RESOLUTION NO. 98-1 2 1
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING BIDS AND AUTHORlZlNG
CONSTRUCTION OF THE SOUTHEAST QUADRANT
PEDESTRIAN CURB RAMP IMPROVEMENTS.
THE EXECUTION OF CONTRACT NO. 3523-2 FOR THE
6 WHEREAS, plans have been reviewed by the City Council of the City of Carlsbad for the
7 construction of the Southeast Quadrant Pedestrian Curb Ramp Improvements, Project No.
3523-2; and 8
WHEREAS, bids have been received by the City of Carlsbad for the construction of said 9
project; and
10
I' Portillo Concrete in the amount of $49,750; and
WHEREAS, the low bid received to construct said project was submitted by
12 WHEREAS, the low and second lowest bid received to construct said project submitted
13 by Portillo Concrete and Fox Construction are responsive; and
14 WHEREAS, the total estimated costs for said project if performed by Portilio Concrete are
15 $62,250 and if performed by Fox Construction are $77,250; and
WHEREAS, Council has previously appropriated $250,000 in the 1997-98 ADA
Pedestrian Curb Ramp Program for design, construction, administration, and inspection of said
16
l7 I/ Project.
18 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
19
1. That the above recitations are true and correct. 20
California, as follows:
21 2. That the low bid of $49,750 submitted by Portillo Concrete for Project No. 3523-2
22 for the construction of the Southeast Quadrant Pedestrian Curb Ramp Improvements is accepted
and the Mayor is hereby authorized to execute a contract therefor. 23 3. That the bid of $64,750 by Fox Construction for Project No. 3523-2 for the
24 construction of the Southeast Quadrant Pedestrian Curb Ramp Improvements is accepted
25
this resolution or such additional days that the City Manager, at his sole discretion, may allow 27
bonds and proof of insurance to the City Purchasing Officer within twenty (20) days of adoption 0' 26
contingent on the failure of Portillo Concrete to provide executed contract documents, suitable
28 The Mayor is hereby authorized to execute a contract therefor under said contingency.
L
Y
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
0 0
4. That the offer award of this contract to lowest or second lowest bidder shall occur
on, or before May 22, 1998.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the 21 day of April , 1998 by the following vote, to wit:
AYES: Council Members Lewis, Kulchin, Hall, Nygaard & Finnila
NOES: None