HomeMy WebLinkAbout2017-06-13; Municipal Water District; Resolution 1575RESOLUTION NO. 1575
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD
MUNICIPAL WATER DISTRICT BOARD (CMWD), RATIFYING AND
AUTHORIZING THE EXECUTION OF CONTRACT CHANGE ORDER NO.4, AND
ACCEPTING THE CONTRACT FOR CONSTRUCTION OF THE TRI-AGENCIES
WATER TRANSMISSION PIPELINES REACH 2-PHASE 1, PROJECT NO. 5008,
AS COMPLETE AND DIRECTING THE SECRETARY TO RECORD A NOTICE OF
COMPLETION AND RELEASE BONDS IN ACCORDANCE WITH STATE LAWS
AND CITY ORDINANCES.
EXHIBIT 1
WHEREAS, the City Council of the City of Carlsbad, California has determined that the Tri-
Agencies Water Transmission Pipelines Reach 2 -Phase 1, Project No. 5008, was completed to the
Board's satisfaction by Dick Miller, Inc. on March 31, 2017; and
WHEREAS, Dick Miller, Inc. submitted a request for change order work in excess of the city
manager's approval limits as outlined in the Carlsbad Municipal Water District's (CMWD) approved
Resolution No. 1527; and
WHEREAS, there is sufficient funding available in the project budget to fund Contract Change
Order No. 4; and
WHEREAS, staff has prepared Contract Change Order No. 4 in the amount of $24,854; and
WHEREAS, the work under Contract Change Order No.4 has already been completed, requiring
ratification of Contract Change Order No. 4 under Carlsbad Municipal Code section 3.28.090(A); and
WHEREAS, the formal Notice of Completion has been prepared.
NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board of the City
of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the Tri-Agencies Water Transmission Pipelines Reach 2-Phase 1, Project No. 5008,
is deemed complete and is hereby accepted by the Board of Directors of CMWD of the
City of Carlsbad.
3. That the secretary of the Board is hereby authorized and directed to execute and record
the Notice of Completion, attached hereto as Attachment A, for the Tri-Agencies Water
Transmission Pipelines Reach 2-Phase 1, Project No. 5008.
4. That Contract Change Order No.4 is ratified and the president of the Board of Directors
of CMWD is authorized to execute Contract Change Order No. 4.
EXHIBIT 1
PASSED, APPROVED AND ADOPTED at a Special Meeting of the Carlsbad Municipal Water
District of the City of Carlsbad on the 13th day of June, 2017, by the following vote, to wit:
AYES: M. Hall, K. Blackburn, M. Schumacher, C. Schumacher, M. Packard
NOES: None.
ABSENT: None.
(SEAL)
;f
Recording requested by:
CITY OF CARLSBAD
When recorded mail to:
City Clerk
City of Carlsbad
1200 Carlsbad Village Dr.
Carlsbad, CA 92008
Notice is hereby given that:
DOC# 2017-0279629
1111111111111111111111111111111111111111111111111111111111111111111111
Jun21, 2017 01:26PM
OFFICIAL RECORDS
Ernest J. Dronenburg, Jr.,
SAN DIEGO COUNTY RECORDER
FEES: $0.00
PAGES: 1
Space above this line for Recorder's Use
NOTICE OF COMPLETION
1. The undersigned is owner of the interest or estate stated below in the property hereinafter
described.
2. The full name of the undersigned is Carlsbad Municipal Water District (CMWD), a municipal
corporation.
3. The full address of the undersigned is 1200 Carlsbad Village Drive, Carlsbad, California
92008.
4. The nature of the title of the undersigned is: In fee.
5. A work or improvement on the property hereinafter described was completed on March 31, 2017.
6. The name of the contractor for such work of improvement is Dick Miller, Inc.
7. The property on which the work of improvement was completed is on Pirgos Way in the City of
Oceanside, County of San Diego, State of California, and is described as Tri-Agencies Water
Transmission Pipelines Reach 2 -Phase 1, Project No. 5008.
CARLSBAD MUNICIPAL WATER DISTRICT
~1
VERIFICATION OF SECRETARY
I, the undersigned, say:
I am the Secretary of the Carlsbad Municipal Water District, 1200 Carlsbad Village
D~ve, Carlsbad, California, 92008. The Executive Board of said District on , J\AMJL \ ~~ , 20_r], accepted the above described work as completed and ordered
that a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on \.. V\1\fL, '.L l.Q~. 20 \1. at Carlsba , a "fornia.
Secretary
CITY OF CARLSBAD
CONTRACT CHANGE ORDER NO. 4
PROJECT: Tri-Agencies Water Transmission Pipelines Reach 2-Phase1
CONTRACT NO. 5008
ACCOUNT NO. 50570009060/500819066
CONTRACTOR:
ADDRESS:
Dick Miller. Inc.
930 Boardwalk Street Ste. H
San Marcos. CA 92078
P.O. NO. P131120
The Contractor is directed to make the following changes as described herein. Changes
shall include all labor, materials, equipment, contract time extension, and all other goods and
services required to implement this change. Payment stated on this change order includes
all charges, direct or indirect, arising out of this additional work including charges for field
overhead, extended home office overhead, delays, disruptions, cumulative impacts, loss of
efficiency, extended equipment costs and overtime premium costs and is expressly agreed
between the City and the Contractor to be the complete and final costs hereof. The
requirements of the specifications, where pertinent and not in conflict with this change order,
shall apply to these changes. This change order is not effective unless signed by the City
Manager and/or the Mayor or his/her designee.
Pursuant to Section 3 of the General Provisions of this contract, perform the following:
Item 1: Relocate the horizontal alignment of an existing sewer lateral at Station 237+50 due
to elevation conflict with the new 18-inch Cement Mortar Lined and Coated
(CML&C) pipe.
Increase to contract cost. ................................................................. $2,062.00
Item 2: Demolish and dispose of concrete to 4-foot below grade from the existing
undocumented vault in conflict with the new 18-inch CML&C tie-in point, and cap
the existing undocumented 12-inch potable water pipeline at Station 248+90.
Increase to contract cost. ................................................................. $1 ,886.42
Item 3: Break out and dispose of the undocumented concrete encasement on the existing
21-inch pipeline at Station 249+00.
Increase to contract cost. ................................................................. $1 ,302.58
-... Tri-Agencies Water Transmission Pipelines Reach 2-Phase 1, Project:# 5008 CC04 page 2
Item 4: Install additional copper anode wiring per SDCWA which was not called out in the
cathodic protection test station details on CP-1 of the contract documents.
Increase to contract cost. ................................................................. $1,724.68
Item 5: Replace existing irrigation control wiring and conduit lines between Station 234+00
and Station 235+00 which were not shown on the plans.
Increase to contract cost.. ................................................................ $2,544.96
Item 6: Furnish and place 118 tons of additional asphalt concrete, labor and equipment to
complete the paving of Pirgos Way.
Increase to contract cost. ............................................................... $15,333.06
TOTAL INCREASE TO THE CONTRACT ................................................ $24,853. 70
TIME FOR COMPLETION OF ALL WORK UNDER THIS CONTRACT SHALL BE
INCREASED BY 62 WORKING DAYS AS A RESULT OF THIS CHANGE ORDER.
RECOMMENDED BY: APPROVED BY:
(o _,) --t")
~N ERING MANAGER (DATE) (DATE)
~ 6-5', '7
DEPAJU ~ HEAD (DATE)
~~ '/L/17
FINANCE DIRECTOR (DATE)
DISTRIBUTION: INSPECTION FILE (ORIGINAL), PURCHASING, CONTRACTOR, DEPUTY DIRECTOR DESIGN
CITY OF CARLSBAD
CONTRACT CHANGE ORDER TRANSMITTAL-C/0 #4
Tri-Agencies Water Transmission Pipelines Reach 2-Phase 1
Project No: 50081
Date Routed: To:
Construction Management & Inspection
Department Head
Finance Director!{),\
City Manager/Mayor
Construction Management & Inspection
Reasons for changes:
Item 1:
Item 2:
Item 3:
Item 4:
Item 5:
Item 6:
During excavation and installation of the new 18-inch CML&C waterline a
sewer lateral was identified in confict with the proposed horizontal alignment at
approximate Station 237+50. The city requested that the contractor relocate
the lateral to avoid the conflict.
The city water department requested the demolition and partial removal of an
existing buried vault in conflict with the proposed alignment of the new 18-inch
waterline at Station 248+90. The vault walls and lid were removed to 4-foot
below grade and the bottom was perforated and backfilled with native sandy
material. The work included cap and abandonment of an unused existing
12-inch potable water pipeline not shown on the plans.
The city requested that the contractor break out and dispose of an
undocumented concrete encasement on the existing 21-inch pipeline not
shown on the plans at Station 249+00. Removal of the concrete encasement
was required to make the connection at the tie-in point.
The San Diego County Water Authority (SDCWA) requested that the
contractor provide additional copper anodes for the cathodic protection wiring
at all test stations. The changes, which were identified by SDCWA during final
walk-through inspection, were not called out in the cathodic protection test
station details on sheet CP-1 of the contract documents.
The city requested additional work be performed to reinstall existing irrigation
control wiring and conduits which were not shown on the plans.
Additional 118 tons of asphalt concrete, labor and equipment were required to
complete the paving of Pirgos Way. The additional asphalt was required in
areas that required deep lift repairs and to pave the actual field measured
limits of paving.
' , -
Project Name: Tri-Agencies Water Transmission Pipelines Reach 2-Phase 1 Project: # 50081
COST ACCOUNTING SUMMARY:
Original contract amount $1,097,197.00
Total amount this C/0 $24,853.70
Total amount of previous C/O's $165,000.00
Total C/O's to date $189,853.70
New Contract Amount $1,287,050.70
Total C/O's as% of original contract 17.30%
Contingency amount encumbered $165,000.00
Contingency increase I decrease $25,000.00
Contingency Subtotal $190,000.00
Total C/O's to date $189,853.70
Contingency balance $146.30