HomeMy WebLinkAbout2611 ACUNA CT; ; CB140916; Permit05-07-2014
City of Carlsbad
1635 Faraday Av Carlsbad.CA 92008
Pool Permit Permit No: GB140916
Building Inspection Request Line (760) 602-2725
Job Address:
Permit Type:
Parcel No:
Valuation:
Reference #:
PG#:
Project Title:
2611 ACUNA CTCBAD
POOL
2154911500 Lot#:
$32,576.00 Construction Type:
GALE RES- 800 SF POOL SHOTCRET
0
NEW
Status: ISSUED
Applied: 04/23/2014
Entered By:
Plan Approved:
SKS
05/07/2014
Issued: 05/07/2014
Inspect Area:
Applicant:
WATERLINE POOLS AND SPAS INC.
Owner;
GALE LARRY L&JULIE A
P.O. BOX 605
CARDIFF CA 92007
760-815-6733
2611 ACUNA CT
CARLSBAD CA 92009
Building Permit
Add'l Building Permit Fee
Plan Check
Add'! Plan Check Fee
Electrical Fee
Plumbing Fee
Strong Motion Fee
Green BIdg Standards (SB1473) Fee
Renewal Fee
Add'l Renewal Fee
Other Building Fee
Additional Fees
$330.43
$0.00
$231.30
$0.00
$33.00
$33.00
$3.26
$1.00
$0.00
$0.00
$0.00
$0.00
TOTAL PERMIT FEES $631.99
Total Fees: $631.99 Total Paynnents To Date: $631.99 Balance Due: $0.00
it Inspector:
FINAL
Date
-APPROV/L
Clearance:
NOTICE: Please take NOTICE ttiat approval otyour project includes ttie 'Imposition' of fees, dedications, reservations, or ottier exactions hereafter collectively
referred lo as "fees/exactions," You have 90 days from the date Itiis permit v»as issued lo protest imposilion of these fees/exactions, Ifyou protest them, you must
follow the protest procedures set forth in Government Code Section 66020(a), and file the protest and any other required information with the City Manager for
processing in accordance with Carlsbad Municipal Code Section 3,32,030, Failure to timely follow that procedure will bar any subsequent legal action to attack,
review, set aside, void, or annul their imposition.
You are hereby FURTHER NOTIFIED that your right to protest the specified fees/exactions DOES NOT APPLY to water and sewer connection fees and capacity
changes, nor planning, zoning, grading or other similar application processing or service fees in connection with this project, NOR DOES IT APPLY to any
fees/exactions of which vou have previouslv been given a NOTICE similar to this, or as to which the ,statute of limitations has oreviouslv otherwise expired,
05-07-2014
City of Carlsbad
1635 Faraday Av Carlsbad.CA 92008
Storm Water Pollution Prevention Plan (SWPPP) Permit
Permit No:SW140132
Job Address:
Permit Type:
Parcel No:
Reference #:
CB#:
Project Title:
2611 ACUNA CTCBAD
SWPPP
2154911500
CB140916
GALE RES- 800 SF POOL
Lot#:
Appiicant:
WATERLINE POOLS AND SPAS INC,
Status:
Applied:
Entered By:
Issued:
Inspect Area:
Tier:
Priority:
Owner:
GALE LARRY L&JULIE A
ISSUED
04/23/2014
SKS
05/07/2014
1
L
P,0, BOX 605
CARDIFF OA 92007
760-815-6733
2611 ACUNA CT
CARLSBAD CA 92009
Emergency Contact:
PIETER DREEUWS
760-815-6733
SWPPP Plan Check
SWPPP Inspections
Additional Fees
$48,00
$57.00
$0.00
TOTAL PERMIT FEES $105.00
Total Fees: $105.00 Total Payments To Date: $105.00 Balance Due: $0.00
FINAL APPROVAL
DATE
SIGNATURE mi
THE FOLLOWING APPROVALS REQUIRED PRIORTO PERMIT ISSUANCE: NGINEERING •BUILDING DFIRE • HEALTH O HAZMAT/APCD
CITY OF
CARLSBAD
Building Permit Appiication
1635 Faraday Ave., Carlsbad, CA 92008
Pti: 760-602-2719 Fax: 760-602-8558
email: building@carlsbadca.gov
www.carlsbadca.gov
Plan Check NcC^ i ^ Cfi t ^
Est. Value 3Z. 5 7<^
Plan Ok. Deposit S / 3
<iPiDate i^/zzJiq |swPP/ C/^^( ^ 2^
JOB ADDRESS . » ^
2JLOU ACUIOA coo<2rr
SUITE#/SPACE#/UNIT#
CONSTR. TYPE OCC, GROUP CT/PROJECT # PHASE # # OF UNITS # BEDROOMS # BATHROOMS TENANT BUSINESS NAME
DESCRIPTION OF WORK: Inclutle Square Feet of Affeittetl Area(s) —
rr'yA./s-rye cycT^/n^ oF Hora2c:r^ tho(.^ ^(90 J'K
EXISTING USE PROPOSED USE GARAGE (SF) PATIOS (SF) DECKS (SF) FIREPIJ\CE
YESn # NOD
AIR CONDITIONING
YES • NOD
FIRE SPRINKLERS
YES • NOO
APPLICANT N NM(IE#(Pr/nT!nt Contact) >. ^ ^ APPLICANT NAME (Secondary Contact)
ADDRESS
I STATE Zip
ADDRESS
CIT)£^ STATE ZiP
PHONE IFAX
CITY STATE
PHONE
EIVIAIL <-\ ,
FAX
EIVIAIL
PROPERTY OWNER NAME pNTRACTOR BUS. NAME
ADDRESS
CITY STATE ZIP STATE ZIP
PHONE FAX PHONE FAX
EtVIAIL EMAIL
ARCH/DtSIGNER NAME & ADDRESS STATE LIC, # CITY BUS, LIC* ^ , / —^
(Sec. 7031.5 Business and Professions Code: Any City or County whicti requires a permit to construct, alter, improve, demolish or repair any structure, prior to its issuance, also requires the applicantfor such permitto file a signed statement that he is licensed pursuantto the provisions ofthe Contractor's License Law (Chapter 9, commendingwlth Section 7000 of Division 3 of the Business and Professions Code) or that he is exempt therefrom, and the basis for the alleged exemption. Any violation of Section 7031,5 by any applicantfor a permitsubjects the applicant to a civil penalty of not more than five hundred dollars {$500}),
Workers' Compensation Declaration: / hereby affitm under penalty of petjury one of the following ileclatations:
I have and will maintain a certificate of consent to self-insure for workers' compensalion as provided by Section 3700 of the Labor Code, forthe performance of the work for which this permit is issued,
I have and will maintain workers' compensation, as required by Section 3700 of the Labor Code, for the performanceof the work for which thispennit is issued. My woriteis' compensation insurance ca-rier and policv
number are: Insurance Co,_ ^TpFTir 'FOV-'^ Policy No, *7dD Z-'^S 70 Expiration Date _
This section need not be completed if the permit is for one hundred dollars ($100) or less,
O Certificate of Exemption: I certify that in the perfomiance of the mt\t lot which this pemiit is issued, I shall not employ any person in any manner so as to become subject to the Workers' Compensation Laws of
California, WARNING: Failure to secure workersy£om^)u^atiQn cguwage is uniawful, and shaii subject an employer to criminal penalties and civii fines up to one hundred thousand dollars (&100,000), in
addition to the cost of compensation, danages as(proyi|jpd fff in Sectioi; 3706 of the Labor code, interest and attomey's fees,
CONTRACTOR SIGNATURE •AGENT DATE v/z3f/y
/ herehy affimi that I am exempt from Contractor's Ucense Law for the following reason:
• 1, as owner of the property or my employees with wages as their sole compensation, will do the work and the structure is not intended or offered for sale (Sec, 7044, Business and Professions Code: The Contrxtor's
License Law does not apply to an owner of property who builds or improves thereon, and who does such work himself or through his own employees, provided that such improvements are not intended or offered for
sale. If, however, the building or improvement is sold within one year of completion, the ovmer-builder will have the burden of proving that he did not build or Improve for the purpose of sale),
• I, as owner of the property, am exdusively contracting with licensed contractors to construct the project (Sec, 7044, Business and Professions Code: The Contractor's License Law does not apply to an owner of
property who builds or improves thereon, and contracts for such projects with contractor(s) licensed pursuant to the Contractor's License Law),
• I am exempt under Section Business and Professions Code for this reason:
1,1 personally plan to provide the major labor and materials for construction of the proposed property improvemenl O Yes • No
2,1 (have / have not) signed an application for a building permit for the proposed work,
3.1 have contracted with the following person (firm) to provide the proposed construction (include name address / phone /contractors' license number):
4,1 pian to provide portions of the work, but I have hired the foilowing person to coordinate, supervise and provide the major work (include name / address / phone / contractors' license number):
5,1 will provide some of the work, but i have contracted (hired) the following persons to provide the wori( indicated (include name / address / phone / type of wori();
^PROPERTY OWNER SIGNATURE •AGENT DATE
COMPLETE THIS SECTION F O It N O N - R E S t 0 E N T I A L B U f L O I M G P i R M I T S ONLY
Is the applicant or future building occupant required to submit a business plan, acutely hazardous matenals registration fomi or risk management and prevention program under Sections 25505,25533 or 25534 of the
Presley-Tanner Hazardous Substance Account Act? • Yes • No
Is the appiicant or future building orcupant required to obtain a permit from the air pollution control district or air quality management district? • Yes • No
Is the facility to be constructed within 1,000 feet of the outer boundary of a school site? • Yes n No
IF ANY OF THE ANSWERS ARE YES, A FINAL CERTIFICATE OF OCCUPANCY MAY NOT BE ISSUED UNLESS THE APPLICANT HAS MET OR IS MEETING THE REQUIREMENTS OF THE OFFICE OF
EMERGENCY SERVICES AND THE AIR POLLUTION CONTROL DISTRiCT,
COMSTBtUCTION tENOING AGENCY
I liereby affirm ttiat tfiere is a construction lending agency for the perfomance of tfie work ttiis permit is issued (Sec, 3097 (i) Civil Code),
Lender's Name Lender's Address
APPtlCANT CERTIFICATION
I certify that I have read the application and state thatthe above Infbimation is coirect and thatthe infbimation on the plans is accuiate. i agree to comply with aii Crfy ordinances and State law relating to building constructkin.
I hereby authorize representative of the City of Carisbad to enter upon the above mentioned property fbr inspectbn purposes, I ALSO AGF!EE TO SAVE, INDEH/INIFY AND KEEP HAFiMLESS THE CITY OF CARLSBAD
AGAINST ALL LIABILITIES, JUDGIWENTS, COSTS AND EXPENSES WHICH MAY IN ANY WAY ACCRUE AGAINST SAID CITY IN CONSEQUENCE OF THE GRANTING OF THIS PERMIT,
OSHA: AT OSHA pemiit is required fbr excavations over 5'0' deep and demolition or construction of structures over 3 stories in height,
EXPIFiATION: Every permit issued by the Building OjfieiaUjQder the provisions of ttiis Code shall expire by limitation and become null and void if the building or v«)rt< authorized by such pemiit is not commenced within
180 days ftom the date of such penmit or if the tjuildint or vwrtfSattorizeifEy^tich pemiit is suspended or abandoned at any time after the is commenced fbr a period of 180 days (Sectbn 106,4.4 Unifbmi Building Code),
ygfAPPLICANT'S SiGNATURE ^ ^f/^'^^
Inspection List
Permit*; CB140916 Type: POOL GALE RES-800 SF POOL SHOTCRET
Date Inspection Item Inspector Act Comments
07/17/2014 55 Fence/Pre-Plaster -Rl
07/17/2014 55 Fence/Pre-Plaster PD AP
07/17/2014 59 Final Pool PD AP
05/23/2014 51 Excav/Steel/Bonding/Fence PD AP
05/08/2014 23 Gas/Test/Repairs PB AP
05/08/2014 51 Excav/Steel/Bonding/Fence PB AP
Friday, July 18, 2014 Page 1 of 1
^ CITY OF
CARLSBAD
PLAN CHECK
REVIEW
TRANSMITTAL
Community & Economic
Development Department
1635 Faraday Avenue
Carlsbad CA 92008
www,carlsbadca,gov
DATE: 05/06/2014 PROJECT NAME: Gale pool construction
PLAN CHECK NO: CB 140916 SET#: I ADDRESS: 2611 Acuna Ct
VALUATION:$32,576 SCOPE OF WORK: 800 sf shotcrete pool construction
PROJECT ID:
APN: 215-491-15
his plan check review is complete and has been APPROVED by:
LAND DEVELOPMENT ENGINEERING DIVISION
Final Inspection by^*fi9CIVI&l division is required: Yes X No
This plan check review is NOT COMPLETE. Items missing or incorrect are listed on
the attached checklist. Please resubmit amended plans as required.
Plan Check Comments have been sent to: wateriinepoolsspas@yahoo.com
r PLANNING^
760-602-4610
ENGINEERING
760-602-2750
FIRE PREVENTION
760-602-4665
: K7\ Linda Ontiveros
V-A 760-602-2773
Linda.Ontiveros@carlsbadca.gov
Remarks:
CBI 40916 Gale pool construction
Outstanding issues will be marked with X
hems that conform to permit requirements are marked
with / -or- have intentionally been left blank.
1. SITE PLAN
Provide a fully dimensioned site plan drawn to scale. Show:
/ Nortti arrow
/ Existing & proposed structures
/ Property„line dimensions
(.,„£flSernents
Show on site plan:
X
X
Draipage patterns
Existing & proposed slopes
/ Existing topography
Retaining Walls (location and height)
/ Indicate what will happen with soil excavated from pool area.
Include on title sheet:
/ Site address
/ Assessor's parcel number
Legal description/lot number
Grading: Quantities of
Cut Fill Import Export
Project does not comply with the following engineering conditions of approval
for project no:
Conditions were complies with by: Date:
Lot/Map No,: 90/M8302
Subdivision/Tract: CT75-04
Reference No(s): DWG I82-6A
E-37 Page 2 of 4 REV 6/2012
CB140916 Gale pool construction
2. GRADING PERMIT REQUIREMENTS
The conditions that require a grading permit are found in Section 11,06,030 of the Municipal
Code,
Inadequate information available on site plan to make a determination on grading
requirements. Include accurate grading quantities in cubic yards (cut, fill, import, export and
remedial). This information must be included on the plans. If no grading is proposed
write: "NO GRADING"
Minor Grading Permit reauired, NOTE: The grading permit must be issued and qradinq
approval obtained priorto issuance of a buildinq permit. A separate grading plan prepared a
registered civil engineer must be submitted together with the completed application form attached,
/ No grading permit required.
3. MISCELLANEOUS PERMITS
note on plans
indicates all
.staging and/or
materials to be
kept clear of the
right of way
/ RIGHT-OF-WAY PERMIT is required to do work in city right-of-way and/or private work
adjacent to the public right-of-way,
A separate right-of-way issued by the engineering division is required forthe following:
Please complete attached right-of-way application form and return to the engineering
department together with the requirements on the attached right-of-way checklist, at
the time of resubmittal.
Right-of-way permit and pool pennit will be issued simultaneously.
E-37 Page 3 of 4 REV 6/2012
CB140916 Gale pool construction
4. STORM WATER
Construction Compliance
/ Project Threat Assessment Form complete.
Enclosed Project Threat Assessment Form incomplete.
/ Requires Tier 1 Storm Water Pollution Prevention Plan. Please complete attached form
and return (SW 14-132 )
Requires Tier 2 Storm Water Pollution Prevention Plan. Requires submittal of Tier 2
SWPPP, payment of processing fee and review by city.
Post-Development (SUSMP) Compliance
/ Storm Water Standards Questionnaire complete.
Storm Water Standards Questionnaire incomplete. Please make the corrections, re-sign
the questionnaire and resubmit with next submittal.
Project is subject to Standard Storm Water Requirements, See city Standard Urban
Storm Water Management Plan (SUSMP) for reference,
http://www,ca risbadca.qov/business/buildinq/Documents/EnqStandsw-stds-vol4-ch2.pdf
Project needs to incorporate low impact development strategies throughout in one or
more of the following ways:
Rainwater harvesting (rain barrels or cistern)
Vegetated Roof
Bio-retentions cell/rain garden
Pervious pavement/pavers
Flow-through planter/vegetated or rock drip line
Vegetated swales or rock infiltration swales
Downspouts disconnect and discharge over landscape
Other:
Attachments: Engineering Application Storm Water Form RIght-of-Way Applicatlon/lnfo Reference Documents
E-37 Page 4 of 4 REV 6/01/12
N!?^ CITY OF
CARLSBAD
STORM WATER COMPLIANCE FORM
TIER 1 CONSTRUCTION SWPPP
E-29
This form is required for all poois, retaining walls or w/henever a buiiding footprint is enlarged.
Development Services
Land Development Engineering
1635 Faraday Avenue
760-602-2750
www.carlsbadca.gov
STORM WATER COMPLIANCE CERTIFICATE
My project is not in a category of permit types exempt from the Construction
SWPPP requirements
^ My project is not located inside or within 200 feet of an environmentally
sensitive area witti a significant potential for contributing pollutants to nearby
receiving waters by way of storm water mnoff or non-storm water
discharge(s).
My project does not require a grading plan pursuant to the Carlsbad
Grading Ordinance (Chapter 15.16 ofthe Carlsbad Municipal Code)
•Y My project will not result in 2,500 square feet or more of soils disturbance
including any associated constmction staging, stockpiling, pavement
removal, equipment storage, refueling and maintenance areas that meets
one or more of the additional following criteria:
• located within 200 feet of an environmentally sensitive area or the
Pacific Ocean; and/or,
• disturbed area is located on a slope with a grade at or exceeding 5
horizontal to 1 vertical; and/or
• disturbed area is located along or within 30 feet of a stomi drain inlet, an
open drainage channel or watercourse; and/or
• construction will be initiated during the rainy season or will extend into
the rainy season (Oct. 1 through April 30).
I CERTIFY TO THE BEST OF MY KNOWLEDGE THAT ALL OF THE ABOVE
CHECKED STATEMENTS ARE TRUE AND CORRECT. I AM SUBMITTING
FOR CITY APPROVAL A TIER 1 CONSTRUCTION SWPPP PREPARED IN
ACCORDANCE WITH THE REQUIREMENTS OF CITY STANDARDS.
I UNDERSTAND AND ACKNOWLEDGE THAT I MUST: (1) IMPLEMENT BEST
MANAGEMENT PRACTICES (BMPS) DURING CONSTRUCTION ACTIVITIES
TO THE MAXIMUM EXTENT PRACTICABLE TO MINIMIZE THE
MOBILIZATION OF POLLUTANTS SUCH AS SEDIMENT AND TO MINIMIZE
THE EXPOSURE OF STORM WATER TO CONSTRUCTION RELATED
POLLUTANTS; AND, (2) ADHERE TO, AND AT ALL TIMES, COMPLY WITH
THIS CITY APPROVED TIER 1 CONSTRUCTION SWPPP THROUGHOUT THE
DURATION OF THE CONSTRUCTION ACTIVITIES UNTIL THE
CONSTRUCTION WORK IS COMPLETE AND APPROVED BY THE CITY OF
CARLSBAD.
OWNER(S)/OV\ AQENT NAME (PRINT)
0WNER(S)/0WNER'S AGENT NAME (SIGNATURE) DATE I
STORM WATER POLLUTION PREVENTION NOTES
1. ALL NECESSARY EQUIPMENT AND MATERIALS
SHALL BE AVAILABLE ON SITE TO FACILITATE
RAPID INSTALLATION OF EROSION AND
SEDIMENT CONTROL BMPS WHEN RAIN IS
EMINENT.
2. THE OWNER/CONTRACTOR SHALL RESTORE
ALL EROSION CONTROL DEVICES TO
WORKING ORDER TO THE SATISFACTION OF
THE CITY ENGINEER AFTER EACH RUN-OFF
PRODUCING RAINFALL,
3. THE OWNER/CONTRACTOR SHALL INSTALL
ADDITIONAL EROSION CONTROL MEASURES
AS MAY BE REQUIRED BY THE CITY
ENGINEERING OR BUILDING INSPECTOR DUE
TO UNCOMPLETED GRADING OPERATIONS OR
UNFORESEEN CIRCUMSTANCES WHICH MAY
ARISE.
4. ALL REMOVABLE PROTECTIVE DEVICES SHALL
BE IN PLACE AT THE END OF EACH WORKING
DAY WHEN THE FIVE (5) DAY RAIN
PROBABILITY FORECAST EXCEEDS FORTY
PERCENT (40%). SILT AND OTHER DEBRIS
SHALL BE REMOVED AFTER EACH RAINFALL.
5. ALL GRAVEL BAGS SHALL BE BURLAP TYPE
WITH 3/4 INCH MINIMUM AGGREGATE,
6. ADEQUATE EROSION AND SEDIMENT
CONTROL AND PERIMETER PROTECTION BEST
MANAGEMENT PRACTICE MEASURES MUST BE
INSTALLED AND MAINTAINED.
SPECIAL NOTES
Project Duration
PROJECT INFORMATION
SiteAddress;
Assessor's Parcel Number;
Project ID: j / <-/0/ ^
Construction Permit No.;
Estimated Construction Start Date
Months
Emergency Contact;
Name; L>f2.e^u'i^S
24 tiour Phone;
Perceived Threat to Storm Water Quality
^^.j^-Q^Me^Jium
Low
If medium box is checked, must attach a site plan
sheet showing proposed work area and location
of proposed structural BMPs
For City Use Only
ARLSBAD
.TIER 1 SWPPP
E-29 Page 1 of 3 REV 4/30/10
Erosion Control
BMPs Sediment Control BMPs
Tracking
Control
BMPs
Non-Storm Water
Management BMPs
Waste Management and Materials
Pollution Control BMPs
Best Management Practice
(BMP) Description Geotextiles & Mats Wood Mulching Earth Dikes and Drainage Swales Slope Drains Silt Fence Sediment Trap Check Dam Fiber Rolls Gravel Bag Berm Street Sweeping and Vacuuming Sandbag Barrier Storm Drain Inlet Protection Stabilized Construction Ingress/Egress Stabilized Construction Roadway Water Conservation Practices Paving and Grinding Ooerations Potable Water/I n-igation Vehicle and Equipment Cleanina Material Delivery and Material Use Stockpile Management Spill Prevention and Cnntrnl Solid Waste Manaoement Hazardous Waste Manaoement Concrete Waste CASQA Designation
Construction Activity EC-7 EC-8 EC-9 EC-11 SE-1 SE-3 SE-4 SE-5 SE-6 SE-7 SE-8 SE-10 TR-1 TR-2 NS-1 NS-3 NS-7 NS-8 WM-1 WM-2 WM-3 WM-4 WM-5 WM-6 WM-8 Grading/Soil Disturbance
Trenching/Excavation
T-Stockpiling
Drilling/Borina
Concrete/Asphalt Saw
cutting
Concrete flatwork
Paving
Conduit/Pipe Installation
Stucco/Mortar Work
Waste Disposal
Staging/Lay Down Area
Equipment Maintenance
and Fueling
Hazardous Substance
Use/Storage
Dewatering
Site Access Across Dirt
Other (list);
Instructions; Begin by reviewing the list of construction activities and checking the box to the left of any activity that will occur during the proposed construction. Add any other activity descriptions in the
blank activity description boxes provided for that purpose and place a check in the box immediately to the left of the added activity description. For each activity descrribed, pick one or more best
management practices (BMPs) from the list located along the top of the form. Then place an X in the box at the place where the activity row intersects with the BMP column. Do this for each activity that was
checked off and for each of the selected BMPs selected from the list. For Example - If the project includes site access across dirt, then check the box to the left of "Site Access Across Dirt". Then review
the list for something that applies such as "Stabilized Constmction Ingress/Egress" under Tracking Conlrol. Follow along the "Site Access Across Dirt" row until you get to the "Stabilized Construction
Ingress/Egress" column and place an X in the box where the two meet. As another example say the project included a stockpile that you intend to cover with a plastic sheet. Since plastic sheeting is not on
the list of BMPs, then write in "Cover with Plastic" in the blank column under the heading Erosion Control BMPs. Then place an X in the box where the "Stockpiling" row intersects the new "Cover with
Plastic" column.
To Ieam more about vitiat each BMP description means, you may wish to review the BMP Reference Handout prepared to assist applicants in the selection of appropriate Best Management Practice
measures. The reference also explains the California Stormwater Quality Association (CASQA) designation and how to apply the various selected BMPs to a project.
E-29 Page 2 of 3 REV 4/30/10
^ CITY OF
CARLSBAD
PLANNING DIVISION
BUILDING PLAN CHECK
APPROVAL
P-29
Development Services
Planning Division
1635 Faraday Avenue
(760) 602-4610
www.carkbadra.eov
DATE: 4/24/14 PROJECT NAIVIE: POOL PROJECT ID:
PLAN CHECK NO: CB140916 SET#: ADDRESS: 2611 ACUNA CT APN:
^ This plan check review is complete and has been APPROVED by the PLANNING
Division.
By: GINA RUIZ
A Final Inspection by the PLANNING Division is required • Yes ^ No
You may also have corrections from one or more of the divisions listed beiow. Approval
from these divisions may be required prior to the issuance of a building permit.
Resubmitted plans should include corrections from all divisions.
• This plan check review is NOT COMPLETE. Items missing or incorrect are listed on
the attached checklist. Please resubmit amended plans as required.
Plan Check APPROVAL has been sent to: WATERLINEPOOLSSPAS@YAHOO.COM
For questions or clarifications on the attaclied checklist please contact the following reviewer as marked:
PLANNING
760-602-4610
ENGINEERING
760-602-2750
FIRE PREVENTION
760-602-4665
1 Chris Sexton
760-602-4624
Chris.Sexton@carlsbadca.gov
1 Kathleen Lawrence
760-602-2741
Kathleen.Lawrence@carlsbadca.eov
Greg Ryan
760-602-4663
Gregorv.Rvan@carlsbadca.gov
X Gina Ruiz
760-602-4675
Gina.Ruiz@carlsbadca.gov
Linda Ontiveros
760-602-2773
Linda.Ontiveros@carlsbadca.gov
Q Cindy Wong
760-602-4662
Cvnthia.Wong@carlsbadca.gov
• • 1 Dominic Fieri
760-602-4664
Dominic.Fieri@carlsbadca.gov
Remarks: FLAT PAD ALREADY CREATED ON PROPERTY FOR POOL THAT WAS PROPOSED
IN 1988 BUT NEVER BUILT. NO EXPANSION FROM THAT EXISTING FLAT PAD, OK TO
APPROVE.