions Code: Any City or County which requires a permit to construct. alter. improve. demolish or repair any structure. prior to its issuance, also requires the applicant for such permit to file a signed statementtnat he is licensed pursuant to the provisions of the Contractor's License Law /Chapter9, commending with Section 7000 of Division 3 of the Business and Professions Code} or that he is exempt therefrom, and the basis for the alleged exemption. Any violation of Section 7031.5 by any applicant for a permit subjects the applicant to a civil penalty of not more than five hundred dollars ($500}).
Workers' Compensation Declaration: I hereby affi'm under penally of perjury one of the folbwing declarations: D I have and will maintain a certificate of consent to self·insure for workers' compensation as provided by Section 3700 of the Labor Code, for the performance of the work for which this permit is issued. D I have and will maintain workers' compensation, as reQuired by Section 3700 of the Labor Code, for the performance of the work for which this penni! is issued. My workers' compensation insurance carrier and policy
number are: Insurance Co Policy No. Expiration Date
;rw,section need not be completed if the penni! is for one hundred dollars ($100) or less. U Certificate of Exemption: I certify that in the performance of the work for which this permit is issued, I shall not employ any person in any manner so as to become subject to the Workers' Compensation Laws of
California. WARNING: Failure to secure workers' compensation coverage is unlawful, and shall subject an employer to criminal penalties and civil fines up to one hundred thousand dollars (&100,000), in
addition to the cost of compensation, damages as provided for in Section 3706 of the Labor code, interest and attorney's fees.
Ji5 CONTRACTOR SIGNATURE 0AGENT DATE
I hereby affirm that I am exempt from Conlractor's License Law for the following reason: 0 ~.as owner of the property or my employees with wages as their sole compensation, will do the work and the structure is not intended or offered for sale (Sec. 7044, Business and Professions Code: The Contractor's
License Law does not apply to an owner of property who builds or improves thereon, and who does such work himself or through his own employees, provided that such improvements are not intended or offered for
sale. If, however, the building or improvement is sold within one year of completion, the owner-builder will have the burden of proving that he did not build or improve for the purpose of sale). ~ I, as owner of the property, am exclusively contracting with licensed contractors to construct the project (Sec. 7044, Business and Professions Code: The Contractor's License Law does not apply to an owner of
property who builds or improves thereon, and contracts for such projects with contractor(s) licensed pursuant to the Contractor's License Law).
D I am exempt under Section Business and Professions Code for this reason:
1. 1 personally plan to provide the major labor and materials for construction of the proposed property improvement. DYes 0No
2. I (have I have not) signed an application for a building permit for the proposed work.
3. 1 have contracted with the following person (firm) to provide the proposed construction (include name address I phone I contractors' license number):
4. 1 plan to provide portions of the work, but I have hired the following person to coordinate, supervise and provide the major work (include name I address I phone I contractors' license number):
5. 1 will provide some of the work, but I have contracted (hired) the following persons to provide the work indicated (include name I address I phone I type of work):
Ji5 PROPERTY OWNER SIGNATURE / DATE
I certify that I have read the applicaijon and state that the above infonnaijon is correct and Umtthe infonnation on the plans is accurate. I agree to complywth all City ordinances and State laws relaijngto building construction.
I hereby authorize representative of the City of Carlsbad to enter upon the above mentioned property for inspection purposes. I .AlSO AGREE TO SAVE. INDEMNIFY AND KEEP HARM.ESS THE CITY OF CARLSBAD
AGAINST ALL LIABILITIES. JUDGMENTS, COSTS AND EXPENSES WHICH MAY IN ANYWAY ACCRUE AGAINST SAID CITY IN CONSEQUENCE OF THE GRANTING OF THIS PERMIT.
OSHA: An OSHA permit is required for excavations over5'0' and demonion or oonstruction of struc1ures over 3 stories in height.
EXPIRATION: Every permit issued by the of this Code shall expire by imitation and become null and void~ 1he building "'"'".v ~,fl,,..;.,.,n lhu
180 days from the date of such permit or if the permit at any time aller 1he work is oommenced for a day·s (Sectillh
...@!APPLICANT'S SIGNATURE DATE
I n
Permit#: CB152200 Type: RESDNTL RAD EBERHARTRES-527SFEXPAND
BASEMENT STORAGE AREA
Date __ II"!SP~Cti()_ll)!~m 111spector Act Comments --------·-------·----
03/31/2016 89 Final Combo Rl 8-10 PLEASE
03/31/2016 89 Final Combo PB AP
03/30/2016 89 Final Combo PB NS
03/04/2016 17 Interior Lath/Drywall AEK AP
02/25/2016 14 Frame/Steei/Bolting/Weldin py PA
02/25/2016 16 Insulation py PA
02/25/2016 34 Rough Electric py PA
11/10/2015 12 Steel/Bond Beam PB AP
11/06/2015 21 Underground/Under Floor py AP
11/06/2015 24 Rough/T opout PY AP
10/14/2015 12 Steel/Bond Beam PB AP
1 0/02/2015 11 Ftg/Foundation/Piers PB AP
09/25/2015 12 Steel/Bond Beam PB AP
09/24/2015 12 Steel/Bond Beam PB AP
09/17/2015 12 Steel/Bond Beam PY PA
08/21/2015 12 Steel/Bond Beam PB PA
Monday, April 04, 2016 Page 1 of 1
EsGil Corporation
In (J>artnersliip witli government for (]Jui{aing Safety
DATE: AUG.04,2015
JURISDICTION: CARLSBAD
PLAN CHECK NO.: 15-2200 SET: II
0 ~PLICANT
)J'JURIS.
0 PLAN REVIEWER
0 FILE
PROJECT ADDRESS: 2050 AVENUE OF THE TREES
PROJECT NAME: SFR BASEMENT STORAGE EXPANSION
D
D
D
D
D
[g)
D
The plans transmitted herewith have been corrected where necessary and substantially comply
' with the jurisdiction's codes.
The plans transmitted herewith will substantially comply with the jurisdiction's building codes
when minor deficiencies identified below are resolved and checked by buildiing department staff.
The plans transmitted herewith have significant deficiencies identified on the! enclosed check list
and should be corrected and resubmitted for a complete recheck.
The check list transmitted herewith is for your information. The plans are being held at Esgil
Corporation until corrected plans are submitted for recheck.
The applicant's copy of the check list is enclosed for the jurisdiction to forward to the applicant
contact person.
The applicant's copy of the check list has been sent to:
RON BAKER
EsGil Corporation staff did not advise the applicant that the plan check has been completed.
EsGil Corporation staff did advise the applicant that the plan check has been completed.
Person contacted: RON Telephone#: 805-698-3056
Date contacted: (by: Email: ron@ronbakerpix.com
Mail Telephone Fax In Person
[g) REMARKS: The applicant to submit to the building department a copy of the letter addressing the adjacent property owner, as
per CBC Section 3307, prior to the permit being issued for review & approval.
By: ALI SADRE, S.E. Enclosures:
EsGil Corporation
D GA D EJ D MB D PC 7/27
9320 Chesapeake Drive, Suite 208 + San Diego, California 92123 + (858) 560-1468 + Fax (858) 560-1576
4. Joists resting on the stringers shall be not less than 2
inches by 8 inches (51 nun by 203 mm) and shall be
spaced not more than 2 feet (610 nun) on center.
5. The deck shall be planks not less than 2 inches (51
mm) thick or wood structural panels with an exterior
exposure durability classification not less than 23/32 inch (18.3 nun) thick nailed to the joists.
6. Each post shall be knee braced to joists and stringers
by members not less than 2-inch by 4-inch (51 nun
by 102 mm); 4 feet (1219 nun) in length.
7. ·A curb which is not less than 2-inch by 4-inch (51
mm by 102 mm) shall be set on edge along the out-
side edge of the deck.
3306.8 Repair, maintenance and removal. Pedestrian pro-
tection required by this chapter shall be maintained in place
and kept in good order for the entire length of time pedestri-
ans are subject to being endangered. The owner or the
owner's agent, upon the completion of the construction activ-
ity, shall immediately remove walkways, debris and other
obstructions and leave such public property in as good a con-
dition as it was before such work was commenced.
3306.9 Adjacent to excavations. Every excavation on a site
located 5 feet (1524 nun) or less from the street lot line shall
be enclosed with a barrier not less than 6 feet (1829 nun) in
height. Where located more than 5 feet (1524 nun) from the
street lot line, a barrier shall be erected where required by the
building official. Barriers shall be of adequate strength to
resist wind pressure as specified in Chapter 16.
SECTION 3307
PROTECTION OF ADJOINING PROPERTY
3307.1 Protection required. Adjoining public and private
property shall be protected from damage during construction,
remodeling and demolition work. Protection shall be pro-
vided for footings, foundations, party walls, chimneys, sky-
lights and roofs. Provisions shall be made to control water
runoff and erosion during construction or demolition activi-
ties. The person making or causing an excavation to be made
shall provide written notice to the owners of adjoining build-
ings advising them that the excavation is to be made and that
the adjoining buildings should be protected. Said notification
shall be delivered not less than 10 days prior to the scheduled
starting date of the excavation.
SECTION 3308
TEMPORARY USE OF STREETS, ALLEYS AND
PUBLIC PROPERTY
3308.1 Storage and handling of materials. The temporary
use of streets or public property for the storage or handling of
materials or of equipment required for construction or demo-
lition, and the protection provided to the public shall comply
with the provisions of the applicable governing authority and
this chapter.
3308.1.1 Obstructions. Construction materials and equip-
ment shall not be placed or stored so as to obstruct access
to fire hydrants, standpipes, fire or police alarm boxes,
2013 CALIFORNIA BUILDING CODE
SAFEGUARDS DURING CONSTRUCTION
catch basins or manholes, nor shall such material or equip-
ment be located within 20 feet (6096 nun) of a street inter-
section, or placed so as to obstruct normal observations of
traffic signals or to hinder the use of public transit loading
platforms.
3308.2 Utility fixtures. Building materials, fences, sheds or
any obstruction of any kind shall not be placed so as to
obstruct free approach to any fire hydrant, fire department
connection, utility pole, manhole, fire alarm box or catch
basin, or so as to interfere with 1the passage of water in the
gutter. Protection against damage shall be provided to such
utility fixtures during the progress of the work, but sight of
them shall not be obstructed.
SECTION 3309
FIRE EXTINGUISHERS
[F) 3309.1 Where required. All structures under construc-
tion, alteration or demolition shall be provided with no fewer
than one approved portable fire extinguisher in accordance
with Section 906 and sized for not less than ordinary hazard
as follows:
1. At each stairway on all floor levels where combustible
materials have accumulated.
2. In every storage and constmction shed.
3. Additional portable fire extinguishers shall be provided
where special hazards exist, such as the storage and use
of flammable and combustible liquids.
[F) 3309.2 Fire hazards. The provisions of this code and the
California Fire Code shall be strictly observed to safeguard
against all fire hazards attendant upon construction opera-
tions.
SECTION 3310
MEANS OF EGRESS
3310.1 Stairways required. Where a building has been con-
structed to a building height of 50 feet (15 240 nun) or four
stories, or where an existing building exceeding 50 feet (15
240 nun) in building height is altered, no fewer than one tem-
porary lighted stairway shall be provided unless one or more
of the permanent stairways are erected as the construction
progresses.
3310.2 Maintenance of means of egress. Required means of
egress shall be maintained at all times during construction,
demolition, remodeling or alterations and additions to any
building.
Exception: Existing means of egress need not be main-
tained where approved tempo1rary means of egress systems
and facilities are provided.
SECTION 3311
STANDPIPES
[F) 3311.1 Where required. In buildings required to have
standpipes by Section 905.3.1, no fewer than one standpipe
shall be provided for use during construction. Such stand-
557
Ronald E. Baker & Judith Eberhart
2050 Avenue the ·rrees
C/1 92008
729-0196
698-3056
Robert Haverkamp
2048 Avenue of the Trees
Carlsbad, CA 92008
July 26, 2015
RE: CBC, Sec: 3307-Protection Of Adjoining Property
Dear Bob,
RECiEIVED
,AUG ][ 9 2015
CITY OF CARLSB.L\D
BUILDIN!.3 DIVISiON
As you know, we will be excavating, building retaining walls and pouring a slab floor, thus creating
additional storage space of approximately 527 s.f. under our house.
In compliance with Section 3307 of the California Building Code, this letter is to notify you that
we will protect your adjacent property from damage during construction, remodeling and
demolition work. This protection, as set forth in Section 832 of the California Civil Code., will
specifically focus on our common Party Wall. As per the plans, the excavation along our party
wall may be of a greater depth than are the walls or foundation of our adjoini11g structure and
located closer to the property line than the depth of the excavation. The exa.ct depth of this
excavation will be a range from zero feet to a depth of approximately 3 feet <lS per the
attached plans. These plans have been drawn and certified by a Licensed Engineer and will be
also approved by the City of Carlsbad. The excavation will commence upon issuance of the
building permit some time in August 2015.
If you have any questions, please do not hesitate to ask.
Sincerely,
I, Robert Haverkamp , acknowledge receipt of this letter as
Date: ?/to/L S Signature:~~~~'t--~..w.c:~,..£.l-~:
DATE: JULY 24, 2015
JURISDICTION: CARLSBAD
PLAN CHECK NO.: 15-2200
EsGil Corporation
In (}Jartnersliip witli government for CBui{d"ing Safety
SET: I
PROJECT ADDRESS: 2050 AVENUE OF THE TREES
~PLICANT
~ ~~RIS.
D PLAN REVIEWER
D FILE
PROJECT NAME: SFR BASEMENT STORAGE EXPANSION & DECK TRELLIS
D The plans transmitted herewith have been corrected where necessary and substantially comply
with the jurisdiction's codes.
D The plans transmitted herewith will substantially comply with the jurisdiction's
codes when minor deficiencies identified below are resolved and checked by building
department staff.
D The plans transmitted herewith have significant deficiencies identified on the enclosed check list
and should be corrected and resubmitted for a complete recheck.
~ The check list transmitted herewith is for your information. The plans are being held at Esgil
Corporation until corrected plans are submitted for recheck.
D The applicant's copy of the check list is enclosed for the jurisdiction to forward to the applicant
contact person.
~ The applicant's copy of the check list has been sent to:
RON BAKER
D EsGil Corporation staff did not advise the applicant that the plan check has been completed.
~ EsGil Corporation staff did advise the applicant that the plan check has been completed.
Person contacted: RON Telephone#: 805-698-3056 ~ate c;:{./;acted:*4-(b#¥4 Email: ron@ronbakerpix.com
-B" Mail ~:_~~ Fax In Person
D REMARKS:
By: ALI SADRE, S.E. Enclosures:
EsGil Corporation
D GA D EJ D MB D PC 7/16
9320 Chesapeake Drive, Suite 208 + San Diego, California 92123 + (858) 560-1468 + Fax (858) 560-1576
eARLSBAD 15-2200
JULY 24, 2015
GENERAL PLAN CORRECTION LIST
JURISDICTION: CARLSBAD PLAN CHECK NO.: 15-2200
PROJECT ADDRESS: 2050 AVENUE OF THE TREES
STORAGE ADD= 527; STORY= TWO; HEIGHT= 24; CONSTRUCTION =V-B;
OCCUPANCY= R3/U; TRELLIS ADD= 100
DATE PLAN RECEIVED BY
ESGIL CORPORATION: 7/16
REVIEWED BY: ALI SADRE, S.E.
FOREWORD (PLEASE READ):
DATE REVIEW COMPLETED:
JULY 24, 2015
This plan review is limited to the technical requirements contained in the International
Building Code, Uniform Plumbing Code, Uniform Mechanical Code, National Electrical
Code and state laws regulating energy conservation, noise attenuation and disabled
access. This plan review is based on regulations enforced by the Building Department.
You may have other corrections based on laws and ordinances enforced by the
Planning Department, Engineering Department or other departments.
The following items listed need clarification, modification or change. All items must be
satisfied before the plans will be in conformance with the cited codes and regulations.
The approval of the plans does not permit the violation of any state, county or city law.
• To facilitate rechecking, please identify, next to each item, the sheet of the
plans upon which each correction on this sheet has been made and return
this sheet with the revised plans.
• Please indicate here if any changes have been made to the plans that are not a
result of corrections from this list. If there are other changes, please briefly
describe them and where they are located on the plans. Have changes been
made not resulting from this list? 0 Yes 0 No
1. Please make all corrections, as requested in the correction list. Submit FOUR new complete sets of
plans for commercial/industrial projects (THREE sets of plans for residential projects). For
expeditious processing, corrected sets can be submitted in one of two ways:
1. Deliver all corrected sets of plans and calculations/reports directly to the City of Carlsbad Building
Department, 1635 Faraday Ave., Carlsbad, CA 92008, (760) 602-2700. The City will route the plans
to EsGil Corporation and the Carlsbad Planning, Engineering and Fire Departments.
2. Bring one corrected set of plans and calculations/reports to EsGil Corporation, 9320 Chesapeake
Drive, Suite 208, San Diego, CA 92123, (858) 560-1468. Deliver all remaining sets of plans and
calculations/reports directly to the City of Carlsbad Building Department for routin~~ to their Planning,
Engineering and Fire Departments.
NOTE: Plans that are submitted directly to EsGil Corporation only will not be reviewed by the City
Planning, Engineering and Fire Departments until review by EsGil Corporation is complete.
CARLSBAD 15-2200
JULY 24, 2015
2. Provide a statement on the Title Sheet of the plans stating that this project shall
comply with the 2013 California Residential Code, which adopts the 2012 IRC,
2012 UMC, 2012 UPC and the 2011 NEG. Section R1 06.1. Revise the note on
Sheet S-0 (bottom right corner) and that under General Notes accordingly.
3. Please add deck trellis addition = 1 00-s.f. under the scope of work.
4. Please show the deck trellis member size and spacing as well as details and
references for all their connections.
5. Please show the outline of the property lines on the details 1 through 4/S-3.
6. Clearly dimension storage addition setbacks from property lines on the site plan.
Section R106.2. See the next tow items as well.
7. If the proposed construction may affect existing construction on adjacent property,
provide the letter required by CBC Sec. 3307.
8. Provide a note on the plans stating that the contractor shall comply with all OSHA
requirements.
9. Please provide an architectural floor plan identifying the existing storage room
and its expansion.
10. Please show a legend on floor plans (as per item #3) identifying the walls to
remain, walls to be demolished and the new walls as well as any new & existing
doors and windows.
11. Please clarify two details #6 on Sheet S4.
12. Please cross reference all the details, as per Sheet S3, on the foundation/
framing plans (except for detail 7/S-3, which is already referenced on keynotes).
13. On Sheet S-2, please specify the pad footing reinforcement size & number.
14. The jurisdiction has contracted with EsGil Corporation located at B320
Chesapeake Drive, Suite 208, San Diego, California 92123; telephone number of
858/560-1468, to perform the plan review for your project. If you have any
questions regarding these plan review items, please contact ALI SADRE, S.E.
at EsGil Corporation. Thank you.
CARLSBAD 15-2200
JULY 24, 2015
[DO NOT PAY-THIS IS NOT AN INVOICE]
VALUATION AND PLAN CHECK FEE
JURISDICTION: CARLSBAD PLAN CHECK NO.: 15-2200
PREPARED BY: ALI SADRE, S.E. DATE: JULY 24, 2015
BUILDING ADDRESS: 2050 AVENUE OF THE TREES
BUILDING OCCUPANCY: R3/U; V-B
BUILDING AREA Valuation
PORTION (Sq. Ft.) Multiplier
TRELLIS 100
STORAGE 527
Air Conditioning
Fire Sprinklers
TOTAL VALUE
Jurisdiction Code CB By Ordinance
-----------------------~
Plan Check Fee by Ordinance .,.. ______________ ____,_
Type of Review: Complete Review
D Repetitive Fee -;l Repeats
-~
Comments:
D Other
0 Hourly
EsGil Fee
Reg. VALUE ($)
Mod.
18,155
$194.421
$126.371
o Structural Only
1--------11 Hr @ • $108.881
Sheet 1 of 1
macvalue.doc +
PLAN CHECK
REVIEW
TRANSMITTAL
DATE: PROJECT NAME:
PLAN CHECK NO: SET#: ADDRESS:
VALUATION: $18,1? SCOPE Of WORK:
Community & Economic
Development Department
1635 Faraday Avenue
Carlsbad CA 92008
www.carlsbadca.gov
PROJECT
APN:
:9\~1\¢\
m This plan check review is complete and has been APPROVED by: T LAND DEVELOPMENT ENGINEERING DIVISION
Final Inspection by Construction Management & Inspection Division is required: Yes No
This plan check review is NOT COMPLETE. Items missing or incorrect are listed on
the attached checklist. Please resubmit amended plans as required.
Remarks:
Plan Check Comments have been sent to:
':' ;r:~:·~~~~;:r~,~~~~:~,~~""r"~::s~;~::~~~~y;ii~7 > ~ ~~0', ,'
i liAND''DEVELO•:fi»MENl, ll 'o ...... ':T'T'" ·'. ' • ' 0 •'TCTjT ,:, Co • ,T • ooTo T '•3:·. ,C
j , .i · T \:,J60-6Q2-2.."i{,5Q ',•. · ,-,,;_:i"i'~' ,,, , ~::::_,:0¥'!-Y' :i,L,llhl>:, ~
Chris Glassen
7 60-602-2 7 84
Christopher.Giassen@carlsbadca.gov
Linda Ontiveros
760-602-2773
Linda.Ontiveros@carlsbadca.gov
VaiRay Nelson
760-602-27 41
VaiRay.Marshall@carlsbadca.gov
1. SITE PLAN
Provide a fully dimensioned site plan drawn to scale. Show:
North arrow
Existing & proposed structures
Existing street improvements
Property lines (show all dimensions)
Easements
Right-of-way width & adjacent streets
Show on site plan:
Driveway widths
Existing or proposed sewer lateral
Existing or proposed water service
Submit on signed approved plans:
DWG No.
Drainage patterns and proposed site elevations. Show all high points
Building pad surface drainage must maintain a minimum slope of one percent towards an adjoining
street or an approved drainage course.
ADD THE FOLLOWING NOTE: "Finish grade will provide a minimum positive drainage of 2% to swale
5' away from building".
Existing & proposed slopes and topography
.. Size, location, alignment of existing or proposed sewer and water service(s) that serves the project.
Each unit requires a separate service; however, second dwelling units and apartment complexes are an
exception.
Sewer and water laterals should not be located within proposed driveways, per standards.
Include on title sheet:
Site address di/ .::';)..~
-~ Assessor's parcel number U.:--I
(-. Legal description/lot number
For commercial/industrial buildings and tenant improvement projects, include: total building
square footage with the square footage for each different use, existing sewer permits
showing square footage of different uses (manufacturing, warehouse, office, etc.) previously
approved.
Show all existing use of SF and new proposed use of SF.
Example:
Tenant improvement for 3500 SF of warehouse to 3500 SF of office.
Lot/Map No.: 7682 LOT 31
Subdivision/Tract: CT 72-11
Reference No(s):
E-36 Page 2 of 6 REV 6/01/12
E-36
2. DISCRETIONARY APPROVAL COMPLIANCE
Project does not comply with the following engineering conditions of approval for project no.:
3. DEDICATION REQUIREMENTS
Dedication for all street rights-of-way adjacent to the building site and any storm drain or
utility easements on the building site is required for all new buildings and for remodels with a
value at or exceeding$ 24 000.00 , pursuant to Carlsbad Municipal Code Section 18.40.030.
Dedication required as follows:
4. IMPROVEMENT REQUIREMENTS
All needed public improvements upon and adjacent to the building site must be constructed
at time of building construction whenever the value of the construction exceeds
$120,000.00, pursuant to Carlsbad Municipal Code Section 18.40.040.
Public improvements required as follows:
Construction of the public improvements must be deferred pursuant to Carlsbad
Municipal Code Section 18.40. Please submit a recent property title report or current grant
deed on the property and processing fee, so we may prepare the necessary Neighborhood
Improvement Agreement. This agreement must be signed, notarized and
approved by the city prior to issuance of a building permit.
Future public improvements required as follows:
Page 3 of 6 REV 6/01/12
~~
-\<f. GRADING PERMIT REQUIREMENTS
0\ ·U ' \\}: ::9 \ \jJ
E-36
~~~onditions that require a grading permit are found in Section 15.16 of the Municipal
/Inadequate information available on site plan to make a determination on grading
requirements. Include accurate grading quantities in cubic yards (cut, fill, import, export and
remedial). This information must be included on the plans. If no grading is proposed
write: "NO GRADING"
Grading Permit required. NOTE: The grading permit must be is.sued and rough grading
approval obtained prior to issuance of a building permit.
Graded Pad Certification required. (Note: Pad certification may be required even if a grading
permit is not required.) All required documentation must be prov11ded to your Engineering
Construction Inspector The inspector will then
provide the engineering counter with a release for the building permit.
No grading permit required.
Minor Grading Permit required. See additional comments for project·· specific requirements.
6. MISCELLANEOUS PERMITS
RIGHT -OF-WAY PERMIT is required to do work in city right-of--way and/or private work
adjacent to the public right-of-way. Types of work include, but are not limited to: street
improvements, tree trimming, driveway construction, tying into public storm drain, sewer and
water utilities.
Right-of-way permit required for:
Page 4 of 6 REV 6/01112
E-36
7. STORM WATER
Construption Compliance
/Project Threat Assessment Form complete.
Enclosed Project Threat Assessment Form incomplete. ~equires Tier 1 Storm Water Pollution Prevention Plan (E-29). Please complete attached form
and return (SW 1.5 -:~)1~)
Requires Tier 2 Storm Water Pollution Prevention Plan. Requires submittal of Tier 2
SWPPP, payment of processing fee and review by city.
Post-Development (SUSMP) Compliance
~orm Water Standards Questionnaire.
Project is subject to Standard Storm Water Requirements. See city Standard Urban
Storm Water Management Plan (SUSMP) for reference.
Indicate areas of impervious surfaces (patios,walkway, etc. ) and pervious areas (landscaping).
Project needs to incorporate low impact development strategies throughout in one or
more of the following ways:
Rainwater harvesting (rain barrels or cistern)
Vegetated Roof
Bio-retentions cell/rain garden
Pervious pavement/pavers
Flow-through planter/vegetated or rock drip line
Vegetated swales or rock infiltration swales
Downspouts disconnect and discharge over landscape
Other:
Page 5 of 6 REV 6/01/12
Attachments:
E-36
8. WATER METER REVIEW
9. FEES
Domestic (potable) Use
What size meter is required?
Where a residential unit is required to have an automatic fire
extinguishing system, the minimum meter size shall be a 1" meter.
NOTE: the connection fee, SDCWA system capacity charge and the
water treatment capacity charge will be based on the size of the meter
necessary to meet the water use requirements.
For residential units the minimum size meter shall be 5/8", except where
the residential unit is larger than 3,500 square feet or on a lot larger than
one quarter (1/4) acre where the meter size shall be%".
Required fees have been entered in building permit.
Drainage fee applicable
Added square feet
Added square footage in last two years?
Permit No.
Permit No.
Project built after 1980
Impervious surface> 50%
Impact unconstructed facility
yes
yes
yes
yes
no
no
no
no
Fire sprinklers required
Upgrade
No fees required
yes
yes
no (is addition over 150' from center line)
no
10. ADDITIONAL COMMENTS
Engineering Application Storm Water Form Right-of-Way Application/ Info. Reference Documents
Page 6 of 6 REV 6/01/12
Fee Calculation Worksheet
ENGINEERING DIVISION
Prepared by: Date: GEO DATA: LFMZ: I B&T:
Address: Bldg. Permit#:
Fees Update by: Date: Fees Update by: Date:
EDU CALCULATIONS: List types and square footages for all uses.
Types of Use: Sq.Ft./Units
Types of Use: Sq.Ft./Units
Types of Use: Sq.Ft./Units
Types of Use: Sq.Ft./Units
ADT CALCULATIONS: List types and square footages for all uses.
Types of Use: Sq.Ft./Units
Types of Use:
Types of Use:
Types of Use:
FEES REQUIRED:
Sq.Ft./Units
Sq.Ft./Units
Sq.Ft./Units
EDU's:
EDU's:
EDU's:
EDU's:
ADT's:
ADT's:
ADT's:
ADT's:
Within CFD: 'YES (no bridge & thoroughfare fee in District #1, reduces Traffic Impact Fee) NO
1. PARK-IN-LIEU FEE: NW QUADRANT NE QUADRANT SE QUADRANT ;W QUADRANT
ADT'S/UNITS: I X FEE/ADT: I =$
2.TRAFFIC IMPACT FEE:
ADT'S/UNITS: I X FEE/ADT:
3. BRIDGE & THOROUGHFARE FEE: DIST. #1
(USE SANDAG)ADT'S/UNITS I X FEE/ADT:
4. FACILITIES MANAGEMENT FEE ZONE:
ADT'S/UNITS: I X FEE/SQ.FT./UNIT:
5. SEWER FEE
EDU's
BENEFIT AREA:
I X FEE/EDU:
EDU's
6. DRAINAGE FEES:
ACRES:
7. POTABLE WATER FEES:
IX
PLDA:
IX
FEE/EDU:
HIGH
FEE/AC:
I=$
DIST.#2
I=$
I=$
I=$
I=$
MEDIUM
I=$
LOW
UNITS CODE CONN. FEE METER FEE SDCWA FEE
DIST.#3
TOTAL
~ CITY OF
CARLSBAD
STORM WATER
COMPLIANCE
ASSESSMENT
B-24
Dev£}gl},ment Services
Building Division
1635 Faraday Avenue
760-602-2719
www.carlsbadca.gov
I am applying to the City of Carlsbad for the following type(s) of construction permit: J'. Building Permit D Right-of-Way Permit
D My project is categorically EXEMPT from
the requirement to prepare a storm water
pollution prevention plan (SWPPP) because it
only requires issuance of one or more of the
following permit types:
Electrical
Fire Additional
Fire Alarm
Fixed Systems
Mechanical
Mobile Home
Plumbing
Project Storm Water Threat Assessment Criteria*
Patio/Deck
Photo Voltaic
Re-Roofing
Sign
Spa-Factory
Sprinkler
Water Discharge
No Threat Assessment Criteria
D My project qualifies as NO THREAT and is exempt from the requirement to prepare a storm water pollution prevention plan (SWPPP) because
it meets the "no threar assessment criteria on the City's Project Threat Assessment Worksheet for Determination of Construction SWPPP Tier
Level. My project does not meet any of the High, Moderate or Low Threat criteria described below.
Tier 1 • Low Threat Assessment Criteria
..:¢;._ My project does not meet any of the Significant or Moderate Threat criteria, is not an exempt permit type (See list above) and the project
meets one or more of the following criteria:
• Results in some soil disturbance; and/or
• Includes outdoor construction activities (such as saw cutting, equipment washing, material stockpiling, vehicle fueling, waste stockpiling).
Tier 2 • Moderate Threat Assessment Criteria
D My project does not meet any of the Significant Threat assessment Criteria described below and meets one or more of the following criteria:
• Project requires a grading plan pursuant to the Carlsbad Grading Ordinance (Chapter 15.16 of the Carlsbad Municipal Code); or,
• Project will result in 2,500 square feet or more of soils disturbance including any associated construction staging, stockpiling, pavement
removal, equipment storage, refueling and maintenance areas and project meets one or more of the additional following criteria:
• Located within 200 feet of an environmentally sensitive area or the Pacific Ocean, and/or
• Disturbed area is located on a slope with a grade at or exceeding 5 horizontal to 1 vertical, and/or
• Disturbed area is located along or within 30 feet of a storm drain inlet, an open drainage channel or watercourse, and/or
• Construction will be initiated during the rainy season or will extend into the rainy season (Oct. 1 through Apri130).
Tier 3 • Significant Threat Assessment Criteria
D My project includes clearing, grading or other disturbances to the ground resulting in soil disturbance totaling one or more acres including any
associated construction staging, equipment storage, stockpiling, pavement removal, refueling and maintenance areas: and/or
[J My project is part of a phased development plan that will cumulatively result in soil disturbance totaling one or more acres including any
associated construction staging, equipment storage, refueling and maintenance areas: or,
D My project is located inside or within 200 feet of an environmentally sensitive area (see City ESA Proximity map) and has a significant
potential for contributing pollutants to nearby receiving waters by way of storm water runoff or non-storm water discharge(s).
I certify to the best of my knowledge that the above
checked statements are true and correct I understand
and acknowledge that even though this project does
not require preparation of a construction SWPP, I must
still adhere to, and at all times during construction
activities for the permit type(s) check above comply
with the storm water best management practices
pursuant to Title 15 of the Carlsbad Municipal Code
and to City Standards.
'The City Engineer may authorize minor variances from the Storm
Water Threat Assessment Criteria in special circumstances where it
can be shown that a lesser or higher Construction SWPPP Tier Level is
warranted.
B-24
Project Address: Assessor Parcel No.
l 5fo?~ <fo. tO·
Date: Project 10:
1-a4-IYQ
Page 1 of 1 Rev_03/09
Construction
SWPPPTier
Level
Tier3
Tier 2
Tier 1
Exempt
OF
BAD
CONSTRUCTION THREAT
ASSESSMENT WORKSHEET FOR
DETERMINATION OF PROJECT'S
PERCEIVED THREAT TO
STORM WATER QUALITY
E-33
Development Services
Land Development Engineering
1635 Faraday Avenue
760-602-2750
www.carlsbadca.gov
Perceived
Construction Threat Assessment Criteria* Threat to
Storm Water
Quality
Tier 3 -High Construction Threat Assessment Criteria
D Project site is 50 acres or more and grading will occur during the rainy season
D Project site is 1 acre or more in size and is located within the Buena Vista or Agua Hedionda
Lagoon watershed, inside or within 200 feet of an environmentally sensitive area {ESA) or
discharges directly to an ESA High D Soil at site is moderately to highly erosive {defined as having a predominance of soils with
D
USDA-NRCS Erosion factors kt greater than or equal to 0.4)
Site slope is 5 to 1 or steeper
D Construction is initiated during the rainy season or will extend into the rainy season {Oct. 1
D
through April 30).
Owner/contractor received a Storm Water Notice of Violation within past two years
Tier 3-Medium Construction Threat Assessment Criteria Medium D All projects not meeting Tier 3 High Construction Threat Assessment Criteria
Tier 2 High Construction Threat Assessment Criteria
D Project is located within the Buena Vista or Agua Hedionda Lagoon watershed, inside or
within 200 feet of an environmentally sensitive area {ESA) or discharges directly to an ESA
D Soil at site is moderately to highly erosive {defined as having a predominance olf soils with
USDA-NRCS Erosion factors kt greater than or equal to 0.4) High
D Site slope is 5 to 1 or steeper
D Construction is initiated during the rainy season or will extend into the rainy season {Oct. 1
through April 30).
D Owner/contractor received a Storm Water Notice of Violation within past two years
D Site results in one half acre or more of soil disturbance
Tier 2 -Medium Construction Threat Assessment Criteria Medium D All projects not meeting Tier 2 High Construction Threat Assessment Criteria
Tier 1 -Medium lnsgection Threat Assessment Criteria
D Project is located within the Buena Vista or Agua Hedionda Lagoon watershed, within or
directly adjacent to an environmentally sensitive area {ESA) or discharges directly to an ESA
0 Soil at site is moderately to highly erosive (defined as having a predominance of soils with
USDA-NRCS Erosion factors k1 greater than or equal to 0.4) Medium D Site slope is 5 to 1 or steeper
D Construction is initiated during the rainy season or will extend into the rainy season {Oct. 1
through April 30).
0 Owner/contractor received a Storm Water Notice of Violation within past two years
D Site results in one half acre or more of soil disturbance
Tier 1 -Low lnsgection Th[eat Assessment Criteria Low D All projects not meeting Tier 1 Medium Construction Threat Assessment Criteria
-Not Applicable -Exempt
*The c1ty engineer may authonze mmor vanances from the construction threat assessment cntena 1n spec1al circumstances
where it can be shown that a lesser or higher amount of storm water compliance inspection is warrante•d in the opinion of
the city engineer
E-33 Page 1 of 1 REV 4/30/10
STORM WATER
STANDARDS
QUESTIONNAIRE
E-34
Development Services
Land Development Engineering
1635 Faraday Avenue
760-602-2750
www.carlsbadca.gov
To address post-development pollutants that may be generated from development projects, the City require's that new development and
significant redevelopment priority projects incorporate Permanent Storm Water Best Management PractiGes (BMP's) into the project
design per the City's Standard Urban Stormwater Management Plan (SUSMP). To view the SUSMP, refer to the Engineering Standards
(Volume 4, Chapter 2) at www.carlsbadca.gov/standards.
Initially this questionnaire must be completed by the applicant in advance of submitting for a development application (subdivision,
discretionary permits and/or construction permits). The results of the questionnaire determine the level olf storm water standards that
must be applied to a proposed development or redevelopment project. Depending on the outcome, your project will either be subject to
'Standard Stormwater Requirements' or be subject to additional criteria called 'Priority Development Project Requirements'. Many
aspects of project site design are dependent upon the storm water standards applied to a project.
Your responses to the questionnaire represent an initial assessment of the proposed project conditions and impacts. City staff has
responsibility for making the final assessment after submission of the development application. If staff determines that the questionnaire
was incorrectly filled out and is subject to more stringent storm water standards than initially assessed by you, this will result in the return
of the development application as incomplete. In this case, please make the changes to the questionnaire and resubmit to the City.
If you are unsure about the meaning of a question or need help in determining how to respond to one or more of the questions, please
seek assistance from Land Development Engineering staff.
A separate completed and signed questionnaire must be submitted for each new development application submission. Only one
completed and signed questionnaire is required when multiple development applications for the same project are submitted concurrently.
In addition to this questionnaire, you must also complete, sign and submit a Project Threat Assessment Form with construction permits
for the project.
Please start by completing Step 1 and follow the instructions. When completed, sign the form at the end and submit this with your
application to the city.
To determine if your project is a priority development project, please answer the following questions:
1. ls your project LIMITED TO constructing new or retrofitting paved sidewalks, bicycle 1 meet
the following criteria: (1) Designed and constructed to direct storm water runoff to adjacent vegetated areas, or
other non-erodible permeable areas; OR (2) designed and constructed to be hydraulically disconnected from
paved streets or roads; OR (3) designed and constructed with permeable pavements or surfaces in
accordance with USEPA Green Streets
2. Is your project retrofitting or redeveloping existing paved or roads that are
designed and in accordance with the US EPA Green
YES
If you answered "yes" to one or more of the above questions, then your project is NOT a priority development project and therefore is
NOT subject to the storm water criteria required for priority development projects. Go to step 4, mark the last box stating "my
project does not meet PDP requirements" and complete applicant information.
answered "no" to both 2.
E-34 Page 1 of3 Effective 6/27/13
CITY OF
STORM WATER
STANDARDS
QUESTIONNAIRE
E-34
Development S.ervices
Land Development Engineering
1635 Faraday Avenue
760-602-2750
www.carlsbadca.gov
o determine if your project is a priority development project, please answer the following questions:
1 . Is your project a new development that creates 10,000 square feet or more of impervious surfaces collectively
over the entire project site? This includes commercial, industrial, residential, mixed-use, and public
on land.
2. Is your project creating or replacing 5,000 square feet or more of impervious surface collectively over the entire
project site on an existing site of 10,000 square feet or more of impervious surface? This includes commercial,
3. Is your project a new or redevelopment project that creates 5,000 square feet or more of impervious surface
collectively over the entire project site and supports a restaurant? A restaurant is a facility that sells prepared
foods and drinks for consumption, including stationary lunch counters and refreshment stands selling prepared
foods and drinks for immediate
4. Is your project a new or redevelopment project that creates 5,000 square feet or more of impervious surface
collectively over the entire project site and supports a hillside development project? A hillside development
project includes development on any natural slope that is twenty-five percent or greater.
5. Is your project a new or redevelopment project that creates 5,000 square feet or more of impervious surface
collectively over the entire project site and supports a parking lot. A parking lot is a land area or facility for the
6. Is your project a new or redevelopment project that creates 5,000 square feet or more of impervious surface
collectively over the entire project site and supports a street, road, highway freeway or driveway? A street,
road, highway, freeway or driveway is any paved impervious surface used for the transportation of
7. Is your project a new or redevelopment project that creates or replaces 2,500 square feet or more of
impervious surface collectively over the entire site, and discharges directly to an Environmentally Sensitive
Area (ESA)? "Discharging Directly to» includes flow that is conveyed overland a distance of 200 feet or less
from the project to the ESA, or conveyed in a pipe or open channel any distance as an isolated flow tram the
the ESA e. not with flows from *
8. Is your project a new development that supports an automotive repair shop? An automotive repair shop is a
facility that is categorized in any one of the following Standard Industrial Classification (SIC) codes: 5013,
5541 or 7536-7539.
9. Is your project a new development that supports a retail gasoline outlet (RGO)? This category includes RGO's
that meet the following criteria: (a) 5,000 square feet or more or (b) a project Average Daily Traffic (ADT) of
100 or more vehicles
1 O.ls your project a new or redevelopment project that results in the disturbance of one or more acres of land and
are expected to generate pollutants post construction?
creates 2,500 square feet or more of
i s surface on the more than 10%?
n"<\N .. , ... n ''yes" to one or more of the above questions, you ARE a priority development project and are therefore subject to
lomnl~•m•>ntonn structural Best Management Practices (BMP's) in addition to implementing Standard Storm Water Requirements such
source control and low impact development BMP's. A Storm Water Management Plan (SWMP) must be submitted with your
lication(s) for development. Go to step 3 for redevelopment projects. For new projects, go to step 4 at the end of this
IQLJiestlonn,alre, check the "my project meets PDP requirements" box and complete applicant information.
you answered "no" to all of the above questions, you ARE NOT a priority development project and are therefore subject
menting only Standard Storm Water Requirements such as source control and low impact development BMP's required for all
evelopment projects. A Storm Water Management Plan (SWMP) is not required with your application(s) for development. Go to ste
at the end of this questionnaire, check the "my project does not meet PDP requirements" box and complete app
E-34 Page 2 of3 Effective 6/27/13
OF
CARLS
STORM WATER
STANDARDS
QUESTIONNAIRE
E-34
Development Serv.[ces
Land Development Engineering
1635 Faraday Avenue
760-602-2750
www.carlsbadca.gov
If you answered "yes," the structural BMP's required for Priority Development Projects apply only to the creation or replacement of
impervious surface and not the entire development. Go to step 4, check the "my project meets PDP requirements" box and
complete applicant information.
If you answered "no," the structural BMP's required for Priority Development Projects apply to the entire development. Go to step 4,
check the meets PDP irements" box info
My project meets PRIOPITY DEVELOPMENT PROJECT (PDP) requirements and must comply with additional stormwater
criteria per the SUSMP a HJ I understand I must prepare a Storm Water Management Plan for submittal at time of application.
I understand flow control (ilycromodification) requirements may apply to my project. Refer to SUSMP for details.
My project does not m;"d PDP requirements and must only comply with STANDARD STORMWATER REQUIREMENTS per
the SUSMP. As part of these requirements, I will incorporate low impact development strategies throughout my project.
Applicant Information and Signature Oox
-DD
Date:
This Box for City Use Only
City Concurrence: NO
*Environmentally Sensitive Areas inclttrlP but are not limited to all Clean Water Act Section 303(d) impaired water bodies; areas
designated as Areas of Special Bioi o;,:;,i Significance by the State Water Resources Control Board (Water Quality Control Plan for the
San Diego Basin (1994) and amenc;,;, nts); water bodies designated with the RARE beneficial use by the State Water Resources
Control Board (Water Quality Control f'lan for the San Diego Basin (1994) and amendments); areas designated as preserves or their
quivalent under the Multi Species Conservation Program within the Cities and County of San Diego; and any other equivalent
environmentally sensitive areas which have been identified by the Copermittees.
E-34 Page 3 of3 Effective 6/27/13
STORM WATER COMPLIANCE FORM
TIER 1 CONSTRUCTION SWPPP
E-29
STORM WATER COMPLIANCE CERTIFICATE
./ My project is not in a category of permit types exempt from the Construction
SWPPP requirements
./ My project is not located inside or within 200 feet of an environmentally
sensitive area with a significant potential for contributing pollutants to nearby
receiving waters by way of storm water runoff or non-storm water
discharge(s).
./ My project does not require a grading plan pursuant to the Carlsbad
Grading Ordinance (Chapter 15.16 ofthe Carlsbad Municipal Code)
./ My project will not result in 2,500 square feet or more of soils disturbance
including any associated construction staging, stockpiling, pavement
removal, equipment storage, refueling and maintenance areas that meets
one or more of the additional following criteria:
located within 200 feet of an environmentally sensitive area or the
Pacific Ocean; and/or,
disturbed area is located on a slope with a grade at or exceeding 5
horizontal to 1 vertical; and/or
disturbed area is located along or within 30 feet of a storm drain inlet, an
open drainage channel or watercourse; and/or
construction will be initiated during the rainy season or will extend into
the rainy season (Oct. 1 through April 30).
I CERTIFY TO THE BEST OF MY KNOWLEDGE THAT ALL OF THE ABOVE
CHECKED STATEMENTS ARE TRUE AND CORRECT. I AM SUBMITTING
FOR CITY APPROVAL A TIER 1 CONSTRUCTION SWPPP PREPARED IN
ACCORDANCE WITH THE REQUIREMENTS OF CITY STANDARDS.
I UNDERSTAND AND ACKNOWLEDGE THAT I MUST: (1) IMPLEMENT BEST
MANAGEMENT PRACTICES (BMPS) DURING CONSTRUCTION ACTIVITIES
TO THE MAXIMUM EXTENT PRACTICABLE TO MINIMIZE THE
MOBILIZATION OF POLLUTANTS SUCH AS SEDIMENT AND TO MINIMIZE
THE EXPOSURE OF STORM WATER TO CONSTRUCTION RELATED
POLLUTANTS; AND, (2) ADHERE TO, AND AT ALL TIMES, COMPLY WITH
THIS CITY APPROVED TIER 1 CONSTRUCTION SWPPP THROUGHOUT THE
DURATION OF THE CONSTRUCTION ACTIVITIES UNTIL THE
CONSTRUCTION WORK IS COMPLETE AND APPROVED BY THE CITY OF
CARLSBAD . .. ·y_ o IV•rr·f &7
.. ,_ ·-.. -.. ,,. ·-.::<: .. -..... .. ..
E-29
STORM WATER POLLUTION PREVENTION NOTES
1. ALL NECESSARY EQUIPMENT AND MATERIALS
SHALL BE AVAILABLE ON SITE TO FACILITATE
RAPID INSTALLATION OF EROSION AND
SEDIMENT CONTROL BMPS WHEN RAIN IS
EMINENT.
2. THE OWNER/CONTRACTOR SHALL RESTORE
ALL EROSION CONTROL DEVICES TO
WORKING ORDER TO THE SATISFACTION OF
THE CITY ENGINEER AFTER EACH RUN-OFF
PRODUCING RAINFALL.
3. THE OWNER/CONTRACTOR SHALL INSTALL
ADDITIONAL EROSION CONTROL MEASURES
AS MAY BE REQUIRED BY THE CITY
ENGINEERING OR BUILDING INSPECTOR DUE
TO UNCOMPLETED GRADING OPERATIONS OR
UNFORESEEN CIRCUMSTANCES WHICH MAY
ARISE.
4. ALL REMOVABLE PROTECTIVE DEVICES SHALL
BE IN PLACE AT THE END OF EACH WORKING
DAY WHEN THE FIVE (5) DAY RAIN
PROBABILITY FORECAST EXCEEDS FORTY
PERCENT (40%). SILT AND OTHER DEBRIS
SHALL BE REMOVED AFTER EACH RAINFALL.
5. ALL GRAVEL BAGS SHALL BE BURLAP TYPE
WITH 3/41NCH MINIMUM AGGREGATE.
6. ADEQUATE EROSION AND SEDIMENT
CONTROL AND PERIMETER PROTECTION BEST
MANAGEMENT PRACTICE MEASURES MUST BE
INSTALLED AND MAINTAINED.
SPECIAL NOTES
Page 1 of 3
Development Services
land Development Engineering
1635 Faraday Avenue
760-602-2750
www.carlsbadca.gov
PROJECT INFORMATION
Site Address: 2050 Ave. of the Trees
Assessor's Parcel Number: 156-290-10-00
Project 1 D Su) IS -,;n g
Construction Permit No.: C£2 j 5 -'i70Q)
Estimated Construction Start Date ------
Project Duration Months
Emergency Contact:
Name: Ronald Baker
24 hour Phone: (805) 698-3056
Perceived Threat to Storm Water Quality
0 Medium
)?f Low
If medium box is checked, must attach a site plan
sheet showing proposed work area and location
of proposed structural BMPs
For City Use Only
REV 4/30/10
Best Management Practice
(BMP) Description 7
CASQA Designation 7
1 Construction Activity
""'] Grading/Soil Disturbance
TrenchinQ/Excavation
Stockpiling
Drilling/Boring
Concrete/Asphalt Saw
cutting
Concrete flatwork
Pavir19_
Conduit/P_i[J_e Installation
Stucco/Mortar Work
Waste Disposal
Stagingllay Down Area
Equipment Maintenance
and FuelinQ
Hazardous Substance
Use/Storage
Dewatering
Site Access Across Dirt
Other (list):
~ ~
o6
"' Q)
1
c'!l
,_
0 UJ
Erosion Control
BMPs
"' OJ "0 Q) ~ @~ UJ ~ ~ U) -~
::J ~ Q) ~ ~ 0 OJ 0
"'C ...c ~ (]) 0 "t::: ·-0... ~ tTI tl ~
co Ol
0 UJ
0 UJ 0 UJ
Q) '-' c Q) lL
Uj
~ uJ (j)
a. ~ 1-c: Q)
E '0 Q)
(j)
<') uJ (j)
Sediment Control BMPs
E "' 0
-"' '-' Q)
6
""i UJ (j)
!!!_
0 0::
Q; ..a u::
Ill uJ (j)
X.
"0 c "' E OJ ~ ~ c Q) (]) --·;;::::: o:l a. ~
Q) "' 0) m Q) CCI ~ ~-~ g' CD _. ::J ...c > CD ::J "'C co Q) (,) c ~...... !::; ro ro
(9 (j) > (j)
(J) ,_ co uJ uJ w (j) (j) (j)
0:5 :E
c -~ c: o:&
E$ .s e UJO..
0
~ w (j)
Tracking
Control
BMPs
c c 0 0 u t5 ..s .s ~ ~ ~ 0 Q) 0 o~:;,o
"'C UJ ""C >.. m-m ro ~ ~ ~~ ...o ~..... ...c rn l3~b3&
~ N
r:C. I-I-
Non-Storm Water
Management BMPs
c 0 ~ i:: Ql "' c
0 "' () Q)
!..... -~ 2 01 ~£
rh z
OJ c '0 c l5
"0 c "' OJ c ·:;: CO• o..C
;;; z
c 0 ~ OJ .E
~ ~
Q) ::c ~ 0..
,_
rh z
c: ~ a. ·:;
CJ
"0 c
"' 0 Ql c u ·c
£ m ~0
co rh z
Waste Management and Materials
Pollution Control BMPs
"0 c "' ~ Ql .2: a;
0
Ql "' :::>
~~ ~ rn ro ~ ~
~ ~ s:
<)!
~
c: Ql E Q) OJ "' c "' ~
..<!' ·c.
-"' ~
<') ~ s:
"0 c "' c ~1 Q)
Ql 1i)
> "' ~ ~ a. 0 (j) (j)
""i ~ s:
Ill ~
"* ~
"' :::0 0 "E ~ :E
~ ~ s:
2 ~
~ '-' c 8
co ~ s:
Instructions: Begin by reviewing the list of construction activities and checking the box to the left of any activity that will occur during the proposed construction. Add any other activity descriptions in the
blank activity description boxes provided for that purpose and place a check in the box immediately to the left of the added activity description. For each activity descrribed, pick one or more best
management practices (BMPs) from the list located along the top of the form. Then place an X in the box at the place where the activity row intersects with the BMP column. Do this for each activity that was
checked off and for each of the selected BMPs selected from the list. For Example -If the project includes site access across dirt, then check the box to the left of "Site Access Across Dirt". Then review
the list for something that applies such as "Stabilized Construction Ingress/Egress" under Tracking Control. Follow along the "Site Access Across Dirt" row until you get to the "Stabilized Construction
Ingress/Egress" column and place an X in the box where the two meet. As another example say the project included a stockpile that you intend to cover with a plastic sheet. Since plastic sheeting is not on
the list of BMPs, then write in "Cover with Plastic" in the blank column under the heading Erosion Control BMPs. Then place an X in the box where the "Stockpiling" row intersects the new "Cover with
Plastic" column.
To learn more about what each BMP description means, you may wish to review the BMP Reference Handout prepared to assist applicants in the selection of appropriate Best Management Practice
measures. The reference also explains the Califomia Stonnwater Quality Association (CASQA) designation and how to apply the various selected BMPs to a project.
E-29 Page 2 of 3 REV 4/30/10
PLANNING DIVISION
BUILDING PLAN CHECK
APPROVAL
P-29
DATE: 7-16-15 PROJECT NAME: PROJECT ID:
Planning Division
1635 Faraday Avenue
(760) 602-4610
www.carlsbadca.e:ov
PLAN CHECK NO: CB 15-2200 SET#: 1 ADDRESS: 2050 Ave of the Trees APN:
l2SJ This plan check review is complete and has been APPROVED by the Planning
Division.
By: Chris Sexton
A Final Inspection by the Planning Division is required Yes ~No
You may also have corrections from one or more of the divisions listed below. Approval
from these divisions may be required prior to the issuance of a building permit.
Resubmitted plans should include corrections from all divisions.
This plan check review is NOT COMPLETE. Items missing or incorrect are listed on
the attached checklist. Please resubmit amended plans as required.
Plan Check APPROVAL has been sent to:
For questions or clarifications on the attached checklist please contact the following reviewer as marked:
PLANNING
760-602-4610
~ Chris Sexton
760-602-4624
Chris.Sexton@carlsbadca.gov
D Gina Ruiz
760-602-4675
Gina.Ruiz@carlsbadca.gov
Remarks:
ENGINEERING
.760c602-2750
FIRE PREVENTION
760~602-4665
Project Address:
PLUMBING,
ELECTRICAL,
MECHANICAL
WORKSHEET
B-18
Permit No.:
Developm_ent Services
Building Division
1635 Faraday Avenue
760-602-2719
www.carlsbadca.gov
Building@carlsbadca.gov
Information provided below refers to worR being done on the above mentioned permit only.
This form must be completed and returned to the Building Division before the permit cant be issued.
B-18
Building Dept. Fax: (760) 602-8558
Number of new or relocated fixtures, traps, or floor drains ....................................................... _/ __
New building sewer line? ......................................................................................... Yes __ No A_
Number of new roof drains? ................................................................................................................ -Q
Install/alter water line? ..................................................................................................................... ~ ... __ ( _
Number of new water heaters?.......................................................................................................... &_
Number of new, relocated or replaced gas outlets?..................................................................... iS(__
Number of new hose bibs? .................................................................................................................. -~
Residential Permits: 11 1 1 vv; /}-New/expanded service: Number of new amps: ----+1......;..........;..,. __
Minor Remodel only: Yes~ No
Commercial/Industrial:
Tenant Improvement: Number of existing amps involved in this project:
Number of new amps involved in this project:
New Construction: Amps per Panel:
Single Phase ............................................................... Number of new amperes
Three Phase ................................................................. Number of new amperes
Three Phase 480 ........................................................ Number of new amperes·----
Number of new furnaces, A/C, or heat pumps?............................................................................ '{)_\
New or relocated duct worl?? .......................................................................... Yes ____ No ~
Number of new fireplaces? .................................................................................................................. -~
Number of new exhaust fans? ............................................................................................................. ~
Relocate/install vent? ............................................................................................................................. i
Number of new exhaust hoods? ......................................................................................................... _E.
Number of new boilers or compressors? ........................................................... Number of HP s.\.
Page 1 of 1 Rev. 03/09
City of Carlsbad
1635 Faraday Av Carlsbad, CA 92008
09-24-2015 Plan Check Revision Permit No:PCR15080
Job Address:
Permit Type:
Parcel No:
Valuation:
Reference #:
PC#:
Project Title:
Applicant:
Building Inspection Request Line (760) 602-2725
2050 AVENUE OF THE TREES CBAD
PCR
1562901000
$0.00
CB152200
Lot#: 0
Construction Type: 58
EBERHART: ADD 116 SF TO BASE
MENT
Owner:
Status:
Applied:
Entered By:
Plan Approved:
Issued:
Inspect Area:
ISSUED
09/14/2015
JMA
09/24/2015
09/24/2015
RON BARKER EBERHART JUDITH E REVOCABLE TRUST 01-09-02
2050 AVENUE OF THE TREES
CARLSBAD CA 92008
805-698-3056
Plan Check Revision Fee
Fire Expedited Plan Review
Additional Fees
Total Fees: $145.00
Inspector:
2050 AVENUE OF THE TREES
CARLSBAD CA 92008
$145.00
$0.00
$0.00
Total Payments To Date: $145.00 Balance Due:
FINAL APPROVAL
Date: Clearance:
$0.00
NOTICE Please take NO'TlCE that approval of your project indudes the "Imposition'' of fees, dedications, reservations, or other exactions hereafter oollectively
referred to as "fees/exactions." You have 90 days from the date tlis perrrit was issued to protest irrposition of these fees/exactions. If you protest them, you must
follow the protest procedures set forth in G:Jvemrrent Code Section 66020(a), and file the protest and any other required information wth the City Manager for
processing in a=rdance wth Carlsbad Munidpal Code Section 3.32.030. Failure to tirrely follow that proceciJre VIAll bar any subsequent legal action to attack,
review, set aside, void, or annul th6r irrposition.
You are hereby FURTHER NOTIFIED that your right to protest the spedfied fees/exactions DOES NOT .APPLY to water and SEMer ronnection fees and capadty
changes, nor planning, zoning, grading or other simlar application ~ing or service fees in ronnection wth this project. NOR DOES IT .APPLY to any
fees/exactions of whidl vou have oreviouslv been~ven a NOTICE sinilar to this or as to whidl the statute of linitations has oreviouslv other\IIAse exnired.
Cicyof
Carlsbad
PLAN CHECK REVISION
APPLICATION
B-15
DeveloP,ment Services
Building Division
1635 Faraday Avenue
760-602-2719
www.carlsbadca.gov
Plan Check Revision No. f C l~ l$-{;-() Original Plan Check No. CPJ { ~.. '2-2()0
Project Address 2050 Avenue of the Trees, Carlsbad, CA 92008 ·Date September 14, 2015
Contact Ron Baker Ph (805) 698-3056 Fax None
Email ron@ronbakerpix.com
Contact Address 2050 Avenue of the Trees City Carlsbad Zip 92008
General Scope of Work
Original plans prepared by an architect or engineer, revisions must be signed & stamped by that person.
1 . Elements revised:
I../ I Plans D Calculations D Soils D Energy D Other
2. 3.
Describe revisions in detail List page(s) where
each revision is
shown
Increase scope of work. Expand the storage room at basement level All Pages
as shown in plans by approximately 116 SF.
5. Does this revision, in any way, alter the exterior of the project? D Yes
6. Does this revision add ANY new floor area(s)7 I./I Yes D No
7.
8.
DYes [2]No
4.
List revised sheets
that replace
existing sheets
All Pages
[2)No
1635 Faraday Avenue, Carlsbad, CA 92008 fh: 760-602-2719 w: 760-602-8558 Email: building@carlsbadca.gov
www.carlsbadca.gov
EsGil Corporation
In CJ?artnersfiip witfi qovernment for <Bui{aing Safety
DATE: SEPT. 22, 2015 ~PLICANT
~ ~~RIS.
JURISDICTION: CARLSBAD D PLAN REVIEWER
D FILE
PLAN CHECK NO.: 15-2200 (REV. #1)-NEW PCR #15-80 __ SET: I
PROJECT ADDRESS: 2050 AVENUE OF THE TREES
PROJECT NAME: SFR BASEMENT STORAGE EXPANSION
[gj The plans transmitted herewith have been corrected where necessary and substantially comply
with the jurisdiction's building codes.
D The plans transmitted herewith will substantially comply with the jurisdiction's
codes when minor deficiencies identified below are resolved and checked by building
department staff.
D The plans transmitted herewith have significant deficiencies identified on the enclosed check list
and should be corrected and resubmitted for a complete recheck.
D The check list transmitted herewith is for your information. The plans are being held at Esgil
Corporation until corrected plans are submitted for recheck.
D The applicant's copy of the check list is enclosed for the jurisdiction to forward to the applicant
contact person.
D The applicant's copy of the check list has been sent to:
RON BAKER
[gl EsGil Corporation staff did not advise the applicant that the plan check has been completed.
D EsGil Corporation staff did advise the applicant that the plan check has been completed.
Person contacted: RON Telephone#: 805-698-3056
Date contacted: (by: ) Email: ron@ronbakerpix.com
Mail Telephone Fax In Person
~ REMARKS: Expansion of the basement storage (116-s.f.) is under this permit. All sheets of
plans were impacted and new sets submitted.
By: ALI SADRE, S.E. Enclosures:
EsGil Corporation
0 GA 0 EJ 0 MB 0 PC 9/14
9320 Chesapeake Drive, Suite 208 + San Diego, California 92123 + (858) 560-1468 + Fax (858) 560-1576
CARLSBAD 15-2200 (REV. #1)-NEW PCR #15-80
SEPT.22,2015
[DO NOT PAY-THIS IS NOT AN INVOICE]
VALUATION AND PLAN CHECK FEE
JURISDICTION: CARLSBAD
#1)-NEW PCR #15-80
PLAN CHECK NO.: 15-2200 (REV.
PREPARED BY: ALI SADRE, S.E. DATE: SEPT.22,2015
BUILDING ADDRESS: 2050 AVENUE OF THE TREES
BUILDING OCCUPANCY: R3/U; V-B
BUILDING AREA Valuation
PORTION (Sq. Ft.) Multiplier
BASEMENT 116
STORAGE
ADDED
Air Conditioning
Fire Sprinklers
TOTAL VALUE
Jurisdiction Code CB By Ordinance
-Bldg. Permit Fee by Ordina~~3
Plan Check Fee by Ordinance
Type of Review: 0 Complete Review
0 Repetitive Fee [-3 Repeats
* Based on hourly rate
Comments:
o Other
0 Hourly
EsGil Fee
Reg. VALUE
Mod.
o Structural Only
11Hr.@ *
=====$=1=1=6 ·=oo:
($)
$145.001
$116.001
Sheet 1 of 1
macvalue.doc +
PLAN CHECK
REVIEW
TRANSMITTAL
DATE:09·16-2015 PROJECT NAME: """""'""'
PLAN CHECK NO: 15-80 SET#: ADDRESS: 2050
VALUATION: $
Community & Economic
Development Department
1635 Faraday Avenue
Carlsbad CA 92008
www .carlsbadca.gov
PROJECT ID: CB15-2200
J\PN: 156-290-10-00
This plan check review is complete and has been APPROVED by the ENGINEERING
Division.
By: CG
A Final Inspection by the Division is required Yes No
This plan check review is NOT COMPLETE. Items missing or incorrect are listed on
the attached checklist. Please resubmit amended plans as required.
For questions or clarifications on the attached checklist please contact the following reviewer as marked:
Gina Ruiz
760-602-4675
Remarks:
.Qbristopher.Giassen@carlsbadca.gov
Linda Ontiveros
760-602-2773
Cindy Wong
760-602-4662
Cynthia.Wong@carlsbadca.gov
Dominic Fieri
7 60-Ei02-4664
Dominic.Fi·eri@carlsbadca.gov
BUILDING PLANCHECK
CHECKLIST
QUICK-CHECK/APPROVAL
Development Services
Land Development Engineering
1635 Faraday Avenue
760-602-2750
www .carlsbadca.gov
ENGINEERING Plan Check for Date: 5
Project Address:
Project Description: THE BASEMENT
ENGINEERING Contact :
Phone:
RESIDENTIAL INTERIOR
RESIDENTIAL ADDITION MINOR
(<$20,000.00)
APN: 1
Email:
Fax:
TENANT IMPROVEMENT
PLAZA CAMINO REAL
. CARLSBAD PREMIER OUTLETS COMPLETE OFFICE BUILDING
OTHER: GYM
r··-··-··-··-··-··-··-··-··-··-··-··-··-··-··-··-··-··-··, OFFICIAL USE ONLY
ENGINEERING AUTHORIZATION TO ISSUE BUILDING PERMIT
BY: DATE: 5
REMARKS:
Notification of Engineering APPROVAL has been sent to
via on 5 -··-··-··-··-··-··-··-··-··-···-··-··-··-··-··-··-··-··-·
E-36 Page 1 of 1 REV 4/30/11
PLANNING DIVISION
BUILDING PLAN CHECK
APPROVAL
P-29
DATE: 9-16-15 PROJECT NAME: PROJECT ID:
Planning Division
1635 Faraday Avenue
(760) 602-4610
WWW.Cilrisb<JdC<J.I:?:OV
PLAN CHECK NO: PCR 15-80 SET#: 1 ADDRESS: 2050 Avenue of the Trees APN:
cg] This plan check review is complete and has been APPROVED by the Planning
Division.
By: Chris Sexton
A Final Inspection by the Planning Division is required Yes ~J No
You may also have corrections from one or more of divisions listf:~d below. Approval
from these divisions may be required to a building permit.
Resubmitted plans should include
This plan check review is NOT COMPLETE. Items missing or incorrect are listed on
the attached checklist. Please resubmit amended plans as required.
Plan Check APPROVAL has been sent to:
For questions or clarifications on the attached checklist please contact the following reviewer as marked:
D
PlANNING
'760-602-4610
760-602-4624
Ch ris.Sexton@carlsbadca.gov
Gina Ruiz
760-602-4675
Gina.Ruiz@carlsbadca.gov
Remarks:
ENGINEERING.
760-602~2750
FIRE PREVENTION
760-602~4665