HomeMy WebLinkAbout2018-06-12; City Council; Resolution 2018-100RESOLUTION NO. 2018-100
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THI; CARLSBAD TRANSNET LOCAL STREET
IMPROVEMENT PROGRAM OF PROJECTS FOR FISCAL YEARS 2018-19 TO
2022-23 FOR INCLUSION IN THE 2018 SAN DIEGO ASSOCIATION OF
GOVERNMENTS REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM.
Exhibit 1
WHEREAS, on Nov. 4, 2004, the voters of San Diego County approved the San Diego
Transportation Improvement Program Ordinance and Expenditure Plan (TransNet Extension
Ordinance); and
WHEREAS, the TransNet Extension Ordinance provides that SANDAG, acting as the Regional
Transportation Commission, shall approve on a biennial basis a multi-year program of projects
submitted by local jurisdictions identifying those transportation projects eligible to use transportation
sales tax (TransNet) Funds; and
WHEREAS, the City of Carlsbad was provided with an estimate of annual TransNet local street
improvement revenues for fiscal years 2019 through 2023; and
WHEREAS, the City of Carlsbad has held a noticed public hearing with an agenda item that
clearly identified the proposed list of projects prior to approval of the projects by its authorized
legislative body in accordance with Section S(A) of the TransNet Extension Ordinance and Rule 7 of
SANDAG Board Policy No. 31.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. That pursuant to Section 2(C)(1) of the TransNet Extension Ordinance, the City of
Carlsbad certifies that no more than 30 percent of its cumulative revenues shall be spent
on local street and road maintenance projects.
3. That pursuant to Section 4(E)(3) of the TransNet Extension Ordinance, the City of
Carlsbad certifies that all new projects, or major reconstruction projects, funded by
TransNet revenues shall accommodate travel by pedestrians and bicyclists, and that any
exception to this requirement permitted under the Ordinance and proposed shall be
clearly noticed as part of the City of Carlsbad's public hearing process.
June 12, 2018 Item #14 Page 4 of 16
4. That pursuant to Section 8 of the TransNet Extension Ordinance, the City of Carlsbad
certifies that the required minimum annual level of local discretionary funds to be
expended for street and road purposes will be met throughout the five-year period
consistent with the most recent Maintenance of Effort Requirements adopted by
SAN DAG.
5. That pursuant to Section 9A of the TransNet Extension Ordinance, the City of Carlsbad
certifies that it will exact $2,483.48, plus all applicable annual increases, from the private
sector for each newly constructed residential housing unit in that jurisdiction (unless
exempted under the TransNet Extension Ordinance,) and shall contribute such exactions
to the Regional Transportation Congestion Improvement Program (RTCIP).
6. That pursuant to Section 13 of the TransNet Extension Ordinance, the City of Carlsbad
certifies that it has established a separate Transportation Improvement Account for
TransNet revenues with interest earned expended only for those purposes for which the
funds were allocated.
7. That pursuant to Section 18 of the Trans Net Extension Ordinance, the City of Carlsbad
certifies that each project of $250,000 or more will be clearly designated during
construction with TransNet project funding identification signs.
8. That the City of Carlsbad does hereby certify that all other applicable provisions of the
TransNet Extension Ordinance and SANDAG Board Policy No. 31 have been met.
9. That the City of Carlsbad agrees to indemnify, hold harmless, and defend SAN DAG, the
San Diego County Regional Transportation Commission, and all officers and employees
thereof against all causes of action or claims related to City of Carlsbad's TransNet
funded projects.
10. That the Carlsbad TransNet Local Street Improvement Program of Projects for fiscal
years 2018-19 to 2022-23 attached to this Resolution as Attachment A is hereby
approved for inclusion in the 2018 San Diego Association of Governments Regional
Transportation Improvement Program.
June 12, 2018 Item #14 Page 5 of 16
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 12th day of June 2018, by the following vote, to wit:
AYES:
NOES:
ABSENT:
M. Hall, K. Blackburn, M. Schumacher, C. Schumacher.
None.
M. Packard.
(SEAL)
June 12, 2018 Item #14 Page 6 of 16
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
Carlsbad, City of
,MRO ID: CB048 ADOeTION: 18-00 -Project Title: El Camino Real and Cannon Road : RTP PG NO: A-25
Project Description: Intersection at El Camino Real and Cannon Road -In Carlsbad, along the :RAS (M-38)
east/north-bound side of El Camino Real just south of Cannon Road; widen to
provide three through lanes, a right turn lane and a sidewalk approaching the
intersection with Cannon Road
Capacity Status: Cl Exempt Category: Non-Exempt
Est Total Cost: $2,285 Open to Traffic: Jun 2020
TOTALJ PRIOR t 18/19 19/20 20/21 21/22 22/23 PE RW CON
Local Funds I $2,285 I $849 i $1 ,436 $325 $1 ,960
TOTAL ! $2,285 ! $849 l $1,436 i $325 $1,960 I
_MPOID: CB12 ADOPTION: 18-00
Project Title: College Boulevard Reach A . RTP PG NO: A-25; B-34
Project Description: College Boulevard from Badger Lane to Cannon Road (.8 miles) -in Carlsbad, .RAS (M-38)
from Badger Lane to Cannon Road, construct a new segment of College Blvd. to
provide 4-lane roadway with raised median, bike lanes and sidewalks/trails in
accordance with Major Arterial standards ·-Capacity Status: Cl Exempt Category: Non-Exempt ... " . . . .. ... .. .. ··--·-·-... ... -
Est Total Cost: $11,952 Open to Traffic: Dec 2020
-··-·--·-···--·-····--···-······----·····---······--·--·······-·····--.•....... ! .. ····rorAC! ····--···-·-·--··-··''""""""""" -... ···-····-....... _ .. __ ................................... .. -····-·-·····--------------------···"·---·
PRIOR , 18/19 19/20 20/21 21/22 22/23 I PE RW CON
Local Funds I $11,952 I $2,774 I $9,178 I $2,774 $9,178
TOTAL I $11,952 1 $2,774 i $9,178 I $2,774 $9,178
M PO CB13 ADOf>TION: 18-00 -
Project Title: Poinsettia Lane Reach E RTP PG NO: A-25; B-34
Project Description: Poinsettia Lane from Cassia Drive to Skimmer Court (.3 miles) -in Carlsbad, RAS (M-38)
construct a new 4-lane roadway with median, bike lanes, and sidewalks/trails to
major arterial standards
Capacity Status: Cl Exempt Category: Non-Exempt
Est Total Cost: $.12,958 Open to Traffic: Jun 2020
-· ----···-.. ·--·-··----. I TOTAL! PRIORI
-····---·---··--·-··----------·------···-------------·----·----------------
18/19 19/20 20/21 21/22
Local Funds I $12,958 1 $1,260 1 $11 ,698
TOTAL 1 $12,958 f $1,2so I $11,698
** Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SANDAG
Page 1
22/23 I PE RW CON
I $1 ,260 $11,698 ' i $1,260 $11,698 I
Friday, May 18, 2018
June 12, 2018 Item #14 Page 7 of 16
Carlsbad, City of
,_MPO ID: CB20
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
ADOPTION: 18-00 ~
Project Title: Pavement Management -Overlay ·RAs (M-38)
Project Description: Street locations by year as follows: FY 18/19 -Palomar Airport Road, Carlsbad TransNet-LSI: CR
Village Drive, Pio Pico. FY's 19/20-FY 20/21 have not been modeled and therefore
the streets have not been identified. -In Carlsbad, on various streets throughout
the City, pavement overlay 1 inch or greater and miscellaneous roadway section
spot repairs.
Capacity Status: NCI Exempt Category: Safety -Pavement resurfacing and/or rehabilitation
Est Total Cost: $14,750 ,
I TOTALJ PRIOR 18/19 19/20 20/21 21/22 22/23 1 PE RW CON
TransNet -LSI I $5,000 ! l $500 $1,500 $1 ,500 $1 ,500 1 $5,000 •
TransNet-LSI Carry Over I $2,500 I $1,500 $1,000 I $2,500
Local Funds I $7,250 l $1,450 $1,450 $1,450 $1,450 $1 ,450 1 $7,250 ' TOTAL ! $14,750 i $2,950 $2,950 $2,950 $2,950 $2,950 1 $14,750
,JVIPO ID: CB21 ADOPTION: 18-00 -'-
Project Title: Pavement Management -Seal
Project Description: Various minor/local roadways within each area encompassed by the streets
included in the overlay program for that year -In Carlsbad, along various
roadways construct/apply street sealing and construct minor roadway pavement
section repair~. . .
Capacity Status: NCI Exempt Category: Safety -Pavement resurfacing and/or rehabilitation
Est Total Cost: $3,750
------------·--------· ------·-· -·-·-----------·--·------· --I TOTAU ___ PRIOR !·----18/19···-· 19/20 20/21 21/22 22/231 PE RW CON
Local Funds , $3,750 ' I $750 $750 $750 $750 $750 1 $3,750 ' TOTAL! $3,750 1 I $750 $750 $750 $750 $150 I $3,750 !
MPOID: CB22 ADOPTION: 18-00 -
Project Title: .Avenida Encinas -Widen from Palomar Airport Road to Embarcadero Lane RTP PG NO: A-29; B-34
Project Description: Avenida Encinas from Palomar Airport Rd. to Embarcadero Lane (1 miles) -in
Carlsbad, Avenida Encinas from Palomar Airport Road southerly to existing
improvements adjacent to the Embarcadero Lane; roadway widening and
parkway construction/improvements.
Capacity Status: Cl Exempt Category: Non-Exempt .. . ·-· . .. ... ... .. -. -.. ··--· . -· --. -. -.. .. ·-. -... ·-. --... . -
Est Total Cost: $5,347 Open to Traffic: Jun 2021
-----------------------------------I . TOTAL.j PRIOR i --·-···-----··-·-------------------·------------------------·
18/19 19/20 20/21 21/22
Local Funds I $5,347 1 $2 ,605 $30 $2,712
TOTAL I $5,347 I $2,605 I $30 $2,712
** Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SAN DAG
Page 2
22/231 PE RW CON
t ' $400 $60 $4,887
' $400 $60 $4,887 '
Friday, May 18, 2018
June 12, 2018 Item #14 Page 8 of 16
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
Carlsbad, City of
Meo ID: CB31
Project Title: El Camino Real Widening -La Costa Avenue to Arenal Road
Project Description: El Camino Real from La Costa Ave to Arenal Rd. (.5 miles) -in Carlsbad, along El
Camino Real from 700 feet north of La Costa Avenue to Arena! Road, widening
along the southbound side of the roadway to provide three travel lanes and a bike
lane in accordance with Prime Arterial Standards
Capacity Status: Cl Exempt Category: Non-Exempt
Est Total Cost: $2,550 Open to Traffic: Jun 2021
I TOT ALI PRIORt 18/19 19/20 20/21 21/22
Local Funds ! $1,925 ; $1,925
Local RTCIP I $625 i $625 1
TOTAL! $2,550 t $625 I $1,925
Mf>O ID: CB32
Project Title: El Camino Real Widening -Cassia to Camino Vida Roble
Project Description: El Camino Real from Cassia Road to Camino Vida Roble (.5 miles) -in Carlsbad,
widen El Camino Real from 900 feet north of Cassia Road to Camino Vida Roble,
along the northbound/east side of the roadway to provide three travel lanes and a
bike lane in accordance with Prime Arterial standards
Capacity Status:· Cl Exempt Category: Non-Exempt -·--·· -· -·-
Est Total Cost: $2,800 Open to Traffic: Jun 2020
--·-··-·-·-··----···-············-·-··········-"·--. ·-····· .... -·····--·---·--·-··----·-·---··--···-··----·-·----·-··-·-··---· -. --·. ·--·---·--···---·-·--····---···-·-·-····"'" ......... --··-----····-----···--··· I TOTAL.,ij PRIOR ! 18/19 19/20
TransNet-LSI Carry Over l $1,360 ! ! $425 $935 i
Earmark Repurposing I $1 ,440 ( $1 ,100 I $340
TOTAL! $2,800 I $1,100 t $765 $935
'Demo ID CA366 repurposed to FHWA transfer number CAT 16-063
Mf>O ID: C834
Project Title: Palomar Airport Road and Paseo Del Norte Right Turn Lane
20/21 21/22
Project Description: Palomar Airport Road from 1-5 to Paseo Del Norte (.1 miles) -in Carlsbad,
widening along eastbound Palomar Airport Road to provide a dedicated right turn
lane to southbound Paseo Del Norte
Capacity Status:: Cl Exempt Category: Non-Exempt
Est Total Cost: $938 Open to Traffic: Jun 2020
I TOTAU PRIOR ' --··-------·--
18/19 19/20 20/21 21/22
TransNet-LSI Carry Over $75 ; $750
Local Funds $113 i
TOTAL , $938 ! $188 j $750
** Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SAN DAG
Page 3
ADOF:!TION: 18-00
. RTP PG NO: A-30; 8-35
•RAS (M-38)
22/23 PE RW CON
$1,925
I $625
I $625 $1,925
ADOF:!TION: 18-00
RTP PG NO: A-25; 8-35
RAS (M-38)
TransNet-LSI: CR
-·-·-··· ·-
....... , ___ ........ ,-----·-··--·-----····--·····--··-·-------·--···
22/231 PE RW
I $425
I $100 $1 ,000
i $525 $1,000
ADOF:!TION: 18-00
RTP PG NO: A-29; 8-34
,RAS (M-38)
TransNet-LSI: CR
CON
$935
$340
$1,275
-
---·-------· -----·-·
22/23 PE RW CON
t $75 $750
I $64 $49
I $139 $799 I
Friday, May 18, 2018
June 12, 2018 Item #14 Page 9 of 16
Carlsbad, City of
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
MF'O ID: CB35 ADOPTION: 18-00 _
Project Title: Palomar Airport Road and Paseo Del Norte Left Turn Lane
Project Description: Palomar Airport Road from 1-5 to Paseo Del Norte (.1 miles) -In Carlsbad,
lengthen the left turn pocket along eastbound Palomar Airport Road to northbound
Paseo Del Norte
Capacity Status: Cl Exempt Category: Non-Exempt
Est Total Cost: $255 Open to Traffic: Jun 2019
-------------
TOTAL.i PRIOR i ---···--------
18/19 19/20 20/21 21/22
TransNet-LSI Carry Over I $2551 $45 I r $210
TOTAL 1 $255[ $45 ! $210
MPO ID: CB36
Project Title: Carlsbad Boulevard Realignment
Project Description: Carlsbad Boulevard from Palomar Airport Road to City limit (3.3 miles) -study the
realignment of Carlsbad Blvd including the relocation of the southbound lanes of
Carlsbad Blvd to the east and the construction of complete street and multi use
trail impro_ve~ents along the coastal corridor --
Capacity Status: NCI Exempt Category: Other -Engineering studies
Est Total Cost: $3,250
I TOTALl PRIOR I 18/19 19/20 20/21
TransNet-LSI I $2,217 I $1,967 j $250
TransNet -LS I Carry Over I $1,033 i $1,033 ;
TOTAL I $3,250 ! $3,000 $250
*$1.497M programmed on CB20
MPO ID: CB37 __ _
Project Title: El Camino Real and College Blvd. Intersection Improvements
Project Description: Intersection at El Camino Real and College Blvd -in Carlsbad, improve El
Camino Real along the southbound approach to the intersection with College
Blvd. to provide three thru lanes and a signal controlled right turn lane
21/22
-RTP PG NO: A-30; B-35
RAS (M-38)
. TransNet-LSI: CR
------
22/23 PE RW
$50
' $50
ADOPTION: 18-00
•RAS (M-38)
· TransNet-LSI: CR
22/23 1 PE RW
I $2,217
'; $1,033
t $3,250 '
ADOPTION: 18-00
RAS (M-38)
-
CON
$205
$205
CON
Capacity Status: NCI Exempt Category: Other -lntersection_channelization projects
Est Total Cost: $1,025
Local Funds $1,025 ! $70 , $955
TOTALJ PRIOR ! 18/19 19/20 20/21 21/22
TOTAL1 $1,025 i $70 ! $955
•• Include SANDAG in progress and pending projects -these projects are subject to change when accepted by SAN DAG
Page 4
22123 ; PE RW CON
$70 $35 $920
$70 $35 $920
Friday, May 18, 2018
June 12, 2018 Item #14 Page 10 of 16
Carlsbad, City of
Ml'O ID: CB43
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
ADOl'TION: 18-00
Project Title: ADA Improvements · TransNet-LSI: CR
Project Description: Roadways in the northwest quadrant of the City of Carlsbad adjacent to public
facilities inlcuding: Carlsbad Blvd, State Street, Roosevelt Street, Carlsbad Village
Drive, Oak Ave., Chestnut Ave, Harding Street -in Carlsbad, construct Priority Level
1 and Priority Level 2 ADA Improvements per the City of Carlsbad Transition Plan
fo~ Public ~ights-of-way
Capacity Status: NCI Exempt Category: Air Quality -Bicycle and pedestrian facilities
Est Total Cost: $1,670
' TOTAL' PRIOR 18/19 19/20 20/21 21/22 22/23 PE RW
TransNet-LSI Carry Over I $1,670 t $1 ,015 i $655 I $175
TOTAL ! $1,s10 I $1,015 I $655 l $175
MPO ID: CB44 ADOl'TION: 18-00
Project Title: Traffic Signal -RAMS "RAS (M-38)
' Project Description: Management System for Arterial roadways throughout the City of Carlsbad and the TransNet-LSI: CR
County -City of Carlsbad annual operations and maintenance cost share for the
Regional Arterial Management System, (RAMS); TransNet-LSI RAMS of $12 is
programmed through FY 2022. TransNet-LSI RAMS of $12 is programmed
through FY 2022
Capacity Status: NCI Exempt Category: Other -Traffic signal synchronization projects
Est Total Cost: $105
! TOTAL,\ PRIOR 18/19 19/20 20/21 21/22 22/23 '. PE RW
TransNet-LSI ' $105 j $59 $12 $12 $12 $12 I $105
TOTAL ! $105 1 $59 $12 $12 $12 $12 I $105
MPO ID: CB45 ADOPTION: 18-00
Project Title: Carlsbad Boulevard and Tamarack Avenue Pedestrian Improvement Project (part SANDAG ID: 1223071
of Lump Sum V17) RAS (M-38)
Project Description: Intersection at Carlsbad Blvd and Tamarack Avenue -reconfigure the intersection
and the approaches to the intersection and provide enhanced facilities for
pedestrians, transit users and bicyclists; SANDAG approved TransNet!ATP swap
on Octobe~ 2~, 2015
Capacity Status: NCI Exempt Category: Air Quality -Bicycle and pedestrian facilities
Est Total Cost: $2,900
----·-----·--··----,--TOTAi) PRIOR:-18/19
---.. ---·--·-----·----·-----------~-----.
19/20 20/21 21/22 22/23 PE RW
TransNet -BPNS I $1 ,054 ! ! $1,054
Local Funds I $1 ,576 1 $1 ,179 1 $397 $500
TDA -Bicycles I $270 j $175 ; $95 i
TOTAL I $2,900 I $1,354 1 $1,546 t $500
CON
$1 ,495
$1,495
·-
CON
-
--CON
$1 ,054
$1 ,076
$270
$2,400
•• Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SAN DAG
Pages Friday, May 18, 2018
June 12, 2018 Item #14 Page 11 of 16
Carlsbad, City of
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
MPO ID: CB46 ADOf>TION: 18-00
Project Title: Terramar Area Complete Street Improvements RAS (M-38)
Project Description: Cannon Road from Carlsbad Boulevard to Avenida Encinas (.5 miles) -in . TransNet-LSI : CR
Carlsbad, construct complete street improvements including the reconfiguration
of the curbline and the addition of medians, pedestrian crossings and parkway
improvements
Capacity Status: NCI Exempt Category: Other -Transportation enhancement activities
Est Total Cost: $1,000
l TOTAL! PRIORI 18/19 19/20 20/21 21/22 22/23 PE RW
TransNet -LSI Carry Over • $1 ,000 [ ' $1,000 $95 I
TOTAL1 $1,000 i $1,000 ! $95
CON
$905
$905
MPO ID: CB47
Project Title: Carlsbad Village Drive and Grand Avenue Improvements
ADOf>TION: 18-00,_ __
1
RAS (M-38)
Project Description: Carlsbad Vtllage Drive and Grand Avenue from Washington Street to State Street
(.1 miles)-in Carlsbad, provide mid-block pedestrian crossing improvements
and sidewalk/parkway improvements at the approaches to the railroad track
_crossings
Capacity Status: NCI Exempt Category: Air Quality -Bicycle and pedestrian facilities
Est Total Cost: $1,320
TransNet-LSI: CR
TOT AU .......... i>Ri0Rf -18/19 19/20 20/21 21/22 22/23 ; PE RW CON
TransNet-LSI $1 ,320 1 r, $1,320 . ' TOTAL: $1,320 1 I $1,320
Mf>O ID: CB:c..4 .... 8,__
Project Title: Chestnut Avenue Complete Street Improvements Valley Street to 1-5
Project Description: C.hestnut Avenue from Valley Street to 1-5 (.8 miles) -in Carlsbad, complete street
improvements including sidewalk improvements and traffic calming features
such as bulb outs and medians
Capacity Status: NCI Exempt Category: Air Quality -Bicycle and pedestrian facilities
Est Total Cost: $1,080
$150
$150
ADOf>TION: 18-00
TransNet-LSI: CR
$1 ,170
$1,170
TOTAL\ PRIOR I 18/19 19/20 20/21 21/22 22/23 PE RW CON
TransNet-LSI Carry Over $1,080 j ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
$1,080 $125 $955
TOTAL ; $1,080 I $1,080 $125 $955
** Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SANDAG
Page 6 Friday, May 18, 2018
June 12, 2018 Item #14 Page 12 of 16
Carlsbad, City of
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
MPO ID: CB49 ADOPTION: 18-00
Project Title: Kelly Drive and Park Drive Complete Street Improvements TransNet-LSI: CR
Project Description: Kelly Drive and Park Drive from El Camino Real to Neblina Drive (1 miles) -in
Carlsbad, complete street improvements including new curblines, sidewalk and
multi use trail improvements and traffic calming features such as bulb outs and
medians
Capacity Status: NCI Exempt Category: Air Quality - Bicycle and pedestrian facilities
Est Total Cost: $4,175
I TOTAL' PRIOR 18/19 19/20 20/21 21/22 22/23 PE RW
TransNet-LSI Carry Over I $4,175 i $210 I $3,965 • $655
TOTALj $4,1751 $210 I $3,965 I $655
MPO ID: CB50 ADOeTION: 18-00
Project Title: Valley Street Complete Street Improvements TransNet-LSI: CR
Project Description: Valley Street from Chestnut Avenue to Magnolia (.28 miles) -in Carlsbad, improve
the right of way to include Class 1 dedicated bike paths, pedestrian paths and
crossings, curbline bulbouts, tree wells_, and parking
Capacity Status: NCI Exempt Category: Air Quality -Bicycle and pedestrian facilities
Est Total Cost: $1,645
I TOTAIJ PRIOR I 18/19 19/20 20/21 21/22 22/23! PE RW
TransNet-LSI '
$1,645 I ! $1 ,645 I $200
TOTAL ! $1,645 I I $1,645 • $200 I
MPO ID: CB51 DOPTION: 18-00
Project Title: Adaptive Traffic Signal Program RAS (M-38)
Project Description: Aviara Parkway -Poinsettia to Palomar Airport Road, Cannon Road -1-5 to . TransNet-LSI : CR
Faraday and Rancho Santa Fe -Calle Barcelona to San Elijo. -in Carlsbad,
construct fiber optic communications upgrades and install traffic measuring
~ systems and adaptive signal control systems to implement adpative traffic signal
c_ontrol along_these roadways. . -. . -.
Capacity Status: NCI Exempt Category: Other -Traffic signal synchronization projects -. --·· ---·-·-
Est Total Cost: $3,125
I TOT AU PRIOR I 18/19 19/20 20/21 21/22 22/23 PE RW
TransNet -LSI ' $1,500 / I $1,500 f f
TransNet -LSI Carry Over i $625 ! I $625 I
Local Funds • $1 ,000 f ' $1 ,000 I ' ;
TOTAL I $3,125 t I $3,125 I
~
CON
$3,520
$3,520
-
CON
$1 ,445
$1,445
-
CON
$1 ,500
$625
$1,000
$3,125
** Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SAN DAG
Page 7 Friday, May 18, 2018
June 12, 2018 Item #14 Page 13 of 16
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
Carlsbad, City of
MPO ID: CB56
Project Title: Chestnut Avenue Complete Street Improvements -1-5 to the Railroad
Project Description: Chestnut Avenue from 1-5 to Railroad (.4 miles) -in Carlsbad, prepare a project
study report to identify the scope of work for the construction of complete street
. improvements including traffic calming and pedestrian improvements
Capacity Status: NCI Exempt Category: Other -Engineering studies
Est Total Cost: $85
TOTAW PRIOR ! 18/19 19/20 20/21 21/22
TransNet-LSI Carry Over $85
TOTAL l $85
MPO ID: CB58
Project Title: Street Light Bulb Replacement Program
Project Description: All streets with public street lights throughout the City. -in Carlsbad, replace light
bulbs with LED bulbs
Capacity Status: NCI Exempt Category: Safety -Lighting improvements
Est Total Cost: $3,645
I TOTAL\ PRIOR 18/19 19/20 20/21 21/22
TransNet-LSI I $2,268 I $345 $1,098 $825
TransNet-LSI Carry Over I $1,057 : $1,057
Local Funds I $320 !· ! $320 I '
TOTAL , $3,645 ; $345 : $2,475 $825
ADOf>TION: 18-00
. TransNet-LSI: CR
22/23 PE RW
$85
$85
ADOPTION: 1_8-00
.RAS (M-38)
. TransNet-LSI: Maint
22123 r PE RW
$245
I
I
' $245
CON
-
CON
$2,023
$1 ,057
$320
$3,400
•• Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SANDAG
Page 9 Friday, May 18, 2018
June 12, 2018 Item #14 Page 15 of 16
RTIP Fund Types
F<>rl<>ral Fundina
EARREPU
Lnr<>/ Fundina
Attachment A
Carlsbad 2018 Regional Transportation Improvement Program
San Diego Region (in $000s)
Earmark Repurposing
Local Funds AC Local Funds -Advanced Construction; mechanism to advance local funds to be reimbursed at
a later fiscal year with federal/state funds
RTCIP Regional Transportation Congestion Improvement Program
TransNet-BPNS Prop. A Extension Local Transportation Sales Tax -Bicycle, Pedestrian and Neighborhood
Safetv Proaram
TransNet-LSI Prop. A Extension Local Transportation Sales Tax -Local System Improvements
TransNet-LSI Carrv Over TransNet -LSI funds previously programmed but not requested/paid in year of allocation
** Include SAN DAG in progress and pending projects -these projects are subject to change when accepted by SAN DAG
Page 10 Friday, May 18, 2018
June 12, 2018 Item #14 Page 16 of 16