RESOLUTION NO. 2010-026
2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
3 CARLSBAD, CALIFORNIA, APPROVING THE ENGINEER'S
REPORT, DECLARING THE CITY'S INTENTION TO REVISE
4 THE FEES FOR SEWER BENEFIT AREAS A, B, G, H, I, AND
K, AND SETTING THE PUBLIC HEARING TO CONSIDER
5 ADOPTION OF ADJUSTED FEE AMOUNTS.
6
WHEREAS, the City Council initially imposed Sewer Benefit Area Fees by Resolution
7
No. 91-21 in January 1991; and
8
WHEREAS, the City Council updated the fee amount for Sewer Benefit Areas C, D, E,
9
and F by Ordinance No. NS-642 on September 17, 2009, and included the updated fee
10
amounts to Title 13 of the Carlsbad Municipal Code by adding Chapter 13.10.080; and
WHEREAS, the City Council updated the fee amount for Sewer Benefit Area H by
Ordinance No. NS-699 on April 6, 2004, and included the updated fee amount to Title 13 of the
Carlsbad Municipal Code by adding Chapter 13.10.090; and14
WHEREAS, the City Council of the City of Carlsbad, California, is considering the update
and adjustment of the fees authorized to be levied and collected within Sewer Benefit Areas A,16
B, G, H, I, and K; and
WHEREAS, the City Council may update and modify the fees for Sewer Benefit Areas A,lo
1Q B, G, H, I, and K by a two-thirds approval of an ordinance consistent with Health and Safety
Code Section 5471 and Government Code Sections 66013 and 66016; and
WHEREAS, any increase in the Sewer Benefit Areas A, B, G, H, I, and K fees which
22 rnay result from the update and adjustment of the existing fees are exempt from the voter
approval requirements of Article XIIID Section 6(c) of the California Constitution (Proposition
24 218, see Richmond v. Shasta Community Services District (2004) 32 Cal 4th 409); and
WHEREAS, at this time there has also been submitted a Report of the Engineer entitled
"Updated Fee Study Report for Sewer Benefit Areas A, B, G, H, I, and K", dated November
27
28
1 2009, hereinafter referred to as "2009 Engineer's Report", said Report generally setting forth the
2 following:
3 A. Boundary map of area of benefit;
4 B. Description of proposed public improvements;
5 C. Updated estimate of cost for said improvements;
6 D. Method and apportionment for distribution of costs based upon benefits received
7 from the proposed public improvements; and
8 WHEREAS, at this time the City Council of the City of Carlsbad, California, is now ready
9 to approve the 2009 Engineer's Report as submitted by the Engineer and to consider the
proposed update and modification of the Sewer Benefit Areas A, B, G, H, I, and K fees.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
12 CARLSBAD, CALIFORNIA, AS FOLLOWS:
SECTION 1. That the above recitals are all true and correct.
14 SECTION 2. That Resolution 91-21 is hereby repealed.
SECTIONS. That this City Council does hereby declare its intention to proceed to
authorize the update and modification of the fees authorized to be levied and collected within
Sewer Benefit Areas A, B, G, H, I, and K by adopting Ordinance No. CS-077 for the
18 purpose of financing the costs and expenses relating to certain public improvements in Sewer
1Q Benefit Areas A, B, G, H, I, and K. A general description of the improvements to be funded is as
20 follows:
oi This fee update is only applicable to Sewer Benefit Areas A, B, G, H, I, and K. The sewer
09 facilities include the construction of trunk sewers consisting of numerous pipeline reaches and
23 the Poinsettia Lift Station. For Sewer Benefit Area A, the pipeline reach includes an 8-inch
24 diameter pipeline from Simsbury Lift Station to a point approximately 5,500 feet northeast
25
referred to as reach VCT1C. For Sewer Benefit Area B the pipeline reach includes a 10-inch
r\r*
diameter gravity flow pipeline approximately 5,000-feet in length referred to as reach NAHT1A.
27 For Sewer Benefit Area "G" the work includes constructing manholes and miscellaneous sewer
28
1
1 improvements on pipeline reach VB2. For Sewer Benefit Area H, the pipeline reaches include a
2 12-inch diameter gravity flow pipeline in Poinsettia Lane from Alicante Road to a point 1,320 feet
3 east referred to as reaches VBT1A, VBT1C, and VBT1D, a 12-inch diameter forcemain from
4 Poinsettia Lift Station to El Camino Real referred to as reach VBT1G and Poinsettia Lift Station.
5 For Sewer Benefit Area I, the pipelines reach VB2 will not be constructed. For sewer Benefit
6 Area K the trunk sewer pipeline reaches NBT3A and NBT3B will not be constructed.
7 The improvements listed above also include costs for right-of-way acquisition, engineering,
8 contract administration, construction engineering, construction inspection, and mitigation
9 measures.
10 REPORT
SECTION 4. The Report, titled City of Carlsbad, Updated Fee Study Report for Sewer
12 Benefit Areas A, B, G, H, I, and K dated November 2009, as submitted by the Engineer, is
hereby approved and adopted by this City Council and shall be kept on file in the Office of the
City Clerk and remain open for public inspection.
15 MAP
16 SECTION 5. That a map of the Sewer Benefit Areas A, B, G, H, I, and K showing the
boundaries and area of benefit to be charged to for the improvements designated as "SEWER
18 BENEFIT AREAS A, B, G, H, I, and K" is included as Figures 1 through 6 to the Report, and the
1Q same is hereby approved and adopted.
20 COST ESTIMATE
21 SECTION 6. The cost estimate, as set forth in the Report of the Engineer, reflects the
22 total updated estimated costs for the improvements, and the method of fee allocation represents
23 a fair method of allocation of the costs to the area of benefit. The updated estimated cost of the
24 improvements is $3,257,000.
25 COST ALLOCATION
SECTION 7. The above fees, as set forth in the Report of the Engineer, shall be
27 applicable to all property within Sewer Benefit Areas A, B, G, H, I, and K except for parcels with
28
1 existing building permits, which are exempt from the fee; said fees shall be payable as a
2 condition of issuing a building permit for the property and portions of the property to be
3 developed. The Benefit Area Fees shall be adjusted annually, effective September 1, according
4 to the change to the Engineering News Record Los Angeles Construction Cost Index (Index)
5 with a base year index as of September 1, 2010. The City Council further finds that adjusting the
6 fee annually according to this Index most accurately reflects the increased construction costs
7 associated with the improvements and that by using this Index the fees shall not exceed the
8 reasonable future construction costs and the fees will not be used for general revenue
9 purposes.
10 SECTION 8. For any and all information relating to these proceedings, your attention is
11 directed to the below designated person:
12
WILLIAM E. PLUMMER
13 DEPUTY CITY ENGINEER
CITY OF CARLSBAD
14 1635 FARADAY AVENUE
CARLSBAD, CA 92008
& TELEPHONE: (760) 602-2768.
1R At least fourteen (14) days prior to the public meeting to consider approval of the
increase in fees for Sewer Benefit Areas A, B, G, H, and I, staff will mail written notice of the time
18 and place of the public meeting, including a general explanation of the matter to be considered
19 to any interested party who files a written request with the City for mailed notice of the meeting
20 .on increased fees.
21 SECTION 9. The public hearing to consider adoption of the Sewer Benefit Areas A, B,
22 G, H, I and K fee increase shall be held on March 9, 2010 at the Council Chambers of the City of
23 Carlsbad.
24 SECTION 10. This action approving the Engineer's Report, declaring the City's intention
25
to revise the fees for Sewer Benefit Areas A, B, G, H, I, and K, and setting the public hearing to
26
consider adoption of adjusted fee amounts is exempt from the California Environmental Quality
27
28
\\
1 Act (CEQA) pursuant to CEQA Guidelines Section 15273(a) (4) and based on the following
2 findings required by CEQA Guidelines Section 15273(c):
3 1. All pipelines, whether existing or proposed, are capital projects and are shown in the
4 current Sewer Master Plan Update adopted in 2003. Further, the pipelines were
5 considered in the Program Environmental Impact Report certified for the Sewer Master
6 Plan Update.
2. Fee program modifications are necessary to (1) maintain service within existing service
areas through construction of sewer lines and system upgrades and maintenance, and
(2) reflect adjustments to the fee program based on, among other things, completed land
development that has reduced anticipated development densities and sewer capacities
11 previously anticipated to be inadequate that instead have been determined sufficient,
1")thereby eliminating the need to construct some sewer facilities.
13
14 ///
15 ///
16 ///
17 ///
18 ///
19 ///
20 ///
21 ///
22 ///
23 ///
24
25
26
27
28
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council
of the City of Carlsbad on the 16th day of February, 2010, by the following vote to wit:
AYES: Council Members Lewis, Kulchin, Hall, Packard, Blackburn
NOES: None
ABSENT: None
ATTEST:
LORRAINE Mr-WQ0D, Gtfy Clerk
Karen R. Kundtz, Assistant City Clerk
(SEAL)